Revision 9
*C-600 CANNOT HAVE SUPPLEMENTAL POWER PACKAGE INSTALLED
Power Package Retrofit Kits
Battery Charger Kits and Supplemental
C-600*, C-600M, S-600, S-700, S-600M and S-610M/DE
Precedent™
Trailer Edition
Installation Manual
Thermo King – by Trane Technologies (NYSE: TT), a global climate innovator – is a worldwide leader in sustainable
transport temperature control solutions. Thermo King has been providing transport temperature control solutions
for a variety of applications, including trailers, truck bodies, buses, air, shipboard containers and railway cars since
1938. For more information, visit www.thermoking.com or www.tranetechnologies.com
Thermo King has a policy of coninuous product and data improvements and reserves the right to change design and specifications without notice. We are
committed to using environmentally conscious print practices.
TK55681-11-IM Jan 2020
©2020 Trane Technologies
Installation Manual
Trailer Edition
Precedent™
C-600*, C-600M, S-600, S-700, S-600M and S-610M/DE
Battery Charger Kits and Supplemental Power Package
Retrofit Kits
TK 55681-11-IM (Rev. 9, 01/20)
Your feedback will help improve our manuals. The survey is accessible through any internet-connected device with a web browser.
Scan the Quick Response (QR) code or click or type the web address http://irco.az1.qualtrics.com/SE/?SID=SV_2octfSHoUJxsk6x to
complete the survey.
2
Introduction
This installation manual was written to assist with the installation of the Thermo King Battery Charger and Supplemental Power Package Retrofit Kits onto
Precedent C-600*, C-600M, S-600, S-700, S-600M and S-610/DE units. Additional kits or individual components (not supplied) are required to complete
liftgate charger applications. Contact your Thermo King dealer for available kits. See “Liftgate Charger Wiring Requirements” on page 75.
*NOTE: C-600 UNIT CANNOT HAVE SUPLEMENTAL POWER PACKAGE INSTALLED.
Due to its complexity, you should not attempt this installation unless you:
• Are an experienced mechanic
• Can safely lift 34 kilos (75 lbs.)
• Are certified or trained in the repair and maintenance of diesel powered refrigeration systems
• Have a basic understanding of electricity and electrical wiring
• Have the necessary tools and equipment to complete the installation.
This manual is published for informational purposes only. Thermo King makes no representations warranties express or implied, with respect to
the information recommendations and descriptions contained herein. Information provided should not be regarded as all-inclusive or covering
all contingencies. If further information is required, Thermo King Corporation Service Department should be consulted.
Thermo King’s warranty shall not apply to any equipment which has been “so installed, maintained, repaired or altered as, in the
manufacturer’s judgment, to affect its integrity.”
Manufacturer shall have no liability to any person or entity for any personal injury, property damage or any other direct, indirect,
special, or consequential damages whatsoever, arising out of the use of this manual or any information, recommendations or
descriptions contained herein.
3
Table Of Contents
NOTE: Match up the part number and conversion that you are doing with the table of
contents page for that conversion.
4
Available Conversion Kits
Convert Alternator Unit to Battery Charger: IMPORTANT: Liftgates or auxiliary items cannot be wired to
Model Battery Charger Kit unit battery or any part of TRU system when battery
C-600, S-600, S-700 model 30 30A 401215* charger is installed. You must install the supplemental
C-600, S-600, S-700 model 50 230V 30A 401210 power alternator package and wire liftgates and auxiliary
S-600M model 30 120A 401261 items to it.
S-610M model 30 120A 401348
Excite Harnesses Battery Cable Kits
S-600M, S-610M/DE model 50 230V 120A 401263
C-600M 120A Std. w/battery charger 9 ft. 422188 45 ft. 401223
Convert Alternator Unit to Battery Charger and add Supplemental Power Alternator:
Model BC and Supp Alt Kit + Alternator + Excite Harness + Battery Cable Kit
C-600 Not Available
S-600, S-700 model 30 30A, 120A 401208 452591 & 422341 Excite Harness Battery Cable Kit
S-600, S-700 model 50 230V 30A, 120A 401210 452591 & 422341 Excite Harness Battery Cable Kit
S-600M, S-610M/DE model 30 120A, 120A 401261 Reuse 120A from unit Excite Harness Battery Cable Kit
S-600M, S-610M/DE model 50 230V 120A, 120A 401263 Reuse 120A from unit Excite Harness Battery Cable Kit
C-600M 120A, 65A below Std. w/battery charger. See chart below to add supplemental power
Any model 50 460V Not Available
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Liftgates or auxiliary items cannot be wired to unit battery or any part of TRU system when battery charger is installed. You must
install the supplemental power alternator package and wire liftgates and auxiliary items to it. You may wish to also install an EON power pack
wired to the supplemental alternator.
