You are on page 1of 26

ELECTRICAL Materials DIV.

16 - RCJ
Material Status in RCJ Project

# Material Supplier's Name Action Code Remarks


1 EARTHING & Light. Protection BAHRA Code 1 we sent letter to PD
ELECTRIC house Code 1 we sent letter to PD
2 Rigid Steel Conduits & Fittings
ABK Code 1 we sent letter to PD
BAHRA Code 1 we sent letter to PD
3 EARTHING & Grounding Cables
Elswedy Code 1 we sent letter to PD
4 Warning Tapes ELFIT Code 1 we sent letter to PD
5 PECD PIPES, ACCESSO. & Fittings NAT'L MKTG.EST.CO Code 1 we sent letter to PD
DECODUCT Code 1 we sent letter to PD
6 PVC Conduits & Fittcings
BAHRA Code 1 we sent letter to PD
7 Duct Spacesr BAHRA Code 1 we sent letter to PD
ELECTRIC house Code 1 we sent letter to PD
8 EMT Conduits & Fittings ABK (Fittings only) Code 1 we sent letter to PD
TABALSA ARABIA Code 1 we sent letter to PD
9 Steel Back Boxes for W.D. ABK Code 1 we sent letter to PD
ABK (Fittings only) Code 1 we sent letter to PD
10 Steel Flexable Conduits & Fittings
TABALSA ARABIA Code 1 we sent letter to PD

11 Square & Octagonal Steel Box ABK (RACO) Code 1 we sent letter to PD
ABK Code 1 we sent letter to PD
12 Pull/Junction Boxes
ALFAREED Stars Code 1 we sent letter to PD
13 Cable Trays Power Solution Code 1 we sent letter to PD

1 of 26
ELECTRICAL Materials DIV.16 - RCJ
Material Status in RCJ Project

# Material Supplier's Name Action Code Remarks


ABUNAYYAN Code 1 we sent letter to PD
14 Disconnect Switches
RADYA INT.(EATON) Code 1 we sent letter to PD
15 Manhole Covers Riyadh Foundary Code 1 we sent letter to PD
16 Elevators Hundai Code 1 we sent letter to PD
17 MV Cables BAHRA Code 1 we sent letter to PD
BAHRA Code 1 we sent letter to PD
18 LV Cables
ELSEWEDY Cables Code 1 we sent letter to PD
19 Bulding Wires BAHRA Code 1 we sent letter to PD
20 UPS System APEC Code 1 we sent letter to PD
21 Steel Poles for Street Lighting Fixtures ALBABTAIN Code 1 we sent letter to PD
22 Low Current Cales For fire alarm NORDEN Cables Code 1 we sent letter to PD
23 Wiring devices ALFANAR Code 1 we sent letter to PD
24 Under Floor Box Legrand Code 1 we sent letter to PD
25 Oil Transforemers STC Code 1 we sent letter to PD
Spectra Code 1 we sent letter to PD
26 Lighting Control System
Gulf ECHO Code 1 we sent letter to PD
27 Ring Main unit - RMU Lucy Electric Code 1 we sent letter to PD
28 Generators AKSA-STE Code 1 we sent letter to PD
29 ATS AKSA-STE Code 1 we sent letter to PD

