Professional Documents
Culture Documents
February 2022
Advanced Condition Monitoring of New and Upgraded Turbine Generators for Highly
Flexible Grid Demands Using Special Fibre Optic Sensors
Case study of dc-MMC interconnecting two HVDC lines with different grid topologies
Connecting two synchronous areas with an HVDC link: The NordLink interconnector
Rob Stephen
CIGRE Science & Engineering Editor-in-Chief
Welcome to this, the 24th edition of CSE, a Scopus registered (ISSN 2426-1335)
magazine which provides the following bene ts:
Despite the travel restrictions due to COVID, CIGRE managed to hold a symposium in
Ljubljana as well as a regional conference in South Africa. We therefore are very
pleased to be able to publish the best paper from the South African conference as
well as best papers from each of the Study Committees represented at the
Symposium. These papers, already peer reviewed, are published in CIGRE Science
and Engineering to acknowledge the work of the authors as well as to make their
work accessible to all stakeholders.
The topics are all very relevant to the industry at present. These include renewable
penetration, HVDC breakers, condition monitoring, a case study of connection of
HVDC lines with different topologies, information synergy, and an international
comparison of electrical clearances for overhead lines.
Authored papers (not included in the “best of” selection) include synthetic data
training for diagnosis, electric eld limits for composite insulators, a case study of an
HVDC link between two synchronous systems, frequency response from solar farms,
and analysis of virtual versus synchronous generators.
Authors are from utilities, manufacturers and academia. This provides both practical
and cutting edge research results for those studying the papers.
As can be seen from the above the papers are all extremely relevant and highly
technical covering information relating to most issues relating to power delivery
globally at present.
For those at the forefront of their area of expertise who wish to publish in CIGRE
Science and Engineering it is noteworthy that the review process is extremely
thorough. Reviewers are selected by the relevant Study Committee chairperson from
If you would like to publish in this prestigious, Scopus registered, magazine please
email Rob Stephen .
AUTHORS
Summary
South Africa is currently experiencing an increasing growth in installation of
embedded solar PV installations on the distribution grid. This is driven by a
reduction in installation and component costs coupled with increasing tariffs
resulting in an attractive nancial business case for customers who wish to reduce
their electricity bill. However, this poses a wide range of technical challenges for
Network Service Providers (NSPs). The conventional design of the distribution grid,
whereby unidirectional power ows from the generation source to the loads no
longer exists. Moreover, the lack of visibility of these installations makes it more
challenging for the development of planning and operational strategies. As it is the
responsibility of the NSP to maintain power quality, safety and network
reliability/stability for their customers, it is essential that the consequences and
potential cost implications brought about by increasing penetration of such
installations on the distribution networks is understood. This paper discusses some
of the signi cant impacts resulting from increasing penetration of solar PV on
distribution grids, mitigation measures for these impacts as well as possible cost
implications for the utility/NSP. Furthermore, recommendations are provided for
planning of future networks with increasing PV penetrations in South Africa.
KEYWORDS
1. Introduction
The technical challenges that were previously identi ed and can be associated with
high and undesirable SSEG penetration levels are:
Power ow uctuations,
Increased technical losses,
Overloading of equipment installed on the grid such as Medium Voltage (MV)/Low
Voltage (LV) transformers and cables,
Grid protection malfunction and
Voltage variation, unbalance and overvoltage.
The most signi cant impact stems from installing PV only at the end of the
networks for both case studies,
Overvoltage, voltage rise and rapid voltage changes/voltage variations are
experienced when installing PV. These impacts are increased as the PV
penetration increases and can have detrimental effects to the equipment that is
currently installed on the network,
Technical losses are decreased when installing PV on the constrained network for
all penetrations below 75% of peak load. However, for the unconstrained network,
the losses already start to increase by 40% penetration,
Equipment loading starts to worsen after 30% penetration for the constrained
network and worsens for any PV penetration in the unconstrained network and
The acceptable hosting capacity based on voltage and thermal loading impacts
was ~15% and ~30% of peak load for the constrained and unconstrained
network, respectively. This occurs in the case where the systems are
only installed at the end of the network. Furthermore, the voltage impacts on the
constrained feeder seems to be worse than for the unconstrained feeder.
Following the results from the case studies, this research aims provide insight into
the network management methods that can be adopted to overcome/alleviate
voltage and asset congestion impacts experienced when increasing PV penetration
in distribution networks.
The mitigation measures with associated locations are illustrated in Figure 1 below.
Details about some mitigation measures from Table 1 and its implementation is
discussed below. It must be noted that the technical solutions provided in the table
are, to a large extent, able to manage voltage violations; however, they are not always
able to effectively manage asset congestion issues. As such, [5] has propose a
combination of solutions, which will also be detailed in Section 2.10 below.
One of the major advantages to this solution is that it does not require any nancial
input from the utility. Furthermore, studies have proven that this solution is highly
effective at managing voltage violations, regardless of the type of network.
Figure 3 - Change in customer voltage that is created when adjusting all the off-load tap positions of
MV/LV transformers on a network [5]
The LV and MV conductors that could be considered for this option is tabulated in
Table 2 and Table 3, respectively.
Table 2 (left) - LV conductors to consider for augmentation of LV network [2, 4] / Table 3 (right) - MV
conductors to consider for augmentation of MV network [4]
When uprating the MV/LV transformers the upgrade of transformers with two
additional tap positions of 2.5% tap size can be considered [2].
Study [8] has indicated that the typical operation of the OLTC as mentioned above
may not be the most suitable as the target voltage is xed and this may result in the
voltage violations at the far end of the LV network. This is especially true for uneven
loads and generation from new technologies such as PV which may cause excessive
wear and tear on the tap changers. It was therefore recommended that an adaptive
control mechanism be considered when implementing this solution. This includes
which leveraging smart meter load data to actively calculate the target voltage.
OLTCs are not currently available for transformers below a certain rating [2].
However, [5] indicated that it is possible to retro t an existing transformer by adding
the active voltage control OLTC capability to it. The ones that were considered in the
studies reviewed had ±8-10% total voltage regulation capability [2, 5, 4, 10]. This
option provides mitigation for voltage issues caused by increasing PV, however, asset
congestion issues still remain a concern.
All the combination solutions were modelled for i) Long Rural (LR) – 692km total
length (incl. 194km Single Wire Earth Return (SWER) conductor),ii) Short Rural (SR) –
329km total length (incl. 54km SWER conductor), iii) Long Urban (LU) – 70km total
length (no SWER) and iv) Short Urban (SU) – 30km total length (no SWER); all 22kV
with pseudo LV networks. The results showed that combination solution 3, 4 and 6
works for all networks and can allow 100% PV penetration without any violations. No
other solutions worked at increasing the PV penetration on the long rural network,
however; option 1, 2 and 5 worked for the short rural and the long urban network
until 20% and 40% PV penetration.
3. Conclusion
Various measures to mitigate/alleviate the technical impacts of increasing PV
penetration on MV and LV networks have been unpacked in this report. It is evident
that no one solution is effective at solving the major issues brought about by
increasing PV penetration on distribution networks. The mitigation measures need
to be considered in conjunction with the PV penetration limits desired. It is
important to note that adjusting regulations for inverters, such as implementing
requirements with tailored Volt-Watt and Volt-Var settings, can allow for improved
quality of supply without any costs to the NSP/utility. The results from the studies
reviewed showed that with the implementation of smart inverters of these tailored
settings, PV penetration of up to 35% can be allowed in some distribution networks.
However, other impacts of high reactive power compensation on existing equipment
must be considered and fully understood prior to this change in regulation.
There are different solutions for different types of networks. There seems to be more
effective measures that exist for urban networks rather than rural networks. Study
[5] has shown that the solutions for rural networks are also much more expensive for
the same desired PV penetration level.
Network reinforcement and OLTC transformers are considered to have the highest
net- bene t for higher PV penetrations (>60%). The network reinforcement option
also seems to be the most effective at resolving asset congestion issues; whereas the
OLTC transformers options is most effective at resolving voltage issues.
It must be understood that the “do-nothing” option can signi cantly decrease the life
of existing plant and inadvertently cost the utility more money in the long run. There
is no doubt that increasing PV penetration leads to increasing grid voltage, thermal
loading and technical losses. These impacts cause network equipment to “run
South Africa does not currently have the aspiration of increasing PV penetration at
the distribution level due to concerns around asset congestion and voltage issues
experienced when doing so. However, it must be noted that these issues may already
be experienced with existing penetrations due to lack of visibility of installations as
well as poorly managed networks. In those cases, the mitigations measures from this
report can be explored as solutions. Furthermore, when South Africa does begin to
explore higher PV penetrations, the recommendations and mitigation measures
detailed in this report, along with applicable simulations, should be considered.
4. Recommendations
The following recommendations are proposed for a successful future utility with
increasing penetration of PV on the distribution grid [2, 4]:
1. It is imperative that the inverter standards, speci cally NRS 097-2-1, are
updated to ensure visibility on the LV network as well as promote smart inverters
with dynamic Volt-Watt and Volt-Var control.
2. Upgrade MV/LV transformers with additional buck taps in the off-load tap
changer during replacement activities.
3. Increase visibility on the LV networks, especially those that are starting to
experience increases in PV penetration. A start would be to install smart meters
at critical points on the LV networks to obtain data and to create LV network
drawings and power ow models for network planners to use in their studies.
This is predominantly for future planning activities as well as for the transition
into the eld of evaluating LV hosting capacity. Currently, the LV network has
been seen as a low priority for utilities but PV has changed this notion for
international Distribution Network Service Providers (DNSPs).
4. Consider and model other complementary mitigation measures such as the
combination solutions presented above. It was evident from the studies that no
one solution can assist with all the technical impacts introduced by increasing PV
penetration on the network.
5. Explore other operational modes for battery systems. The studies showed that
operation behind-the-meter BESS in self consumption mode did not really
mitigate the voltage issues on the network. Smarter solutions need to be
developed and implemented. This can also be informed by regulation and
incentives can be given to those who implement smarter batteries for the utility’s
bene t.
6. Consider demand control measures to alleviate the impacts of increasing PV on
the network. This could include active control of large loads in customer
premises in a smart way.
7. Consider the impact that Electric Vehicles (EVs) may have on the overall impact
in the future grid with increased penetration of PV.
Bibliography
1. A. Pandarum, “Impact of Increasing Distributed Solar PV Systems on Distribution
Networks in South Africa,” International Journal of Energy and Power
Engineering, vol. 15, no. 1, pp. 47-53, 2020.
AUTHORS
Summary
D ue to the observation of new stability challenges in the high penetration of
renewable energy resources in weak grids, there is a need for assets to stabilize
power systems. Synchronous Condensers (SynCons) are a well-known technology as a
system strength remediation. However, SynCons capital cost is a drawback for their
operation. Virtual Synchronous Generators (VSGs) are a new technology that can
mimic synchronous machines behaviour. Therefore, there is a need to investigate
and compare SynCons and VSGs performance in weak grid integration of renewable
energy resources. This paper investigates VSG's performance in weak grid
integration of a solar farm in a single machine in nite bus (SMIB) system. The VSG
performance is compared to a SMIB case with the utilization of a SynCon.
PSCAD/EMTDC is selected for time-domain analysis of the SMIB case, and all system
equipment is modelled in detail. Different Australian grid code tests are applied to
the SMIB system to evaluate the VSG and SynCon's impact. The simulation results
show that the VSG performs better than SynCon in the weak grid system and
improves stability.
KEYWORDS
Weak grid - Virtual Synchronous Generator - Synchronous Condenser - Network Stability - Australian
Grid Code - Grid Following - Grid Forming
To avoid curtailing maximum power extraction from solar farms in low strength
networks, one or a combination of fast-acting solutions such as Static VAR
Compensators (SVCs), Static Synchronous Compensators (STATCOMs), Synchronous
Condensers (SynCon), and grid-forming inverters (GFMI) with synthetic inertia
capability (virtual synchronous generator) should be considered as an additive to
those plants. Generally, the Virtual Synchronous Generator (VSG) can provide
additional features that can generate revenue if the ancillary market is available
apart from increasing network stability; in contrast, the former solutions can only
provide reactive power support.
This paper analyzes and compares two leading solutions, synchronous condenser
and virtual synchronous generator (VSG). Each solution's impact is investigated on
an actual Australian network scenario when a solar farm is connected to a low system
strength network. To compare a SynCon performance and a VSG performance in a
weak grid, different test scenarios are applied on a SMIB case with the SynCon and
the VSG. The test scenarios are selected based on the Australian grid code. The tests
include the large-signal tests, such as fault ride-through capability and small-signal
tests, such as voltage reference step change. The SMIB case is considered as a very
weak grid, which the solar farm cannot operate stably without any system
remediation techniques. Finally, the simulation is done in PSCAD/EMTDC software to
evaluate the VSG and SynCon performance.
Moreover, there are different reactive current injection requirements during voltage
dip or reactive current absorption for high voltage ride-through and speci c voltage
settling time for each IBR, challenging IBRs to comply with those rules. Also, IBRs
interaction with other installed IBRs in weak grids can cause stability issues.
Therefore, remediation assets to increase system strength such as SynCon and GFMI
are required. In Section 3, the SynCons and VSGs are described brie y as
remediation assets for IBRs operation in weak grids.
GFMIs in their standard forms are designed to respond based on droop functions.
Thus, standard GFMIs are unable to provide inertia. However, these GFMIs can be
equipped with synchronous generators (SG's) swing equation to provide synthetic
inertia, commonly referred to as virtual synchronous generators. Typically, GFMI can
be categorized as droop-based GFMIs, VSGs, and virtual-oscillation-control-based
GFMIs [15]. However, due to the popularity and diversity of VSG applications, this
work focuses only on VSG and its impact on system strength.
VSGs act as voltage-controlled sources in the power network and can increase inertia
to the network [16]. Thanks to their voltage-controlled control technology, VSGs can
be connected to an inverter-based resource (IBR) plant in weak grids to support
terminal voltage, similarly to SynCons. The installation of VSGs in a renewable
energy plant can be easily conducted by retro tting several existing GFLIs with the
VSG control, as that only requires rmware updates. Alternatively, larger VSGs with
equipped battery energy storage systems (BESSs) can be installed in weak parts of a
power system to support multiple IBRs in these areas [15]. The reactive power
amount used for regulating the IBR plant's terminal voltage can be provided by
VSGs' reactive power and voltage controls. Thanks to their voltage-controlled
operation, VSGs can offer terminal voltage support to an IBR plant in weak grids by
injecting/absorbing reactive power to/from the grid. Hence, excessive reactive power
extraction from the IBR plant for voltage control in low strength networks can be
avoided. Thus, the IBR plant has more headroom for active power control.
Moreover, VSGs have been theoretically proved to have a more robust response than
the conventional grid-following STATCOMs in weak grids [18, 19]. In addition, it has
been found that installations of VSG can enhance the grid strength viewed by nearby
IBR plants [18]. This feature makes VSG become a candidate for improving weak grid
stability challenges.
This section presents VSGs' strengths and weaknesses in supporting a solar farm
connected to a weak network. The advantages of VSGs can be summarized as follows.
1. The imbalance between demands and supplies in the power system might lead to
frequency deviations. Active power injection/absorption, also known as primary
reserve, is required from the plants to support the system frequency in these
scenarios. VSG's installation in IBR plants extends the plant's active power
absorbing or injecting capability due to the BESS attached to the VSGs' DC bus,
which means the VSGs enable the plant to provide a more signi cant
contribution to the frequency support [18]. However, this function is not
available in a SynCon due to the lack of a prime mover, while it has already been
up and running with the VSG control in several industrial projects [15]. Further
researches and developments are required to enable the operations of SynCon
with BESSs for the frequency support purpose.
For VSGs disadvantage, only low over-current capability compared to SynCons can
be considered. The over-current limitation is the thermal limits of the power
electronic switches (IGBTs) inside VSGs. As a result, the VSGs' over-current
capability is only 20%-40% of its rated current, which is much lower than the
counterpart of a SynCon [21].
The control diagram of the VSG can be found in Figure 3. P and Q in this gure are
the active and reactive power measured at the terminal of the VSG. ig,abc and ic,abc
are the grid-side current and the converter-side current of the LCL lter used in the
VSG, respectively. vc is the voltage across the capacitor of the LCL lter. The PWM
outputs drive the semiconductor switches inside the VSG. All control parameters of
the VSG can be found in Appendix I.
The simulation results of the tests in the test-bed SMIB are presented in the
following subsections. The improvements brought by SynCons and GFMIs on
enhancing the system strength and inertia are revealed. Performance comparisons
of the remediation assets are also detailed below.
4.1. Fault-Ride-Through
Two tests are applied on the SMIB case to compare the enhancements brought by the
SynCon and the VSG in terms of the FRT capability and the fault recovery. In the rst
test, a three-phase bolted fault, which is the most severe fault scenario, occurs at the
SF's PoC and lasts for 120 ms. The responses of the system in the three scenarios are
presented in Figure 3.
