You are on page 1of 25

CONTENTS

Construction Site Safety


20. Electricity on Site

Electricity hazards Causes of electric shock

Unlike most other hazards which can be seen, felt • Contact between a live conductor and
or heard there is no advance warning of danger earth
from electricity; and electricity can kill. • Contact between phase and neutral
conductors (as the body is likely to be of
Electricity and electrical installations on
less resistance than any load)
construction sites must always be treated with the
utmost care and be under the control and According to the Health and Safety Executive, the
supervision of experienced competent persons. majority of electrical accidents happen because
Hazards arise through faulty installations, lack of people are working on or close to equipment which
maintenance and abuse of equipment. is either:

In the Construction Industry, in one year, there • assumed to be dead, but is in fact live
were 194 reported accidents resulting in injury, • known to be live, but workers have not
and over 200 dangerous occurrences involving received adequate training, lack adequate
electricity. Accidents involving live overhead lines equipment or have not taken adequate
are a particular concern as, in the same period, precautions
one in three proved fatal.

Electric shock is a major hazard; the severity of


the shock will depend on the level of electric
current, and the duration of the contact.

At low levels of current, about 1 milliamp, the


effect may be only an unpleasant tingle but
enough to cause loss of balance or a fall; medium
levels, of about 10 milliamps, can cause muscular
tension so that anything grasped is hard to
release. High levels of electric shock, of 50
milliamps or above, for a period of about one
second, can cause fibrillation of the heart which
can be lethal. Electric shock also causes burning Check it's dead before it kills you
of the skin at the points of contact.
Electric shock is not the only hazard. The very
Fuses cannot be regarded as adequate high temperature that results from electric arcing
protection against electric shock. A fuse is can produce severe and deep-seated burns. An
intended only to protect equipment from damage. electric arc also produces intense ultra violet
They are commonly rated at 3, 5, 10 or 13 amps radiation which can damage the eyes (arc eye).
for domestic and normal business use.
An electrical short circuit or the use of unstable or
1 milliamp is a one thousandth part of an amp badly maintained equipment can ignite flammable
materials, resulting in a fire or explosion.

© Construction Industry Training Board GE 700/20


March 1996
CONTENTS FIRST PAGE

Legislation British Standards

The Health and Safety at Work Act 1974 BS 2754 Construction of electrical equipment for
protection against electric shock
The Electrical (Overhead Lines) Regulations 1970
BS 4293 Specification for residual current
The Electricity Supply Regulations 1988 operated circuit breakers 1993
The Electricity at Work Regulations 1989 BS 4363 Specification for distribution assemblies
The Low Voltage Electrical Equipment (Safety) for electricity supplies for construction and building
Regulations 1989 sites 1991

The Construction (Design and Management) BS 5345 Code of practice for selection and
Regulations 1994 installation and maintenance of electrical
apparatus for use in potentially explosive
The Provision and Use of Work Equipment atmospheres
Regulations 1998
BS 7071 Specification for portable residual current
The Management of Health and Safety at Work devices 1992
Regulations 1999
BS 7288 Specifications for socket outlets
incorporating residual current devices (SRCDs)
References
BS 7375 Code of practice for the distribution of
HSE Guidance Notes, etc. electricity on construction and building sites

GS 6 Avoidance of Danger from Overhead BS 7430 Code of practice for earthing 1998
Electrical Lines 1991 BS 7671 Requirements for electrical installations,
PM 29 Electrical Hazards from Steam/Water IEE wiring regulations 16th edition
Pressure Cleaners 1988 BS EN 60309 Plugs, socket-outlets and couplers
HSG 47 Avoiding Danger from Underground for industrial purposes
Services 1989
Other references
HSG 85 Electricity at Work: safe working
Institute of Electrical Engineers
practices 1993
A Commentary and Guide to the IEE Regulations
HSG 107 Maintaining portable and transportable (16th edition)
electrical equipment 1994
Chartered Institute of Building Services
HSG 118 Electrical safety in arc welding 1994 Engineers
HSG 141 Electrical safety on construction sites Code of Practice for Interior Lighting and Lighting
1995 Guide for Building and Civil Engineering Sites
HSR 25 Memorandum of guidance on the
Construction Industry Training Board
Electricity at Work Regulations 1989
Memorandum of Guidance on the Electricity at EE 111 IEE Regulations Study Notes
Work Regulations 1989 VID 018 Video training programme Danger of
The Electricity at Work Regulations 1989 Death
Approved Code of Practice, Use of Electricity at
Quarries

20/2
CONTENTS FIRST PAGE

Regulations Employees, in turn, have a duty under these


regulations to tell their employer of any work
All electrically powered tools are covered by the situation which presents a risk to themselves or
Provision and Use of Work Equipment their workmates, or of any matter which affects
Regulations 1998 their health and safety.

The Provision and Use of Work Equipment (For further information see Construction Site
Regulations 1998 require that an employer only Safety, Module 2, General Safety Legislation)
supplies work equipment that is correct and
Both sets of regulations additionally require the
suitable for the job and ensures that the
employer to provide employees with adequate
equipment is maintained and kept in good working
information, instruction and training to be able to
order.
carry out any work task to the best of their ability
Where the use of the equipment involves a and in complete safety.
specific risk to the health and safety of employees, It cannot be emphasised too strongly that the
the use of the equipment must be restricted to installation, maintenance and repair of
specified workers. electrical services must only be done by a
competent, qualified electrician.
All work, and that includes work on electrical
systems, or work with electrical equipment, must Many electrical risks can be eliminated, or reduced
have been subject to a risk assessment under the by careful attention to design and planning
Management of Health and Safety at Work aspects before the start of work. Remaining risks
Regulations 1999. can be controlled by good management practices
during work.
The Management of Health and Safety at
Work Regulations 1999 place a requirement on Planning and management are key requirements
every employer to make a suitable and sufficient of the Construction (Design and Management)
assessment of every work activity to detect and Regulations 1994.
define any hazard that either employees might
These regulations place health and safety
encounter during their work, or any other persons
responsibilities on the client, designers and
who might be affected by the employer’s
contractors, and provide a framework for the
operations.
management of risks, including electrical risks.
Once those hazards have been identified, it is the
A planning supervisor must be appointed by the
employer’s duty to put control measures in place,
client and provided with relevant health and safety
to remove or reduce those hazards as far as is
information which could include a location plan (if
reasonably practicable.
available) of the electrical supply system.
Where a hazard is identified that requires it, the
Hazards must be identified and inherent risks that
employer must offer health surveillance to
may arise must be eliminated or reduced.
employees. This must be appropriate, taking into
account the risks to health and safety that have The main principles of risk control should be
been identified. utilised, of which the following are a selection:

