Professional Documents
Culture Documents
STATEMENT(SWMS)
Document Class: X
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 2 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
CONTENTS
1 GENERAL .............................................................................................................................................4
2 REFERENCE DOCUMENTS ................................................................................................................4
3 DEFINITIONS AND PROJECT IDENTIFICATION ...............................................................................4
3.1 Abbreviations: ......................................................................................................................................4
4 SCOPE& PURPOSE .............................................................................................................................5
4.1 SCOPE ..................................................................................................................................................5
4.2 PURPOSE .............................................................................................................................................5
5 RESPONSIBILITIES .............................................................................................................................5
5.1 CONTRACTOR Site Manager ..............................................................................................................5
5.2 CONTRACTOR Site HSSE Manager ...................................................................................................6
5.3 Contractor Superintendent and/or Supervisor .................................................................................6
5.4 Contractor HSE Supervisor ................................................................................................................6
5.5 Sub-contractor Superintendent or Field Supervisor .......................................................................7
6 SAFE WORK SYSTEM .........................................................................................................................8
6.1 General Construction Method Statement & Hazid workshop of Subcontractor ...........................8
6.2 Safe Work Method Statement Preparation ........................................................................................8
7 SWMS & JSA DOCUMENT FLOW ......................................................................................................9
8 SAFE WORK METHOD STATEMENT (SWMS) ................................................................................10
8.1 Preparation of the SWMS..................................................................................................................10
8.2 What should go into the Safe Work Method Statement .................................................................11
9 JOB SAFETY ANALYSIS (JSA) ........................................................................................................12
9.1 Concepts/ definitions ........................................................................................................................12
9.2 Multiple JSAs for 1 Safe Work Method Statement .........................................................................12
9.3 JSA Sequence ....................................................................................................................................13
9.4 Identify Steps .....................................................................................................................................13
10 SWMS &JSA MEETING......................................................................................................................18
10.1 The example list of Questions at the SWMS & JSA meeting ........................................................18
11 START MEETING ...............................................................................................................................20
12 APPENDIX ..........................................................................................................................................20
APPENDIX 1: SAMPLE JSA FORM ...............................................................................................................21
APPENDIX 2: EXAMPLE COMPLETED JSA FORM .....................................................................................22
APPENDIX 3: CONTRACTORS JSA FORMAT .............................................................................................23
APPENDIX 4: JSA CHECKLISTS ...................................................................................................................24
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 3 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 4 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
1 GENERAL
This procedure covers the HEALTH, SAFETY, SECURITY AND ENVIRONMENTS (HSSE)
REQUIREMENTS) on Job Safety Analysis (JSA) & Safe Work Method Statement (SWMS)
Procedure for the NSRP Complex Project.
Safe Work Systems on a construction site are fundamental to a safe work site. This process
includes as Permit to Work (PTW) requirements, Safe Work Method Statement (SWMS), Job
Safety Analysis (JSA), START meeting ‘safe work briefing’ for the work crew before work
starts.When site conditions change, and as required, risk assessments applicable to the severity
of the work task.
This procedure addresses both the aspects of the SWMS and JSA.
A written SWMS and JSA are documents that identify the work process, the hazardss to which the
workforce or the environment might be exposed and the control measures to be adopted to reduce
the risk of harm to “as low as reasonably practical” (ALARP) level. The process shall incorporate
line management ownership, support and responsibility from the top down.
2 REFERENCE DOCUMENTS
Following documentation will be used together with this specification.