From Figure 3, the post-fault responses are signi cantly improved when either the
SynCon or the VSG is connected to the PoC. Without these ancillary devices, long
oscillatory transients in the PoC voltage, i.e., VPoC, the PoC active power, i.e. PPoC, and
its reactive power, i.e., QPoC, persist for almost 1.6 s after the fault clearance. In
addition, as shown in Figure 3(a), the spikes in VPoC exceeds 1.5 pu. These poor
Moreover, these poorly damped transients in the post-fault voltage can trigger the
SF's high-voltage ride-through (HVRT) function. This causes a mode cycling
behaviour when the SF keeps entering and exiting the HVRT mode. The transitions
between the normal operating mode and the HVRT mode of the inverters in the SF
can contribute to the inadequate transient responses.
With the presence of the SynCon, VPoC, QPoC are quickly dampened and settle 0.17 s
after the fault clearance, as shown in Figure 3(a). A voltage overshoot of 25% is
recorded in this case, which shows a noticeable improvement compared to the base
case. Moreover, thanks to the high overcurrent capability of the SynCon, a relatively
high amount of reactive power is generated to support the grid during the fault, as
shown in Figure 3(d). However, the SynCon results in the low-frequency oscillatory
transient in the power responses presented in Figure 3(b) and Figure 3(e). The
oscillation lasts for about 2 s after the fault clearance with the highest overshoot of
15 MW. The frequency of observed oscillation is around 1.6 Hz.
In the third scenario, the VSG is used for supporting the SF operation. The voltage
and the power responses are well-damped by the VSG. All the responses settle within
0.17 s after the fault clearance. The overshoot and settling time of VPoC are very
similar to those in the case where the SynCon is installed. Moreover, as depicted in
Figures 3(b) and 3(e), no power oscillation is recorded when the VSG is installed.
Because the frequency in Figure 3(f) rises above one pu after the fault clearance, the
VSG absorbs an amount of active power to tackle the frequency deviation. As a result,
the power responses are overshoot-free in this case, which shows a signi cant
improvement compared to the case with the SynCon.
In general, compared to the base case, the highest voltage overshoot reduces by a
factor of two and stably settles to the pre-fault condition with the presence of either
the SynCon or the VSG. Besides, the power overshoot and settling time in the case
with the VSG is only 1/6 and 1/12 of the counterparts in the case of the SynCon,
respectively.
The SMIB case is tested with a shallower fault to validate the robustness of the VSG.
In Figure 4, a fault occurs at 5 s and is cleared at 5.43 s, with a residual voltage of 0.5
pu. Similar to the previous case, without neither the SynCon nor the VSG, poor
transients are recorded in VPoC, PPoC, and QPoC. The peak voltage oscillation reaches
1.6 pu, which can trigger protection devices, leading to a disconnection of the SF
from the grid. Although the SynCon damps the voltage transient effectively, this
device pollutes the power responses with subsynchronous oscillations, eventually
damped after 1.3 s since the fault clearance. Finally, the VSG shows its effectiveness
in enhancing both the voltage and the power responses. The voltage and power settle
within 0.16 s with minimal oscillations and overshoots. In general, reductions of
eight times and ten times are recorded in the settling time and the overshoot of the
power response when replacing the SynCon with the VSG.
Overall, the VSG is superior in damping the poor post-fault transients, which the SF
experiences in weak grids. Furthermore, compared to the SynCon, the VSG provides
similar support in the voltage recovery while not generating the subsynchronous
Figure 4 - The responses of the system to a three-phase bolted fault at the PoC: (a) the PoC voltage, (b)
the active power transfer measured at the PoC, (c) the reactive power transfer measured at the PoC, (d)
the reactive power contributed by the remediation asset, and (e) the active power contributed by the
remediation, (f) the frequency at the PoC.
The test results are illustrated in Figure 5 and Figure 6. In Figure 5, at 5 s, a step fall
is applied to the POC voltage. Right after the disturbance, the voltages in all three
cases deviate from the reference. The lowest nadir is recorded in the case with the SF
only. In contrast, the SynCon and the VSG in the other two cases increase their
reactive powers, i.e., Qsupport, to tackle the disturbance resulting in shallower nadirs
in these cases. Similar behaviours are observed with the rising voltage disturbance
in Figure 6, where the SF's voltage deviation is restrained by the reactive power
compensations provided by either the SynCon or the VSG.
Figure 6 - The responses of the system to a step change from 1.0 pu to 0.95 pu in the PoC voltage: (a)
the PoC voltage, (b) the active power transfer measured at the PoC, (c) the reactive power transfer
measured at the PoC, (d) the reactive power contributed by the remediation asset, and (e) the active
power contributed by the remediation , (f) the frequency at the PoC
In general, the SF itself can smoothly transit to the new power setpoint with
negligible oscillations and overshoots. However, with the SynCon being active,
severe undamped oscillations occur in all the responses after the step change,
re ecting the system's unstable operation. The unstable behaviour of the SynCon is
because of its exciter interaction and the SF [12]. The peak-peak magnitude of the
active power oscillation is almost 80 MW. Additionally, the voltage persistently
uctuates between 1.06 pu and 0.96 pu. These responses will result in a
disconnection of the system from the grid in reality. These oscillatory behaviours are
not observed in the case with VSG activated. The VSG retains the smooth transition
of the SF and further restrain the voltage overshoot right after the step change
Figure 8 - The responses of the system to a step change from 0.85 pu to 0.65 pu in the active power
reference: (a) the PoC voltage, (b) the active power transfer measured at the PoC, (c) the reactive
power transfer measured at the PoC, (d) the reactive power contributed by the remediation asset, and
(e) the active power contributed by the remediation , (f) the frequency at the PoC
Without the SynCon and the VSG, severe oscillation is observed in the voltage
response even in the steady-state after the frequency ramp, which causes
oscillations in the SF's active and reactive power responses. The presence of the
SynCon helps dampen the voltage but, similarly to previous tests, pollutes the active
power response with low-frequency oscillations. The magnitude of the power
Figure 9 - The responses of the system to a frequency ramp from 50 Hz to 51 Hz at a rate of 2Hz/s: (a)
the PoC voltage, (b) the active power transfer measured at the PoC, (c) the reactive power transfer
measured at the PoC, (d) the reactive power contributed by the remediation asset, and (e) the active
power contributed by the remediation, (f) the frequency at the PoC
5. Conclusions
Due to a need for performance comparison between SynCons and VSGs in weak grid
integration of renewable energies, in this paper, the solar farm in the SMIB scenario
with low SCR at the PoC is modelled in PSCAD/EMTDC. Different Australian grid code
tests, such as frequency disturbance, voltage disturbance, reference active power
step, and fault ride-through capability, are applied in the system considering three
con gurations: with SynCon, with VSG, and without any asset. The simulation results
Aknowledgment
We acknowledge FIMER contribution by providing a PSCAD solar inverter model for
the purpose of this study.
References
1. P. Tielens, and D. Van Hertem, "The relevance of inertia in power systems,"
Renewable and Sustainable Energy Reviews, vol. 55, pp. 999-1009, 2016.
2. D. Kim, H. Cho, B. Park, and B. Lee, "Evaluating In uence of Inverter-based
Resources on System Strength Considering Inverter Interaction Level,"
Sustainability, vol. 12, no. 8, pp. 3469, 2020.
3. AEMO, "System Strength Impact Assessment Guideline," 2018.
4. S. Hadavi, M. Z. Mansour, and B. Bahrani, "Optimal Allocation and Sizing of
Synchronous Condensers in Weak Grids With Increased Penetration of Wind and
Solar Farms," IEEE Journal on Emerging and Selected Topics in Circuits and
Systems, vol. 11, no. 1, pp. 199-209, 2021.
5. M. Z. Mansour, S. P. Me, S. Hadavi, B. Badrazadeh, A. Karimi, and B. Bahrani,
"Nonlinear Transient Stability Analysis of Phased-Locked Loop Based Grid-
Following Voltage Source Converters Using Lyapunov's Direct Method," IEEE
Journal of Emerging and Selected Topics in Power Electronics, pp. 1-1, 2021.
6. Y. Cheng, S. Huang, J. Rose, V. A. Pappu, and J. Conto, "ERCOT subsynchronous
resonance topology and frequency scan tool development.", 2016 IEEE Power and
Energy Society General Meeting (PESGM), pp. 1-5.
7. W. Du, Q. Fu, H. Wang, and Y. Wang, "Concept of modal repulsion for examining
the subsynchronous oscillations caused by wind farms in power systems," IEEE
Transactions on Power Systems, vol. 34, no. 1, pp. 518-526, 2018.
8. R. Yan, T. K. Saha, F. Bai, and H. Gu, "The anatomy of the 2016 South Australia
blackout: A catastrophic event in a high renewable network," IEEE Transactions
on Power Systems, vol. 33, no. 5, pp. 5374-5388, 2018.
9. H. T. Mokui, M. A. Masoum, and M. Mohseni, "Review on Australian grid codes for
wind power integration in comparison with international standards." pp. 1-6.
AUTHORS
Summary
The vast majority of HVDC installations so far are of the point-to-point type, which
connects two points in an AC grid, or two AC grids, by a DC link. As HVDC becomes
more prevalent, it will be highly bene cial to start interconnecting HVDC links on the
DC side into multiterminal systems, and eventually, to form HVDC grids. This
reduces the number of needed converter stations radically, making HVDC more cost-
effective, as highly expensive converters are avoided. Also, power losses are
reduced. However, multiterminal HVDC requires access to reliable and fast DC circuit
breakers for fault clearing. The VSC-assisted resonant current (VARC) technology,
pioneered by SCiBreak, can combine these features at acceptable cost. Furthermore,
VARC ef ciently lends itself to modularization, whereby a breaker is assembled from
a number of identical series-connected breaker modules. This brings two important
bene ts. First, scalability in terms of voltage at minimum engineering effort is
obtained. Second, fault tolerance can be achieved by adding one or more redundant
breaker modules. In case one of the modules fail to operate, the remaining modules
can still interrupt the fault current.
Given the criticality of HVDC equipment for the electrical energy system, type testing
of components is of paramount importance. KEMA Labs in Arnhem, Netherlands
have set up an infrastructure in line with the latest standardization activities for
HVDC breaker testing, that uses low-frequency short-circuit generators to provide
fault currents similar to those in HVDC.
1. Introduction
The transition to a decarbonized electricity supply system calls for increased use of
HVDC power transmission. The best sites for renewable energy sources are often
located far from consumers. Often long cables need to be used, for instance in the
case of offshore wind power, and here the HVDC is the only choice since AC cables
cannot feasibly be made longer than approx. 100 km. Also, the variable nature of
renewables, such and wind and solar power, makes more long-distance transmission
necessary, so that the variability can be balanced out over a larger area.
As HVDC links become more prevalent it will become favorable to connect them into
multiterminal connections, that may eventually evolve into a DC grid. This can save
investment cost, since the number of costly converter stations can be reduced. In
addition, security of supply is improved since power can be routed in alternative
paths in case of a converter fault, for instance. However, in order for this to be
possible HVDC circuit breakers (CBs) need to be available as a mature technology at
feasible cost. Development efforts to this end have been made since the 1970s.
Recent endeavors include the hybrid HVDC CB[2]. It is based on using a mechanical
contact (an ultra-fast disconnector, UFD) for conducting the current in the normal
case, whereas power semiconductors are used for interruption. While this concept
has been shown to work well in lab tests, it is rather costly, as the power
semiconductors need to be dimensioned for both the full returning voltage and the
full fault current. To reduce cost, a mechanical breaking element, such as a vacuum
interrupter (VI) can be used instead. However, it needs a zero-crossing in the current
to stop conducting and start blocking voltage. Zero crossings are normally present in
any AC circuit, but to interrupt DC an arti cial zero crossing must be provided. An LC
resonant circuit connected in parallel with the VI, where the capacitor is initially
charged to high voltage, can be used to provide a current pulse that cancels out the
line current through the VI. A type of DC breaker that relies on this solution is the
active current injection HVDC CB [3]. It can be manufactured at reasonable cost, but
interruption is comparatively slow and takes 2−8 ms. Furthermore, it requires
specialized vacuum interrupters, and a fast high-voltage switch to block the
capacitor voltage in the normal case.
In [4] a new class of DC CBs was rst presented. It also uses a resonant circuit, but in
this case it is excited by a small voltage source converter (VSC). Hence it is named
VSC assisted resonant current (VARC™) breaker. It offers several bene ts. Cost can be
kept low as the power electronics only need to be rated for a fraction of the voltage
handled by the breaker. High–speed operation is possible with proven operating
times of below 2 ms. In addition, this type of breaker can be manufactured using
mostly standard, off-the-shelf, components.
HVDC grids of any considerable complexity will require DC circuit breakers to clear
faults. A DC short- circuit fault propagates rapidly, meaning that it needs to be
cleared in few milliseconds to avoid having to block the converters, which would
mean disrupted transmission in the grid. In addition, in a DC circuit the peak fault
current is not limited by the network impedance, only the current rate of rise,
implying that the DC CB has to limit the fault current before it rises to a level that is
harmful for equipment in the grid. If a suf ciently fast HVDC breaker cannot be
provided, the only option is to connect series inductance, but that causes additional
cost and power losses. A further requirement on HVDC circuit breakers is that cost
must not be excessive. Since the purpose of developing HVDC grids is to save
investment cost it is obvious that the cost of the breaker cannot approach that of a
converter station, even though it is clear that a DC breaker will be considerably more
expensive than an AC breaker of similar rating.
Figure 1 - Comparison of HVDC point-to-point connections (left), and an HVDC grid with HVDC circuit
breakers (right)
Inductance exists in all power systems, which means that the line current cannot
immediately be brought down to zero. Instead, an alternative path must be provided
for the current when the interruption through the VI is executed. The new current
path shall cause a high, preferably constant, opposing voltage that exceeds the
source voltage in the system, thereby forcing line current down to zero. Metal oxide
varistors (MOV), possess that property, and are widely used for voltage limiting in
power systems. An MOV is connected across the interrupter terminals, and its
clamping voltage is in this context called the transient interruption voltage (TIV), see
[1]. It is selected to be approximately 50% higher than the system DC voltage. The
MOV also serves the purpose of limiting the voltage across the vacuum interrupter to
a level it can withstand.
An FPGA-based control system controls the VSC, the VI, and the charging circuits in
the module, as well as to maintain communication with other modules and the
substation controller. The VSC control requires fast sampling with low propagation
delay, both to be able to accurately switch the VSC during the resonant current
excitation and to be able to quickly detect when the module successfully has
interrupted the current. The sampling period and sampling delay are therefore both
less than a microsecond. All components used in the breaker module are commercial
off-the-shelf, which lowers the cost. The modules are designed to be stackable, with a
maximum number of six modules in a stack.
Like other types of DC circuit breakers, VARC requires auxiliary power. The standby
auxiliary power need of each breaker module is, however, very low, in the range 10-
20 W. The auxiliary power system is dimensioned primarily by requirements on the
breaker recharge time, i.e. the time for the breaker to be ready for a repeated rapid
open-close-open sequence. Auxiliary power supply of 300 W to each module results
in a recharge time of 90 seconds, after which an open-close-open cycle can be
A prototype HVDC CB consisting of three modules (Figure 5), fully demonstrating the
operation of a modular circuit breaker, was designed, built, and tested as part of the
PROMOTioN project. This circuit breaker was designed for operation at 80 kV, with a
TIV of 120 kV. For the targeted 80 kV system voltage, high voltage isolation
transformers operating at 50 Hz were chosen for the auxiliary power supply. The
main ratings of this circuit breaker are compiled in Table 1.
Rated DC voltage 80 kV
4.2. Results
Short-circuit test were carried out at various current levels, as summarized by Table
2 below. Representative waveforms from a fault current interruption test (TF100) are
shown in . The tests TC100 and TF100 represent load current switching and fault
current interruption, respectively. The test TF100* at 15 kA shows the maximum
breaking capacity of the breaker. TF100, the rated maximum fault current breaking
test, was initially performed according to speci cation, with 2 ms operation time, and
then again with 1.5 ms operation time to demonstrate the capability of the breaker.
The test TC10 illustrates low-current switching and the TDT test illustrates
interruption with long subsequent suppression time and high energy dissipation. All
tests except TF100* were made at both current directions without changes to the
circuit breaker or its settings.
5. Conclusion
A full-scale modular HVDC circuit breaker of the VARC type has been designed and
tested. The tests conform that the circuit breaker allows for a neutralization speed of
1.5 ms at 12 kA interrupted current, and a maximum interruptible current of 15 kA.
It is thus proven that the modularization of the VARC concept works under realistic
HVDC fault conditions. The modular design, provides scalability, so that any multiple
of 40 kV can be chosen as the TIV of the circuit breaker. Furthermore, the design
enables fault tolerance through redundancy, as well as a reduction in component
cost and testing.
In summary: fast, inexpensive, scalable, and fault-tolerant HVDC circuit breakers are
now ready for deployment.
Acknowledgments
The work described in this paper was made possible thanks to support of InnoEnergy
Scandinavia, Svenska Kraftnät and the Swedish Energy Agency.
This work was supported by the European Union’s Horizon 2020 research and
innovation program under grant No.691714.
References
1. CIGRE Technical Brochure 683 “Technical Requirements and Speci cations of
State-Of-The-Art HVDC Switching Equipment” (Joined Working Group
A3/B4.34, April 2017).