2 of 26
ELECTRICAL Materials DIV.16 - RCJ
Material Status in RCJ Project

# Material Supplier's Name Action Code Remarks


approved Lighting fixtures items
# Description Status Remarks
1 Type I Code 1 Follow comments
2 Type IE Code 1 Follow comments
3 Type A Code 1 Follow comments
4 Type AE Code 1 Follow comments
5 Type C Code 1 Follow comments
6 Type CE Code 1 Follow comments
Remaining Lighting Fixtures TS
# Description Status Remarks
1 Type B Preparing Sub site deals direct with the supplier
2 Type BE Preparing Sub site deals direct with the supplier
30
3 Type G Preparing Sub site deals direct with the supplier
4 Type GE Preparing Sub site deals direct with the supplier
5 Type H Preparing Sub site deals direct with the supplier
6 Type HE Preparing Sub site deals direct with the supplier
7 Type J Preparing Sub site deals direct with the supplier
8 Type K Preparing Sub site deals direct with the supplier
9 Type L Preparing Sub site deals direct with the supplier
10 Type M Preparing Sub site deals direct with the supplier
11 Type F Preparing Sub site deals direct with the supplier
12 Type T Preparing Sub site deals direct with the supplier
13 Type V Preparing Sub site deals direct with the supplier
14 Type W Preparing Sub site deals direct with the supplier

3 of 26
ELECTRICAL Materials DIV.16 - RCJ
Material Status in RCJ Project

# Material Supplier's Name Action Code Remarks


Low current systems material satus - honeywell turkey limitted
Material Status Remarks
Data Network system Code 02 partial approval as a brand system but RC will
change the design
WiFI system - HAUWAI Code 1 we sent letter to PD
Master Clock system - bodet Code 03 requesting Rev 02 from supplier
security sytem ( Access control & IP CCTV ) Code 04 requesting Rev 02 from supplier
31
Structure Cabling system - R&M Code 03 Rev01 is Under review
IP Telephony not submitted yet supplier delayed much time
MATV System not submitted yet supplier delayed much time
Puplic Address System not submitted yet Rev 00 is ata site since 18/10/2021
Fire alarm system Code 02 Rev 01 is under review
BMS Code 03 Requisting Rev01 from the supplier

4 of 26
Non Approved Material in RCJ Project - Electrical
# Material # Supplier's Name Action Code Status of TS Remarks

1 ABK - MK Code 2 At Site Rev02


1 Under Floor Trunking
2 Electric House - LEGRAND Code 2 At Site Rev02
3 EMT Conduits 1 ABK -Panasonic Code 3 At Site REV01
1 ALFANAR Code 3 Preparing Resub. Supplier working on it
4 Ring Main unit
2 LUCY Electric Code 1 sent at site on 27/01/2021
1 CUMMINS Code 2 Preparing Resub.
5 Generators
2 AKSA-STE (CUMMINS) Code 2 Under review Rev02

we contacted Engr. Shady today and will arrange


1 ALFANAR Code 3 Preparing Resub. meeting ASAP to check all open casses related to
ALFANAR like RMU, tranformers & Panels.
6 Oil Transformers
2 STC Code 3 Preparing Resub. Supplier delayed much time we request Rev02 Since
22/12/2020
3
1 ABK - GE Code 2 Preparing Resub. supplier not Cooperative , 7 reminders now
7 Automatic transfer Switch
3 AMFCO Code 2 Under review sent on 3/3/2021
2 ALFANAR - Preparing Sub they working on it

ACB & MSB is under review , supplier request for PO


3 AMFCO Under review At Site or LOI to provide factory shop dwg, we sent letter to
8 LV Switchboards,Panelboards Purchasing department and still pending.

supplier request for PO or LOI to provide factory shop


4 NCM - SCHNIDER Hold dwg, we sent letter to Purchasing department and still
pending.

9 Lighting Fixtures,indoor & Outdoor 1 National Lighting Code 3 Under review We send type I & IE on 29/12/2020 , also outdoor
lighting fixtures was sent to the site.