The employer must provide employees with • if possible avoid the risk
comprehensible and relevant information on any • combat risks at source
risks that exist in the workplace and of any
control measures that are in place to reduce • give priority to those measures which will
those risks. protect all the workforce

20/3
CONTENTS FIRST PAGE

The planning supervisor must also prepare a (ii) ‘Electrical equipment’ includes everything
health and safety plan at the pre-tender stage of from overhead to underground cables with
the contract. This plan should contain information thousands of volts, right down to 6 volt circuits
on the project health and safety risks, and the and even battery-powered hand lamps. The
means to eliminate or reduce them. spark from the switch on a hand lamp could
be a source of danger in an explosive
A principal contractor must be appointed to
manage and co-ordinate the work and also to atmosphere.
develop the health and safety plan. This should (iii) ‘Danger’ is the risk of injury to any person
contain all the relevant information on how health
and safety risks will be managed. (iv) ‘Injury’ means death or any injury caused
by electricity. This covers electric shock,
The principal contractor also co-ordinates the electric burns, fires, arcing or explosions
activities of other contractors and may make site caused by electricity.
rules.
Contractors must co-operate with the planning • the strength and capability of electrical
supervisor and comply with any rules or directions equipment must not be exceeded in such a
given. way as may give rise to any danger
Reference
Electricity at Work Regulations The Electricity at Work Regulations 1989,
Regulation 5
The Electricity at Work Regulations apply to all
situations involving electricity, at any place of All electrical equipment which may be exposed to:
work, and place legal obligations on both • mechanical damage
employers and employees.
• the effects of weather, temperature, etc.
The main points of the regulations are, briefly: • wet, dirty or corrosive conditions
• all systems shall be of such a construction • flammable or explosive dusts or gases
so as to prevent, so far as is reasonably
practicable, any danger. must be constructed, or protected to prevent, so
far as reasonably practicable, any danger arising.
• all work activity, on or near a system,
including operation, use or maintenance, Reference
shall be carried out, so far as it is The Electricity at Work Regulations 1989,
reasonably practicable, so as not to give Regulation 6
rise to any danger. • all conductors which may give rise to
• any equipment provided to protect people danger must be insulated, protected, so
while they are at work on, or near, any placed and have other precautions taken
electrical equipment shall be suitable for so as to prevent danger
use and properly maintained. Reference
Reference The Electricity at Work Regulations 1989,
The Electricity at Work Regulations 1989, Regulation 7
Regulation 4 • earthing, or other protective measures
must be taken to prevent cables, other than
Notes
circuit cables, from becoming live
(i) ‘System’ includes every part of the system
or installation, all conductors and electrical Reference
equipment, whether the system is electrically The Electricity at Work Regulations 1989,
Regulation 8
alive or dead.

20/4
CONTENTS FIRST PAGE

• placing switches in the neutral side of a • adequate access, lighting and working
circuit is prohibited, unless specific safety space must be provided, as necessary, to
precautions are taken prevent any injury from occurring
Reference Reference
The Electricity at Work Regulations 1989, The Electricity at Work Regulations 1989,
Regulation 9 Regulation 15
• all joints and connections must be • no person is to be engaged in work, where
electrically sound and mechanically technical knowledge or experience is
suitable for use necessary to prevent danger, unless they
have the knowledge and experience or are
Reference
under the appropriate supervision
The Electricity at Work Regulations 1989,
Regulation 10 Reference
The Electricity at Work Regulations 1989,
• the use of fuses, or circuit breakers, to
Regulation 16
protect electrical systems is required
Note
Reference
The Electricity at Work Regulations 1989, ‘Technical knowledge and experience’ means
Regulation 11 that the person must be competent to do their
job. To be considered competent a person
• a suitable means must exist for:
needs:
cutting off the electricity supply to any item adequate knowledge of electricity
of electrical equipment good experience of electrical work
an understanding of the system being worked
isolating any such item on

identifying circuits where appropriate practical experience of that type of system


knowledge of the hazards that might arise
Reference and the precautions that need to be taken
The Electricity at Work Regulations 1989,
Regulation 12 ability to immediately recognise unsafe
situations
• adequate precautions must be taken to
prevent any danger when work is taking Electricity supply
place near equipment that has been made
electrically dead, especially to prevent it The supply of electricity on construction sites will
from becoming live again normally be provided by one or both of the
following:
Reference
The Electricity at Work Regulations 1989, 1. A public supply from the local electricity
Regulation 13 company
• no work is to take place on, or near, live 2. A site generator, where public supply is not
conductors unless: practicable or is uneconomic
it is unreasonable to make the conductor Public supply
dead, it is reasonable to allow live work, or A public supply of electricity being provided
suitable precautions have been taken depends on the following items:
Reference • written application being made to the local
The Electricity at Work Regulations 1989, electricity company, as soon as possible at
Regulation 14 the planning stage