Alternator and Belt Removal New Tensioner Pulley and Belt Installation
1. Open front curbside and roadside door panels. 6. Remove c-clip from center of tensioner.
2. Disconnect following alternator harness connections: • Slide smooth pulley off tensioner and discard.
• 1-pin connector (WRPM-02) 7. Install new grooved pulley onto tensioner.
• 2-pin connector (WRPM-02)
• Reinstall c-clip onto tensioner.
• 2-pin connector (SENSE, EXC)
• Terminal ring (CHA-01) 8. Install new belt and adjust to proper tension.
• Terminal ring (2A-01) 781875 - Belt S-600
3. Loosen adjusting bolt for pulley tensioner. 781856 - Belt S-700
6
C-600 / S-600 / S-700 Model 30 - Charger 401215
7
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
8
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
9
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
10
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
11
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
12
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
13
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
High Voltage Battery Charger Harness Installation Programming the SR4 Controller
25. Route high voltage harness attached to battery charger to the See “Reconfiguring the SR4 Controller / Trouble Shooting” on page 74
Blower and Fans Control Box. to complete the installation.
26. Open cover and remove the blind grommet inside box. Install harness
conduit fitting and nut securely.
27. Route and attach wires to the Evaporator Fan High Speed contactor
high voltage terminals on the bus bar:
• Attach one wire to L1, L2 and L3.
NOTE: The wires can be put in any order onto the contactor since
the battery charger rectifies the 3 phase, however the ground wire
must only be attached to the ground stud.
28. Attach ground wire (GND) to ground stud inside box.
29. Close and secure the Control box and Blower and Fans Control box
covers.
30. Reinstall door hinge brackets.
31. Reinstall roadside door panel.
32. Close and secure roadside and curbside doors.
14
C-600 / S-600 / S-700 Model 30 - Charger 401215 (continued)
.
.
.
*1'
Ground Stud
$%$
15
S-600 / S-700 Model 30 - Charger 401208 + Alternator 452591
IMPORTANT: Sense Harness (422188 and 422189) is required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator.
Failure to rewire will result in battery charger fault.
16
S-600 / S-700 Model 30 - Charger 40-1208 + Alternator 452591
17
S-600 / S-610M/DE / S-700 Model 30 - Alternator 401209
IMPORTANT: Your unit must already be equipped with a Battery Charger to install the supplemental power package.
Sense Harness (422188 and 422189) is required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from the
unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator.
Failure to rewire will result in battery charger fault.
19
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Liftgates or auxiliary items cannot be wired to unit battery or any part of TRU system when battery charger is installed. You must
install the supplemental power alternator package and wire liftgates and auxiliary items to it. You may wish to also install an EON power pack
wired to the supplemental alternator.
20
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210
21
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued)
22
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued)
23
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued)
24
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued)
25
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued)
26
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued
27
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 40-1210 (continued
High Voltage Battery Charger Harness Installation Programming the SR4 Controller.
21. Route high voltage harness attached to battery charger into the See “Reconfiguring the SR4 Controller / Trouble Shooting” on page 74 to
Blower and Fans Control Box. complete the installation.
22. Open cover and remove the blind grommet inside box and install
harness conduit fitting and nut securely.
23. Route and attach wires to the Evaporator Fan High Speed contactor
high voltage terminals on the bus bar:
• Attach one wire to L1, L2 and L3.
NOTE: The wires can be put in any order onto the contactor since
the battery charger rectifies the 3 phase, however the ground wire
must only be attached to the ground stud.
24. Attach ground wire (GND) to ground stud inside box.
25. Early Production Units Only - Check fuse size and change if needed.
• Replace the 10 amp fuses with the 15 Amp fuses supplied.
26. Close and secure the Control box and Blower and Fans Control box
covers.