5 of 26
Non Approved Material in RCJ Project - Electrical
# Material # Supplier's Name Action Code Status of TS Remarks

10 Lighting Control System


1 Spectra - EATON Code 1
3 Gulf ECHO Code 2 Under review
11 Structured Cabling System 3 HBS - Under review Supplier working on it

12 2 HBS - Under review They will send by this week , UPS TS for data and
comm. Racks & Data network TS.
13 UPS for data network 1 HBS - Preparing sub Preparing as per RC Requierments
14 TV System 1 HBS - Preparing sub
1 HBS - Preparing Sub Supplier working on it
15 Puplic Address 2
3
1 HBS - Preparing Sub Supplier working on it
16 Access Control 2
3

1 HBS - Bodet - Preparing Sub the supplier will revise the TS as per RC requierments
17 Master Clock System
3
1 HBS - Preparing Sub Supplier working on it
18 IP CCTV System 2
3
1 HBS - Preparing Sub prepare the revised
19 Fire Alarm System 2
3

20 Low Current Cables for MATV 1 SAUDI Media (FRACARRO) At Site Hold by FTCO will be submitted along with the submittal of the MATV

6 of 26
Pending Materials At site
# Description Supplier / Manufacturer Code TS Status Remarks
preparing REV02 and will update as soon as receive feedback from supplier
1 Under Floor Trunking ABK - MK Code 2 Preparing Resub.

already approved by Lucy


2 Ring Main unit ALFANAR Code 3 Preparing Resub.

already approved by AKSA


3 Oil Transformers ALFANAR Code 3 At Site

ABK - GE Code 2 Preparing Resub. supplier delayed much time to submit Rev0, already approved by EMAFCO ABB

4 Automatic transfer Switch


STE - At Site already approved by EMAFCO ABB

ALFANAR - under review sent ACB,DP,MDP,MCC,PP,SLP&LP TS REV00 at site


5 LV Banel Boards AMFCO Code 3 Preparing Resub. supplier preparing response on comments
NCM - SCHNIDER Hold - LOI Stage

6 Structure Cabling System HBS Code 3 At Site the TS is at site and the sample board too

7 Fire Alarm System HBS Code 2 At Site as per log sheet, not submitted yet however we sent at site since 18/5/2021

8 Data network HBS Code 2 Hold RC team will prepare a new design, the HAUWAI sytem is approved

9 Ligthing Fixtures NATIONAL Lighting At Site the site is deal direct with the supplier
Low Current System - TS Status
# Description Supplier Status
1 UPS for data network HBS Preparing sub
2 TV system HBS Preparing sub
3 Puplic Address HBS Preparing sub
4 Access Control HBS At Site
5 Master Clock System HBS Preparing Sub
6 IP CCTV System HBS At Site

Interior Lighting Fixtures TS


# Description Supplier Status
1 Type I NLC Code 1
2 Type IE NLC Code 1
3 Type A NLC Code 1
4 Type AE NLC Code 1
5 Type B NLC Preparing Sub
6 Type BE NLC Preparing Sub
7 Type C NLC Code 1
8 Type CE NLC Code 1
9 Type G NLC Preparing Sub
10 Type GE NLC Preparing Sub
11 Type H NLC Preparing Sub
12 Type HE NLC Preparing Sub
13 Type J NLC Preparing Sub
14 Type K NLC Preparing Sub
15 Type L NLC Preparing Sub
16 Type M NLC Preparing Sub
17 Type F NLC Preparing Sub
18 Type T NLC Preparing Sub
19 Type V NLC Preparing Sub
20 Type W NLC Preparing Sub

Outdoor Lighting Fixtures TS


# Description Supplier Status
1 Type L1 NLC Submittal At site
2 Type L4 NLC Submittal At site
3 Type L5 NLC Submittal At site
4 Type L7 NLC Submittal At site
5 Type L8 NLC Submittal At site
6 Type L9 NLC Submittal At site
7 Type L10 NLC Submittal At site

LV Panel Boards TS
# Panel Type Supplier Status
1 ACB EMAFCO At Site
2 MSB EMAFCO At Site
3 DP EMAFCO Preparing Sub
4 MDP EMAFCO Preparing Sub
5 SLP EMAFCO Preparing Sub
6 TEB EMAFCO Preparing Sub
7 PP EMAFCO Preparing Sub
em - TS Status
Remarks

g Fixtures TS
Remarks
Follow comments
Follow comments
Follow comments
Follow comments