20/5
CONTENTS FIRST PAGE

• the name, address, and telephone number Overhead power lines


of the main contractor and developer,
giving the full site address and a location Generally electricity supplies above 33,000 volts
plan are routed overhead. Supplies below this voltage
may be either overhead or underground.
• details of the maximum demand load (in
kilowatts) which is likely to be required Overhead lines are normally un-insulated and can
during construction be lethal if contact, or near contact, is made.
Electric arcs may jump a considerable distance.
• details of the maximum final demand load
The Electrical (Overhead Lines) Regulations 1970
(in kilowatts) which will be required when
give the minimum distances of conductors from
the job is complete
ground level. Care should be taken when
• dates when the supply is needed dumping, tipping waste, regrading, landscaping, or
• a discussion with electricity company staff when in unplanned storage areas, etc. not to
to determine the necessary precautions to reduce these minimum clearances.
avoid damage or hazards from any existing See especially Guidance Note GS 6
overhead or underground cables
Minimum height of overhead cables
• the establishment of supply points (where
incoming cables will terminate), switch 400 kV 7.3 m
gear, metering equipment and 275 kV 7.0 m
requirements for earthing 132 kV 6.7 m
33-66 kV 6.0 m
Generators 11-33 kV 5.2 m
Generators may be provided, and will be powered Except for roads, when the minimum height is
by petrol or diesel engines. Attention should be 5.8 m or in inaccessible places where the
given to the siting of such equipment, in order to minimum height may be reduced to 4.6 m.
minimise pollution caused by noise and fumes.
• Any private generating plant must be Working near overhead power
installed in accordance with BS 7375. You lines
are advised to seek advice from the local
electricity company The local electricity company should be consulted
before any work commences and a safe system of
• If the generator will produce over 55 V ac it work should be devised and implemented.
must be effectively earthed. A competent
person should test the effectiveness of the Regulation 14 of the Electricity at Work
earth Regulations requires that either the power lines be
made DEAD or suitable precautions taken to
• The principle of low voltages and their
prevent any danger.
advantages should be considered further
where portable generators are used on site Practical steps that can be taken to prevent
danger from any live electrical cable or apparatus
• Not all portable generators available for use
include the placing of adequate and suitable
on site have the 110 voltage output centre
barriers.
tapped to earth. This is particularly true of
generators having dual voltage selectable If access is possible only from one side, then a
• The metal framing of the generating set barrier, on this side only, will suffice. If the
should be bonded to the metalwork of the overhead line crosses the site barriers will be
site distribution system required on both sides of it. If there is a danger to
people carrying metal scaffold poles, ladders or
• Generators in excess of 10 kVA may other conducting objects, the barrier should
require advice from a specialist exclude both people and mobile plant.

20/6
CONTENTS FIRST PAGE

Working near overhead power lines

Any ground level barriers should consist of either: There should be a general rule prohibiting the
(a) a stout post and rail fence, or storage of materials in the area between the
overhead lines and the ground-level barriers.
(b) a tension wire fence, earthed at both ends, Precautions are necessary even though work in
having flags on the wire. The fence being the vicinity of the line may be of short duration.
earthed in consultation with the electricity
company, or • Before doing any work on site consult the
local electricity company. They will
(c) large steel drums (for example 200-litre oil normally arrange a site meeting (which is
drums) filled with rubble or concrete, and usually a free service) and advise on
placed at frequent intervals, or heights, distances and other precautions. A
(d) an earth bank, not less than 1 m high and Code of Practice of Do’s and Don’ts is
marked by posts to stop vehicles, or available from most companies
(e) substantial timber baulks, to act as wheel • It must be assumed that all overhead lines
stops and cables are live unless advised
Fences, posts, oil drums, etc. should be made as otherwise by the electricity company
distinctive as possible by being painted with red • All work should be carried out under the
and white stripes. As an alternative, red and white direct supervision of a responsible
plastic warning flags or hazard bunting should be supervisor, appointed by the employer, who
used on wire fences. is familiar with the hazards likely to be
encountered

20/7
CONTENTS FIRST PAGE

• Ensure that safety precautions are It is essential that all those involved, particularly
observed machine operators, are aware of the hazards.
• All plant, cranes and excavators may be Before any excavation work commences:
modified with suitable physical restraints to
limit their operations where applicable • ensure that employees have proper and
safe work procedures and are working
• Additional care may be needed as work under adequate supervision
proceeds because of reduced clearances
• Electronic proximity warning devices may • check with the electricity board that it is
be fitted on crane jibs, etc. safe to commence work

Note • obtain advice on the location and


If any work takes place after dark notices and ownership of any underground electricity
cross bar should be illuminated. Height to be cables
specified by the electricity company.
Where it is necessary to work beneath live • check plans to establish cable routes, as
overhead lines, additional precautions will be well as their depth and voltage
required to prevent the upward movement of
• use cable location devices where
ladders, scaffold poles, crane jibs, excavators
necessary and mark cable routes
buckets, etc. Specific advice should be sought
from the electricity company, or from the Health During excavation:
and Safety Executive.
• regard all buried cables as live. Do not
Working in proximity of underground
assume that pot-ended cables are dead or
cables
disused
Damage to live underground cables during
excavation work is the cause of a number of • hand-digging should be employed when
accidents resulting in injuries and disruption of nearing the assumed line of the cable
supplies. There have been occasions when such
accidents have been fatal. The electricity company • excavators and power tools should not be
should be consulted before the commencement of used within 0.5 m of the indicated line of
any work, which may result in the exposure of, or cable
damage to, underground electricity cables.

