AL DUR PHASE II

INDEPENDENT WATER AND POWER PROJECT

OWNER: CONTRACTOR:

TURN OVER PACKAGE – 0WJC-INTAKE SYSTEM 1

SUB SYSTEM:

1WAZ001 – INTAKE PUMP AND HYDRAULIC UNIT STREAM 1

AD2-C2-W0-WAZ01-QEE-SIS-00024
OWNER: CONTRACTOR:

TABLE OF CONTENTS
SECTION DESCRIPTION PAGE

1 ECC Package
1.1 Erection Completion Certificate
1.2 Reference Documentation
1.2.1 P&ID with system identified
1.2.2 ECC Battery Limits Definition
1.2.3 Functional Description and O&M Manuals List
1.2.4 Lay out identifying system area
1.2.5 Data Sheets
1.2.6 Single Line Diagram
1.2.7 Equipment List
1.2.7.1 Mechanical Equipment Lists
1.2.7.2 Electrical Equipment Lists
1.2.7.3 I&C Equipment Lists
1.2.8 Lines Lists
1.2.9 Valves Lists
1.2.10 Cables Lists
1.2.11 Codes and Standards List
1.3 Mechanical / Electrical / I&C Erection Documents
1.3.1 Mechanical Erection Documents

1.3.2 Electrical Erection Documents

1.3.3 I&C Erection Documents


Resulted from
1.4 Red Line Construction activity
( If available)

1.5 NCRs between EPC and Vendors


1.6 ECC PunchList
2 CCC Package
OWNER: CONTRACTOR:

2.1 PRE-COMMISSIONING PROTOCOLS


2.1.1 Pre-Commissioning Procedures
2.1.1.1 Mechanical Pre-Commissioning Procedures

2.1.1.2 Electrical Pre-Commissioning Procedures

2.1.1.3 I&C Pre-Commissioning Procedures

2.1.2 Calibration Certificates


2.1.3 Completed and Signed Protocols
2.1.3.1 Mechanical Completed and Signed Protocol

2.1.3.2 Electrical Completed and Signed Protocol

2.1.3.3 I&C Completed and Signed Protocol

2.2 COMMISSIONING PROTOCOLS


2.2.1 Commissioning Tests Procedures
2.2.2 Commissioning Tests Reports
2.2.3 Calibration Certificates (if applicable)
2.2.4 Commissioning Completion Certificates CCC signed
3 FUNCTIONAL TEST PROTOCOLS: Performance & Reliability Tests

3.1 Reliability and Performance Test Procedures

3.2 Reliability and Performance Test reports

3.3 Calibration Certificates

3.4 Test Calculation Sheets(if applicable)

4 TURN-OVER PUNCHLIST

4.1 PunchList
Provided within thirty (30)

5 RED LINE/AS BUILT DRAWINGS days after Provisional

Acceptance.

5.1 Red line / As built drawing


6 TOP Transfer Certificate

6.1 TOP Transfer Certificate


OWNER: CONTRACTOR:
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.ECC Package

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.1 Erection Completion Certificate

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II INDEPENDENT WATER AND POWER PROJECT


ERECTION COMPLETION CERTIFICATE

Construction turn over to Commissioning the following system:

System

ECC No.

Date

EPC Construction Manager EPC Quality Manager

Name and date

Signature

ECC package documentation list attached:

Commissioning acceptance:
EPC Commissioning
Acceptance Partial acceptance Rejection
manager

Name and date

Signature

Owner review and comments:


OWNER: CONTRACTOR:

Name/Signature/date

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2 Reference Documentation

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.1 P&ID with system identified

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.2 ECC Battery Limits Definition

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

ECC Battery Limits Definition


ITEAM Description KKS Code Drawing No.

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.3 Functional Description and O&M manuals list

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.4 Lay out identifying system area

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.5 Data sheets

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.6 Single Line Diagram

ECC PACKAGE NAME

ECC PACKAGE CODE


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.7 Equipment Lists

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

List of Equipments
ITEAM NAME of Equipment KKS Mark

1 DISTRIBUTION BOARD WEA-DB-LP-N-002

2 DISTRIBUTION BOARD WEA-DB-LP-N-003

3 DISTRIBUTION BOARD WEA-DB-LP-E-002

4 48W, 6800 LM, 4000K LED LIGHT FIXTURE, IP 65 N/A


48W, 6800 LM, 4000K LED LIGHT FIXTURE, IP 65
5 N/A
WITH EMERGENCY PACK
6 100W LED FLOOD LIGHT N/A

7 15W LED BULKHEAD LIGHT N/A


13A SPN TWIN SWITCHED SOCKET OUTLET –METAL
8 N/A
CLAD
3P+N+E SURFACE MOUNTED INDUSTRIAL SOCKET
9 N/A
OUTLET-16A, 415V IP65
10 20A 1 GANG 1 WAY SWITCH-METAL CLAD N/A