Follow comments
Follow comments

g Fixtures TS
Remarks
oards TS
Remarks
MADINAH HAJJ CITY - PACKAGE 1
ELECTRICAL MATERIAL READY FOR MANUFACTURING
Discipline: ELECTRICAL Date: October 17, 2016
S. Item Description Supplier's Name Material Status Status for Manufacturing
No.
MV SWITCHGEAR AL FANAR APPROVED

METERING RING MAIN UNIT AL FANAR APPROVED INITIAL APPROVAL - SEC DATA REQUIRED

SECONDARY UNIT SUBSTATION Al FANAR APPROVED INITIAL APPROVAL - SUBJECT TO SEC APPROVAL

TRANSFORMER AL FANAR APPROVED

MV VARIABLE FREQUENCY DRIVE ZAMIL (ROCKWELL) APPROVED

GENERATORS ZAHID TRACTOR APPROVED


(MODEL C18) (CATERPILLAR)
AUTOMATIC TRANSFER SWITCHES
(ATS) ABDULKARIM (GE) APPROVED

UPS INDOOR ABDULKARIM (SCHNEIDER) APPROVED INITIAL APPROVAL (IP RATINGS)

CENTRAL BATTERY SYSTEM & EXIT


LIGHTS SAUDI LIGHTING (CEAG) APPROVED

DISCONNECT SWICTHES ABDULKARIM (GE) APPROVED BOQ/RATING AS PER SITE REQUIREMENTS

WIRING DEVICES -
POWER SOCKET OUTLETS AND AL FANAR (CONTACTUM) APPROVED BOQ AS PER SITE REQUIREMENTS
LIGHTING WITCHES
WIRING DEVICES - ABDULKARIM (HONEYWELL) APPROVED BOQ AS PER SITE REQUIREMENTS
TYPE R15
WIRING DEVICES -
INDUSTRIAL SOCKET OUTLETS ELECTRIC HOUSE (LEGRAND) APPROVED BOQ AS PER SITE REQUIREMENTS
TYPE R41 & R45
WIRING DEVICES - INITIAL APPROVAL - APPROVED MODULE FROM
TELECOMMUNICATION OUTLET AL FANAR (CONTACTUM) APPROVED APPROVED STRUCTURED CABLING
(FACE PLATES & FRAMES ONLY)

MAGNETIC MICRO SWITCH ABDULKARIM (HONEYWELL) APPROVED BOQ AS PER SITE REQUIREMENTS

FLOOR BOXES AND ACCESSORIES ABDULKARIM (MK) APPROVED INITIAL APPROVAL - SUBJECT TO THE NEXT
REPLY TO COMMENTS & SAMPLE
TT1 - LANDSCAPE LIGHTING POLE INITIAL APPROVAL - SUBJECT TO CALCULATION
AND FIXTURE AL NASSER APPROVED AND SAMPLE APPROVAL
STREET LIGHTING POLES AND
LUMINAIRES AL BABTAIN APPROVED INITIAL APPROVAL - SAMPLE APPROVAL

LIGHTING CONTROL SYSTEM ARENCO (SCHNEIDER) APPROVED

CLOCK SYSTEM AL SANIE (BODET) APPROVED INITIAL APPROVAL - REPLY TO COMMENTS

ELECTRICAL MANHOLE & HAND


HOLE COVERS IMDAD (DUCAST) APPROVED INITIAL APPROVAL - SUBJECT TO SAMPLE

PRECAST CONCRETE MANHOLE SULB AL JAZEERA APPROVED INITIAL APPROVAL - SUBJECT TO SAMPLE
AND HAND HOLE
LOW CURRENT CABLES -
FIBER OPTIC CABLE FOR MV MEFC APPROVED INITIAL APPROVAL - SUBJECT TO SEC APPROVAL
NETWORK

