Professional Documents
Culture Documents
Inspection of Storage Tanks: OISD - 129 Amended Edition
Inspection of Storage Tanks: OISD - 129 Amended Edition
Amended edition
FOR RESTRICTED
CIRCULATION
No.
OISD - STANDARD-129
First Edition, November 1988
Amended edition, August, 1999
1
2
OISD STANDARD - 129
First Edition, November 1988
Amended edition, August, 1999
FOR RESTRICTED
CIRCULATION
No.
Prepared by
COMMITTEE ON
INSPECTION OF STATIC EQUIPMENT
3
NOTES
4
FOREWORD
The Coordinator,
Committee on “Inspection of Static Equipment,
Oil Industry Safety Directorate,
2nd Floor, “Kailash”
26, Kasturba Gandhi Marg,
New Delhi – 110 001
5
COMMITTEE
ON
INSPECTION OF STATIC EQUIPMENT
List of Members
---------------------------------------------------------------------------------------------------------------------------
Name Designation & Position in
Organisation Committee
---------------------------------------------------------------------------------------------------------------------------
1. Sh. R.K. Sabharwal CMNM-IOC (R & P) Leader
6
INSPECTION OF STORAGE TANKS
CONTENTS
1.0 Introduction
2.0 Scope
3.0 Definitions
3.1 Atmospheric Storage Tanks
3.2 Low Pressure Storage Tanks
3.3 Types of Storage Tanks
3.3.1 Fixed Roof Tanks
3.3.2 Floating Roof Tanks
3.3.3 Fixed-cum-Floating Roof Tanks
3.3.4 Open Roof Tanks (Without Roof)
3.3.5 Horizontal Cylindrical Tanks
7
SECTION PAGE NO.
15.0 Documentation
15.1 Documentation for New Tanks
15.2 Documentation for Tanks in Service
8
SECTION PAGE NO.
16.0 References
ANNEXURES
9
INSPECTION OF STORAGE TANKS
10
3.3.5 Horizontal Cylindrical viii) To maintain proper maintenance and
Tanks inspection records and tanks history.
Horizontal cylindrical tanks are of two ix) To advise regarding schedules of tanks
types ; inspection and also statutory
requirement schedules.
(i) ABOVE GROUND TANKS
5.0 TOOLS REQUIRED FOR
Above ground tanks are mounted INSPECTION
horizontally above ground and are
approachable externally. Tools required in general for tank
inspection are as follows:
(ii) UNDER GROUND TANKS
i) Ultrasonic Thickness Meter
Underground tanks are placed in
earth, masonry or concrete pit and packed ii) Radiographic Equipment
around with sand, earth or clay leaving no
air space between the tank and the pit. iii) Dye Penetrate Kit
Inspection of tanks during fabrication shall be carried out as per the requirements of
the applicable codes, specifications, drawings etc. This inspection requires regular checks on
the work at various stages as it progresses.
i) Study of all the technical specifications and the code to which the tank is to be built.
v) Checking of painted underside of the bottom plate prior to these being laid.
vii) Checking of each batch of electrodes as per specifications and assurance of its use as per
suggested methods of their manufactures and codes.
ix) Evaluating spot radiography of butt welded annular (radial) joints and vacuum box test of
the portion of weld on the bottom plate on which shell is to be erected.
x) Checking of fit-ups and noting of curvature and plumb readings before and after welding of
the shell courses.
xi) Evaluating radiography of butt welded joints as per the applicable code.
xii) A thorough visual check and oil penetrate testing of the inside shell to bottom weld seam
before welding from outside.
xiv) Checking of set up of curb angle, roof trusses and roof plates prior to welding.
xvi) Checking of whether PWHT of clean out doors and shell nozzles, where applicable, have
been done. After PWHT & before hydro testing, all such weld joints shall be inspected
visually & MPI or DP tested. NOTE 1
i) Bottom tests with vacuum box/air test. I) Bottom Plate test with vacuum box/air test.
ii) Water fill-up/Hydraulic test (Atm/LP tanks) ii) Oil penetrate test of pontoon rims to bottom.
deck plate joint.
iii) Roof air test or Roof vacuum box test. iii) Vacuum box test of top deck plates.
iv) Rigidity/Collapsibility test (Vacuum test) iv) Pontoon air test/water test.
xxv) After the water fill-up test inspection of tank for any uneven excessive settlement.