11 20A 1 GANG 2 WAY SWITCH-METAL CLAD N/A


OWNER: CONTRACTOR:

12 20A 2 GANG 2 WAY SWITCH-METAL CLAD N/A

13 13A SPN SINGLE SWITCHED SOCKET IP 65 N/A

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.8 Lines List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

List of Lines
ITEAM NAME of Instruments KKS Mark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.9 Valves List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

List of Valves

ITEAM Line and Isometric description KKS Mark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.10 Cables List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.2.11 Codes and Standards List

ECC PACKAGE NAME


OWNER: CONTRACTOR:

ECC PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.3 Mechanical / Electrical / I&C Documents


OWNER: CONTRACTOR:

ECC PACKAGE NAME

ECC PACKAGE CODE

List of Electrical RFI


INSPECTION
ITEAM NAME RFI No.
STATUS
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS ACCEPTED
1 SPML-ALD-RFI-C-5714
AFTER ERECTION_LV SWITCHGEAR STREAM-1
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-6095 ACCEPTED
2
AFTER ERECTION_DCS ROOM STREAM-1
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-5844 ACCEPTED
3
AFTER ERECTION_DCS ROOM STREAM-2
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-6524 ACCEPTED
4
AFTER ERECTION_CORRIDOR
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-6886 ACCEPTED
5
AFTER ERECTION_MV SWITCHGEAR SREAM-1
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-7073 ACCEPTED
6
AFTER ERECTION_UPS ROOM
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-7127 ACCEPTED
7
AFTER ERECTION_LV COMMON ROOM
VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-7622 ACCEPTED
8
AFTER ERECTION_BATTERY ROOM
OWNER: CONTRACTOR:

VISUAL INSPECTION OF CABLE TRAY /LADDERS /CONDUITS SPML-ALD-RFI-C-8055 ACCEPTED


9
AFTER ERECTION_LV SWITCH GEAR STREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ LV SPML-ALD-RFI-C-5715 ACCEPTED
10
SWITCHGEAR STREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ DCS SPML-ALD-RFI-C-6096 ACCEPTED
11
ROOM STREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ DCS SPML-ALD-RFI-C-5843 ACCEPTED
12
ROOM STREAM-2
13 VISUAL INSPECTION OF CABLES AFTER LAYING_ CORRIDOR SPML-ALD-RFI-C-6523 ACCEPTED

VISUAL INSPECTION OF CABLES AFTER LAYING_ MV SPML-ALD-RFI-C-6884 ACCEPTED


14
SWITCHGEAR SREAM-1
VISUAL INSPECTION OF CABLES AFTER LAYING_ UPS SPML-ALD-RFI-C-7074 ACCEPTED
15
ROOM
VISUAL INSPECTION OF CABLES AFTER LAYING_ LV SPML-ALD-RFI-C-7125 ACCEPTED
16
COMMON ROOM
VISUAL INSPECTION OF CABLES AFTER LAYING_ BATTERY SPML-ALD-RFI-C-7621 ACCEPTED
17
ROOM
VISUAL INSPECTION OF CABLES AFTER LAYING_ LV SWITCH SPML-ALD-RFI-C-8056 ACCEPTED
18
GEAR STREAM-1
VISUAL INSPECTION AFTER ERECTION_ LV SWITCH GEAR SPML-ALD-RFI-C-5713 ACCEPTED
19
STREAM-1

List of Electrical RFI


INSPECTION
ITEAM NAME RFI No.
STATUS
VISUAL INSPECTION AFTER ERECTION_ DCS ROOM SPML-ALD-RFI-C-6094
20 ACCEPTED
STREAM-1
VISUAL INSPECTION AFTER ERECTION_ DCS ROOM SPML-ALD-RFI-C-5842 ACCEPTED
21
STREAM-2
22 VISUAL INSPECTION AFTER ERECTION_ CORRIDOR SPML-ALD-RFI-C-6525 ACCEPTED

VISUAL INSPECTION AFTER ERECTION_ MV SPML-ALD-RFI-C-6885 ACCEPTED


23
SWITCHGEAR SREAM-1
24 VISUAL INSPECTION AFTER ERECTION_ UPS ROOM SPML-ALD-RFI-C-7072 ACCEPTED

VISUAL INSPECTION AFTER ERECTION_ LV SPML-ALD-RFI-C-7126 ACCEPTED


25
COMMON ROOM
VISUAL INSPECTION AFTER ERECTION_ BATTERY SPML-ALD-RFI-C-7620 ACCEPTED
26
ROOM
VISUAL INSPECTION AFTER ERECTION_ LV SWITCH SPML-ALD-RFI-C-8057 ACCEPTED
27
GEAR STREAM-1
VISUAL INSPECTION OF LOCAL CONTROL PANEL SPML-ALD-RFI-C-7710 ACCEPTED
28
AFTER ERECTION_WEA-DB-LP-N-002
OWNER: CONTRACTOR:

VISUAL INSPECTION OF LOCAL CONTROL PANEL SPML-ALD-RFI-C-7711 ACCEPTED


29
AFTER ERECTION_WEA-DB-LP-N-003
VISUAL INSPECTION OF LOCAL CONTROL PANEL SPML-ALD-RFI-C-7712 ACCEPTED
30
AFTER ERECTION_WEA-DB-LP-E-002
LIGHTING CIRCUIT AND SOCKET OUTLETS, SPML-ALD-RFI-C-7783 ACCEPTED
31 INSULATION RESISTANCE, EARTH CONTINUITY AND
POLARITY CHECKS_WEA-DB-LP-N-002
LIGHTING CIRCUIT AND SOCKET OUTLETS, SPML-ALD-RFI-C-7784 ACCEPTED
32 INSULATION RESISTANCE, EARTH CONTINUITY AND
POLARITY CHECKS_WEA-DB-LP-N-003
LIGHTING CIRCUIT AND SOCKET OUTLETS, SPML-ALD-RFI-C-7785 ACCEPTED
33 INSULATION RESISTANCE, EARTH CONTINUITY AND
POLARITY CHECKS_WEA-DB-LP-E-002

List of I&C RFI


INSPECTION
ITEAM NAME RFI No.
STATUS
1

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.4 Red Line


(Resulted from Construction activity)
OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.5 NCRs between EPC and Vendors


OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

NCR List
Issued Closed
ITEAM Description NCR No. From To
date date
1

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

1.6 ECC PUNCHLIST

TOP PACKAGE NAME


OWNER: CONTRACTOR:

TOP PACKAGE CODE

ECC PUNCH LIST LOG SHEET


See Appendix 7.3 Master Punch list LOG of《AD2-C3-00-YDC-GGP-CON-00028 Project
Punch List Procedure》
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2. CCC Package

TOP PACKAGE NAME


OWNER: CONTRACTOR:

TOP PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.1 PRE-COMMISSIONING PROTOCOLS


OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

List of pre-commissioning procedures


ITEAM NAME procedure No. STATUS

5
OWNER: CONTRACTOR:

List of pre-commissioning protocols


INSPECTION
ITEAM NAME RFI No.
STATUS
1

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2 COMMISSIONING PROTOCOLS


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.1 Commissioning Test Procedures


OWNER: CONTRACTOR:

List of commissioning procedures


ITEAM NAME Procedure No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.2 Commissioning Test Reports


OWNER: CONTRACTOR:

List of commissioning test reports


ITEAM NAME RFI No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.3 Calibration Certificates (if applicable)


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

2.2.4 Commissioning Completion Certificates


OWNER: CONTRACTOR:

AL DUR PHASE II INDEPENDENT WATER AND POWER PROJECT


COMMISSIONING COMPLETION CERTIFICATE

System

TAG number

Date

Acceptance result The system and sub-system commissioning work are qualified completed.

SUPPORTING DOCUMENTATION:

Refer to Section 4.1 to 4.4 for the related documentation.


OWNER: CONTRACTOR:

Remark:

ISSUED BY EPC Commissioning EPC HAYA Commissioning


Engineer Commissioning Manager Manager
SIGNATURE

NAME

DATE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3. FOUNDATION TEST PROTOCOLS:


PERFORMANCE & RELIABILITY TESTS
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.1 Reliability and Performance Test Procedures


OWNER: CONTRACTOR:

List of Reliability and Performance Test Procedures


ITEAM NAME Procedure No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.2 Reliability and Performance Test Reports


OWNER: CONTRACTOR:

List of Reliability and Performance Test reports


ITEAM NAME RFI No. Remark

5
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.3 Calibration Certificates


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

3.4 Test Calibration Certificates(if applicable)


OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

4. TURN-OVER PUNCHLIST
OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE

MASTER PUNCH LIST LOG SHEET


See Appendix 7.3 Master Punch list LOG of《AD2-C3-00-YDC-GGP-CON-00028 Project
Punch List Procedure》
OWNER: CONTRACTOR:

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

5. RED LINE/ AS BUILT DRAWING

TOP PACKAGE NAME


OWNER: CONTRACTOR:

TOP PACKAGE CODE

AL DUR PHASE II
INDEPENDENT WATER AND POWER PROJECT

6. TOP Transfer Certificate


OWNER: CONTRACTOR:

TOP PACKAGE NAME

TOP PACKAGE CODE