POWER SMART (BT CABLES) APPROVED BOQ AS PER SITE REQUIREMENTS

LOW CURRENT CABLES -


FIRE ALARM CABLES ANIXTER (PRYSMIAN) APPROVED BOQ AS PER SITE REQUIREMENTS

14 of 26
MADINAH HAJJ CITY - PACKAGE 1
ELECTRICAL MATERIAL READY FOR MANUFACTURING
Discipline: ELECTRICAL Date: October 17, 2016
S. LOW CURRENT CABLES -
Item Description Supplier's Name Material Status Status for Manufacturing
No. FIRE ALARM CABLES
CONTROL LINK (NORDEN) APPROVED BOQ AS PER SITE REQUIREMENTS

LOW CURRENT CABLES - RASA (BELDEN) APPROVED BOQ AS PER SITE REQUIREMENTS
LIGHTING CONTROL

APPROVED
UNDER REVIEW
NOT APPROVED
NO SUPPLIER

15 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
2 METERING RING MAIN UNIT 1 AL FANAR 16-NOV-15 APPROVED

1 ELSEWEDY APPROVED

3 TRANSFORMER 2 AL FANAR 16-NOV-15 NOT APPROVED

1 AL KHORAYEF (CUMMINS) 20-MAR-16 CODE C - NEW QUOTATION


WITH PROCUREMENT/CONTRACTS

7 GENERATORS 2 SASCOM (CUMMINS) 20-MAR-16 CODE D - REJECTED

1 KONE APPROVED

8 ELEVATORS 2

1 L&T EMAIL NOT APPROVED CONSULTANT COMMENTS - NO DATE


5-APR-16 SUPPLIER NOT SUBMITTING

9 LOW VOLTAGE MAIN 2


DISTRIBUTION BOARDS (MDB)

1 L&T EMAIL NOT APPROVED CONSULTANT COMMENTS - NO DATE


5-APR-16 SUPPLIER NOT SUBMITTING

10 MOTOR CONTROL CENTER & 2


STARTERS (MCC)

16 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
10 MOTOR
No.
CONTROL
Item
STARTERS (MCC)
CENTER &
Description
No.
Supplier's Name L.O.I Date Material Status Remarks

17 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
EMAIL CONSULTANT COMMENTS - NO DATE
1 L&T 5-APR-16 NOT APPROVED SUPPLIER NOT SUBMITTING

11 MOTOR CONTROL PANELS (MCP) 2

* ABB CONFIRMATION LETTER THAT FAT TEST WILL


BE CONDUCTED ON ABB PREMISSES
EMAIL * SEISMIC PROTECTION TEST CERTIFICATE
1 L&T 5-APR-16 NOT APPROVED * CONTROL AND POWER SLD/DIAGRAMS
* HEAT DISSIPATION & VINTILLATION REQUIREMENTS
12 POWER FACTOR CAPACITOR * OVERALL WEIGHT OF EACH PANELS

1 L&T EMAIL NOT APPROVED CONSULTANT COMMENTS - NO DATE


5-APR-16 SUPPLIER NOT SUBMITTING

13 SYNCHRONIZATION PANEL 2

EMAIL CONSULTANT COMMENTS - NO DATE


1 L&T 5-APR-16 NOT APPROVED SUPPLIER NOT SUBMITTING

14 DISTRIBUTION PANEL (DP) 2

18 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
EMAIL CONSULTANT COMMENTS - NO DATE
1 L&T 5-APR-16 NOT APPROVED SUPPLIER NOT SUBMITTING

15 FINAL BRANCH PANELS (LP & PP) 2

EMAIL CONSULTANT COMMENTS - NO DATE


1 L&T 5-APR-16 NOT APPROVED SUPPLIER NOT SUBMITTING

16 FEEDER PILLAR 2

1 SESCO (ASCO) 21-OCT-15 APPROVED

AUTOMATIC TRANSFER SWITCHES


17 (ATS) 2

1 APEC 2-FEB-16 NOT APPROVED CODE D - REJECTED

RETURNED To PROCUREMENT, REQUEST TO SUBMIT


18 UPS - INDOOR 2 HSB (RIELLO AROS) 25-JAN-16 NOT APPROVED APC-SCHNEIDER ABDULKARIM
EMDAD/AS/FTCO/1278, Dated 9-Oct-16
MODERN COMMUNICATION TYPE TEST CERTIFICATE
3 (CTECH) 15-FEB-16 NOT APPROVED To BE SUBMITTED ON 25-OCT-16