27. Reinstall door hinge bracket.
28. Reinstall roadside door panel.
29. Close and secure roadside and curbside doors.
28
C-600 / S-600 / S-700 Model 50 (230 Volt Only) - Charger 401210 (continued
981,76
1HZ)XVHV
.
.
*1
'
$%$
29
S-600 / S-700 Model 50 (230 Volt Only) - Charger 40-1210 + Alternator 452591
31
S-600 / S-610M/DE / S-700 Model 50 (230 and 460 Volt) - Alternator 401347
IMPORTANT: Your unit must already be equipped with a Battery Charger to install the supplemental power package.
Sense Harness (422188 and 422189) is also required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator.
Failure to rewire will result in battery charger fault.
33
S-600M Model 30 - Charger 401261 Optional Supplemental Power
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Liftgates or auxiliary items cannot be wired to unit battery or any part of TRU system when battery charger is installed. You must install
the supplemental power alternator package and wire liftgates and auxiliary items to it. You may wish to also install an EON power pack wired to the
supplemental alternator.
If you want supplemental power, skip steps 1-5 below. Supplemental Power
(Using existing 120 amp alternator)
Charger Only IMPORTANT: Disconnect any liftgate or auxiliary items from the unit
battery or charging system and rewire them to the supplemental
Alternator and Belt Removal alternator. Failure to rewire will result in battery charger fault.
1. Open front curbside and roadside door panels.
Sense Harness Installation
2. Disconnect following alternator harness connections:
• 2-pin connector (2Y-02, EXC-02) 6. Attach sense harness 2-pin connector (SENSE, EXC) to alternator.
• 2-pin connector (WRPM-02) 7. Route single (EXC) wire into control box:
• 1-pin connector (WRPM-02) • Insert (EXC) wire firmly into pin C of 3-pin (ALT. CONNECTOR)
• Terminal ring (CHA-01) located on the battery charger harness installed earlier.
• Terminal ring (2A-02)
• Attach 3-pin (ALT. CONNECTOR) to the mating connector
3. Cut alternator belt. (2Y-02, EXC-02) located inside the control box.
4. Remove and discard alternator belt. 8. Route single (SENSE) wire to accessory positive (+) battery power.
DO NOT connect this to unit’s battery.
5. Remove alternator bolts and alternator.
IMPORTANT: Connect SENSE wire to the closest accessory battery if
NOTE: Alternator will no longer be used.
using multiple batteries.
NOTE: Additional kits or individual components (not supplied) are
required to complete liftgate charger applications. Contact your
Thermo King dealer for available kits. See “Liftgate Charger Wiring
Requirements” on page 75.
34
S-600M Model 30 - Charger 401261 Optional Supplemental Power
35
S-600M Model 30 - Charger 401261 (continued)
36
S-600M Model 30 - Charger 401261 (continued)
37
S-600M Model 30 - Charger 401261 (continued)
38
S-600M Model 30 - Charger 401261 (continued)
39
S-600M Model 30 - Charger 401261 (continued)
Install the following harnesses inside the control box: Install the following wires onto the battery charger:
19. Diode Harness: 23. Remove the two screws from the charger cover, loosen connectors and
install the following wires from the battery charger power harness:
• wire (2ASR4-02) to 2A on SR-4 controller board.
• (CHBC-02) to connection A.
• wire (2AEXP-02) to 2A on expansion module.
• wire (LOAD-01) to connection B.
20. Battery Charger Harness:
• wire (BATT-01) to connection C.
• 4-pin connector (JCANH-01, JCANL-01, JSH-02, JCH-01) to
J33 on SR-4 controller board. • Reinstall cover, tighten screws and connectors.
• 3-pin (ALT. CONNECTOR) to mating connector (2Y-02, ECX- 24. Route low voltage harness out of control box and connect the 8-pin
02) from the main harness. connector to mating connector on Battery Charger.
• Route 8-pin connector, temperature sensor and ground wire out of
control box. These will be connected in a later step. Battery Charger Installation
25. Attach nameplate onto battery charger box cover.
21. Battery Charger Power Harness:
26. Install a nylon washer onto each stud.
• wire (2AEXP-01) to 2A on expansion module.
27. Install battery charger onto studs.
• wire (2ASR4-01) to 2A on SR-4 controller board.