DRG. NO.
LOCATION
PRODUCT STORED
TYPE OF TANK
CAPACITY
ERECTION CONTRACTOR
CHECK LIST
CHECKS REMARKS
3. Check that all examinations and tests have been carried out and
scrutinise the available records. Check whether PWHT is carried
out for clean out doors and nozzles wherever applicable.
6. Measure and record wall thickness of shell, bottom, roof & Nozzles
8. Check proper installation of seal between shell and tank roof (for
floating roof tank)
10. For floating roof tanks, check foam dam and foam system
wherever provided. For fixed roof tanks, check the functioning
of foam pourer lines and its connections with the tank wherever
provided.
11. Check and inspect internals, steam coils, float gauge, roof drains, etc.
14. Check that painting quality and coat thickness are as per
specification
15. Check that the required relief valves P&V, Valves and other tank
mountings are installed after proper resetting etc.
16. For emergency roof drains, check that water seal is maintained.
19. Check the tank earthing and megger the earthing cable.
The projecting out portion of the Entire tank shell shall be visually
bottom plates (annular plates) shall be scanned for signs of corrosion, pitting,
visually examined for any corrosion /thinning cracking etc. Findings of external
and ultrasonically gauged. inspection, service conditions and history will
be guiding factors for such observations. All
11.3 INTERNAL INSPECTION weld joints shall be examined carefully. The
vapour space and liquid level line are likely
Prior to internal inspection, an areas of corrosion. However, if the walls are
external inspection of the tank shall be done alternatively wet and dry or the contents are
as specified earlier. Before commencing the corrosive chemicals, the entire shell can be
internal inspection, the tank must be emptied attacked. The shell should be inspected
of liquid, freed of gases and cleaned out. from inside by erecting scaffolding/ladders at
For the tanks which have contained leaded four locations when severe corrosion is
petroleum products, it shall be ensured that found. The middle courses shall be closely
the tank has been thoroughly cleaned off examined for tanks containing light products
lead hazard and is safe for entry. Formal like gasoline and Naphtha. Thickness
entry permit from appropriate agency shall measurements with ultrasonic thickness
be taken before entering the tank. [For work meter shall be taken to supplement those
permits refer OISD-Std-105 (Work Permit measurements obtained from the outside.
System)].
11.3.3 Tank Bottom
11.3.1 Roof and Structural
Members After the tank has cleaned of its
sludge, it shall be visually inspected to
i) FIXED ROOF obtain the first indication of the condition of
the bottom.
Visual inspection and thickness
measurements of roof trusses and structural The tank bottom plates shall be
members shall be carried out. The visually inspected for pitting, corrosion and
supporting members shall be rejected when weld cracks. The weld joints shall be
the overall loss in thickness of material thoroughly cleaned and visually inspected
exceeds 25 per cent. The welds and bolts of for cracks or defects by magnifying glass
the structure shall be examined for wherever joints of shell and annular ring and
damage/loss. The results of measurements inspected for any leakage. Suspected
on the supporting structure may be recorded cracks may be identified by dye penetrate or
as shown in Fix.3 vacuum box testing. Depressions in the
bottom and in the areas around or under the
ii) FLOATING ROOF roof supports and the pipe coil supports shall
be checked closely. Any water that gets into
The underside and internals of the tank may collect and remain at these
floating roof shall be inspected for corrosion points thereby causing accelerated
and deterioration. The floating roof seals corrosion. Tanks bottoms shall be checked
shall be inspected from the underside. The thoroughly for thickness over the entire area.