1 SAUDI LIGHTING (CEAG) 16-FEB-16 APPROVED

19 CENTRAL
LIGHTS
BATTERY SYSTEM & EXIT 2

19 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. SYSTEM & EXIT Supplier
19 CENTRAL
No. LIGHTS
BATTERY
Item Description
No.
Supplier's Name L.O.I Date Material Status Remarks

1 ABDULKARIM (GE) N/A APPROVED

20 DISCONNECT SWICTHES 2

1 ELECTRIC HOUSE (LEGRAND) 23-DEC-15 NOT APPROVED CONSULTANT COMMENTS


WIRING DEVICES -
21 POWER SOCKET OUTLETS AND 2 ABUNAYYAN (SCHNEIDER) 10-MAR-16 CANNOT COMPLY
LIGHTING WITCHES
3 AL FANAR (CONTACTUM) APPROVED EXCEPT FOR S20 Weather Proof, R55 Shaver, R15

1 ELECTRIC HOUSE (LEGRAND) 23-DEC-15 APPROVED APPROVED: TYPE R31, 32, R41 & R45

22 WIRING DEVICES - 2 ABUNAYYAN (SCHNEIDER) 10-MAR-16 CANNOT COMPLY


INDUSTRIAL SOCKET OUTLETS

3 AL FANAR (CONTACTUM) NOT AVAILABLE IN CONTACTUM PRODUCT RANGE

FINAL APPROVAL SUBJECT TO THE APPROVAL OF


1 ELECTRIC HOUSE (LEGRAND) 23-DEC-15 APPROVED SAMPLE INCLUDING THE APPROVED DATA MODULE
FROM APPROVED STRUCTURED CABLING SUPPLIER
WIRING DEVICES - 2 ABUNAYYAN (SCHNEIDER) 10-MAR-16
23 TELECOMMUNICATION OUTLET
(FACE PLATES & FRAMES ONLY)
CONSULTANTS COMMENTS
3 AL FANAR (CONTACTUM) NOT APPROVED FINAL APPROVAL SUBJECT TO THE APPROVAL OF
SAMPLE INCLUDING THE APPROVED DATA MODULE
FROM APPROVED STRUCTURED CABLING SUPPLIER

20 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
1 ELECTRIC HOUSE (LEGRAND) N/A NOT IN THE LEGRAND PRODUCT RANGE

24 MAGNETIC MICRO SWITCH 2 ABDULKARIM (HONEYWELL) N/A APPROVED

3 AL FANAR (CONTACTUM) N/A NOT IN THE CONTACTUM PRODUCT RANGE

1 ELECTRIC HOUSE (LEGRAND) N/A NOT APPROVED CONSULTANT COMMENT - NO DATE


UNDER FLOOR TRUNKING SYSTEM
25 AND ACCESSORIES INCLUDING 2 ABDULKARIM (MK)
FLOOR BOXES
3 AL FANAR (CONTACTUM)

1 AL NASSER 25-MAY-16 NOT APPROVED CONSULTANT COMMENTS (ON HOLD, PRIORITIZE


IMDAD AS PER ENGR. UMAR)
FOR T1A.1 & T1A.2
26 INDOOR LIGHTING FIXTURES 2 IMDAD (LITETECH) 25-MAY-16 NOT APPROVED COMMENTS RECEIVED 16-OCT-16