28. Install a M6 flat washer and M6 locking nut onto each stud and tighten
• Route remaining wires out of the control box.
nuts securely.
22. Jumper Wire Installation:
29. Route the two ground wires to the unit ground plate located behind the
• wire (2-03) from 2A on control board to 2 on relay board. control box and connect as follows:
• Single wire (CHBC-01) to ground plate 6 GND PLT
• Single wire (CHBC-02) to ground plate 6 GND PLT-01
30. Secure temperature sensor on frame member with a clamp.
40
S-600M Model 30 - Charger 401261 (continued)
41
S-600M Model 30 - Charger 401261 (continued)
High Voltage Battery Charger Harness Installation Programming the SR4 Controller
31. Route high voltage harness attached to battery charger to the
Blower and Fans Control Box. See “Reconfiguring the SR4 Controller / Trouble Shooting” on page 74 to
complete the installation.
32. Open cover and remove the blind grommet inside box. Install harness
conduit fitting and nut securely.
33. Route and attach wires to the Evaporator Fan High Speed contactor
high voltage terminals on the bus bar:
• Attach one wire to L1, L2 and L3.
NOTE: The wires can be put in any order onto the contactor since
the battery charger rectifies the 3 phase, however the ground wire
must only be attached to the ground stud.
34. Attach ground wire (GND) to ground stud inside box.
35. Close and secure the Control box and Blower and Fans Control box
covers.
36. Reinstall door hinge brackets.
37. Reinstall roadside door panel.
38. Close and secure roadside and curbside doors.
42
S-600M Model 30 - Charger 401261 (continued)
.
.
.
*1'
$%$
Ground Stud
43
S-600M Model 30 - Alternator 401262
IMPORTANT: Your unit must already be equipped with a Battery Charger to install the supplemental power package.
Sense Harness (42-975 or 42-976) is required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator. Failure
to rewire will result in battery charger fault.
120 Amp Alternator Installation Sense Harness Installation
1. Open front curbside and roadside door panels. 6. Attach sense harness 2-pin connector (SENSE, EXC) onto alternator.
2. Install the shim and pulley onto the generator pulley with the supplied M8 7. Route wires into control box:
screws and flatwashers.
• Insert (EXC) wire firmly into pin C of 3-pin (ALT. CONNECTOR)
• Tighten bolts to 21 N•m (16 ft-lb). located on the battery charger harness installed earlier.
3. Installed supplied pulley onto alternator. • Attach 3-pin (ALT. CONNECTOR) to the mating connector
(2Y-02, EXC-02) located inside the control box.
• Tighten M16 nut to 61 N•m (45 ft-lb).
8. Route single (SENSE) wire to accessory positive (+) battery power.
4. Install alternator onto bracket with supplied hardware.
DO NOT connect this to unit’s battery.
• Tighten M8 alternator bolt s to 23 N•m (17 ft-lb). IMPORTANT: Connect SENSE wire to the closest accessory battery if
• Tighten M10 alternator bolts to 30 N•m (22 ft-lb). using multiple batteries.
5. Install new belt and adjust to proper tension. NOTE: Additional kits or individual components (not supplied) are
required to complete liftgate charger applications. Contact your Thermo
King dealer for available kits. See “Liftgate Charger Wiring
Requirements” on page 75.
9. Secure all wiring with band wraps.
10. Close and secure all doors.
45
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Liftgates or auxiliary items cannot be wired to unit battery or any part of TRU system when battery charger is installed. You must install
the supplemental power alternator package and wire liftgates and auxiliary items to it. You may wish to also install an EON power pack wired to the
supplemental alternator.
If you want supplemental power, skip steps 1-4 below. Supplemental Power
(Using existing 120 amp alternator)
Alternator and Belt Removal
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit
1. Open front curbside and roadside door panels. battery or charging system and rewire them to the supplemental
2. Disconnect following alternator harness connections: alternator. Failure to rewire will result in battery charger fault.
• 1-pin connector (WRPM-02)
Sense Harness Installation
• 2-pin connector (WRPM-02)
• 2-pin connector (SENSE, EXC) 5. Attach sense harness 2-pin connector (SENSE, EXC) to alternator.