Traffic passing beneath overhead power lines

20/8
CONTENTS FIRST PAGE

• exposed cables should be supported and as is reasonably practicable, so constructed or


protected against damage. They should not protected that danger is prevented.
be used as hand and footholds
Wherever possible a reduced voltage system
• consult the local electricity company in all should be used.
cases of doubt
Site offices and other accommodation should be a
Reference standard installation to the current IEE
HSG 47 Regulations.
The memorandum of guidance on the Regulations All units for site use should comply to BS 4363
(Regulation 14 paragraphs 24 onwards) also deals and Installations with the BS 7375. Plugs, sockets
with overhead power lines and underground and couplers must conform to BS 4343.
cables.
BS 4343 recommends use of the following units:
Site distribution Supply incoming unit (SIU)
As a first general guide, all wiring, etc. should • Ratings up to 300 amps per phase. These
conform to the IEE Regulations, even though units include main switch gear and
much of it will be temporary. Makeshift metering equipment
arrangements cause accidents and must be
avoided. Mains distribution unit (MDU)
All switch gear should be freely accessible and • For the control and distribution of electricity
capable of being locked in the ‘off’ position. on site. 415 V three-phase, 230 V single-
Regulation 6 of the Electricity at Work Regulations phase ac
1989 specifically states that any electrical
equipment that may be exposed to adverse or A combined supply incoming and distribution unit
hazardous conditions must be, so far (SIDU) may be used in some installations.

BS 4363 Units

20/9
CONTENTS FIRST PAGE

Transformer units (TU) Earthing


TU 1 single-phase 230 V – 110 V All metal parts of the distribution systems and fixed
TU 3 three-phase 415 V – 110 V appliances not carrying a current must be
effectively earthed in accordance with BS 7430
Transformer units are available with different outlet
Code of Practice for Earthing, to either:
ratings, i.e. 16, 32 or 60 amps. Some units have
socket outlets switched through miniature circuit • the metallic sheath and armouring of the
breakers for added protection. incoming supply cable
Such transformer units can be used for portable • the earthed terminal supplied by the supply
tools and plant, and general floor lighting. authority
Outlet units (OU) • a separate earth electrode system
• 110 V socket outlet units Periodic maintenance, inspection and testing is
essential.
• 16 or 32 amp
Earthing via water pipes or gas pipes is not
Such outlet units can be used for portable tools, permitted.
floodlighting and extension outlets. They are not
usually protected by circuit breakers. Monitored earthing systems are recommended for
all transportable plant operating at any voltage
Extension outlet units (EOU) above 110 V and supplied with flexible cables. In
these systems a very low voltage current
• 110 V socket outlet
circulates continuously in the earthing circuit. If
• 16 amp this circuit is broken or interrupted the supply to
the plant is automatically cut off until the earth
Such units can be used for portable tools, local
path is made effective.
lighting and hand lamps.
They are not usually protected by circuit breakers. Plugs, socket outlets and couplers
Markings Only components to BS 4343 should be used.
This covers both single and three-phase supplies
All supply, distribution and transformer units and is intended to prevent plugs designed for one
should be marked with the warning sign shown voltage being connected to sockets of another.
below from BS 5378 Safety signs and colours. This is achieved by different positions of the key-
way in plug and socket.
Examples

A supplementary sign with the word DANGER,


and indicating the highest voltage likely to be
present, should be placed below the warning sign.

20/10
CONTENTS FIRST PAGE

Accessories should be marked with the maximum Cables on the ground


rated operating voltage and current. Colour coding
The use of cables laid upon the ground is
may sometimes be used.
dependent on the nature of work being carried out,
Operating voltage Colour and should be:
(ac) at 50/60 Hz • only permitted for short periods
25 Violet • provided with additional protection, such as
50 White a reinforced sleeve
110-130 Yellow
220-240 Blue • clearly marked, so as not to constitute a
318-415 Red tripping hazard
500-750 Black
Suspended cables
Cables Suspended cables are permissible on condition
that:
In all site offices, workshops, huts and similar
premises, wiring, which is of permanent nature, • there is no tension or strain on connections
should comply with the IEE Wiring Regulations.
• they are adequately marked for protection
Cables used for site distribution
• they are supported on proper hooks not
• Cables that carry more than 65 volts (with nails
respect to earth) should have a continuous
• spans over 3 m are supported by catenary
armour or sheath, which is effectively
wires on poles
earthed. (This requirement does not apply
to arc welding processes.) • they are at a minimum height of 5.8 m
above ground
• Where trailing cables are used sheathing
must be earthed in addition to the normal
earth conductor Installations
All cables should have an overall protective • Installations should be in accordance with
sheathing. The three most common types in use plans drawn up by a competent person
are:
• Any work or alterations to the installation
• tough rubber sheathing (TRS), resistant to may only be undertaken by a competent
wear and abrasion. Not used near solvents person
or oils
• The installation should conform with IEE
• polyvinyl chloride (PVC). For site office and Regulations, and BS 7375 Code of
permanent work. Not suitable for outside Practice for the distribution of electricity on
work at low temperature construction sites
• polychloroprene (PCP). This is the best all
General
round type
• All installations should comply with the
Buried cables regulations as for permanent installations,
All buried cables should be: with good workmanship, and the use of
correct materials
• at least 0.5 m below ground
• protected with tiles or covers or placed in a
duct
• in a trench marked to indicate their route

20/11
CONTENTS FIRST PAGE

Testing and drying rooms, or for water and cooking


apparatus, tend to be left on.
• Every installation should be tested in
accordance with the IEE Regulations at Work on site
three-monthly intervals or shorter periods if
The activities of sub-contractors and others
necessary
installing electrical equipment, lifts, heating,
ventilation etc. must be carefully monitored to
• The record of any testing and inspections
ensure that they do not jeopardise electrical safety
should be made by a responsible person
or leave an installation in a dangerous condition.
on the appropriate certificates
The Electricity at Work Regulations 1989 apply to
• Testing and inspections must include: all work on site, irrespective of the voltage and
a visual inspection whether it is a permanent or temporary supply.