1 AL NASSER 25-MAY-16 APPROVED

27 TT1 - LANDSCAPE LIGHTING POLE 2 IMDAD (ARCLIGHT) 25-MAY-16 UNDER REVIEW


AND FIXTURE

1 ARENCO (SCHNEIDER) 10-NOV-15 APPROVED

28 LIGHTING CONTROL SYSTEM 2

21 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
1

29 DATA COMMUNICATION 2
EQUIPMENTS

30 IP BASED TELEPHONY 2

ACTIVE COMMUNICATIONS AND


31 DATA PROCESSING EQUIPMENT 2

32 STRUCTURED CABLING SYSTEM 2

33 WIRELESS DATA NETWORK 2

22 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
1 INMAA TECHNOLOGIES (BOUYER) 04-OCT-16 NOT APPROVED UNDER PREPARATION - 13-OCT-16

34 PUBLIC ADDRESS SYSTEM 2

1 AL SANIE (BODET) 23-MAR-16 APPROVED

35 CLOCK SYSTEM 2

1 HSB 04-MAY-16 NOT APPROVED CONSULTANT COMMENTS - NO DATE

36 AUDIO VISUAL SYSTEM 2

CANNOT COMPLY, SUPPLIER IS NOT SUBMITTING


1 NAHLA AL-TAYEF (FRACARO) 17-FEB-16 NOT APPROVED RETURNED TO PROCUREMENT
EMDAD/AS/FTCO/1203, Dated 18-Aug-16

37 IP TV SYSTEM CODE D - REJECTED


2 CMT TECHNOLOGIES 6-JUN-16 NOT APPROVED RETURNED TO PROCUREMENT
EMDAD/AS/FTCO/1207, Dated 21-Aug-16

3 HSB 6-JUN-16 NOT APPROVED UNDER PREPARATION - NO DATE

38 ROOM MANAGEMENT SYSTEM 2

23 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description
38 ROOM MANAGEMENT SYSTEM Supplier's Name L.O.I Date Material Status Remarks
No. No.
3

1 IDEX 6-MAR-16 APPROVED

39 PARKING MANAGEMENT SYSTEM 2

1 BTC (HONEYWELL) AS PER ENGR. UMAR NOT APPROVED CONSULTANT COMMENTS - NO DATE
24-MAY-16

40 IP CCTV SYSTEM 2

AS PER ENGR. UMAR


1 BTC (HONEYWELL) 24-MAY-16 NOT APPROVED CONSULTANT COMMENTS - NO DATE

41 ACCESS CONTROL SYSTEM 2

1 REQUESTED SINCE 17-JUL-16


EMDAD/AS/FTCO/1159
ROAD BLOCKERS, GATE BARRIERS
42 & SECURITY SCREENING 2
EQUIPMENTS
3

1 ABDULKARIM (EDWARDS) UNDER REVIEW

43 FIRE ALARM SYSTEM 2

24 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
ItemSYSTEM
43 FIRE ALARM Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
3

25 of 26
MATERIAL SUBMITTAL STATUS REPORT - PACKAGE 2
Discipline: ELECTRICAL Date: October 17, 2016
S. Supplier
Item Description Supplier's Name L.O.I Date Material Status Remarks
No. No.
1 CONTROL LINK (NORDEN) EMAIL NOT APPROVED UNDER PREPARATION - THURSDAY, 13-OCT-16

44 LOW CURRENT CABLES - 2 AL RAJHI TELECOM (BT CABLES) EMAIL NOT APPROVED UNDER PREPARATION - NO DATE
FIRE ALARM CABLES

1 CONTROL LINK (NORDEN) EMAIL NOT APPROVED UNDER PREPARATION - THURSDAY, 13-OCT-16

45 LOW CURRENT CABLES -


PUBLIC ADDRESS 2 AL RAJHI TELECOM (BT CABLES) EMAIL UNDER PREPARATION - NO DATE

APPROVED 13
UNDER REVIEW 1
NOT APPROVED 18
NO SUPPLIER 8

26 of 26