2. Häfner J., Jacobson B.: Proactive hybrid HVDC-breakers – A key innovation for
reliable HVDC grid, Cigré symposium, Bologna, Italy, 2011.
3. Tokoyoda S., Tahata K., Kamei K., Kikuchi K., Yoshida D., Oukaili S., Yamamoto R.,
Ito H.: DC circuit breakers for HVDC grid applications – HVDC and power
electronics technology and developments, CIGRE LUND 2015, paper 135
4. Ängquist L., Norrga S., Modeer T.: A new dc breaker with reduced need for
semiconductors, EPE’16 ECCE Europe, Karlsruhe, Germany, 2016.
5. L. Ängquist, S. Nee, T. Modéer, A. Baudoin, S. Norrga, N. A. Belda ”Design and test
of VSC assisted resonant current (VARC) DC circuit breaker” (15th IET Internation
al Conference on AC and DC Power Transmission (ACDC 2019), 5-7 Feb. 2019,
Coventry, UK).
6. A. Lesnicar and R. Marquardt, “An innovative modular multilevel converter
topology suitable for a wide power range,” in 2003 IEEE Bologna Power Tech
Conference Proceedings,, vol. 3, 2003.
7. M. Poikilidis, R. Smeets, N. Belda, S. Nee, S. Mebrahtu-Melake, T. Inagaki,
"Document on failure mode analysis of HVDC circuit breakers", deliverable 10.5
of the EU Horizon 2020 project PROMOTioN, 2020.
8. S. Liu et al., "Modeling, Experimental Validation, and Application of VARC HVDC
Circuit Breakers," in IEEE Transactions on Power Delivery, vol. 35, no. 3, pp.
1515-1526, June 2020.
9. S. Nee, T. Modeer, L. Ängquist, S. Norrga and A. Baudoin, "Tank test circuit for fast
DC circuit-breakers," 15th IET International Conference on AC and DC Power
AUTHORS
Summary
The fast-rising amount of renewable energy with volatile electrical power
generation results in a need of grid stabilization demands. New highly exible power
stations in combination with upgrading projects of existing units request for
improved generator design solutions tailored to these new grid requirements. In
parallel the decreasing prizes of electrical energy at the liberalized market leads to
cost pressure on the power plant assets of the utilities. This forces manufacturers to
develop a new generator portfolio with higher ef ciency, excellent reliability at all
kind of operation regime, adequate maintenance intervals and much lower lifetime
operation costs.
The following bre optic sensors are examined, most of them use Fibre Brag Grating
(FBG) technology:
In a second example the need of stator winding copper temperature monitoring with
bre brag arrays is pointed out, to avoid undiscovered thermal hot spots at the high
voltage winding insulation system resulting in sudden defects with high economic
impact.
KEYWORDS
Fibre optic sensors - bre brag grating technology - online monitoring of operational stress - grid
demand - fast load fluctuation - on-site eld validation - stator end-winding vibration - operational
temperature distribution of copper conductor, high voltage stator winding
1. Introduction
The fast-rising amount of renewable energy with volatile electrical power generation
results in a reorientation of the electric energy market [1] and a need of grid
stabilization demands [2]. New highly exible power stations in combination with
upgrading of existing units with lifetime extension request for improved generator
design solutions tailored to these new grid requirements [3]. In parallel the
decreasing prizes of electrical energy at the liberalized market leads to cost pressure
on the power plant assets of the utilities. This forces manufacturers to develop a new
generator portfolio with higher ef ciency, excellent reliability at all kind of operation
regime, adequate maintenance intervals and much lower lifetime operation costs.
For grid stabilization with reactive power demands it includes optimized design for
new state-ot-the-art synchronized rotating condensers [4].
Table 1 - List of different type of sensors installed during prototype running procedure in the generator
test eld of the factory; Fibre Optic Sensors (FOS) highlighted in green
As can be seen, for FRT more than 300 FOS of different kind had been installed at the
generator and remotely online monitored from the test eld control room. This
includes the following type of bre optic sensors, most of them use Fibre Brag
Grating (FBG) technology.
Figure 1 - Array of bre optic temperature sensors applied at narrow side of copper conductor Roebel
bar before starting of HV insulation taping
Figure 2 - Working principle of cantilever type bre optical accelerometer based on intensity
modulation of light reflected at a mirror and vibration sensor produced with non-metallic elements
made of insulation material
Figure 3 - Examples of FOA sensor locations at different type of stator end-winding design depending
on generator power and cooling category
Figure 4 - Fibre optic dynamic strain sensor with application examples at top of a stator winding bar
The mechanical overstressing of a stator bar high voltage insulation system, that is
mainly caused by high dynamic-mechanical transients or thermo-mechanical
stresses due to overload conditions could lead to accelerated fatigue. Therefore, it is
recommended for speci c applications of hydro or turbine generators that the strain
should be measured in addition to the vibration behaviour of the winding overhang.
Permanent installation of strain sensors had been performed at two top layer
winding bars of different electrical phase in the slot exit region of an indirect cooled
generator, see Fig. 5. Four FBG strain sensors were applied at each bar at different
axial locations (blue arrows in Fig. 5 → ) to measure the dynamic mechanical tension
of the insulation in this highly stressed part of the overhang.
Figure 5 - Tiny FBG strain sensors (small black strips marked with blue arrows) xed with white glue
and adhesive tape strips on the surface of stator winding insulation at end-winding involute – two top
bars at phase separation
As shown in Fig. 6 (b) and (c) the sensor body is made of ceramic, glass prisms,
Faraday crystal, optical polarizers of glass and high temperature resistant plastics,
which makes it completely dielectric.
Figure 6 - Principle of magnetic flux sensor with a Faraday crystal (a) and practically realized bre optic
sensor (c) as small as a 1cent coin
The new bre optic magnetic ux sensors were implemented at stator winding
overhang of turbine and hydro generators [9] to measure the magnetic eld
distribution at axial locations between stepped core and front-end bar connections
as shown in Fig. 7. Because these ux sensors are made of non-metallic material, the
applied sensor and connection line could easily be positioned all over the end-
winding construction without taking into consideration any obstruction of high
electric or magnetic eld distribution as demonstrated in given image sections of
Fig. 7.
Figure 7 - Application of magnetic flux sensors at stator winding exit in stepped core area of an indirect
cooled generator
Fibre optic accelerometers can easily measure the vibrational behaviour and
dynamic-mechanical stress of stator end-windings operating at high potential well
above 10 kV and even higher. Different type of sensors are commercially available on
the market and several application papers are presented so far [10], [11]. With this
important information it is expected to get better knowledge on stress dependent
changes in the end winding structure and to ensures a reliable long-term operation
even in harsh peakload condition. The following example gives an impression of
online end-winding vibration monitoring
Figure 8 - Monitoring of stator end-winding behavior during different generator load conditions at
volatile grids (a) End-winding vibration level at start-up and shut-down process of a gas turbine
generator in peak load cycle (b) Displacement of four selected stator bar front-end locations (top to
bottom bar connections) in correlation to generator power condition
Different rotor speed dependent low level vibration resonance peaks at rotor
speed of ~ 700 rpm during typical gas turbine leaning cycles before starting the
ramp up of a gas turbine with the generator running in motor mode,
Some normal end winding resonance peaks during transient ramp up of the rotor
to full speed before synchronization to grid,
Low vibration level of end-windings at synchronous load operation of the
generator as expected by design requirements,
During fast ramp down only one load rejection resonance peak because of
transient winding current at the moment of disconnection from grid,
No thermal equilibrium of stator end-winding reached and therefore no thermo-
mechanical in uences on winding basket resonance behavior measurable.
Figure 9 - Bottom half of an indirect cooled generator stator with marked positions of FBG sensors
measuring axial distribution of copper conductor temperature
Figure 10 - Copper temperature distribution of selected top and bottom bars at stator end-winding area
between lead end and core end during test eld run – indirect air-cooled generator
The following valuable information can be collected from the given temperature
readings:
Figure 11 - Axially measured copper conductor temperature distribution at top and bottom layer bars
compared with conventional slot RTD reading during test eld run
The copper conductor temperature at top layer bars is signi cantly higher than
at bottom layer bars because of higher eddy current losses at top bars generated
by greater magnetic ux density at upper part of the core slots.
The in uence of radial cooling zones between warm and cold air sections is only
signi cant at bottom layer bars. At top layer bars the cooling air ow is too much
in uenced by mixed air gap ow.
The bre optic slot temperature sensors (brown dots in Fig. 11) located near
conventional RTD sensor position reproduce the difference between warm and
cold cooling air zones in an excellent way. But because these temperature
sensors are placed on top of insulated copper bars the measured temperature is
about 7 K lower than the warm spot temperature measured with FBG arrays
directly at copper conductor surface without high voltage insulation in between.
The temperature reading of conventional slot RTD sensor installed according to
IEC Speci cation is about 30 K lower than the measured copper conductor hot
spot temperature of the stator winding. Nevertheless, the thermal class
temperature of the insulation system of 155°C is far away to be touched. Also, the
utilization temperature of the stator winding insulation of 130°C is not reached.
The FBG temperature arrays installed directly at the copper conductor surface
produce an excellent thermal image of the local temperature distribution inside the
stator winding during generator operation. After some years of in eld operation at
different type of generators no sensor defects due to broken bre or even sensor
related temperature drift has been observed on any installed FBG sensor. During
a planned maintenance stand still the sensor readings were checked. After waiting
some time for cooling down, the reading from the FBG sensor were compared with
the conventional slot RTD and the cooling air thermometer. All values of comparable
locations within the cooled down generator stator do agree within a margin of ±1°C,
which is accurate enough for monitoring purposes.
5. Conclusions
A severe peak load operation regime of rotating machines due to volatile grid
demands results in accelerated wear of components and enhanced aging of the
stator winding insulation with increasing risk of unexpected sudden break-down.
Therefore, the exact knowledge of stator winding behaviour as one of the most
stressed parts of the generator is essential for long-term prediction of a new
designed machine. Extensive prototype Factory Running Tests (FRT) need to be
performed [17].
It has been shown in the paper, that the use of different kind of bre optic sensors
can essentially help to achieve a realistic picture of stator winding stressing. The
advantage of bre optic sensors (FOS) is that they can be placed at all critical winding
locations because they do not have any metallic and magnetic parts and therefore do
not in uence the high electrical and magnetic elds at generator stator.
A short description of different type of FOS including a sample application has been
given for the following Fibre Bragg Grating (FBG) sensors:
In a second example the need of stator winding copper temperature monitoring with
bre bragg arrays is demonstrated, to avoid undiscovered thermal hot spots in the
high voltage winding insulation system resulting in sudden defects with high
economic impact. This essential information gathered from sets of FOSs applied at
calculated winding locations ensures a reliable long-term operation of the end-
windings even in harsh operation condition.
References
1. Hans-Werner Sinn: Buffering volatility: A study on the limits of Germany’s energy
revolution, European Economic Review, Volume 99, October 2017, pp. 130 – 150
2. ENTSO-E Completing the map – Power system needs in 2030 and 2040 – Status
November 2020 · Version for public consultation, ENTSO-E, Rue de Spa 8, 1000
Brussels, Belgium
3. Hendrik Steins: Design validation, operational data assessment and new
maintenance concepts - using the example of the new air pressurized SGen-
2000P technology, 14. Essener Tagung - Generatoren in konventionellen
Kraftwerken, Windparks und Wasserkraftwerken, HdT, February 2020, Essen,
Germany
4. M. Baca, K. Walli, A. Joswig: Proper design and con guration of synchronous grid
stabilizers to cover the wide variety of requirements, IEEE PES General Meeting,
August 2018, Portland, Oregon, USA
5. T. Bosselmann, M. Willsch: Optical Sensors for Harsh Environments – Product
Portfolio – Sensors for Power Generators & Gas Turbines, Corporate Technology -
Siemens AG, 2017
6. Thomas Bosselmann: Innovative applications of bre-optic sensors in energy and
transportation, 17th Optical Fibre Sensor Conference OFS, Bruges, 23. –
27.05.2005
7. J. R. Weidner: Direct Measurement of Copper Conductor Temperature at
Generator Windings with Fibre Bragg Grating Sensors, SC A1 Rotating Machines,
Contribution PS1/Q1.6, Cigre 2012, Paris, France
8. L. Hübner, T. Bosselmann, A. Jungiewicz, G. B. Gabrielsen, E. Feilkas, K. Dybvik, H.
Daum, M. Villnow: Monitoring of winding overhang vibrations on large
synchronous motors, Petroleum and Chemical Industry Conference Europe,
Amsterdam, 6.6.2014
9. M. Villnow, M. Willsch, T. Bosselmann, B. Schmauss, T.Hildinger, T. Hess:
Distributed magnetic eld measurement on stator winding heads of a 300 MVA
water turbine motor-generator using ber-optical magnetic eld sensors, Proc.
IEEE Sensors, Nueremberg, 2010
10. Tetreault, A.: On-line End Winding Vibration Measurement Using Fiber Optic
Sensor Technology, EPRI Major Component Reliability (MCR) European Workshop,
Barcelona, April 12th – 14th, 2011
11. P. Kung, L. Wang, M. I. Comanici: Stator End Winding Vibration and Temperature
Rise Monitoring, 2011 Electrical Insulation Conference, Annapolis, Maryland, 5 -
8 June 2011
12. C. Kreischer, H. Steins, S. Strack, J. R. Weidner: New Diagnostic Procedure for
Monitoring of Stator End Winding Vibration at Generators with Rapid Load
Demand Fluctuation, Cigre SC A1 Meeting and Colloquium, Madrid 2015, Spain
13. André Tétreault: On-line End Winding Vibration Measurement Using Fiber Optic
Sensor Technology, EPRI Conference, Barcelona 2011, Spain
14. J. Letal, B. Satmoko, N. Manik, G. Stone: Stator end-winding vibration in two-pole
Machines, Petroleum and Chemical Industry Conference, Cincinnati 2018, USA
15. T. Tanaka, H. Murayama, K. Hattori, K. Takahashi, “Direct measurement of strand
temperature of turbogenerator with FBG sensors” Paper A1-109, Cigre 2012,
Paris, France
16. N. M. Theune, M. Kaufmann, J. Kaiser, M. Willsch, T. Bosselmann, P. Krämmer:
Fiber Bragg Gratings for the Measurement of Direct Copper Temperature of
AUTHORS
Summary
Line Impedance Resonance Analysis (LIRA) is a characterization method akin to
FDS (Frequency Domain Spectroscopy) and TDR (Time Domain Re ectometry), all of
which are commonly used for cable system characterization and diagnostics. These
methods are typically restricted to of ine measurements due to safety requirements
which limits the usability for condition monitoring as this ideally should be
performed continuously and not at discrete intervals. Online condition monitoring is
usually performed with DTS (Distributed Temperature Sensing), a technique based
on temperature measurements via ber optics, but this method is limited to
detecting temperature changes in the system. An online monitoring system based on
LIRA, which can provide detailed data on the condition of the cable system, is
proposed as an alternative and complementary solution to DTS. The proposed
system does not require a galvanic connection to the cables as it uses non-intrusive
signal inducers and sensors; it is easily adaptable to different cable types and
con gurations and provides automated analysis based on continuous
measurements. To ease data management, the proposed system is cloud-based and
uses a data visualization dashboard built upon cable infrastructure maps in which
different cable sections can be highlighted and historical and present data can be
compared. This makes it possible for the user to handle the large data sets. In this
paper the system is described both with respect to hardware and software in
addition to a presentation of a case study implemented at the Kithaironas Wind Park,
installed by Total Eren in Greece. The wind park comprises 30 turbines and 16 km of
medium voltage cables which was installed in 2012. The technical background of the
LIRA methodology is presented as well as the approach towards solving the
additional challenges associated with online measurements such as the galvanic
decoupling of signal injection and pickup.
online monitoring - diagnostics - cables - wind farm - line impedance resonance analysis - TDR - FDS
- DTS - asset management
Due to the high costs associated with faults avoiding them by condition monitoring
and ageing assessment is an attractive feature of any support system. In addition,
being able to rapidly locate a fault to speed up repairs is also desirable. The different
types of faults are commonly divided into shunt fault, open circuit faults and sheath
faults (described in detail in CIGRE TB773 Fault location on land or submarine links
[4]). Fault location is divided into pre-location and pinpointing techniques. Pre-
location can, for instance, be performed with Time Domain Re ectometry (TDR) and
the pinpointing with acoustic methods. Condition monitoring and ageing assessment
can be performed by measuring partial discharge characteristics, voltage withstand
and dielectric response. Line Impedance Resonance Analysis (LIRA) is capable of
both fault detection and condition monitoring during operation [5]–[7].
2. LIRA methodology
LIRA is based on measurements of the surge impedance of a cable at a large range of
frequencies, thereby assessing the cable condition in the frequency domain. This has
the advantage that the frequency content of the measurement signal can be easily
modi ed according to the most suitable range for the cable that is being measured. A
large range of cable lengths can be conveniently and reliably measured with this
technology – from just a few meters to hundreds of kilometers. The algorithms at the
heart of the LIRA technology are derived from the theory of electromagnetic wave
propagation in transmission lines and the well-known Telegrapher´s Equation.