the continuity of final circuit conductors Particular care is needed in respect of any
alterations and extensions to existing installations,
the continuity of protective conductors especially in the identification of circuits.
the earth electrode resistance Reference
the insulation resistance HSG 85 and HSG 141

polarity
Residual current devices
the earth fault loop impedance
RCDs or ELCBs (earth leakage circuit
the correct operation of residual current breakers)
devices and fault voltage operated
When installed, these devices sense a current
protective devices
flow to earth, or an imbalance in the current in the
Weekly inspections should be made of the whole circuit. They disconnect the supply before a
system, including all portable electric tools. person can receive a potentially lethal shock. They
Records should also be kept of all these also protect plant and equipment, and prevent the
installation from catching fire. RCDs must be
inspections.
installed by competent electricians and should be
regularly tested.
Power requirements
RCDs do not reduce current flow, nor the voltage,
The calculation for power requirements should be only the time that the current flows (about 30
left to an experienced person or to the electricity milliseconds), and thereby the severity of the
company. shock.
Advice on suitable RCDs for construction sites
To enable the total site requirements to be should be sought from manufacturers.
established, a site demand table listing items of
plant, equipment and general site requirements It should be noted that the use of a RCD does not
should be completed (see Appendix D). A guide to give 100% guarantee of safety.
voltages required for typical plant is also listed in The device does not have a fail-safe feature and
Appendix D. will not give an indication if it is faulty. Additionally,
because it only protects against earth faults, it will
When computing the demand, it is permissible to not function if current is passing from a live to
allow a diversity factor (assuming not all neutral phase. It is possible for a worker to get an
appliances will be in use at the same time), and a electric shock even though a RCD is fitted to the
figure of not more than 50% is generally circuit and is operating correctly.
acceptable. Care should be taken to ensure that
items such as lighting and heating remain at their
full rated value, because heaters used in huts

20/12
CONTENTS FIRST PAGE

Portable and hand-held electric An appropriate maintenance system should be


established for all portable electrical equipment
tools and should include user checks, regular visual
All portable and hand-held electric tools should be inspections and combined inspection and
selected according to the principles of risk control. electrical testing as necessary. It is recommended
For example, where there is a very high risk of that 110 V portable and hand-held tools should
electric shock, due to site conditions, the use of have the following inspection and testing facilities.
air-operated equipment will eliminate the risk. • User check Weekly
Reduced voltage systems for use with • Visual inspection Monthly
portable and hand-held electric tools • Combined inspection and test before first
A reduced low voltage system, i.e. virtually safe, use and thereafter three-monthly.
which is recommended as the safest type of
General advice is given in HSG 107 Maintaining
system for building and construction sites, is one
portable and transportable electrical equipment.
where the phase to earth voltage does not exceed:
Insulating tape by itself is neither a legal nor
• 55 volts to earth in the case of a single satisfactory repair, either on conductors or the
phase centre tapped to earth supply cable sheath.

• 63.5 volts to earth in the case of a three Long leads trailing over the ground or floor and
phase neutral point earthed supply creating a tripping hazard must be avoided. Care
must be taken in the use of cable drums or reels,
The maximum recommended voltage to earth for a as internal cable terminations may become loose.
reduced low voltage system is stated as 65 volts. They can overheat and cause a fire. Drums and
Both of these systems will offer a phase to phase reels should be inspected regularly for signs of
voltage of 110 volts for supplying power tools on damage or wear.
site.
All insulated or double-insulated tools
A reduced low voltage system will eliminate the manufactured in accordance with BS 2754 and
risk of death from a phase to earth shock in the with the recognised symbol attached, give extra
majority of situations. Other safer systems, i.e. protection against the danger of electric shock.
compressed air, battery power etc., should be
considered when working in confined spaces or Fuses
damp conditions.
Fuses usually blow for a reason. The reason
Outputs of 240 volts or 110 volts should be investigated and rectified before a fuse
is replaced.
110 volt systems that are neither centre tapped or
neutral point earthed can be equally as lethal as a Nails, screws, wire or silver paper must never be
240 volt system in phase to earth faults. In certain used to replace fuses. It is illegal as well as very
situations, even reduced low voltages are not safe. dangerous.
The maximum voltage for portable and hand-held
electric tools should be 110 V centre tapped to Lighting
earth. Flexible cables should be kept as short as Lighting is needed for safety, productivity and
possible, frequently checked for damage and security.
properly repaired as necessary.
The Construction (Health, Safety and Welfare)
Regulations require that every working place,
approach, dangerous opening and lifting appliance
be adequately and suitably lighted.

20/13
CONTENTS FIRST PAGE

There are many different types of lighting, each • adaptable, remembering that 50 to 100%
with its own most suitable application. Advice more light is required for persons over 40
should be sought in order to obtain the best light years of age
for a particular place, considering such factors as
colour rendition, humidity and flammable or • increased if necessary, because more light
explosive atmosphere, etc. will be required in hazardous situations and
when goggles are worn
Reference
PM 38 Selection and use of electrical hand • so positioned that it can be screened or
lamps shielded from reflective surfaces, on traffic
routes, etc.
Levels of illumination • treated as a heat source, with the
Illumination is measured in units of lumens or lux, possibility of burns or fire hazards
which is the amount of light falling on one square
metre. Site lighting
Light meters are used to check levels of Area lighting with floor lights or beam floodlights:
illumination. Illumination should be measured at • all areas should receive light from at least
the workplace, not at the light fitting.
two directions
There are certain factors which can affect the
• fittings mounted on poles, towers and high
efficiency of lighting, such as:
masts must be securely stayed
• the amount of daylight available
• fittings spaced at usually not more than two
• the cleanliness and maintenance of light or three times the mounting height
fittings and reflectors
• the reflections from walls and ceilings
• the distance of the light source from the
workplace
• shadows thrown from furniture and fittings

When considering the level of illumination required


at a workplace, it should be remembered that if the
distance from the light source to the workplace is
doubled, the illumination level will be reduced to
one quarter (inverse square law). For
recommended levels for site lighting, see
Appendix B.