legs and sleeved of the floating roof shall be This may be supplemented by hammer
checked for deterioration, bowing, and testing. The number of measurements to be
shifting. The dip pipe, centering and anti- taken will depend on the size of the tank and
rotational devices, emergency roof drain the degree of corrosion found. However,
pipe, free/breather vents, and rim vents, minimum three thickness readings per plate
shall be checked for any sign of should be taken. When severe corrosion
corrosion/thinning out. exists, more readings shall be taken in the
attacked areas to determine the minimum Drain sumps shall be carefully
remaining metal thickness. checked for cracks, pitting, leak in the weld,
and measured in particular when corrosion
Corrosion on the underside of flat at the underside of the tank bottom plates
bottom tanks resting on soil or on pads has been suspected/found.
cannot be checked from outside. From the
inside, the corrosion may be detectable by 11.3.5 Linings
hammering. Erratic readings with ultrasonic
thickness instrument are also indications of When the inside surface of a tank
underside corrosion. To carry out a positive are lined with corrosion resistant material
inspection and accurate check, it is such as sheet lead, rubber, organic and
recommended to cut out representative inorganic coatings, or concrete inspection
sections of coupons (at least 300 mm in shall be made to ensure that the lining is in
least dimension) of the bottom plate. The good condition, that is in proper position and
underside of the coupons shall be inspected. it does not have holes or cracks in the
If very severe corrosion is found, additional rubber lining as evidenced by bulging. A
coupons shall be removed from tank bottom holiday detector may be used to thoroughly
plate. The cut out opening in the bottom check the lining for leaks and holidays, care
plate shall be patch welded using fresh must be taken so that the test voltage does
material of appropriate thickness. The welds not approach a value that might puncture the
of the patch plate shall be tested with lining.
vacuum box. If tank is suspected leaking,
then the cutting operations shall be done Hardness testing of the rubber lining
under strict observations because of shall be carried out while inspecting the tank
possible entrapped hydrocarbons. internally.
A pit or a very small area reduced to Buckling of shell plates will always
the retiring thickness is however taken as occur in the upper half of the tank shell, as
not weakening the plate appreciably from the upper courses are thinner than the lower
the standpoint of resisting pressure. The courses.
average thickness, over a distance in a
longitudinal direction equal to 16 times the 12.2.2 Loading Conditions
minimum allowable thickness, is a good rule
to follow in establishing a plate thickness for Buckling of shell plates may occur
a corroded area. Repairs to such areas are when the stability of the tank shell is
required only to prevent leakages when insufficient to withstand one or the
corrosion progresses completely through the combination of the following loads:
plate. This average thickness can be
considered as the measured plate thickness. (a) Wind on the outside of the tank shell. For
open tope tanks also the wind load on the
inside of the tank shall be considered.
(b) Internal vacuum inside the tank due to be tested by applying internal air pressure
the setting of vacuum. also. The internal air pressure shall not
exceed the weight of the roof plates or 75
(c) Dead load of roof and supporting mm of water column. After application of air
structures. pressure, the joints are checked by soap
solution.
12.2.3 Method of Calculations
The roof integrity may also be
The stability of the corroded tank checked by creating internal vacuum inside
shell against buckling shall be controlled in fixed roof tanks. It is current practice to test
accordance with the calculation method the roof after construction at vacuum of 25
given is BS-2654-part 3 `Higher Design mm of water column. Vacuum is produced
Stresses'. by controlled draining of water after
hydrostatic test. The vacuum test shall be
It is then necessary to specify the done with utmost care and in no case shall
average thickness of the corroded shell vacuum exceed 25 mm of water column.
courses, especially of the upper half of the
tank shell. In the floating roof tanks, new
pontoon box welding should be checked by
It is also pointed out that: air and soap solution. Alternatively, these
may be checked by floating the roof of the
(a) Maximum wind gusts mostly result in a tank with water and checking the pontoon
wind load which is approx. 20% higher compartments for any leak.
