Site Instruction

Project Title Development of Infrastructure Facilities for Sur Industrial Estate SI- No 044
Contract Title 9/2019/PEIE/HQ-9 Pages 01
Issued By Al Hatmy Engineering Consultancy LLC
To Towell Infrastructure Projects Co. LLC

CC: Public Establishment for Industrial Estates - Madayn

Reported by Nittananda Paul, Civil Engineer Reported on: 03.02.22


Location CB, 5D

Type of work Civil Electrical


Road Water and Fire Fighting
Sewage Other _____
_____
Description of Finding
44.01 Location:
Road 3, 4 in CB & Road no. 20 in 5D

Observation:
The edges of the granular sub-base are not compacted
properly. Verge strips are also absent at the edges of the
road in the filling area.
Edges of the granular sub base filling materials in the
above mentioned roads are not compacted and no
arrangement made to retain the soil in the position
especially in the filling areas. So, in future sliding or
erosion of soil below kerb stone or road due to rain or
flood may damage the road.
Instruction:
Compaction for all layers must be done properly and
the compaction test results to be submitted in time. The
width of the verge strips at the edges of the roads is to
be executed as per the Oman Highway Design
Standard.
Take the appropriate measures to retain the filled and
compacted soil in location to prevent erotion or sliding
of soil below kerb stone or road.

Attachments:

Reported by: Issued by: Date


Name: Nittananda Paul Name: Hirak Roy 03.02.22
Civil Engineer Resident Engineer
Signature: Signature:

Page | 1 of 2 576486380.docx 14 Feb. 22