The mounting of lights


Lighting should be: • 230 V is generally accepted for fixed
floodlighting, mounted well above ground
• mounted as high as possible above the
work level • installations to BS 7375, equipment to
BS 4363
• positioned so as to prevent glare, dazzle or
reflection • additional lighting should be provided in
• able to change position as work proceeds hazardous areas

Dust and dirt on lights can absorb up to 20% of


their output and cleaning is often cost-effective in

20/14
CONTENTS FIRST PAGE

maintaining adequate levels of lighting for both Types include dispersive, cargo, cluster,
working and safety. fluorescent trough, wall glass unit, bulkhead unit
tungsten or fluorescent.
Local lighting
• Fittings should be similar to the industrial
This is usually of the tungsten filament type. indoor type but waterproof
• It is used to supplement the general area • They should be mounted centrally,
lighting scheme overhead where possible
• Small sources of light tend to produce • They should be spaced usually one-and-a-
shadows; they should be used with a half times mounted height, but the
diffuser or be hung in rows manufacturer's recommendations should
• Lights should be positioned in the same be followed
direction as the permanent source in order
• They should be mounted as high as
to show up any blemishes in the work
possible to give an even spread of light
• Pendant fittings should be supported so as
• Mains voltage (230 V) should only be used
not to tension the supply cable. They
where the installation is well protected and
should be of the festoon type only with
of a permanent nature. Reduced voltages
moulded on lampholders and protective
should be used for regular site work
guards

• The common type of lighting used by


operatives should be 110 V reduced
voltage
• Care should be taken not to dazzle or
cause a nuisance to anyone outside the
site boundary
For a guide to the characteristics and types of
electric lamp, see Appendix C.

Dispersive lighting
Used over working areas, walkways, ladder
access, stairs, etc.

20/15
CONTENTS FIRST PAGE

Hand lamps Most systems contain provisions for the physical


locking off of switches, etc. and the retention or
• Hand lamps must never be run from a 230 display of keys or permits.
V supply. They should be used on 110 V
or lower, and preferably from a safety extra One copy of the permit must be retained for the
low voltage supply (SELV) duration of the work by the person to whom it is
issued. Before apparatus is made live again, the
• Lamps should all be insulated or double permit must be returned for cancellation. At
insulated to BS 4533 Class 2 cancellation it must be countersigned by both the
holder and the authorised person.
• The use of extra low voltage hand lamps,
even down to 12 V, does not give any The authorised person should keep a record in the
protection against fire or explosion in job file of the issued permits and their cancellation.
flammable or potentially explosive Before work starts, the authorised person should
atmospheres if the bulb is broken. In such ensure that the Permit to Work will cover the
hazardous areas, only lamps to BS 5345 making safe from all possible sources of supply.
should be used
If the work is handed over from one competent
• Special care is needed in sumps, pits, etc. person to another, the permit is to be endorsed by
where petrol, LPG fumes or other the authorised person and transferred to the
flammable gas might collect. All electrical second operative.
equipment should be BASEEFA approved
Under no circumstances should anyone work on,
• In confined spaces, boilers, tunnels, maintain, repair or otherwise adjust high voltage
cramped locations or other hostile damp or apparatus except in accordance with the
humid atmospheres, lamps supplied should instructions and terms of a formal Permit to Work
work at 25 volts system. See HSG 85

Permit to Work Dealing with electric shock


emergencies
Permit to Work systems are essential to ensure
safe working and freedom from hazards where On a construction site, a plan should be prepared
high-voltage electrical supplies, cables and for potential emergencies that may occur,
equipment exist, particularly in installation, including electric shock. This is a requirement of
maintenance or construction work. the Management of Health and Safety at Work
Regulations 1999.
The Electricity at Work Regulations 1989 and the
The plan should include:
Management of Health and Safety at Work
Regulations 1999 both indicate the need for • posting notices in appropriate and
written safe systems of work in specific prominent places publicising the
circumstances. A Permit to Work system should emergency procedures
form part of that ‘safe system’.
• training sufficient workers in the
Permits to Work must only be issued by an procedures to follow in treating an electric
appointed authorised person, using duplicate and shock casualty, including first aid action
numbered printed forms as the example shown • instructing workers in the action to take in
(see Appendix E). They must be signed by an the event of someone receiving an electric
authorised person and by the competent person shock. For example, switching off the
who is to carry out (or be responsible for) the work electrical supply, calling the emergency
described on the permit. services, etc.

20/16
CONTENTS FIRST PAGE

Construction Site Safety


20. Appendix A

Safety checklist • Have the necessary precautions been


taken to ensure that cables do not hang
Permit to Work directly from nails, etc. which may cause
insulation damage?
• Are the instructions clear about who can
grant permits and the time when a permit • Are cables protected from the edges of
comes into operation or expires? sharp objects?
• Who is the manager responsible for • Have all possible precautions been taken
overseeing Permit to Work systems? to ensure that suspended cables do not
• What is the procedure for co-ordinating the carry any weight? Are they supported by
activities of different trades working on the rods or catenary wires?
same job? • Are all cables visible, with, if necessary,
• What is the procedure for informing other yellow and black or red and white plastic
contractors and sub-contractors that a bunting strips attached?
Permit to Work system exists? • Is there an adequate supply of extension
• Have all operatives been instructed and cable for use on the site?
trained in safety procedures, such as • Are all junctions and repairs properly
Permit to Work systems, locking off, and carried out by qualified personnel?
treatment for electric shock?
• Are electrical circuits used for the correct
• Have Permit to Work documents and
purpose? I.e. lighting circuits must not be
procedures been checked and agreed by
used for power tools, especially where
the employer and employee
lighting festoons are fitted with trailing
representatives to ensure all necessary
leads
safeguards have been provided?
• Are buried cables correctly protected by a
• Is the Permit to Work procedure regularly
450 mm cover and cover tiles? Is the line
reviewed and updated?
of the cable also clearly marked?
(See HSG 85) • Are cables capable of carrying the load
required and are they adequate for their
Cables
purpose?
• Have all necessary precautions been taken
where overhead lines exist close to the Plugs, etc.
site?
• Are all plugs in good condition, not cracked
• Are distribution cables so positioned that or otherwise damaged?
they do not cause a hazard at openings,
passages, ladders, stairs, etc.? • Are splash-proof covers being used as
necessary?
• Have precautions been taken to ensure
that cables lying on the ground have been • Are the correct plugs properly fitted to
protected from physical damage or wet equipment, especially those used by sub
conditions? contractors?