S-000-1654-0001V Worker’s Occupational Health and Safety Management Plan
S-000-1654-0004V HSSE&S Management System
3 DEFINITIONS AND PROJECT IDENTIFICATION
Project Title :Nghi Son Refinery and Petrochemical Complex Project
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 5 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
4 SCOPE& PURPOSE
4.1 SCOPE
This SWMS and JSA Procedure were developed for all CONTRACTOR and its Subccontractors
activities performed during the Employer Project. The prevention of incidents is a cornerstone of
the CONTRACTOR HSSE Policies and Procedures. The Job Safety Analysis shall be used as one
of the Safe Work System Tools to prevent potential incident during routine and non-routine
activities. Prior to the start of a job, JSA will be prepared covering all steps within a job which may
expose employees to physical, biological or chemical Safety. JSA shall be produced for critical
tasks. The JSA Procedure will also provide a method for supervisors to involve employees in
conducting a safety analysis of jobs and to provide supervisors with a document for training
employees. The Job Safety Analysis and Safe Work Method Statement (SWMS) serves as the
attachment of the Permit to Work System.
Typically, SWMS and JSA cover only one construction activity or operation.
4.2 PURPOSE
The purpose of the SWMS is to plan for work activities that present an increased risk of injury
and/or ill health and to prevent damage to existing facilities. A SWMS outlines
The Safety and risks associated with a particular task or activity
The control measures to be implemented to minimise the evaluated risks.
The method on how the work is to be managed safely
5 RESPONSIBILITIES
5.1 CONTRACTOR Site Manager
Site Manager will hold the ultimate responsibility for ensuring that this JSA and SWMS procedures
are developed, effectively implemented, and regularly updated and maintained, to ensure that it is
applied to relevant activities performed throughout the construction and commissioning phases.
The responsibilities of the Site Manager include, but are not limited to, the following:
Provide necessary resources to facilitate the effective implementation of this Procedure.
Ensure that the responsibilities of key participants under this procedure are communicated to
those personnel under his direction.
Ensuring that the personnel appointed under this procedure are competent to carry out the
tasks for which they are assigned.
Segregating areas and assigning the responsibility for control in those areas to the Section
Managers.
Ensuring that Line management are competent in the risk assessment process
Ensuring that the JSA and SWMS are subject to active assurance, and that a self-regulatory
review and/or audit of the JSA and SWMS implementation are carried out on a regular basis.
Site Manager shall also act upon all recommendations and proposed improvements.
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 6 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 7 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
Attending START to ensure that the contents of SWMS and JSA’s are fully disclosed to, and
understood by the workforce.
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 8 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 9 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
PTW
↑Before the actual work at site
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 10 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
The SWMS and JSA will detail the HSE requirements to be followed and will serve as a record to
demonstrate compliance with HSE legislative and contractual requirements. CONTRACTOR’s and
Subcontractor employees performing the work shall be responsible for implementing the actions
identified in the SWMS and JSA which shall be consistent with the scope of work.
The sample of contents of SWMS shall be referred to the appendix 6.
The method statement is compiled taking into account any risk assessment that has been carried
out for the specific task or activity. Key elements of the method statement shall include:
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 11 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 12 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 13 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 14 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
9.4.3 Hazards
Dropping an object from height
Being struck by an object or making harmful contact with an object
Getting caught on, in or between objects (e.g. line of fire)
Pressure releases/loss of containment
Hazardous materials
Toxicity
Being exposed to various airborne contaminants, such as biological species, gases, mists, fumes,
dust etc.
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 15 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
Vibration
Temperature
Driving / Vehicles
Test Equipment
Cable Detectors
Gas Detectors
Self Contained Breathing Apparatus (SCBA) and Breathing Apparatus on supply hoses
including air compressor
Rescue Equipment
Lifting Slings, Shackles, Chains and Gear
Explosives
Spill Response Kits
Ladders
Fixed and Mobile Scaffolds
Lifting Equipment / Cranes / fork lifts
Hoists / Mobile Elevated Platforms
Shoring Systems
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 16 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
Task Lighting
Portable / Mechanical Hand Tools
Welding Machines
Excavators, compaction rollers, graders, bulldozers, front end loaders
Tipper trucks
Delivery / transport vehicles
Passenger vehicles (e.g., buses, pick-up trucks, passenger vehicles)
9.4.6 Communication
Communication, signalling and notification problems
Lack of coordination between the jobs in the same geographical area or the interrelated systems
including controls
9.4.7 Moving and Handling
Moving equipment Safety’s
Slipping or falling from one level to another
9.4.8 Health
Causing a strain due to pushing, pulling, bending, twisting or lifting
Coming in contact with chemicals
Health Safety
Night shift work
Extended work days
Worker fatigue
Being exposed to environmental Safety, e.g. heat, cold, noise, ionising or solar radiation.