Given that the measurements are taken in the frequency domain, ef cient frequency
domain algorithms can be applied to produce calculated cable properties, which give
valuable insight into the cable condition. Moreover, given that this technology is fully
transparent regarding the frequency content of the measurement signal, it is
possible to derive these quantities at multiple frequencies, giving valuable insight as
well as quality control over the calculated properties.
LIRA calculates physical properties of the cable based on the above, inclusive of
cable capacitance, cable resistance, cable inductance, characteristic impedance,
cable attenuation and other, proprietary property calculations like Delta G, a wide
band tangent Delta calculation. Additionally, the cable impedance changes resulting
from the measurements can be derived and visualized as a function of the cable
length (denoted the Spot Signature of the cable measurement), thereby making it
intuitive and easy to detect and monitor the development of suspected cable fault
locations.
3. Sensor design
A capacitive and inductive pickup are used to measure the voltage and current
signals induced by the current injector which can be of capacitive or inductive
design. Devising such pickups is a challenge due to several reasons. First, the
injected signal is superimposed on the operating voltage and current as this is an
online technique which means that the power frequency should be ltered out by the
sensors. This implies that an ideal pickup should have a response such as in Figure
1a or 1b with no signal transfer at 50/60 Hz and acting as a band pass lter from 100
kHz to 20 MHz. Second, the gain at the relevant frequency band is limited, mainly
due to the space available in the cable termination bays. The capacitive pickup
consists of a conductive plate which partially covers the surface of the connector. The
larger the plate the more gain which is in turn limited by the available space. This is
also valid for the inductive pickup, manifested as a Rogowski coil in the current
con guration. Third, the frequency response of the actual pickups, shown
schematically in Figure 1c and 1d, differs from the ideal response due to stray
capacitance and coil resistance. For instance, the number of windings, distance
between windings and the loop area are some parameters which in uence the gain
as well as the position and magnitude of the resonance in the Rogowski coil.
4. Data acquisition
An overview of the Data AcQuisition (DAQ) system is provided in Figure 2. This gure
represents the essence of the components that are installed on-site. For each cable
phase studied, inductive and capacitive sensors need to be installed along with the
measurement hardware electronics that controls the signal injection and the system
that receives the signal from the sensors. The output from the measurement
electronics are real and imaginary values of the current and the voltage respectively
at each sampling interval. These values are then passed through a LAN connection
on to a controlling unit (the Gateway), which then packages the signal and passes the
data on to the cloud sub-system. The Gateway is responsible for the management of
the measurement devices and can control multiple such cable measurement
con gurations simultaneously through the local area network. The Gateway is also
responsible for performing data integrity checks and for changing measurement
parameters should this be required.
These principles have been guiding the overall design, and a typical Internet of
Things (IoT) architecture has been adopted for the system, where the locally placed
data acquisition system is responsible for collecting the measurements, whereas a
back-end processing and storage sub-system has been implemented as a cloud data
processing solution. The front-end user interface has been implemented as a web-
client so that it can be made available in a web browser on any type of device, be it
mobile phones, tablets, or desktop.
Given the nature of the data in that new measurements are repeatedly captured and
analyzed, it has been an important aspect to capture the data contextual information
in the presentation layer/dashboard, as and when new measurements are available.
Also, the dashboard functionality should be highly visual, and should provide the
essential information for each measurement at a glance. The main element of the
dashboard has therefore chosen to be the cable under measurements, displayed in a
map, so that it is easily observed which cable is measured, and what the data is.
6.2. Implementation
The collaboration between Total Eren and Wirescan was initiated in 2019 with
technical studies of cables, terminations, and practicalities around constructing an
IoT system for cable monitoring on this speci c windfarm. The system was
eventually installed, commissioned, and put into operation in November 2020 [1].
6.3. Operation
The system has at the time of writing been in operations for 75 days. The system has
behaved as predicted, although some external events have allowed for appropriate
stress testing of the system, including power failures and loss of internet. However,
the system has re-established the measurement campaign and the connectivity to
the cloud system every time such an event has occurred. The dashboard for
monitoring the activity for one of the cables under measurement is shown in Figure
6.
References
[1]
The installation was signi cantly delayed due to the on-going COVID-19 pandemic
AUTHORS
Summary
The electrical clearance (D) in Japan is calculated from the sum of Safety distance
(Ds) and Minimum air clearance required to prevent a disruptive discharge between
phase conductors and objects at earth potential during fast front or slow front
overvoltages (Del). Del is ‘clearance increment’ and depends on the system voltage.
This is the same idea as in foreign countries. The interpretation of the technical
standards (Ministerial Ordinance) for electrical appliances and materials (hereinafter
referred to as ‘Interpretation of Technical Standards’) stipulates a clearance value
that increases with rising voltage (hereinafter referred to as ‘clearance increment’).
The clearance increment varies depending on the safety distance and has been set
as 12 cm / 10 kV above 60 kV for other structures and trees, and 15 cm / 10 kV above
35 kV for buildings.
The clearance increments in other countries are generally set to about 6 cm / 10 kV,
so as the voltage rises, Japan's clearance is clearly larger than in other countries.
When the clearance was established in Japan in 1959, there were no 500 kV
overhead transmission lines (hereinafter referred to as ‘OHL’), and the clearance of
extra-high voltage OHL had not been suf ciently studied. Since then, the number of
OHL of 170 kV class and above has been increasing rapidly. It was thought that if
these clearances could be reviewed to be comparable to those in other countries, the
height of towers would be reduced and the area of tree trimming that interferes with
OHL would be reduced, leading to cost savings in the construction and maintenance
of OHL. Based on these circumstances, in order to explore the possibility of
reviewing the electrical clearance of EHV OHL in Japan, we conducted overseas
survey on the regulations of Germany, France, Canada, and the United States and
then not only the electrical clearance values but also basis for their setting were
This amendment of the electrical clearance will reduce the height of 500 kV towers
by about 2 m, thereby reducing the cost of materials, transportation, and assembly of
the towers. In addition, by reviewing the electrical clearance from the conductor to
the tree, the area of trees to be cut down as obstacles can be reduced, especially
when the conductor swings sideways in the wind. Therefore, it will reduce not only
the compensation cost of new OHL, but also the maintenance cost of existing OHL.
This paper describes the results of the studies and investigations that formed the
basis for the rst revision of Japan's electrical clearances in 61 years, and the effects
of the regulatory changes on the design and cost of OHL.
KEYWORDS
1. Introduction
The interpretation of the technical standards (Ministerial Ordinance) for electrical
appliances and materials (hereinafter referred to as ‘Interpretation of Technical
Standards’) stipulates a clearance value that increases with rising voltage
(hereinafter referred to as ‘clearance increment’). The clearance increments vary
depending on the type of object approaching the conductor, with ‘other
structures*1 and trees’ set at 12 cm / 10 kV and ‘buildings’ at 15 cm / 10 kV. However,
in other countries, they are generally set at around 6 cm / 10 kV, and as the voltage
class increases, the deviation from the Japanese clearance becomes more
pronounced.
This standard value was set in 1959, but at that time, 500 kV overhead lines did not
exist and the clearance for EHV lines was not fully considered. Since 1959, the
number of EHV OHL above 170 kV has been increasing rapidly. Therefore, if this
clearance can be revised, the cost of construction and maintenance of OHL will be
reduced.
*1In Interpretation of Technical Standards, structures other than ’buildings, roads (except those
with infrequent vehicular and human traf c), pedestrian bridges, railroads, tracks, cableways,
overhead communication lines, low-voltage (600 V or less) or high-voltage (7,000 V or less)
overhead electric lines, low-voltage or high-voltage train lines, and other electric lines
exceeding 7,000 V’ are de ned as ‘other structures’.
The safety distance (Ds) was calculated from model cases in each country, and there
was no signi cant difference between Japan and other countries for buildings and
other structures. On the other hand, the clearance increment (Del) is 6.4 cm / 10 kV
in the United States and Canada, 6.2 cm / 10 kV in Germany (average of 35 kV or
more), and 7.5 cm / 10 kV in France, so the clearance increment in Japan is
remarkably large. As a result of this, the divergence from Japan's clearance becomes
striking as the voltage class grows larger (Figure 1 and 2).
*5 ‘The minimum insulation gap’ is de ned as the air gap that does not cause ashover for the
assumed switching surge and short-time overvoltage.
*6 ‘The standard insulation gap’ is de ned as the air gap that allows lightning-induced ashover
to occur between the arc horns and not between the wires and the tower.
Figure 1*7: Comparison of electrical clearance Figure 2*7: Comparison of electrical clearance
*7Figures 1 and 2 are taken from Figures 3.1 and 3.3 in Electrical clearance for extra high
voltage overhead transmission lines exceeding 170 kV, JESC E2012 (2013), (in Japanese) [13]
36 0.35
52 0.60
72.5 0.70
100 0.90
123 1.00
145 1.20
170 1.30
245 1.70
300 2.10
420 2.80
525 3.50
Figure 5 - Calculation the clearance increment from Minimum insulation gap against switching impulse
voltage in Japan
L=1.115 x Z+0.021
Where,
L: Standard insulation gap (m), Z: Arcing horn gap (m)
187 1.53 (100%) 3.44 (225%) 5.22 (341%) 3.56 (233%) 5.40 (353%)
220 2.36 (100%) 3.62 (153%) 5.40 (229%) 3.92 (166%) 5.85 (248%)
275 3.03 (100%) 3.98 (131%) 5.76 (190%) 4.64 (153%) 6.60 (218%)
500 4.82 (100%) 5.30 (110%) 7.08 (147%) 7.28 (151%) 10.05 (209%)
Figure 10 - Reduction effect of EHV overhead transmission line towers passing through mountainous
areas
7.2. Effect of reducing the area of trees that are cut down
as obstacles to conductor
The expected reduction in the area of tree falling on conductors due to the
amendment of electrical clearance is described as follows. The reduction ratio in the
area of tree trimming, determined from the required clearance when the conductor
swings 60 degrees and sideways in high winds, is 3.8 % for overhead transmission
lines of 170 kV and above, which can be reduce the compensation cost (see Figure
11) [13]. This is not a temporary compensation at the time of OHL construction, but
lasts as long as the facility exists, so this economic effect is also signi cant.
8. Conclusions
As in Japan, the electrical clearance in other countries is calculated based on the
standard clearance value plus the clearance increment per 10 kV, but since the
Japanese clearance increment used to be larger than in other countries, there was a
maximum divergence of about 3 m in 500 kV. The Japanese electrical clearance was
amended for the rst time in 61 years on February 25, 2020 after many years of
study and recent overseas surveys. This will reduce the height of 500 kV towers by
about 2 m, which will reduce the material and assembly costs of the towers and
reduce the area of trees to be cut down as obstacles. It will not only reduce the cost of
constructing new OHL, but also the cost of maintaining the existing one, which will
have a signi cant economic impact.
References
1. Technical Standards for Electrical Facility in Japan (in Japanese)
2. National Electrical Safety Code (NESC) C2 (2017)
3. National Bureau of Standards Handbook H43
4. CSA standard C22.3 No.1-15 Overhead Systems (CSA)
5. EN 50341-1 Overhead electrical lines exceeding AC 1 kV - Part 1: General
requirements - Common speci cations
6. EN 50341-2-4 Overhead electrical lines exceeding AC 1 kV - Part 2-4: National
Normative Aspects (NNA) for GERMANY
7. VDE 0210-1 Overhead electrical lines exceeding AC 1 kV Part 1: General
requirements – Common speci cations
8. EN 50341-2-8 Overhead electrical lines exceeding AC 1 kV - Part 2-8: National
Normative Aspects (NNA) for France
9. UTE C11-001 Conditions techniques auxquelles doivent satisfaire les
distributions d'énergie électrique - Arrêté technique
10. Insulation Design Standard for Power Transmission Lines, IEEJ Recommendation,
1958 (in Japanese)
AUTHORS
Summary
The energy transition and the ght against climate change are among the crucial
challenges of current times and a major focus of RTE's commitment. As a TSO, RTE
takes actions to reduce the environmental footprint of its new projects, enhance the
exibility and resilience of the transmission network and facilitate the integration of
renewable energies.
RTE believes new approaches are essential in this context in order to innovate and
nd sustainable solutions to overcome these challenges.
In this light, RTE is extending its efforts through an ambitious and comprehensive
eco-design approach. RTE is raising awareness among its teams and disseminating
the necessary tools so that taking the environment into account in each decision,
along with the technical and economic criteria, becomes engrained in the company’s
practices. In 2020, RTE carried out the LCA (Life Cycle Assessment) of an electrical
offshore substation, with an expert rm in the eld.
This article’s goal is to share the main lessons, both at the methodological and
results level, with the CIGRE members. The identi cation of the main sources of
impact and related ways of implementing eco-design are part of the study's
deliverables and should enable improvements to be taken since the short term (and
along the assets life).
The LCA methodology is based on a multi-step and multi-criteria analysis, from the
extraction of raw materials to the end of infrastructure life. The perimeter of the LCA
is the full offshore substation (all electrical equipment, auxiliary equipment,
platform systems and structures) all over the asset life, except the HV export cables
and the IAC cables.
The main ambition is to drive the company choices in design, supply chain,
construction, operations and maintenance aspects. The vision is to reduce the
environmental footprint of all the infrastructure all over its life cycle, create a
positive integration within the environment, foster technical and social innovations,
and support new solutions for the sustainable development of a future decarbonized
system infrastructure.
KEYWORDS
1. Introduction
As part of the energy transition and more speci cally of the offshore renewable
energies development, RTE, the French TSO, has extended its activities to the
maritime domain and included within its scope the offshore substations for the
future French offshore wind-farms (from public tender AO3 awarded in 2019
onwards). In the context of offshore grid connection projects, RTE plays a major role
in the planning and development of offshore renewable energies, both at a pilot and
commercial scale. According to the multi-year energy programme (French PPE, [1]),
the objective of wind power at sea is to achieve a power of approximately 5 GW in
2028. RTE is responsible for nancing, designing, building and operating the
offshore power infrastructure, its substations (platforms) and HV cables network.
Some of the main environmental factors assessed through these LCA’s are: the
impact on reduction of greenhouse effect gases, the depletion of natural resources,
eutrophication and acidi cation of seas, and air pollution. These indicators go back
into the iteration of design choices, proposing ways and strategies for the eco-design
improvement and consolidation into the company processes and assets.
However, designing an asset in such a way to integrate the environment as one of the
key drivers needs to cover all the asset life cycle. Within this context and with the
ambitions described in the previous chapter, RTE decided then to perform a life cycle
assessment (LCA) for a full offshore substation scope.
Although the LCA method is well-known and used by the industry, our
bibliographical study put in evidence that the present work study represents a rst-
in-its-kind (at the time of writing and as regards to the study perimeter and its
approach).
The ows of materials and energy taken and released into the environment at each
stage are then weighted and aggregated to quantify environmental impact
indicators. For example, the indicator of climate change, expressed in kilograms of
CO2 equivalent, results from the sum of greenhouse effect gas emissions weighted by
the global warming factors of the various gases.
Given the innovative nature of the study, an iterative process has been put in place
to perform the analysis [2]. In the LCA context, an iteration is an action loop making
it possible to collect the input data, to model the system in the LCA software, to
output the results of the analysis and to interpret them.
The typical scheme of French offshore grid connections and the position of the OSS
are shown in Fig. 2 below.
The topside (usually 3 to 5 oors) which houses the HV/LV electrical equipment,
the control and protection equipment, the auxiliary systems, the HV subsea
cables connections and the other platforms facilities
The substructure, which supports the topside. Different types of substructures
are possible (monopile, jacket or concrete). The substructure also support the j-
tubes for the routing and mechanical protection of subsea cables from
underwater to on-board the topside.
The topside and substructure assembly is xed to the ground by foundations, the
nature of which varies in particular depending on the soil characteristics, the
topside size and weight and the meteocean conditions (varying from hollow metal
piles driven into the ground to drilled piles, pre-piled or post-piled structures).
As a reference and for entry data to the study, a preliminary basic design develop by
RTE was taken. For the electric power equipment, the information provided was more
detailed as it was sourced from RTE’s equipment panel.
For the study, the following assumptions are considered for the offshore substation
design:
The LCA perimeter does not include the 225 kV subsea cables. The reason of such
choice is that the LCA objective is to isolate and analyse the impacts of the offshore
substation from an eco-design perspective. For the same reason, the 66 kV inter-
array cables and the rest of offshore wind-farm are also outside the scope of the
study, this being under the responsibility of the offshore wind-farm developer
company.
In view of the bibliographic analysis carried out as part of this study, the Functional
Unit (FU) retained for this study is: "Collect the offshore wind-farm power production
and raise voltage level from 66 kV to 225 kV, for an installed capacity of the wind
farm of 1 MW and a water depth of 18 m, and for a design life of 25 years".
Finally, more than 98% (by mass) of the elements were modelled and the Circularity
Footprint Formula called CFF method (European Commission, DG ENV) was used to
model the end of life.
This new method, aimed at evaluating the contribution of products to the circular
economy, was developed to modify the rules for allocating the impacts / bene ts of
recycling as well as to take into account additional factors making it possible to
integrate degradation of materials during recycling.