• Terminal ring (CHA-01) 6. Route single (EXC) wire into control box:
• Terminal ring (2A-01) • Insert (EXC) wire firmly into pin C of 3-pin (ALT. CONNECTOR)
3. Remove alternator belt. located on the battery charger harness installed earlier.
4. Remove alternator bolts and alternator. • Attach 3-pin (ALT. CONNECTOR) to the mating connector
(2Y-02, EXC-02) located inside the control box.
NOTE: Alternator will no longer be used.
7. Route single (SENSE) wire to accessory positive (+) battery power.
DO NOT connect this to unit’s battery.
IMPORTANT: Connect SENSE wire to the closest accessory battery if
using multiple batteries.
NOTE: Additional kits or individual components (not supplied) are
required to complete liftgate charger applications. Contact your
Thermo King dealer for available kits. See “Liftgate Charger Wiring
Requirements” on page 75.
46
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power
47
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
48
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
49
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
50
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
51
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
Install the following harnesses inside the control box: Install the following wires onto the battery charger:
18. Diode Harness: 22. Remove the two screws from the charger cover, loosen connectors and
install the following wires from the battery charger power harness:
• wire (2ASR4-02) to 2A on SR-4 controller board.
• wire (CHBC-02) to connection A.
• wire (2AEXP-02) to 2A on expansion module.
• wire (LOAD-01) to connection B.
19. Battery Charger Harness:
• wire (BATT-01) to connection C.
• 4-pin connector (JCANH-01, JCANL-01, JSH-02, JCH-01) to
J33 on SR-4 controller board. • Reinstall cover, tighten screws and connectors.
• 3-pin (ALT. CONNECTOR) to mating connector (2Y-02, ECX- 23. Route low voltage harness out of control box and connect the 8-pin
02) from the main harness. connector to mating connector on Battery Charger.
• Route 8-pin connector, temperature sensor and ground wire out of
control box. These will be connected in a later step. Battery Charger Installation
24. Attach nameplate onto battery charger box cover.
20. Battery Charger Power Harness:
25. Install a nylon washer onto each stud.
• wire (2AEXP-01) to 2A on expansion module.
26. Install battery charger onto studs.
• wire (2ASR4-01) to 2A on SR-4 controller board.
27. Install a M6 flat washer and M6 locking nut onto each stud and tighten
• Route remaining wires out of the control box.
nuts securely.
21. Jumper Wire Installation:
28. Route the two ground wires to the unit ground plate located behind the
• wire (2-03) from 2A on SR-4 controller board to 2 on relay board control box and connect as follows:
• Single wire (CHBC-01) to ground plate 6 GND PLT
• Single wire (CHBC-02) to ground plate 6 GND PLT-01
29. Secure temperature sensor on frame member with a clamp.
52
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
53
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued))
High Voltage Battery Charger Harness Installation Programming the SR4 Controller.
30. Route high voltage harness attached to battery charger into the See “Reconfiguring the SR4 Controller / Trouble Shooting” on page 74 to
Blower and Fans Control Box. complete the installation.
31. Open cover and remove the blind grommet inside box and install
harness conduit fitting and nut securely.
32. Route and attach wires to the Evaporator Fan High Speed contactor
high voltage terminals on the bus bar:
• Attach one wire to L1, L2 and L3.
NOTE: The wires can be put in any order onto the contactor since
the battery charger rectifies the 3 phase, however the ground wire
must only be attached to the ground stud.
33. Attach ground wire (GND) to ground stud inside box.
34. Close and secure the Control box and Blower and Fans Control box
covers.
35. Reinstall door hinge bracket.
36. Reinstall roadside door panel.
37. Close and secure roadside and curbside doors.
54
S-600M / S-610M / DE / Model 50 - (230 Volt Only) Charger 401263
Optional Supplemental Power (continued)
.
.
*1
'
$%$
55
S-610M Model 30 - Charger 401348
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from
the unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Liftgates or auxiliary items cannot be wired to unit battery or any part of TRU system when battery charger is installed. You must
install the supplemental power alternator package and wire liftgates and auxiliary items to it. You may wish to also install an EON power pack
wired to the supplemental alternator.
Alternator and Belt Removal New Tensioner Pulley and Belt Installation
1. Open front curbside and roadside door panels. 6. Remove c-clip from center of tensioner.
2. Disconnect following alternator harness connections: • Slide smooth pulley off tensioner and discard.
• 1-pin connector (WRPM-02) 7. Install new grooved pulley onto tensioner.