9.4.9 Environment
Likely to cause environmental pollution/ problem
Lack of disposal of Hazardous waste
Handling situations of violence, traffic and security
Vehicle Safety
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 17 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
Mitigation
Changing the job’s working procedure/finding a new way to do the job to eliminate Safety
Changing the physical conditions that create the Safety
Questioning the necessity for or frequency of doing a Safetyous task
Engineered solutions
Provision of personal protective equipment
Waste Management Controls
Warning Signs
Designated Supervision
Training Passport
Competence Certification
Firewatcher / Banksman / Standby Man
Protection
Personal Protective Equipment (PPE) to minimize impact of the risk if it were to occur.
From the above, elimination has the highest and PPE has the least ranking as a means of
controlling Safety. Methods for controlling Safety include:
Provide additional training
Respiratory protection
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 18 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
The risk assessment process will identify critical elements required for the work to be performed
safely. The following key points highlight several critical elements to be considered during the
assessment process.
For effective implementation of the JSA, the Task Supervisor shall brief and explain the contents
of the JSA during the START, to all work leaders and workers involved in the task covered by the
JSA. This will ensure that the workers are following the correct and safe methods for the
task and that any equipment to be used in the task is safe to use.
All SWMS&JSA meeting shall be recorded in the form at Appendix 5. The result of the meeting
shall be reflected to the SWMS & JSA as the result of meeting.
After the draft version is completed by the Subcontractor or Work team, the JSA and SWMS
meeting shall be arranged to review the contents of SWMS and JSA.
The Safe Work Method Statement may also incorporate information and specific requirements
pointed out or discussed at the meeting. Based on the suggestions or pointed out the concerning
by the attendees the specialists of manufacturers / suppliers of plant, equipment and substances;
and other HSSE specialists shall be added to the method statement.
In certain cases, the Safe Work Method Statement may identify training needs for CONTRACTOR
and its Subcontractor employees and the use of competent persons or specially-trained operators
for certain activities.
10.1 The example list of Questions at the SWMS & JSA meeting
10.1.1 General question
What is the task?
Who is going to carry out the task – CONTRACTOR, its Subcontractors, specialist subcontractors
or a combination of these groups?
Who will control and supervise the task?
When the work starts and finishes?
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 19 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
10.1.2 Resources
What plant will be used? Is this adequate?
Are any special tools, equipment or clothing necessary?
Which persons are required to carry out the work and what will be their individual roles? How will
each person in the work crew be consulted with regards to the work tasks, Safety and local
conditions?
Will members of the work crew need any specialist training?
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 20 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
11 START MEETING
Having successfully developed a Method Statement with all Safety identified and risks reduced to
ALARP, the next step will be to communicate the contents to the workforce that will be involved in
the task.
CONTRACTOR and its Subcontractors will conduct START meeting, where the Safety and
controls will be communicated and the step by step process (as detailed in the SWMS) will be
discussed, such that all work group members will be able to understand what is required of them to
safely complete the work activity.
12 APPENDIX
Appendix 1: JSA Sample sheet
Appendix 2: JSA Completed Sample
Appendix 3: CONTRACTOR JSA FORM
Appendix 4: JSA Checklists
Appendix 5: SWMS& JSA Meeting Form
Appendix 6: Sample of SWMS Format
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
D R A
N
I 22-JUL 4
- 2 0 1
Employer Doc. No.
NSRP Complex Project Rev. 0
D R A
N
I 22-JUL 4
- 2 0 1
Employer Doc. No.
NSRP Complex Project Rev. 0
JSA OVERVIEW
THE COMPLETION OF A QUALITY JSA HAS 4 STEPS: CHECKLIST - These items are required for a quality JSA
STEP 1 – PLANNING & PREPARATION Is the JSA Team Leader familiar with the JSA process?