The LCA study and methodology has made the object of a 3-months “critical review”
by an independent panel, according to the requirements speci ed in the ISO14067
standard in the case of possible communication to the general public. A panel of
technical experts and stakeholders was constituted, with the aim to challenge and
corroborate the eco-design hypotheses, data and suggestions for improvements, and
to allow the communication of results to the general public.
Figure 3 diagram shows the global results from the rst iteration (base calculation)
LCA on an OSS entire cycle. Impacts are shown on a series of indicators considered in
the study:
Climate change
Particulate matter
Photochemical ozone formation
Acidi cation
Freshwater eutrophication
Abiotic depletion (elementary, reserve base)
Cumulated energy
For each indicator (column), the cumulative max / min values are reported.
The results are differentiated per phase of the OSS life cycle (in different colours). It
appears that, for the entirety of the considered indicators, the phases bringing the
most signi cant impacts are the Manufacturing (fabrication) and Operations (O&M)
phases.
It is worth observing that the impacts appearing in green in the diagram correspond
to negative values (thus indicating impacts which are to be avoided). This is the case
of recycled material (used for fabrication instead of new raw materials,) or to the
recycling of these materials at the end of asset life (instead of waste disposal), as
recorded in the CFF method. On the opposite, the impacts appearing in positive
values in the graphs represents impacts onto the environment.
Steel is of course the main substation structure component. Our results show that
steel production, which generates high GHG emissions (4 ton CO2e/ton of primary
steel), is responsible for the majority of impacts resulting from the structure.
Electrical equipment production has a signi cant impact on the reduction of abiotic
mineral resources, in particular because of the production of copper contained in
transformers and lead contained in batteries.
Manufacturing of C&P equipment and Telecom systems has the greatest contribution
to the eutrophication potential of freshwater, due to the manufacture of the electronic
components constituting this equipment. Electronic equipment is made up of several
metals, including metals that are more or less critical from a geological point of view.
The more critical the metal, the more the extraction and re ning stages will generate
energy consumption and local impacts on natural environments, and especially on
freshwater life.
Focusing on the structure fabrication analysis (ref. Fig. 5 below), the piles (in blue)
and the jacket (primary structure in red, secondary in grey) have the highest impacts
on most of environmental indicators (from climate change to cumulated energy)
apart from the decrease in abiotic resources, which is mainly impacted by the
painting and corrosion protection systems (for the zinc / aluminium coatings
fabrication).
Focusing on the Operations (O&M) phase, the impacts of this phase are strongly
dominated by the electrical losses of the power transmission asset. With reference to
the gure 3) “Results of the global LCA (per functional unit: 1MW)”, those are
represented by the yellow contributions (identi ed as “Use” in the diagram).
Interestingly, it clearly appears the signi cant contribution of the operations and
maintenance life of the asset compared to the construction and installation phases;
as a consequence, the positive changes that can be brought on the electrical
transmission performance acquire importance in the light of the global LCA.
It is important to note that the results presented above include power transformer
losses modelled with a “European Business As Usual 2035” electricity prospective
mix. The sensitivity analyses carried out allow to study the impact of modelling
losses with either the French electricity mix or a 100% Wind Mix. Because electrical
losses are the primary source of impacts, the choice of the electrical mix used to
model them is a very important value.
The graph above (Fig.7) shows the variations in the impact of electric losses, which
are the only parameter impacted by the variation of the load factor. For the varying
parameter, and for the two analysed scenarios, the differences in results observed
are, for all impact indicators, of the order of 10% compared to in the reference
scenario. Losses remain a very signi cant element on the overall environmental
impact of the offshore substation, even with a low load factor.
In this study, RTE has chosen as the electricity production mix to be taken into
account to assess the environmental impact of electrical losses a mix of average
European production by 2035. This choice was made because the electricity network
France is interconnected to the European electricity grid, and that the electricity
mixes are changing in particular because of the energy transition. However, this
choice is not obvious.
The objective of this sensitivity analysis is to study the impact of the choice of the
electricity mix modelled for the losses on the results of the study. As indicated in the
diagram at Fig.8, the reference case in blue (forecast European Mix BAU 2035) was
compared with two variants:
For the variant parameter, and for the two analysed scenarios, the differences in
results observed are quite signi cant. Thus, the choice of energy mix for loss
compensation has a great in uence on the results of the study.
The results of the LCA study are calculated from data related to an OSS equipped
with 2 transformers of a certain power capacity. In order to study the in uence of the
power to be transformed on the LCA and environmental impacts, two variants were
modelled, changing the main power transformers number (reference 2 transformers)
ref. diagram below (Fig.9):
This is because although the structure and other equipment may be less important
to support a single transformer, these quantities are not divided by two. Similarly,
the differences in impact (weighted to the MW installed) between a substation
equipped with three transformers and the reference case with one transformer are
from -1% to -12% depending on the indicators. Thus, the variation in the number of
transformers or in power to be transformed does not signi cantly impact the results
of the life cycle analysis presented above.
The OSS offshore installation site and in particular its water depth also play a role.
Therefore, a sensitivity analysis case compares the 18 m water-depth reference case
(in blue) to 100 m water depth (in red) ref. diagram in Fig.10.
The different impacts brought by this variant mainly affect the OSS manufacturing
and installation phases, as well as its end of life. The graph below shows the
variations in impacts related to the manufacture, transport and end of life of the
substation, which are the parameters impacted by the 100 m water depth case.
The change in the OSS structure resulting from 100 m water depth mainly impacts
the manufacturing phase, in fact a greater quantity of materials is used to build the
structure. On all life cycle, the impacts of the 100m scenario are between 4% and 9%
greater than the impacts of the reference scenario depending on the indicators.
This preliminarily indicates that the water depth of the OSS installation site is an
important element of the environmental assessment, although additional work is
required to re ne these results.
OSS fabrication:
Minimize substructure and foundations (for example, by choosing a site as
shallow as possible, or with oating solutions); enhance weight optimisation /
reduction (mainly for steel and scour protection material, but also in general);
enable equipment life extension; increase of recovered and re-used
quantities at the end of the asset life.
OSS transportation:
Optimize global transportation routes / modes of transport; enable cleaner /
less polluting fuels for maritime and onshore transportation.
OSS operation:
Promote technologies with low electrical loss rates; improve Electricity Mix
and purchase greener electricity to compensate for losses; replace SF6 by
alternative gases and / or 0% leaks.
End of life:
Develop designs in order to increase reuse and recycling ratios
Promote effective methodologies and treatment to maximise actual recycling.
5. Conclusions
Within the context of offshore wind-farms grid connection projects, the LCA study
presented is a rst-in-its-kind to date, for several reasons: its comprehensive
perimeter of a full offshore substation; its iteration to nd alternative choices; its
systemic approach to design.
The study enabled RTE to gain an initial view of the environmental impacts of the
offshore substation, encompassing the construction phases (manufacturing,
transportation, installation) and operations phases (service, maintenance, removal,
recycling/disposal) for all its infrastructure and equipment.
The study allowed identifying the elements that contribute the most to these
impacts, and documenting a subject which remains little treated in the current
scienti c literature.
Iterations have been done in the study, in order to pick several alternatives in design
both for the electric power equipment and the infrastructure, depending on the
technical feasibility and the sensitivity on the overall environmental footprint.
In the detailed engineering phase, RTE will be able to re ne this study, by using
more precise data and comprehensive information, and remove the limits which
have been identi ed.
To go further, the ambition is to drive the company choices in design, supply chain,
construction, operations and maintenance aspects. On the path forward, the software
model will allow to manipulate the components based on the technological choices
made, and ascertain quantitatively the resulting effects.
Therefore, the future step will be to use the platform model such as an
environmental calculator during the detail engineering phase and for other next
projects. This environmental calculator will provide the elements allowing to decide
Moreover, this method shall be extended to all the power transmission network. It
will be interesting to see the bene ts of a systematic LCA approach on such a full
scale system and study how global optimisation can be achieved through a wide
range of parameters.
References
1. PPE - Décret n° 2020-456 du 21 avril 2020 relatif à la programmation
pluriannuelle de l'énergie
2. EcoAct and Elys Conseil – OSS LCA Bibliographic analysis and methodology
report - 2020
AUTHORS
Summary
Dc-dc converters for high voltage direct current (HVDC) applications are interesting
devices for the development of multi-terminal and dc grid schemes. They can adapt
the differences between the dc systems (voltage level, technology and/or line
topology) and provide additional protection, controllability and redundancy services.
This paper presents a case study of a non-isolated dc-dc converter interconnecting
the NordLink and Cobra cable projects. This interconnection requires a dc-dc
converter to adapt the dc voltage and the line topology (the rst project being a ±525
kV rigid bipole while the second is a ±320 kV symmetric monopole). The case study
has been modelled in Matlab/Simulink and several scenarios are simulated. A rst
set of 8 simulations change the power ow directions verifying the adequate
behavior of the dc-dc converter and HVDC links. Based on the previous simulations,
additional 16 cases are simulated to verify the system behavior during faults. Two
faults are proposed: a pole-to-ground on the positive pole of the rigid bipole line and
another on the positive pole of the monopole. It is shown that the dc-dc converter can
interconnect two existing lines without changing their initial control strategy. For the
normal operation simulations, a fast power variation through the dc-dc converter is
tested proving that the line protections are not triggered. The power perturbations
created by the dc-dc converter are small enough to keep the system under normal
operation conditions. During the fault simulations, the dc-dc converter is able to
isolate the healthy side from the fault disturbance ( rewall capability). The healthy
dc side observes a power disturbance (loss of power ow through the dc-dc
converter) without triggering the protections, allowing the continuous power
transmission and regaining steady state conditions. The dc-dc converter employs full
bridge submodules to be able to block the fault currents, without the presence of dc
circuit breakers.
dc-dc HVDC converters - dc-MMC - grid topologies - multi-terminal dc grid - modular multilevel
converters
1. Introduction
High voltage direct current (HVDC) transmission lines are currently used to transmit
high power over long distances. The interest in interconnecting two or more HVDC
lines has risen in the latest years inspiring multiple publications and a CIGRE
working group (B4.76) dedicated to the study of dc-dc converters for HVDC
applications.
HVDC transmission system does not have an established standard yet, hence, the
installation features vary from one project to another, such as the operation voltage,
the technology (line commutated converter or voltage source converter), the line
topology (e.g. bipole, monopole), the grounding strategy (e.g. start point reactor), the
protection scheme or the conductor type used (cable or overhead lines). Dc-dc
converters are important devices for the development of future dc grids [1] as they
provide the interface needed to interconnect HVDC systems with different
characteristics. Several HVDC dc-dc converters have been proposed in the literature
to interconnect two dc systems [2], but the literature focuses mainly on the
interconnections between two dc systems with different voltage levels [3], while the
impact of their grid topology is not often considered.
There are four different grid topologies for HVDC transmission systems: asymmetric
monopole (Fig. 1a), symmetric monopole (Fig. 1b), bipole (Fig. 1c) and rigid bipole
(Fig. 1d) [4]. Each topology behaves differently in case of a fault. There are different
possible faults: faults pole-to-ground, pole-to-pole, or internal faults in a converter.
Both monopoles and the rigid bipole must stop the power transmission during any
fault and they remain inoperative until the fault is cleared. Compared to the
monopoles, the rigid bipole can be recon gured to isolate a fault on a converter. Then
it can use the healthy conductors and converters to exchange, up to, half of the rated
power. However, the rigid bipole loses the complete power exchange capacity in case
of a fault in a conductor. In case of a pole-to-ground fault, the symmetric monopole
and the rigid bipole have a pole displacement leading to an increased voltage (pole-
to-ground) on the healthy pole. The symmetric monopole can experience voltages up
to 2 p.u., whereas, voltages around 1.4 p.u. have been reported for a given rigid
bipole application [5]. The main advantage of the bipole is its inherent redundancy.
Contrary to the rigid bipole, the bipole continues the power transmission, without
interruption, for any fault except the pole-to-pole fault. The bipole use the healthy
pole and the metallic/ground return to exchange up to half the rated power without
being subject to voltage or currents disturbances.
The paper starts by presenting the main characteristics of the HVDC lines to
interconnect. Section 3 presents the topology and control of power converters (ac-dc
and dc-dc). Section 4 presents the parameters of the simulation model. The
simulation results are shown in section 5 and the conclusions are given in section 6.
Figure 2 - Map of the North Sea region presenting NordLink and Cobra cable. The dc-dc converter is
proposed at the crossing point
The MMC controller is designed in line with [12]. A general control diagram is
presented in Fig. 4a. Three energy controllers (total, horizontal and vertical) manage
the energy by setting the current references (Iref diff and Iref ac), which are a linear
combination of the upper and lower arm currents Iup and Ilow. The control changes
the ac current reference depending on the control mode, either voltage control or
Figure 3 - Circuit diagram of the ac-dc modular multilevel converter: submodule (SM), arm inductor (L)
and half bridge submodules (HBSM)
The power control in the rigid bipole is modi ed (Fig. 4b): both MMCs (positive and
negative pole) control the total energy with the ac current and have a common dc
terminal voltage ΔVdc to control the dc power [13]. The station controlling the
voltage implements the control presented in Fig. 4a including VCC.
Figure 4 - MMC control diagrams (a) The general control strategy for power or voltage control mode
The converter is controlled to keep the internal energy constant, while a power is
transferred between dc systems. The control strategy is a cascaded structure with
the high level control following the energy references and the low level controlling
the currents. There are three energy controllers per converter phase: total energy
(Σ), total difference (ΔT) and the difference between the upper and lower arm (Δu-l).
The internal currents are controlled to follow the references given by the energy
controllers, the pole imbalance (on the monopole side) and the power reference, as
shown in Fig. 6. In this work, a power control mode is implemented, but additional
controllers can be added to control the voltage on the dc sides.
4. Simulation model
Figure 7 shows the schematic of the simulation model implemented in
Matlab/Simulink. The 7 converters were implemented using the parameters
presented in Table 1. The converters use average arm models, including the blocked
state, depending if they are composed by HBSM [15] or FBSM [16]. The cables are
modelled using the wideband model from the Best Paths project [17]. The model
considers two reference points: the rst on the dc side of the RB, which is grounded
through a resistance (RG) of 0.7 Ω as presented in [5]; the second, on the ac side of
the SyM line through a star point reactor as shown in Fig. 7 [18, p. 291].
The ve converter stations implement a fault detection algorithm, which uses local
voltage and current measurements to detect a fault. The fault detection algorithm
blocks the converter before the arm current reaches 3 kA, as the complete case study
was designed using IGBT valves rated at 1.5 kA and 3 kV. After blocking the
converter, it is assumed that the fault current circulates through the by-pass
thyristors integrated within the SMs [18]. In addition, the algorithm trips the station
ac circuit breakers (ACCB) to stop the fault current contribution from the ac side. The
fault detection algorithm has a 300μs delay [19] to emulate the detection,
communication and tripping time inside a converter station. An additional 100ms
delay is added to the ACCB opening signal. With regard to the voltage
measurements, the algorithm triggers the block signal if the measurements deviate
5. Simulation results
The proposed case study interconnecting two HVDC lines using a dc-dc converter
may have multiple power ow distributions around the system. Figure 7 shows the
positive convention for the dc currents, which are also used for the power direction.
The positive power direction in the lines are from the dc side towards the power
controlled stations, whereas the positive convention in the dc-dc converter is from
the RB to the SyM line. Eight power ow variations are proposed to test the system
during normal operation, i.e. without faults. Based on these eight power ow
scenarios, the fault behavior is analyzed considering 2 different fault locations per
case, which gives a total of 16 fault simulations. The considered fault locations are: a
fault on the positive pole of the rigid bipole (P-Ctrl RB+) and a fault on the positive
pole of the V-Ctrl SyM station, as shown in Fig. 7. The details of the power ow
directions and fault locations are organized in Table 2.
Table 2 - Variations of the case study, where the positive conventions (+) are shown in Fig. 7. In the RB
and SyM lines from right to left (towards the P-Ctrl stations) and in the dc-dc converter from the RB to
the SyM
The simulation starts with nominal voltage and power reference on the RB and SyM
lines, 1000 MW and 300 MW respectively. After reaching the steady state, a power
reference is sent to the dc-dc converter to exchange power (400 MW) between dc
systems in both directions. The simulation results in normal operation are shown in
Fig. 8, for case 1: positive power ow in the lines and bidirectional exchange through
the dc-dc converter. The results obtained for the other 7 cases are similar: the
uctuations presented in Fig. 8 are representative for all tested normal operation
cases. The power exchange measured at the ve converter stations are presented in
Fig. 8a. It can be seen that the stations in voltage control mode change their power
exchange to compensate the power through the dc-dc converter (magenta line), while
the stations in power control keep their power exchange invariant as their references
have not been changed (solid lines).