than the wind loads specified in building
regulations. Experience has shown that 13.1.2 Weld Repair
the gust value must be applied in the
stability calculation for the shell. The weld repairs should be carried
out by gouging/grinding the leaky spot and
(b) Vacuum valves ordered with a vacuum welding. Repairs shall be inspected for their
setting of 65 mm water gauge often start integrity by vacuum box test/air test.
to open at 65 mm water gauge but are
fully open at 75 mm or 85 mm water 13.1.3 Repairs to Roof when Tank
gauge. is in Service
The higher value must be applied in the When deep pits in tank plates are
stability calculation for the shell. not closely spaced and extensive, and thus
do not affect the strength of the tank, they
13.0 METHOD OF REPAIRS AND can be repaired by other methods if welding
INSPECTION is not practicable. Any methods that will
stop the corrosion and plug the leaks will be
Method described hereunder for satisfactory. Filling with proprietary air-
repair are recommended ones. Other hardening adhesive may be suitable if it will
methods confirming to sound engineering not be affected by the tank contents. Any
practice may also be applied. These repair other material of a putty like nature that
methods have been outlined to highlight the hardens upon drying should be used only for
inspection required prior to, during and after temporary repair. Such material must be
repairs. able to tolerate the tank contents in addition
to making a tight bond with the steel plate.
13.1 ROOF REPAIRS In all cases the pits shall be cleaned
thoroughly.
13.1.1 Roof Replacement
Leaks in the roof are commonly
Entire or partial replacement of repaired by "Spot Patches" that don not
corroded roof plates shall be done with new involve cutting, welding, riveting or bolting of
plates of thickness as provided in the the steel. The soft patches can be made
original design. After replacement the from a variety of materials including canvas,
welding of the roof plates shall be checked asbestos, rubber, neoprene, glass cloth,
for leaks using vacuum box. The roof may FRP, FRE, Asphalt and Proprietary mastic
or Plastic sealing material, the choice of thickness provided in the original design.
depending upon the contents of the tank and The replacement plates can be taken in to
service conditions. The patches may be the tank through window cut in bottom shell
applied when tank is in service. The course. A new bottom may be laid on the
patches may be in much the same manner old bottom when it is not possible to take out
as normally applied to the roof a building. the old plates. This arrangement has been
shown in Fig. No. 4A, 4B and 4C. However,
The above are temporary methods by this arrangement, capacity of the tank will
of repair. Proper and permanent repairs be reduced. Nozzles and heating coils
shall be carried out at the earliest should be re-positioned on the renewed
opportunity. bottom as per the operational requirement.
v) Bottom layout and test results of the xi) Test certificates of seal.
bottom.
xii) Calibration charts.
vi) Heating coil layout and test results.
xviii) Foam system drawing. a) Tank inspection and repairs card (Ref.
Fig. 15.2.1)
xix) Cooling system drawing
b) Data Record History Card (Ref. Fig
xx) Wind girder drawings 15.2.2)
1. A person shall not go alone on the roof 3. No hot work shall be carried out inside
of storage tanks for inspection. the tank prior to gas freeing of the same.
No walking shall be done on the roof Hot work on bottom plates shall be done
plates where thinning/perforations are under strict supervision where perforation
observed. Necessary planking may be and/or leaks are observed.
provided for walking on such roofs.
Air test pressure shall NEVER exceed the
Ultrasonic thickness measurements shall specified limits.
not be carried out when the tanks is
receiving or dispatching. 4. All loaded tanks must be completely
shot blasted and thoroughly cleaned
Entry on to the deck of a floating roof shall before entering. API publication No.
be restricted when the floating roof is more 2015, 2015A, 2015B & 2202 shall be
than 5 metres below the top angle ring. referred for the storage tanks
containing loaded petroleum products.
2. H2s may be present inside the storage
tanks in hydrocarbon service. In case 5. Safety belts shall be worn while working
of floating roof tanks, H2S may be on Bosun's chair.
present above roof also. necessary
safety precautions shall be taken while
inspecting such tanks.
ANNEXURE - III