• 2-pin connector (WRPM-02)
• Reinstall c-clip onto tensioner.
• 2-pin connector (SENSE, EXC)
• Terminal ring (CHA-01) 8. Install new belt and adjust to proper tension.
• Terminal ring (2A-01)
3. Loosen adjusting bolt for pulley tensioner.
4. Remove and discard belt.
5. Remove alternator bolts and alternator.
NOTE: Alternator will no longer be used.
56
S-610M Model 30 - Charger 401348
57
S-610M Model 30 - Charger 401348 (continued)
58
S-610M Model 30 - Charger 401348 (continued)
59
S-610M Model 30 - Charger 401348 (continued)
60
S-610M Model 30 - Charger 401348 (continued)
61
S-610M Model 30 - Charger 401348 (continued)
62
S-610M Model 30 - Charger 401348 (continued)
63
S-610M Model 30 - Charger 401348 (continued)
Install the following harnesses inside the control box: Install the following wires onto the battery charger:
21. Diode Harness: 25. Remove the two screws from the charger cover, loosen connectors and
install the following wires from the battery charger power harness:
• wire (2ASR4-02) to 2A on SR-4 controller board.
• (CHBC-02) to connection A.
• wire (2AEXP-02) to 2A on expansion module.
• wire (LOAD-01) to connection B.
22. Battery Charger Harness:
• wire (BATT-01) to connection C.
• 4-pin connector (JCANH-01, JCANL-01, JSH-02, JCH-01) to
J33 on SR-4 controller board. • Reinstall cover, tighten screws and connectors.
• 3-pin (ALT. CONNECTOR) to mating connector (2Y-02, ECX- 26. Route low voltage harness out of control box and connect the 8-pin
02) from the main harness. connector to mating connector on Battery Charger.
• Route 8-pin connector, temperature sensor and ground wire out of
control box. These will be connected in a later step. Battery Charger Installation
27. Attach nameplate onto battery charger box cover.
23. Battery Charger Power Harness:
28. Install a nylon washer onto each stud.
• wire (2AEXP-01) to 2A on expansion module.
29. Install battery charger onto studs.
• wire (2ASR4-01) to 2A on SR-4 controller board.
30. Install a M6 flat washer and M6 locking nut onto each stud and tighten
• Route remaining wires out of the control box.
nuts securely.
24. Jumper Wire Installation:
31. Route the two ground wires to the unit ground plate located behind the
• wire (2-03) from 2A on control board to 2 on relay board. control box and connect as follows:
• Single wire (CHBC-01) to ground plate 6 GND PLT
• Single wire (CHBC-02) to ground plate 6 GND PLT-01
32. Secure temperature sensor on frame member with a clamp.
64
S-610M Model 30 - Charger 401348 (continued)
65
S-610M Model 30 - Charger 401348 (continued)
High Voltage Battery Charger Harness Installation Programming the SR4 Controller
33. Route high voltage harness attached to battery charger to the See “Reconfiguring the SR4 Controller / Trouble Shooting” on page 74 to
Blower and Fans Control Box. complete the installation.
34. Open cover and remove the blind grommet inside box. Install harness
conduit fitting and nut securely.
35. Route and attach wires to the Evaporator Fan High Speed contactor
high voltage terminals on the bus bar:
• Attach one wire to L1, L2 and L3.
NOTE: The wires can be put in any order onto the contactor since
the battery charger rectifies the 3 phase, however the ground wire
must only be attached to the ground stud.
36. Attach ground wire (GND) to ground stud inside box.
37. Close and secure the Control box and Blower and Fans Control box
covers.
38. Reinstall door hinge brackets.
39. Reinstall roadside door panel.
40. Close and secure roadside and curbside doors.
66
S-610M Model 30 - Charger 401348 (continued)
.
.
.
*1'
$%$
Ground Stud
67
C-600M Model 30 - Alternator 401341
IMPORTANT: Your unit must already be equipped with a Battery Charger to install the supplemental power package.
Sense Harness (422188 and 422189) is required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from the
unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator.
Failure to rewire will result in battery charger fault.