Figure 8 - Simulation results in normal operation for the case 1. (a) Power per station. (b) Pole-to-
ground voltage, positive (+) or negative (-) measured at the different converter terminals in the system
(the negative poles were inversed to simplify the visualization). (c) Total energy in the converters
Regarding the fault simulations, the starting sequence is the same, but the dc-dc
converter only exchanges power in one direction: positive from RB to SyM and
negative in the opposite direction. After reaching the steady state, a fault of 1 Ω to
ground is simulated (at 2s), at the terminals of the P-Ctrl RB+ or V-Ctrl SyM as shown
in Fig. 7. The results presented in Fig. 9 are the worst cases per station found when a
fault in the RB line is simulated (odd cases of Table 2). During the fault, the voltage in
the faulted pole drops to zero as shown in Fig. 9a. At the fault instant (t=2s), the
negative pole in the RB has an increased voltage reaching -880 kV for the 15th case
(see Fig. 9b). The steady state voltage for this pole stabilizes at -762 kV, which
represents 1.45 p.u., similar to the results found in [5]. On the SyM side (Fig. 9b-c),
the voltages do not exceed ±10% of the nominal voltage for any case, which agrees
with the initial control design.
Figure 10 presents the higher dc currents measured at the RB (Fig. 10a), the SyM
(Fig. 10b) and the dc-dc converter (Fig. 10c) terminals for the cases when the fault is
on the RB side. Figure 10a shows a peak of 8 kA for the currents measured in V-Ctrl
RB+ converter. It is worth mentioning that the converter protection strategy blocks
the MMC under 400μs after the fault. The currents observed in V-Ctrl RB+ continue
to rise until the ACCB is opened: after 2.1 s, which illustrates how the ac currents
feed the fault in that pole. On the SyM side (Fig. 10b) the currents have a
perturbation due to the loss of power from/to the dc-dc converter (t = 2s). After the
transient, the currents reach the operation point where the voltage controlled
stations exchange the same power as the power controlled stations (behavior
expected without the use of dc-dc). Figures 9b-c and 10b illustrate that the dc-dc
converter can act as a rewall during a fault in a RB, as the healthy link continues
normal operation once the dc-dc converter is blocked, irrespectively of the state of
the other link.
Figure 10 - Dc currents during and after the fault on the RB side (worst cases). (a) currents in all four
MMCs in the RB line. (b) Currents measured in the SyM. (c) Currents measured in the dc-dc
Figure 11 - Dc voltages pole-to-ground during and after the fault on the RB side (worst cases). (a)
positive pole in RB. (b) Negative pole RB. (c) Positive pole SyM. (d) Negative pole SyM
Figure 12a shows the currents in the RB and how they recover steady state values
after the fault. Similar to the results presented in Fig. 10, the power and voltage
controlled stations nd the operation point where the dc-dc is absent. Figure 12b
presents the dc currents in the SyM and how they are blocked in a short time (less
than 50 ms). The currents through the dc-dc converter are presented in Fig. 12c. The
dc-dc converter is able to isolate the RB line during a fault in the SyM allowing the
rst to regain steady state operation without triggering any protection.
Figure 13 presents the energy in the dc-dc converter during and after the 16 faults
cases of Table 2. Figure 13a presents the cases for a fault on the RB side. In these
scenarios the energy variations are near 1% of the nominal value (30.24 MJ). For the
cases where the fault is located on the SyM (Fig. 13b), the energy in the converter
increases up to 110% as a consequence of the FBSMs charging as they stop the fault
current.
Figure 13 - Energy in the dc-dc converter for (a) a fault in the RB (odd cases of Table 2) and (b) a fault in
the SyM (even cases of Table 2)
6. Conclusions
Dc-dc converters are needed for the interconnection between dc systems with
different characteristics. The present publication explores the hypothetical
interconnection between the NordLink (rigid bipole - RB) and Cobra Cable
(symmetric monopole – SyM), using a non-isolated dc-dc converter.
The case study was modelled and simulated in Matlab/Simulink. The power ow in
the lines and through the dc-dc converter was changed to simulate 8 possible normal
conditions. These initial simulations validated that the exchange of power between
the two lines does not trip any protection. After validating the converter behavior in
normal operation, a set of 16 fault cases were simulated. Satisfactory results were
obtained for the dc-dc converter rewall capability: in case of a fault in a line, the dc-
dc converter is able to stop the fault propagation to the healthy system. This rewall
capability was validated independently of the power ow direction or the fault
location. If enough FBSMs are installed in the dc-dc converter, the rewall capability
can be ensured without the presence of dc circuit breakers.
The case study proposed in this paper did not change the grounding strategy and
reference points of the initial links. A dc reference is found on the RB and an ac
reference on the SyM line. In this particular case, no problems were found, but
further studies must be carried to check the impact of multiple reference points on
the protection strategy and isolation coordination.
Further studies should evaluate the impact of the ac faults on the dc-dc converter
control strategy and fault detection algorithm. Additional fault studies should be
done to assess the dc-dc converter behavior under different fault conditions.
Different types of faults and locations should be tested. Supplementary studies can
be done for the degraded operation, where a fault in the interconnected system leads
to the isolation of a portion of a line (e.g. a three-terminal system or the RB
recon guration into an asymmetric monopole - isolating the faulted converter).
Acknowledgment
This work has been supported by a grant overseen by the French National Research
Agency (ANR) as part of the “Investissements d’Avenir” Program (ANE-ITE-002-01).
References
1. CIGRE WG. B4.52, “HVDC Grid Feasibility Study.” CIGRE, Apr-2013 [Online].
Available: https://ecigre. org/publication/533-hvdc-grid-feasibility-study
2. J. D. Páez, D. Frey, J. Maneiro, S. Bacha, and P. Dworakowski, “Overview of DC–DC
Converters Dedicated to HVdc Grids,” IEEE Transactions on Power Delivery, vol.
34, no. 1, pp. 119–128, Feb. 2019.
3. D. Jovcic, P. Dworakowski, G. Kish, A. Jamshidi Far, A. Nami Abb, A. Darbandi, and
X. Guillaud, “Case Study of Non-Isolated MMC DC-DC Converter in HVDC Grids,” in
CIGRE Symposium 2019, 2019.
4. D. Gómez, J. D. Páez, M. Cheah-Mane, J. Maneiro, P. Dworakowski, O. Gomis-
Bellmunt, and F. Morel, “Requirements for interconnection of HVDC links with DC-
DC converters,” in IECON 2019-45th Annual Conference of the IEEE Industrial
Electronics Society, 2019, vol. 1, pp. 4854–4860.
5. M. Goertz, C. Hirsching, S. Wenig, K. M. Schäfer, S. Beckle, J. Reisbeck, M. Kahl, M.
Suriyah, and T. Leibfried, “Analysis of overvoltage levels in the rigid bipolar MMC-
HVDC con guration,” in 15th IET International Conference on AC and DC Power
Transmission (ACDC 2019), 2019, pp. 1–6.
6. G. J. Kish and P. W. Lehn, “Modeling techniques for dynamic and steady-state
analysis of modular multilevel DC/DC converters,” IEEE Transactions on Power
Delivery, vol. 31, no. 6, pp. 2502–2510, 2015.
7. G. J. Kish, M. Ranjram, and P. W. Lehn, “A Modular Multilevel DC/DC Converter
With Fault Blocking Capability for HVDC Interconnects,” IEEE Transactions on
Power Electronics, vol. 30, no. 1, pp. 148– 162, Jan. 2015.
8. T. Lüth, M. M. Merlin, T. C. Green, F. Hassan, and C. D. Barker, “High-frequency
operation of a DC/AC/DC system for HVDC applications,” IEEE Transactions on
AUTHORS
Summary
The integration of new technologies is an on-going element of Grid Modernization.
New technologies receive intense focus, sometimes at the expense of emphasis or
awareness in other areas. Grid automation is an inherently complex task, bringing
together many specializations. Utilities have evolved internal organizational
structures that recognize and support the multi-disciplinary approach needed for
successful automation implementation. IEC 61850 and disruptive Internet of Things
(IoT) technologies present new paradigms that can challenge these traditional
structures and adoption of such technologies may best be supported by refactoring
traditional work ows. In such restructuring, emphasis is often placed on addressing
new requirements and integrating new methods of engineering systems. In doing so,
it is easy to overlook on-going needs of existing systems and functions or to neglect
to take the opportunity to review whole-of-life information management of the
system. For some systems, additional design effort can yield dividends in additional
functionality or reduced operational expense.
The introduction of IEC 61850 brings a need for closer cooperation between
protective relay engineering, substation automation, SCADA, eld test and
communication system functions. For some utilities this can represent a signi cant
restructuring of work ows and responsibilities, thus presenting an opportunity for
improved cooperation and information sharing between historically-independent
functional groups.
Systems are becoming more complex and offer a growing number of capabilities. It is
necessary to manage those capabilities in a manner that simpli es each person’s
role and assists them to avoid mistakes that negatively impact system performance.
An integrated method of managing equipment and securing access to information is
one tool that can aid this process.
KEYWORDS
1. Introduction
The evolution of the grid, the development and inclusion of new control devices and
the foreseeable integration of IoT devices each expand the amount and diversity of
information used in grid management.
Recent introductions such as IEC 61850 and Phasor Measurement Units are
examples of new technologies which provide new operational data, but also depend
on speci c functionalities of the associated communications and con guration
management systems.
New sources of data can enable new applications such as system stability analysis
from phasor measurements or allow new business practices such as performing
maintenance based on asset monitoring instead of on a periodic basis.
2. Business drivers
Many utilities have organizational structures that have separate responsible entities
for functions such as power system planning, control system design, protection,
communication, system engineering (con guration, testing and maintenance),
operations, asset management, disturbance analysis, etc. These separate areas of
responsibility and their operating procedures have evolved with the evolution of the
grid. IEC 61850 integrates aspects of several of these areas of responsibility. Some
utilities have found that adoption of these new technologies can stimulate or even
The adoption of new technologies and standards typically provides value in terms of
offering additional functionality coupled with manageable additional engineering to
achieve that functionality. The adoption of new technologies does not replace the
need to properly engineer system design, however, they may provide tools to
simplify that task or parts of it. The framework provided by complex standards
provide for consistent and interoperable interpretations of data, commands and
con guration information. Without such common frameworks, the implementation of
complex functions would require additional engineering and expense.
3. Design considerations
When integrating new technology or new functionality, the impacts of that technology
or functionality on other aspects of the utility business need to be considered, so as
to ensure that all services and support needed by the new technology (e.g.
communication system updates, additional staff training, etc.) are also incorporated
as part of the project.
Further bene t may also be derived if it is feasible to also integrate the new
technology with other stakeholder use cases. For example: The provision of
enhanced communication services may permit access to additional data for other
purposes such as asset health monitoring, remote device access for engineering and
maintenance, etc. If the needs of all utility divisions are considered as part of any
project, the overall capability and ef ciency of the utility may be enhanced by using
the opportunity to also integrate support for the various data use cases of each group
of users. At a minimum, any new automation project should consider on-going
system operation and management needs as part of the design process. This may
consider aspects such as:
4. Architectural considerations
The need to ensure isolation of the automation system equipment from the corporate
IT network (and, beyond that, the public internet), while also allowing controlled
access to data from various users will typically lead to a review of the communication
system architecture requirements. Guidance on this is available from various
sources, e.g.: NIST SP-800-82 [1]. When controlling access into an operational
automation device network, it is usually appropriate to use architectures that
conform to a “Zones and Conduits” model as described in IEC 62443 [2] where data
between a less trusted network (the “Enterprise Zone”) and a more trusted network
(the automation system zones) is only permitted through controlled paths (the
conduits) and is monitored and managed to ensure that only permitted traf c passes
between zones. Each utility should make its own determination regarding such
architectural analysis and how its cybersecurity policies can be implemented while
also providing the required functionality. In general, zones are rewalled from each
other and care should be taken to avoid simply opening “holes” through the rewall
for automation system traf c: More sophisticated architectures with demilitarized
zones and jump servers are typically required that do not permit direct access from
one zone to another.
When the various kinds of substation and distribution devices are included, together
with the various communication systems used to access those sites and the
integration with data collected for various operational and non-operational purposes
is directed to the users who have responsibility for that information, an architecture
might result such as that shown in Figure 1. Different kinds of data will typically use
different protocols: Operational data might use IEC 60870-5 or IEC 61850; fault
records might be collected as COMTRADE les; maintenance engineering will usually
use a proprietary vendor protocol. The integrated system is responsible for ensuring
that each user is provided access to the information required to perform their role
and to isolate that data from any impact caused by other users or functions.
5. Standards
IEC 61850 is now seen to provide functional bene ts and is expanding its reach to
wider segments of the electric utility space, but it still does not address all functional
requirements.
Various functions remain out-of-scope for IEC 61850. For example: A protection relay
may have settings and settings groups that can be modi ed remotely, but not
protected by the same kind of cybersecurity authorization requirements (e.g.
username, password) as would be required through a typical vendor’s maintenance
tool. As of the beginning of 2022, the only aspect of device management discussed in
IEC 61850 is an ability to update IED rmware and con gurations, described in
Technical Report IEC TR 61850-90-16 [3].”
Access to the data within IEDs may be made for many purposes. Different users have
differing data access needs to perform their responsibilities. Work is underway to
de ne how an IED using IEC 61850 might impose role-based-access restrictions to
different data for different users, but this remains a work in progress and includes
considerable complexity. For non-IEC 61850 access, each different device may
impose whatever restrictions or controls the manufacturer implements through their
maintenance tools. In addition to this, the utility may determine that addition
cybersecurity access controls are required over and above those available natively
in the product tools. Enforcing the utility’s cybersecurity policies might require
additional procedures (work ows, training, etc.) or additional technical measures to
manage data access, create auditable logs, verify device operation, etc.
6. Other considerations
Following is a list of some factors that may affect design choices and therefore should
be considered during grid automation system projects:
7. Conclusions
Utility automation systems consist of many differing subsystems. There is typically a
range of equipment types, functions performed, data available and communication
protocols supported by that equipment. Many users have a legitimate need to access
some subset of information available in the various subsystems and may have
differing needs for the timeliness of that access (from the immediate update of
operational SCADA data to historical archive data retrieval). An integrated
automation system should give all users timely access to all information they need to
perform their tasks, irrespective of the actual source of that information. All access
should be secured appropriately to allow authorized access and prevent
unauthorized access or alteration. Each user should have such access with the
minimum of impediment caused by cybersecurity functions that control the access.
The process should be suf ciently intuitive as not to require extensive training.
References
1. National Institute of Standards and Technology: Special Publication (NIST SP) -
800-82 Rev 2 Guide to Industrial Control Systems (ICS) Security, NIST,
Gaithersburg, USA, 2015.
2. International Electrotechnical Commission: IEC TS 62443-1-1:2009 Industrial
communication networks - Network and system security - Part 1-1: Terminology,
concepts and models, IEC, Geneva, 2009.
3. International Electrotechnical Commission: IEC TR 61850-90-16:2021
Communication networks and systems in power utility automations - Part 90-16:
Requirements of system management for Smart Energy Automation, IEC, Geneva,
2021.
AUTHORS
Summary
The downsizing of gas-insulated switchgear (GIS) and gas insulated transmission
line (GIL) will lead to a reduction in their cost, installation area, manufacturing
energy, and use of SF6, which is an extremely potent greenhouse gas. However, there
is a limitation in the insulation techniques by the conventional composite material
technology.
For NMC materials, epoxy resin with SiO2 micro- ller (MC) was lled with 1 vol % of
nano ller (SiO2, TiO2, SrTiO3, Al2O3) to fabricate a 1/4 size cone-type spacer model. In
the case of positive LI voltage in 0.5 MPa-abs, the scale parameter (η) of the Weibull
distribution of the FOV of the nTiO2- lled and nSrTiO3- lled NMC materials was
increased by 12% and 20%, respectively, compared to the MC (without nano- ller).
For ε-FGM, 1/4 size cone type insulating spacer was also produced as well as NMC,
and FOV was measured. ε-FGMs with relative permittivities (εr) distributed between
12.7 and 4 were designed and fabricated using SrTiO3 and SiO2 micro- llers. The FOV
KEYWORDS
Insulating Spacer - GIS - nano-micro composite - functionally graded materials - flashover voltage
1. Introduction
The downsizing of gas-insulated switchgear (GIS) and gas insulated transmission line
(GIL) will lead to a reduction in their cost, installation area, manufacturing energy,
and use of SF6, which is an extremely potent greenhouse gas. However, there are
limitations to conventional composite materials technology. Therefore, Fuji Electric
Co., Ltd has participated in the "Development of Innovative Functional Insulating
Materials for Electric Power Apparatus" project subsidized by the New Energy and
Industrial Technology Development Organization (NEDO) since 2017, and it has
collaborated with several universities and materials manufacturers to use nano-
micro composite (NMC) material and permittivity functionally graded material (FGM)
to improve the performance of insulating spacers [1]-[7]. Fig. 1 shows an image of an
insulating bus comprising a cone-type insulating spacer and tanks. The target value
for downsizing this spacer is 30% of its diameter and 50% by volume.
First, in order to clarify whether NMC is applied to the cone type insulating spacer
and the insulating property is improved, a 1/4 size cone-type spacer model was
fabricated, and FOV in the SF6 gas was measured by standard lightning impulse
voltage.
Next, to clarify whether ε-FGM is applied to the cone type insulating spacer and the
insulating property is improved, similarly a 1/4 size cone-type spacer model was
fabricated, and the FOV was measured. And the inverse analysis system of
permittivity distribution was newly developed in order to form the electric eld
grading by ε-FGM accurately and ef ciently.