20/17
CONTENTS FIRST PAGE

• Are all plugs being used suitable for the • Have the tools or machines been checked
site conditions prevailing? to ensure that there are no cracks, or
missing pieces ?
• Have any plugs been forced into the wrong
sockets (by the removal of keys, etc.)? • Is the chuck in good condition and is the
correct key attached?
• When plugs have been fitted, have the
correct connections been made, with the • Have checks been carried out to ensure
wire being correctly colour coded? that any bit retaining mechanism is in good
working order?
• Are cable grips being used and is the earth
cable fitted with some slack, so that it is the • Have checks been made to ensure that the
last to be pulled out? nameplate is secure with details of:

• Have all possible steps been taken to Type Serial number


ensure that there are no improvised Voltage Volts ac/dc
junctions, nails, matches, silver paper, etc.
Frequency (normally 50 HZ)
being used in place of the correct
equipment? Current Amps
• Is the correct type of fuse with the proper Speed RPM
rating fitted? and other details, depending on
• Have earth leakage breakers been fitted? manufacturer?

• Have all made-up leads or extension • Is there a system of regular planned


cables, etc. been correctly assembled by a inspections and maintenance, by a
competent electrician? competent person, when the power tools
are returned to stores? (See HSG 107)
Power tools • Have checks been carried out to ensure
• Are all power tools used manufactured to that the permissible number of power tools
BS 2769 (Kite Mark) or double insulated on each circuit has not been and is not
mark (BS 2754)? being exceeded?
• Are power tools only being issued to
specific employees and not for general
use?
• Have users been properly and adequately
trained?
• Is the tool fitted with the correct type and
size of plug? • Are the provisions of the Abrasive Wheel
Regulations and the Provision and Use of
• Is the plug undamaged? Work Equipment Regulations being
• Are cable clamps secure? complied with?

• Have checks been made to ensure that


Checklist for operatives
trailing leads are not cut or frayed?
• Are all machines disconnected before any
• Is the cable protected from excessive
adjustment or work is carried out on them?
flexing by a rubber sleeve where the cable
enters the tool? • Are all machines disconnected when not in
use?
• Are all screws in place and secure?
• Have checks been carried out to ensure
that any colour codings are correct?

20/18
CONTENTS FIRST PAGE

• Are cables of an adequate rating for the Precautions near live overhead power
tool that is being used? lines
• Are checks carried out to ensure that no • Has an essential ongoing system of liaison
unofficial cables, etc. are being used? between employer or contractor and the
• Have instructions been issued to ensure electricity company been established?
that no makeshift repairs or maintenance • Where overhead power lines have been
are carried out? diverted or (if possible) made dead, or
• Are all defects reported immediately to a where live lines remain, have all practicable
competent person? steps been taken to provide adequate
barriers, goal posts, etc. to comply with the
• Is the machine kept clean and free from relevant regulations?
damp?
• Have adequate arrangements been made
• Are all connections correctly made,
for the passage of tall plant, etc. at specific
including waterproofing?
times where overhead power lines have
• Are all operatives aware that they should been made dead?
never carry any tool or machine by its
cable? Work beneath overhead power lines
• Have instructions been issued to ensure • On sites where work will take place below
that no machine is started or stopped overhead power lines, have additional
under load? precautions, as necessary, been taken, as
well as the provision of barriers with
Working near overhead power passageways?
lines • Is all work carried out under the direct
supervision of a responsible person,
• Is everyone working on site aware that no familiar with the hazards, after consultation
work should take place: with local electricity company?

(i) within 9 m of overhead power Passage beneath overhead power lines


lines on wood, concrete or steel poles,
or • If there is no work or passage of plant
under overhead power lines, have barriers
(ii) within 15 m of overhead power lines been positioned so as to prevent any close
on steel towers, or approach of any plant, equipment or
personnel to within at least 6 m from the
(iii) until the electricity company is overhead power lines? (See guidance note
consulted for advice? GS6)
Are all personnel working close to overhead power
lines aware that the distances mentioned in the • Does all plant passing under overhead
preceding question are measured horizontally at lines use a defined passageway, protected
ground level from directly below the outermost by barriers, etc.?
conductor?
Note
Alterations to buildings
Electricity companies have different rules for the
• Have all electrical circuits been identified
lateral swing of conductors in high winds and the
before any work is allowed to start?
distance of barriers may vary between
companies.

20/19
CONTENTS FIRST PAGE

• Is there a plan to remove old wiring and


equipment which is no longer required, as
early as possible?

Commissioning new parts of the


electrical installation
• Has the principal contractor prepared an
agreed plant commissioning programme?

• Are all the relevant contractors aware of


this programme?

• Is the programme regularly monitored?

• Is each part of the installation that is being


worked on securely isolated (lock tag and
try)?