65 Amp Alternator Installation Sense Harness Installation
1. Open front curbside and roadside door panels. 9. Attach sense harness 2-pin connector (SENSE, EXC) onto alternator.
2. Loosen adjusting bolt for pulley tensioner.
10. Route single (EXC) wire into control box:
3. Remove and discard belt.
• Insert (EXC) wire firmly into pin C of 3-pin (ALT. CONNECTOR)
4. Remove c-clip from center of tensioner.
located on the battery charger harness.
• Slide grooved pulley off tensioner and discard.
• Attach 3-pin (ALT. CONNECTOR) to the mating connector
5. Install new smooth pulley onto tensioner.
(2Y-02, EXC-02) located inside the control box.
• Reinstall c-clip onto tensioner.
11. Route single (SENSE) wire to accessory positive (+) battery power.
6. Installed supplied pulley from kit onto alternator.
DO NOT connect this to unit’s battery.
• Tighten M16 nut to 61 N•m (45 ft-lb).
IMPORTANT: Connect SENSE wire to the closest accessory battery if
7. Install alternator onto bracket with supplied hardware. using multiple batteries.
• Tighten M8 alternator bolt s to 23 N•m (17 ft-lb).
NOTE: Additional kits or individual components (not supplied) are
• Tighten M10 alternator bolts to 30 N•m (22 ft-lb). required to complete liftgate charger applications. Contact your
8. Install new belt and adjust to proper tension. Thermo King dealer for available kits. See “Liftgate Charger Wiring
Requirements” on page 75.
781876 - Belt S-600 / S-610M/DE
12. Secure all wiring with band wraps.
781857 - Belt S-700
13. Close and secure all doors.
69
C-600M Model 50 (230 and 460 Volt) - Alternator 401342
IMPORTANT: Your unit must already be equipped with a Battery Charger to install the supplemental power package.
Sense Harness (422188 and 422189) is also required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from the
unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator.
Failure to rewire will result in battery charger fault.
• Tighten M10 alternator hardware to 23 N•m (17 ft-lb). 8. Secure all wiring with band wraps.
• Tighten M8 alternator hardware to 30 N•m (22 ft-lb). 9. Close and secure all doors.
71
S-600M Model 50 - (230 and 460 Volt) Alternator 40-1264
IMPORTANT: Your unit must already be equipped with a Battery Charger to install the supplemental power package.
Sense Harness (42-975 or 42-976) is also required and must be ordered separately.
DANGER: To prevent serious injury or death, switch the unit controls to the OFF position and remove the Positive (+) battery cable from the
unit’s battery. Disconnect the remote power supply at its source and remove power cable from unit (if applicable).
IMPORTANT: Disconnect any liftgate or auxiliary items from the unit battery or charging system and rewire them to the supplemental alternator.
Failure to rewire will result in battery charger fault.
73
Reconfiguring the SR4 Controller / Trouble Shooting
74
Liftgate Charger Wiring Requirements
Additional kits or individual components (not supplied) are required to complete liftgate battery
charging applications. Contact your Thermo King dealer for available kits.
For safety under all conditions especially high ambient and high load or fault conditions, Thermo King Recommends:
• Liftgate battery charging battery cables to be 2 gauge cross linked polyethylene wire per SAE J1127 Type SGX insulation rating 125C (257F).
• Liftgate battery charging battery cables be protected in a metal conduit per National Electric Code. Plastic conduit is not acceptable unless it is rated to
125C (257F).
• Only the positive, negative and battery sense cables can be run in the same conduit. These wires must also have an insulation rating of 125C (257F).
Do not run the fuel pump power, the fuel level sensor wires, or the fuel lines through the same conduit.
• Positive cable to be equipped with a 100 amp slow blow fuse.
75
TK-55681-11-IM January 2020
Revision 9
Installation Manual
Thermo King – by Trane Technologies (NYSE: TT), a global climate innovator – is a worldwide leader in sustainable
transport temperature control solutions. Thermo King has been providing transport temperature control solutions
for a variety of applications, including trailers, truck bodies, buses, air, shipboard containers and railway cars since
1938. For more information, visit www.thermoking.com or www.tranetechnologies.com
Thermo King has a policy of coninuous product and data improvements and reserves the right to change design and specifications without notice. We are
committed to using environmentally conscious print practices.