2.1. Experimental
Table 1 lists the nano- llers used in the
experiment. Bisphenol A epoxy resin
was used as the main agent, alicyclic
acid anhydride was used as the curing
agent, and dimethylbenzylamine Table 1 - List of nano llers for each sample
(BDMA) was used as the catalyst. The
micro- ller was lled with 47 vol% SiO2
(hereafter referred to as (a) MC). Four
kinds of nano- llers, SiO2, TiO2, SrTiO3,
and Al2O3, were selected and lled to 1
vol% of MC. Here, the above samples are
referred to as (b) NMC-nSiO2, (c) NMC-
nTiO2, (d) NMC-nSrTiO3, and (e) NMC-
nAl2O3, respectively.
It has been reported that the initial electron emission from the insulating spacer
contributes to the polarity effect appearing in the impulse FOV of the epoxy spacer in
GIS. However, this study shows that the deep electron trap level is formed by
nanocomposite from the analysis by quantum chemical calculation, and that this
improves the FOV in the model electrode system in SF6 gas. From the above research
report, the effect of deep trap level formation by the nano ller addition on the
ashover voltage characteristics of the insulation spacer model obtained in this
study is discussed from the viewpoint of creeping discharge generation and
progress. That is, the following are assumed: FOV generation by the initial electron
supply from the insulating spacer surface and the streamer generation condition of
Schumann and the creeping discharge process from the streamer progress at the
insulator interface to the dielectric breakdown.
Fig. 4(a) shows an example of the discharge trace after the ashover test, while Fig.
4(b) and 4(c) show a model diagram of the creeping discharge mechanism at negative
and positive impulse voltages for the insulating spacer model. As shown in Fig. 3 and
Table 2, the FOV of the nano- ller added spacer sample hardly changed in the
negative polarity, while the FOV of NMC-nTiO2 and NMC-nSrTiO3 greatly improved in
the positive polarity. That is, when the HV conductor had a negative polarity, the FOV
improvement effect was not observed by the addition of nano ller because the initial
electron injection from the HV conductor became the main factor of the FOV
determination. However, when the HV conductor had a positive polarity, the initial
Figure 4 - Example of discharge trace after flashover test and discharge model diagram of polarity effect
in GIS spacer model
In this study, a cone-type FGM spacer made by variable compounding casting was
used. For this reason, it was assumed that the dielectric permittivity was in the axial
direction, and its distribution in the radial direction was uniform. Here, as shown in
Fig. 5(a), the inside of the spacer is divided into small regions, and each dielectric
permittivity is set to εi. The potential at the boundary of different regions on the
surface of the spacer is de ned as Vi.
Because each region is formed into a thin plate shape, it can be replaced with a
parallel plate capacitor. That is, it can be expressed by a series capacitance, as shown
in Fig. 5(b). To approximate the desired electric eld intensity distribution, the
desired dielectric permittivity distribution can be attained using an inverse solution
approach by considering a method to assign a voltage to each capacitance by
changing the dielectric permittivity. In the analysis, an appropriate dielectric
permittivity distribution was given to the spacer, and electric eld analysis was
performed using the nite element method to obtain the potential sharing of each
part of the spacer. From this potential sharing, the dielectric permittivity distribution
of each region of the spacer was attained and used to perform electric eld analysis.
This process was repeated to gradually reduce the electric eld intensity. Once the
electric eld intensity distribution converged, the calculation was terminated.
3.2. Experimental
For ε-FGM, a 1/4 cone-type insulating spacer was fabricated by a exible mixture
casting method as shown in Fig. 7, and the FOV was measured. The ε-FGM spacer
had a seamless distribution of εr = 12.7 - 4.0 (red line) from the HV conductor to the
grounded tank in the radial direction. In comparison with the ε-FGM spacer, the
uniform spacer had a permittivity εr = 4.0. We used two kinds of llers, SrTiO3 and
SiO2, and their composite with epoxy resin. SrTiO3 had a large permittivity of εr=332
and, as the main ller, was used to determine the εr distribution of the ε-FGM spacer.
The mixing ratio of the two composites was continuously controlled with two syringe
pumps and a static mixer, and then combined to create a cone-type ε-FGM spacer
(diameter: 60 mm), as shown in Fig. 8. A uniform spacer with the same shape and
size as the ε-FGM spacer was fabricated using only the SiO2 composite.
Moreover, the discharge of the uniform spacer is all creeping discharge on the
concave side, and it is suggested that the high-voltage shield edge, which has the
largest electric eld, is the origin. On the other hand, the discharge of the ε-FGM
spacer is gap discharge on the concave side (11 pieces) and a creeping discharge on
the convex side (3 pieces), suggesting that the dielectric permittivity distribution of
ε-FGM relaxes the electric eld at the shield edge of the high-voltage side and
improves the ashover voltage [10].
Fig. 10 shows the cross section of Actual Figure 10 - Actual size cone-type spacer model
size cone-type FGM spacer. The outer
diameters of HV conductor is 90 mm
and the inner diameter of grounded
tank is 240 mm, respectively. The
con guration of the grounded tank
around the spacer is modi ed in
consideration of the actual GIS spacer.
The relative permittivity (εr) is reduced
in 6 steps from εr=10 around the HV
conductor to εr=4 around the grounded
tank.
Fig. 12(a) shows a uniform spacer of εr=4, and Fig. 12(b) shows a FGM spacer of
εr=10-4. In Fig. 12(b), the white region is εr=10, the black region is εr=4, and the gray
region between them is a graded region.
5. Conclusions
The summaries of this study are described below.
1. As a result of measuring the FOV in SF6 gas at 0.5 MPa-abs with 1/4 size cone-
type spacer applying NMC material, it was shown that, for positive impulse
voltages, the use of nTiO2 or nSrTiO3 increased the FOV by 12% or 20%,
respectively, compared with the MC.
2. By the inverse analysis method of the dielectric permittivity distribution, the
maximum electric eld around the ε-FGM spacer is reduced, and as a result, it is
It was clari ed that both NMC and ε-FGM can improve the insulation characteristics
of the cone-type insulating spacer. And, by applying the FGM technology in the range
of pressure of 0.5-0.6 MPa-abs in 245 kV class GIS, it was clari ed in the actual size
that FOV of the FGM spacer increased about 21-29 % over uniform spacer of the
conventional technology. That is to say, this indicates that the application of the FGM
technology is very effective in gas insulation and gas solid insulation systems such
as GIS and GIL, and the target of size reduction of about 30% in comparison with the
conventional one at the beginning is expected.
In the future, AC withstand voltage test, partial discharge test, long term withstand
voltage test, etc. will be carried out for 30% downsizing of 245 kV class GIS spacer
and bus duct con gurations.
Acknowledgment
This paper is based on results obtained from a project (JPNP12004) commissioned
by the New Energy and Industrial Technology Development Organization (NEDO).
References
1. N. Matsuoka, Y. Fuchi, M. Kozako and M. Hikita, “Effect of Permittivity Variation on
Surface Flashover of GIS Epoxy Spacer Model in SF6 Gas,” IEEE ICD, pp.96-99,
2016.
2. K. Abe, K. Ohzuno, M. Kozako, M. Hikita, H. Mitsudome, H. Yanase and K. Okamoto,
“Partial Discharge Inception Voltage Characteristics for Nano-micro Composites
under Impulse Voltage in SF6 Gas”, IEEE CEIDP, pp.738-741, 2019.
3. Hitoshi Okubo, Hideki Shumiya, Masahiro Ito and Katsumi Kato,“Insulation
Performance of Permittivity GradedFGM (Functionally Graded Materials) in SF6
Gas under Lightning Impulse Conditions”, Conference Record of the 2006 IEEE
International Symposium on Electrical Insulation, IEEE, pp.332-335, 2006.
4. Hitoshi Okubo, Hideki Shumiya, Masahiro Ito and Katsumi Kato, “Optimization
Techniques on Permittivity Distribution in Permittivity Graded Solid
Insulators”, Conference Record of the 2006 IEEE International Symposium on
Electrical Insulation, IEEE, pp. 519-522, 2006.
5. H.Okubo, K.Kato, N.Hayakawa, M.Hanai, M.Takei, “Functionally Graded Materials
and their Applicationsto High Electric Field Power Equipment”, CIGRE SC D1 –
COLLOQUIUM IN HUNGARY BUDAPEST, 2009.
6. N. Hayakawa, K. Kato, H. Hama, Y. Hoshina and T. Rokunohe, “Electric Field
Grading Techniques in Power Apparatus Using Functional Materials,” CIGRE
Paris Session, D1-309, 2014.
AUTHORS
Summary
D owntimes of high-voltage equipment can be reduced by detecting abnormalities
before faults occur, a task that can be performed by machine-learning (ML)
diagnostic systems. Training such diagnostic systems requires data containing fault
conditions. However, fault-condition measurements are often not available due to
low fault rates. This raises the question of whether ML-diagnostic systems trained
with synthetic data are valid predictors for real applications.
In this paper, synthetic data is generated with digital simulations of normal- and
fault conditions of a high-voltage pantograph disconnector to train multiple ML-
diagnostic systems. A system selection is executed using normal-condition
measurements and the synthetic data only. Finally, the performance of the selected
systems is evaluated with measurements of a disconnector with additional weight
load.
The results show that most of the ML-systems trained with synthetic data are
capable to detect the fault conditions. The systems based on arti cial neural
networks show the best diagnostic performance.
KEYWORDS
Fault detection - fault diagnosis - fault simulation - machine learning - power engineering
1. Introduction
The digitalisation of energy systems in recent years has generated a large amount of
data that is dif cult to interpret by experts due to the numerous dependencies and
complexity of the systems. Diagnostic systems based on machine learning (ML) have
the potential to learn these complex dependencies [3] and diagnose pre-fault or fault
conditions [4]–[7]. The rules for evaluating the condition of the equipment are
determined by the ML algorithm [8]. To train the ML-based diagnostic systems well,
large amounts of data containing both normal and fault conditions are required [9]–
[13]. Due to the high reliability of equipment and low adoption levels of connected
monitoring systems, there are only limited measurements available, especially fault-
condition measurements [4], [14], [15]. A solution to this challenge is to train and
verify the ML-based diagnostic systems with synthetic data.
However, training ML-based diagnostic systems with synthetic data raise the
question of whether these systems can improve the quality of the diagnosis for real
applications.
This paper examines the training, veri cation and validation of diagnostic systems
trained with synthetic data, as shown in Fig. 1. A key in generation of proper training
data is to develop a computer-implemented electromechanical model of the device
to be diagnosed. Then, a statistical simulation method is developed to parametrize
the model for fault- and normal conditions. The basis for the fault-condition
simulations is the knowledge from operational experience and literature. Synthetic
data are generated for the drive motor current of a pantograph disconnector during a
making process and features are extracted from the synthetic data. In the second
step, ML-diagnostic systems and a threshold diagnostic system are trained and
created with the generated synthetic data of the pantograph disconnector. An
evaluation of the performance of diagnostic systems to determine the best diagnostic
systems for the task is carried out using the synthetic data and normal condition
measurements. Finally, the selected diagnostic systems trained with the synthetic
data are tested with measurements from a pantograph disconnector loaded with
additional weight. These measurements are generated by experiments in a
laboratory environment.
70.4 % of the disconnector major failures result in not closing or opening and 6.7 %
result in locking in the open or closed position [20]. Fig. 3 shows the origin of major
failures of 1,493 reported failures. The most major failures (34.8%) occur due to
failures in the mechanical operating mechanism.
The simulation of the variation within the normal condition requires normal-
condition measurements of the monitored value or values to determine model
parameters. An optimisation of m model parameters is conducted to minimise the
error between the measurement and the model’s output. This results in n parameter
sets of 𝑆1,…,𝑛 for the model. Each set contains m parameters of 𝑃1,…,𝑚. These
parameter values are used to calculate probability distributions for each parameter
and to t a normal distribution, as shown in Fig. 4 a). When a normal-condition
simulation is conducted, the parameter values of the electromechanical model are
randomly selected according to the probability distribution of each parameter [28]–
[31].
The proposed method is not capable of simulating drastic fault conditions resulting
in a completely changed equipment behaviour. Only faults or failure modes that can
be linked to parameters of the electromechanical model can be simulated.
Figure 4 - (a) Normal- and abnormal-condition distribution of the motor friction parameter [28] / (b)
Fault de nitions [28]
check and b upper , F and b lower , F are the upper and lower thresholds. The output of
n n
⎧⎪
⎪⎪ 1 if F n ≥ b upper ,F ⎫⎮
⎮⎮
⎪⎪ n ⎮⎮
OF = ⎨⎪
⎪⎪ 1 if F n ≤ b lower ,F ⎮⎮
⎬⎮ (1)
n
n ⎪⎪ ⎮⎮
⎪⎪ 0 if b < F n < b upper ,F
⎮⎮
⎪⎪ lower ,Fn n
⎮⎮
⎩ ⎭
⎧⎪ normal condition , if max ⎧⎪ O ,. . .,O ⎫⎮ = 0
⎪⎪ ⎨⎪ F F n ⎬⎮
1
Out = ⎨⎪ (2)
⎪ ⎩ ⎭
⎪⎪ f ault condition , if max ⎪⎨ O ,. . .,O ⎮⎬ = 1
⎧ ⎫
⎪⎩ ⎪⎩ F 1 Fn ⎮
⎭
b u0 + b l0 b u 0 − b l0
b up , F = +X (3)
n 2 2
b u0 + b l0 b u 0 − b l0
b low , F = +X (4)
n 2 2
The T-based diagnostic system only detects but does not classify fault types. For a
fault type classi cation, a knowledge management system would be necessary.
[1] Note that the threshold for ML systems q is different from the T-based system threshold b.
a CD normalCondition + CD faultCondition
WCDR a = (13)
a n normalCondition + n faultCondition
Figure 7 - Absolute (red) and gradient features (green) highlighted in the motor current signal. The
features represent physical events in the disconnector’s closing process
Seven physical and electrical faults, listed in Table III, are simulated. The faults are
based on the operational knowledge of utility personnel. For this paper, the
parameter distributions for simulating abnormal conditions are uniform and range
from 5 s to 25 s (Fig. 4 a). A starting point of 5 s ensures that the parameter to
simulate the fault condition is selected outside of the established normal-condition
distribution. Such a starting point results in fault conditions that match theoretical
fault analysis [28]. In total, 20,000 simulations are carried out in eight groups, each
containing 2,500 simulations. One group contains normal-condition data, where the
normal distribution of the parameter is assumed. The other seven groups contain the
synthetic data simulated with the abnormal conditions from Table III.
Short circuit or deformation of the drive motor windings Factor for motor magnetisation function
Short circuit of the drive motor windings, increased Motor resistance value
cable resistance
In the next step, the main discrete features are extracted from every generated
synthetic signal. The ANFIS- [24] and ANN-based [33] systems are trained with the
features extracted from the 20 000 synthetic normal- and fault-condition data. The
task is to classify if the data belongs to a fault condition or a normal condition. For
the training, the simulations are divided into 80% training data and 20% validation
data for the training of the ANN- and ANFIS-based diagnostic systems to avoid
over tting.
Because the computing time for the ANFIS training is remarkably longer than that
for the ANN training, a subset of the extracted features is used as ANFIS input. In
order to nd the most valuable features for each ANFIS model, a sensitivity analysis
for all features and the hyperparameters listed in Table IV is conducted. Each
training is repeated 24 times with the same con guration to minimize the possibility
that the nal result is a local minimum. To train diagnostic systems with different
fault sensitivities, three fault-condition de nitions (FD = 5 s, FD = 10 s, and FD = 15 s)
are determined, as shown in Fig. 4 b).
Table 6 - Percental deviation of characteristic values of the synthetic data’s boxplots to the corresponding boxplot
values of the measurements
Figure 10 - (a) Histogram of the ANN models’ output -(b) Histogram of the ANFIS models’ output
Fig. 10 b) shows a histogram of the output of all ANFIS-based models for all
simulated data. 92.1% of the outputs are in the range between –0.5 and 1.5. The
ANFIS models do not converge to certain values. The threshold 𝑞𝐴𝑁𝐹𝐼𝑆 needs to be
adjusted in order to nd the optimal fault thresholds. Therefore, 𝑞𝐴𝑁𝐹𝐼𝑆 is variated in
the range of –0.1 to 1.1 in increments of 0.1.
For a fault de nition of 𝐹𝐷 = 5 𝑠 the Pareto frontiers of the T-based systems are
superior to the ANN- and ANFIS-based systems. The T-based systems have a smaller
HW for the simulations than the ANFIS- and ANN-based systems, but there are T-
based systems that always classify the measurements correctly, leading to the
largest AuF ( 𝐴𝑢𝐹 = 0.86 ) of the three methods. The results show that the ANN-based
systems are superior to the ANFIS- and T-based systems for a fault de nition of FD =
10 s and FD = 15 s, with AuFs of 0.966 and 0.998, respectively. For these fault
de nitions, there are T-, ANFIS- and ANN-based systems that always classify the
conditions of the measurements correctly.