20/20
CONTENTS FIRST PAGE

Construction Site Safety


20. Appendix B
Recommended levels for site lighting

Applies to both indoor and outdoor activities and relates to the value on the ground, floor or horizontal working
plane.They may require adjustment according to district brightness.

Purpose Governing factors Design value lux

Security Depending on the degree of risk 5–30

Movement and handling Movement of people, machines and vehicles, handling of 20


materials, walkways and access routes

Stores and stockyards For stored goods, etc. 30

Site entrances 30

General work area General rough work, site clearance 50

Craft work Reinforcing concreting, shuttering erection, bricklaying, 100


scaffolding

Fine craft work Joinery, all work with power tools and circular saws, plastering, 300
painting, electrical, plumbing, shop fitting, brickwork

Special work (3) Retouching paint, french polishing 500

Site huts Rest rooms, locker rooms, toilets 150

Site offices On desks and reference tables, general lighting of drawing 500
office

Drawing offices on site On drawing boards 750

Emergency lighting For escape and standby purposes 5–70

20/21
CONTENTS FIRST PAGE

Construction Site Safety


20. Appendix C
Guide to the characteristics and types of electric lamp

Brief lamp Tungsten Tungsten Mercury Fluorescent Sodium Sodium


characteristics filament halogen vapour tubular vapour vapour
(GLS) (T-H) (MBF) (MCF) low high
pressure pressure
(SOX) (SON)

Wattage range 40/1500 300/2000 50/2000 6/85 35/180 250/1000

Voltage range 25/250 110/250 200/250 110/250 200/250 220/250

*Efficacy 10-18 17-22 35-55 41-68 124-175 80-100


(Lumens Watt)

Colour rendering Good Good Fair Good Poor Good

Resistance to Poor Fair Good Good Good Good


vibration

Normal life (hours) 1000 2000 7500 5000/7500 6000 6000

Restrictions on None Horizontal None None For road None


use or on position 4 degrees lighting only

* The efficacy is the measure of effectiveness of converting electrical energy into usable light

20/22
CONTENTS FIRST PAGE

Construction Site Safety


20. Appendix D
Electrical demand for construction sites
Plant Portable Tools Site Lighting Temp
415 V 3 phase 110 V 1/3 phase 110 V 1 phase Accommodation
230 V 1 phase

Type kW No Total Type kW No Total Location Type kW Requirement kW


Tower crane Chasers Lighting
Hoist Hammers Heating
Platform Saw drills Water heating
hoist drying
Compressor Sanders Cooking
Pump 'A' Vibrators Power
Pump 'B' Air blowers Printing, etc.
Saw bench Dehumidifiers Fixed
Batching Floodlighting
plant
Total load Total load Total load Total load
Diversity factor Diversity factor Diversity factor Diversity factor
Demand load Demand load Demand load Demand load

For calculation purposes - check only the formula: ixV = W should be used
where i = current in amps
V = voltage
W = wattage

Typical electrical supplies used on construction sites


Volts Phase Derived from Special provision Application

415 3 Supply undertaking Fixed and transportable equipment above 5 hp, e.g.
crane, hoist, compressor, concrete mixer, and large
scale personnel amenities
240 1 Supply undertaking Site offices, personnel amenities and fixed
floodlighting
110 3 415 V transformer Secondary winding phase Transportable equipment up to 5 hp, e.g. vibrators,
to earth 64 V pumps, site lighting other than fixed floodlighting, and
hand tools
110 1 230 V transformer Secondary winding outers All portable and transportable tools up to 2.5 hp and
to earth 55 V site lighting
50 1 Transformer Secondary winding outers Dangerous situations, tunnelling work, inside boilers,
to earth 25 V confined spaces
25 1 Transformer Secondary winding outers Dangerous situations, tunnelling work, inside boilers,
to earth 12.5 V confined spaces

20/23
CONTENTS FIRST PAGE

Construction Site Safety


20. Appendix E
Permit to Work on high voltage equipment

No.

Issued to ........................................................................ Job ..................................................................................

I hereby declare that it is safe to work on the following H.V. apparatus which is dead, isolated from all live
conductors and is connected to earth.

All other apparatus is dangerous

SWITCHING AND ISOLATING. The apparatus is disconnected from all live conductors by the following operations.

EARTHING. The equipment is earthed at the following points

DANGER NOTICES. Are posted at

AUTOMATIC FIRE EXTINGUISHING CONTROL has been rendered inoperative at

OTHER PRECAUTIONS

Signed .................................................................. Date ............................................ Time ....................................


(Authorised person)

I hereby declare that I accept responsibility for carrying out work on the apparatus detailed on this permit and that no
attempt will be made by me, nor by any man under my control, to carry out work on any other apparatus

Signed .................................................................. Date ............................................ Time ....................................

Note: After signature for work to proceed, this receipt must be signed by, and the Permit to Work retained by, the
person in charge of the work until work is suspended or completed and the clearance section has been signed.

This is to certify that the work authorised above has been completed or stopped* and that all men under my charge
have been withdrawn and warned that it is no longer safe to work on the apparatus specified on this Permit to Work
and that gear, tools and additional earthing connections are all cleared. Automatic fire extinguishing control has been
restored.

Permit to Work is hereby cancelled

Signed .................................................................. Date ............................................ Time ....................................


(Authorised person)

20/24
CONTENTS FIRST PAGE

Construction Site Safety


20. Appendix F
High voltage safety

THIS IS TO CERTIFY THAT .................................................................................................................

is the person responsible on this site for seeing that the Rules for the safe operation of H.V.
systems and the Permit to Work system are complied with in every respect.

Signed .............................................................................. Date ............................................................

Status .............................................................................. Company .....................................................

The authorised person(s) for H.V. switching, isolation, testing and earthing is (are):

................................................................................................................................................................

................................................................................................................................................................

................................................................................................................................................................

................................................................................................................................................................

20/25

You might also like