If there is no existing JSA relevant to the work, the whole team undertaking the job The JSA must involve the Supervisor and people performing the work
activity must be involved in the development of a new JSA. JSAs can be typed or Is there an existing WMS or similar JSA for the work?
handwritten on this template. Where existing JSAs relevant to the job exist, these
can be used or reviewed as a guide and changes can be made on by computer or Are chemicals or hazardous materials involved (include MSDS)
hand.
Are required Permits and clearance certificates in place?
STEP 2 ‐ JSA FORM
Effect to others working nearby and surrounding environment considered?
Use Section (A) and/or the Work Method Statement and JSA Team Member
Is additional PPE required?
knowledge of the job as a prompt to identify hazards.
Ensure A Step Back 5x5 is completed prior to starting the task
Identify the potential incidents or hazardous conditions for each step.
Identify controls for each step to reduce the risks to As Low As Reasonably
Practical (ALARP). Work Method Statements (WMS) can be used as a guide. Expiry and Review
The JSA is to be reviewed and signed by the work party on a weekly basis
1.
or when a change in the work activity occurs.
The Hierarchy of Controls shall be applied when identifying controls.
Amendments and reviews shall be reflected in section (F) of the JSA.
2.
- a) Eliminate Hazard If a Permit to Work is governing the job, a copy of the JSA is to be
3.
provided with the closed out copy of the Permit
b) Substitute with less hazardous alternative
Ensure new work crew members to the job review and sign on to the JSA
4.
c) Use engineering controls The JSA is to be retired and stored when that work is completed.
5.
D R A
N
I 22-JUL 4
- 2 0 1
Employer Doc. No.
NSRP Complex Project Rev. 0
Vehicles Driving Hazards Harm to Flora / fauna Caught – in, on, under, between, against
Muscular Stress Falling Objects Historical Sites Exposure – temperature, chemicals, noise, dust
Mental Stress Noise Vegetation Clearing Slip, Trip or Fall – from heights, same level
Repetitive Work Radiation Spills/Leaks Complete Manual Handling Risk Assessment attached
Heights Hydrocarbon/Gas Release Other Mobile/Stationary Equipment Overexertion/ excessive force – lifting, pushing, pulling,
Lone Worker Surfaces Pressure (Stored Energy) Escape of Material – oil spill, gas release, light spill
D R A
N
I 22-JUL 4
- 2 0 1
Employer Doc. No.
NSRP Complex Project Rev. 0
Moving Objects Human Factors Light Spill incorrect use of tools or equipment
Asbestos Chemicals Other (List additional Hazards below) perceived pressure, haste
arduous tasks
Body protection Spill prevention and clean Light shields communications, instruction
up
Weather conditions
hot/dry
Other wet
windy
cold
D R A
N
I 22-JUL 4
- 2 0 1
Employer Doc. No.
NSRP Complex Project Rev. 0
Title: JOB SAFETY ANALYSIS (JSA) & SAFE WORK Contractor Doc. No.
Page 26 of 28
METHOD STATEMENT(SWMS) S-000-1654-0100V
Subcontractor Name/Signature
A. Subject Discussed
B. Attendance List
10
C. Feedback
D R A
IN
22-JU
L - 2 014
Employer Doc. No.
NSRP Complex Project Rev. 0
2.1
2.0 References
etc
3.1
3.0 Responsibilities
etc
4.1
4.0 Equipment
etc
5.1
5.0 Materials
etc
D R A
N
I 22-JUL 4
- 2 0 1
Employer Doc. No.
NSRP Complex Project Rev. 0
6.1
6.0 Resources
etc
7.1
7.0 Procedure
etc
8.1
8.0 Safety
etc
9.1
9.0 Attachments
etc
Prepared by: Checked by HSE Dept Review CONTRACTOR Approval OWNER Approval
D R A
N
I 22-JUL 4
- 2 0 1