The Pareto frontier systems of the ANN- and ANFIS-based systems show good
validation results for the normal-condition measurements, with a 𝑊𝐶𝐷𝑅1 of up to
100% for 𝐹𝐷 = 15 𝑠. However, there are ANN-based systems with good results for the
simulated data where the validation for measurements shows comparably poor
results (clustered in a 𝑊𝐶𝐷𝑅20 range between 99.1% and 99.8%, highlighted with a
red arrow). This indicates that ANFIS- and ANN-based systems trained with
simulated data also need to be validated with measurements.
An overall improvement in the Pareto frontiers with an increasing fault de nition can
be observed. This indicates that the transferability of the Pareto frontier systems
trained with simulated data to measurements is better with a fault de nition FD = 15
s. The ANN-based frontier systems outperform the T- and ANFIS-based ones.
Therefore, ANN-based systems, trained with synthetic data with a fault de nition FD
= 15 s and a high WCDR for measurements and simulated data should be chosen for
the real application.
Therefore, these diagnostic systems are evaluated for seven measurements of the
disconnector loaded with additional weight. Because the systems are not trained to
identify this additional weight load, the evaluation validates whether the diagnosis
output is plausible or not. The evaluation checks whether 1) all seven measurements
of additionally loaded disconnector are diagnosed as normal conditions (insensitive),
2) the rate of fault-condition diagnosis increases with increasing weight (plausible),
or 3) the rate of fault-condition diagnosis is unrelated to the weight (implausible).
Fig. 14 shows a detail of the results of the ANN-based systems trained with 𝐹𝐷 = 15 𝑠
and a high WCDR for both synthetic data and measurements. The ANN-based
systems are marked according to whether they are implausible, plausible or
insensitive. The gure shows, that none of the ANN-based systems trained with 𝐹𝐷 =
15 𝑠 and a high WCDR for synthetic data and measurements show implausible
diagnosis for the data of the disconnector loaded with additional weight. This
indicates that utilizing MLdiagnostic systems for real applications is possible.
Figure 14 - Diagnosis of additional weights on the disconnector arms for systems trained with 𝐹𝐷 = 15 𝑠
Quantity of data 1 2 1 3
sets
Table 8 - Fault-condition diagnosis rate of systems S1 and S2 regarding weights on the disconnector arms
Additionally, the remaining ANN- and ANFIS-based diagnostic systems are tested
with the measurements from the disconnector loaded with additional weight. In total,
65.7% of the ANN-based systems trained with 𝐹𝐷=15 𝑠 are plausible, 15.0% are
insensitive, and 19.3% are implausible systems for weights attached to the
From the previous analysis we can conclude that transferring ML-based diagnostic
systems to real-world application is possible and even detect fault conditions they
are not trained for.
5. Conclusion
In this paper, it is examined whether synthetic data can be used to generate
diagnostic systems for real-world application when fault-condition measurements
are not available. ANN- and ANFIS-based diagnostic systems trained with synthetic
data and T-based diagnostic systems were considered. The synthetic data were
generated with an electromechanical model of a disconnector and a normal-
condition and a fault-condition simulation method. Different fault intensities were
considered in the process. A multi-criteria veri cation and validation was conducted
on the rate of correct diagnoses for measurements and simulated data to identify
potential diagnostic systems for real-world application. The multi-criteria evaluation
prevented selecting over tted of ANN and ANFIS models, models that always
predicting the normal conditions for measurements. The evaluation shows that the
rate of correct diagnosis for synthetic data depends on the fault type, the fault
intensity, the ML algorithm and the algorithm hyperparameters.
The ANN-based diagnostic systems with a high WCDR for both synthetic data and
measurements are the most appropriate for the pantograph disconnector. These
diagnostic systems are validated against measurements from a disconnector with
additional weight load to imitate a fault that the diagnostic systems are not trained
with. Even though the diagnostic systems are not trained for that speci c use case,
65.7% of the ANN-based diagnostic systems and 92.2% of the ANFIS-based ones
were capable of plausibly detecting the modi cation.
The investigation shows that ML-based diagnostic systems trained with synthetic
data are promising and it could be applied to other equipment and applications.
Further research is needed to validate the proposed method for other applications.
References
1. Ewg, Energiewirtschaftsgesetz: Gesetz über die Elektrizitäts- und Gasversorgung
EnWG. Letzte Änderung 18/12/2018., 2005.
2. Y. Han und Y. H. Song, “Condition monitoring techniques for electrical equipment
- a literature survey”, IEEE Trans. Power Delivery, 18. Jg., Nr. 1, pp. 4–13, 2003.
3. H. Su und K. T. Chong, “Induction Machine Condition Monitoring Using Neural
Network Modeling”, IEEE Trans. Ind. Electron., 54. Jg., Nr. 1, pp. 241–249, 2007.
4. M. Zekveld und G. P. Hancke, “Vibration Condition Monitoring using Machine
Learning” in IECON 2018 - 44th Annual Conference of the IEEE Industrial
Electronics Society, 2018.
5. S. Ma, M. Chen, J. Wu, Y. Wang, B. Jia und Y. Jiang, “High-Voltage Circuit Breaker
Fault Diagnosis Using a Hybrid Feature Transformation Approach Based on
Random Forest and Stacked Autoencoder”, IEEE Trans. Ind. Electron., 66. Jg., Nr.
12, pp. 9777–9788, 2019.
6. T. Boukra, A. Lebaroud und G. Clerc, “Statistical and Neural-Network Approaches
for the Classi cation of Induction Machine Faults Using the Ambiguity Plane
Biographies
AUTHORS
Summary
Hydrophobic properties of composite insulators might be deteriorated in service
by continuous corona activity on the housing material itself or by corona from the
metal parts directed towards the housing. This issue should be considered already at
the design stage, i.e., the electric eld should be controlled and limited in a few
sensitive areas of an insulator. The criteria for limitation of the electric eld in the
sensitive areas of composite insulators are well established in the international
literature, but not implemented yet in CIGRE/IEC recommendations. In this paper,
the criteria are evaluated by electric eld calculations of twenty-six commercially
available insulators from seven different manufacturers. Laboratory test results then
con rm the results of calculation interpretation. It seems that manufacturers of line
composite insulators design their products with these criteria in mind. Thus,
standardization in relevant IEC standards should be considered, as these criteria are
already widely adopted.
composite insulator - electrical eld - hydrophobicity - water drop corona - laboratory test method
1. The limit of electric eld on the grading/corona ring and end tting. Note, the
criterion cannot be properly applied for arcing horns because the electrical eld
might be intentionally increased on them to attract the power arc and protect the
hardware.
2. The limit of electric eld along the housing surface.
3. The limit of electric eld at the so-called triple point (where air and housing meet
the metal end tting). An example of the triple point adopted from a draft of the
revised IEC standard 62217 is shown in Figure 1.
All three criteria listed above are normally veri ed by electric eld calculations. The
rst criterion can also be veri ed by a standard RIV, or corona test described in IEC
[3] and [4]. The third criterion cannot be veri ed by a test but only by calculation.
The goal of this paper is to update the state-of-the-art of criteria and test methods for
the veri cation of the limitations of the electric eld via literature and CIGRE/IEC
activities. Additionally, recent results of electric eld calculations and tests for the
commercially available insulators already purchased by different power utilities are
analyzed. Following the latter issue, a group of eight European power companies
(both TSOs and DSOs) together with the Independent Insulation Group (I2G, Sweden)
is running a collaborative research project intended to benchmark composite
insulators. The electric eld calculation/veri cation is one of the activities within the
project. The following companies supported this project: 50Hertz (Germany),
Amprion (Germany), APG (Austria), E.ON (Germany), Fingrid (Finland), RTE (France),
Statnett (Norway), Svenska kraftnät (Sweden).
1. The limit of E- eld on the grading ring and end tting 1,8 kV/mm
2. The limit of average E- eld along the housing surface 0,42 kV/mm
3. The limit of E- eld at the so-called triple point 0,35 kV/mm.
Figure 2 - Typical examples of electric eld calculations for different designs of composite insulators
(adopted from [2]). Colour scale: 0 – 0,5 kV/mm tangential electric eld in top-right image and 0 – 2
kV/mm normal electric eld in remaining images. Blue colour indicates low electric eld while red
colour indicates high electric eld
Figure 3 - Left: tangential electric eld along insulator (dark red = above 0,5 kV/mm). Middle: inspection
by daylight UV camera revealing corona activity on insulator in humid service conditions. Right:
deterioration of the rst shed of the insulator due to corona (adopted from [13])
To verify the results of limitation of the electric eld along the housing based on
calculations, a proposal for the test was indicated in [1] and later the procedure for
the Water Drop Induced Corona (WDIC) test was developed and veri ed on several
insulator designs, both for single insulator strings and more advanced insulator
assemblies [2], [5]-[8], [14], [15], examples are shown in Figure 4. Comparison of
electric eld calculations and their veri cation by WDIC testing revealed that the test
method is reproducible (con rmed by a Round Robin Test in ve international
laboratories [8]), representative, repeatable, and cost-effective. Thus, the test ful ls
all four formal IEC requirements for the test procedure and will be included in CIGRE
TB developed by Working Group (WG) B2.57.
As the rst step for wider international acceptance, the proposed electric eld limits
and the WDIC test method were included in the draft of the TB prepared by CIGRE
WG B2.57. This WG is currently developing the guidelines for the application of
composite overhead line insulators and is expected to be published in the beginning
of 2022.
The need to control electric eld in critical (sensitive) areas of composite insulators
is also for the rst time described in the new draft of IEC 62217 (new Annex D) [16],
which is under consideration of IEC TC 36 MT 19. The criteria are also discussed in
the new draft of IEC 61109 [17], which is under consideration of IEC TC 36 MT 18.
Table 1 - Summary of insulators used for electric eld calculations and testing
To simulate a worst-case scenario from an electric eld point of view, the 3D electric
eld calculations were performed for the phase having the highest electric eld
stress. Only six to eight sheds (or shed pairs in case of the alternating pro le) at the
HV end of the insulator were normally modelled. This simpli cation is based on I2G’s
earlier experience with similar calculations, where it was shown that only a few
sheds close to the insulator ttings are exposed to the highest electric eld stress [2].
Such simpli cation does not in uence the results but reduces drastic time for
calculations. The potentials of phase conductors and connected metal hardware were
set to values corresponding to the maximum system voltage. The potential of the
tower structure, ground surface, insulator upper (grounded) end tting, and shield
wires, were set to zero. If the arcing horn/grading ring arrangement was not
symmetric, the electric eld stress was evaluated on both sides of the insulator and
the highest values were conservatively used. The permittivity values used for the
insulating materials were as follows: air – 1; housing – 3 (for both silicone types, HTV
and LSR); glass ber core – 5. The chosen values are “typical” based on many years’
experiences and are applied to all types of silicone rubber insulators.
The results of the calculations are summarized in Table 2 using traf c light
principles (GREEN colour illustrates the results below the criterion and RED colour
illustrates the results above the criterion). For Emax values averaged along any 10
mm of housing surface, the results which are very close to the criterion of 0,42
kV/mm, are illustrated by YELLOW colour. The results of the electric eld calculations
allow to assume that all manufacturers are well aware about the proposed and
internationally disseminated criteria, despite that they are not yet prescribed by IEC.
This is because only 12% of the investigated insulators need small adjustments of
the position of grading rings to avoid water drop induced corona (normally 2-10 cm
up), and only 4% of the insulators (1 of 26) has too high electric eld stress at the
triple point. The excessive electric eld values noted on metal parts (grading rings
and ttings) are of second order importance in our case, because for all investigated
insulators possible corona from these parts will be oriented away from the insulating
body of the insulator.
Applying the proposed criteria for the limitation of electric eld stress, no grading
devices are needed for distribution class insulators (de ned as < 110 kV). For
transmission class insulators, one grading ring at the HV tting is normally needed
from 110 kV and up to 170 kV and two grading rings (at both ends) are required
starting typically from 220 kV. These estimations based on calculations are
con rmed by the answers to the specialized questionnaire distributed within this
project, see Figure 7. The answers to the questionnaire received from 50 utilities
cover the experience with about 9 million overhead line composite insulators
installed at transmission and distribution voltage levels. These insulators are
estimated to represent about 25% of all installations of line composite insulators
worldwide with the average time in service 24 years (with a maximum of 40 years)
[19]. One of the questions was if power utilities are using grading/corona rings and if
they do, at which voltage levels.
Figure 7 - Application of grading rings depending on voltage level (the results from the special
questionnaire distributed for power utilities). The Y-axis shows the number of answers related to the
speci c voltage level
Test method:
The test set-up and the test environment (minimum 45% humidity) were as per the
RIV-test (IEC 60437), with a simulated tower making the test arrangement
equivalent to service conditions. An example of the set-up is presented in Figure 8.
The wetting of the bottom part of the insulators was done by using the spray bottle
recommended for the wettability test according to IEC 62073, from a distance of
approximately 25 cm and lasting approximately 5 s, until the distribution of water
drops was saturated. All metallic parts were then properly dried with a piece of
paper/cloth to make sure that no water drop corona from metal would mask the main
test result, i.e., corona on housing. The conductivity of the water was as for standard
IEC rain, i.e., 100 μS/cm. The test voltage was applied in the same way as for the
corona test (IEC 61284), i.e., the voltage was rst increased to the corona inception
voltage (or, if reached rst, 120% of maximum operating voltage) and then reduced
to a target voltage of 100% of the maximum operating voltage. Observation of visible
corona was done at these two voltage levels, with the voltage kept for 60 seconds at
each level to allow for proper documentation using still image cameras.
The observation of corona was made by two standard photo cameras (Nikon D70),
installed in parallel, and using 30 seconds exposure time. One camera was placed on
a tripod on the oor and the other in the sky-lift at a height slightly above the bottom
of grading ring. It is important to document the results by photographs taken from
above and below the sensitive area of the test object since the corona activity could
otherwise be hidden from one of the directions.
The criterion was absence of visible corona at 100% of maximum operating voltage.
Examples of detected corona are presented in Figure 9 and Figure 10 and are
directly compared with the corresponding results of electric eld calculations.
Figure 8 - Example of set-up for the WDIC test for the cross-arm arrangement with simulation of both
conductor bundle and tower
Figure 10 - Second example of typical results obtained in the WDIC test. Left: visible corona in the test;
right: indication to get visible corona (respective maximum electric eld >0,42 kV/mm)
Test results
The results of the WDIC tests are summarized in Table 3. A Red-Yellow-Green traf c
light rating system is again applied, i.e., GREEN colour illustrates insulators which
PASSED, YELLOW colour illustrates borderline cases (valid only for electric eld
calculations), and RED colour illustrates that an insulator DID NOT PASS the test. The
results of tests are compared with electric eld calculations.
A summary of the test results in comparison with the calculations is very promising
(considering note below Table 3):
For calculated values above the criterion of 0,42 kV/mm three out of three
electric eld calculations were con rmed by the test, i.e., 100%.
For calculated values below 0,42 kV/mm all fteen electric eld calculations were
veri ed by the test (no corona), i.e., 100%.
For calculated values very close to the criterion of 0,42 kV/mm (within 5%), three
out of four electric eld calculations were con rmed by the test, i.e., 75%. In this
speci c case, however, it might be complicated to be sure about the visibility of
corona.
4. Conclusion
The obtained results showed that the earlier proposed, internationally-disseminated
and recognized criteria for the limitation of the electric eld in sensitive areas of
overhead line composite insulators, work well. This was veri ed for the
comprehensive array of twenty-six commercial insulators from the storages of
participating utilities (26 to be calculated and 22 to be tested). The results of electric
eld calculations are also well supported by the results of the Water Drop Induced
Corona (WDIC) test. At present, these criteria are under discussion in two IEC
maintenance teams revising the IEC 62217 and IEC 61109. For IEC 62217, it has
already been decided to include a general description of the electric eld
requirements, leaving the criteria to the product standards. These criteria are
already included in several utilities' technical speci cations worldwide and it is high
time to nalize their standardization in relevant IEC standards.
The WDIC test complies with IEC requirements for a new test and became mature via
Round Robin Test in different laboratories. The comparison of test results with the
calculations showed the results are 100% con dent with the proposed criteria and
75% con dent in borderline cases very close to the criteria. This test will be included
in CIGRE technical brochure prepared by WG B2.57. This test can be easily
References
1. A.J. Philips, A.J. Maxwell, C.S. Engelbrecht, I. Gutman: “Electric Field Limits for the
Design of Grading Rings for Composite Line Insulators”, IEEE Transactions on
Power Delivery, Vol. 30, No. 3, June 2015, p.p. 1110-1118
2. I. Gutman, P. Sidenvall: “Optimal Dimensioning of Corona/Grading Rings for
Composite Insulators: Calculations & Veri cation by Testing”, World Congress &
Exhibition on Insulators, Arresters & Bushings, Munich, Germany, 18-21 October
2015
3. IEC Standard: “Radio interference test on high-voltage insulators”, IEC 60437
Second Edition, 1997-09
4. IEC Standard: “Overhead lines - Requirements and tests for ttings”, IEC 61284
Second Edition, 1997-09
5. P. Sidenvall, N. Sundin, I. Gutman, L. Carlshem, R. Kleveborn: “Development of
test method to verify composite insulators from water induced corona point of
view”, 32nd Electrical Insulation Conference (EIC), Philadelphia, Pennsylvania,
USA, 8 -11 June 2014, paper S11-3
6. P. Sidenvall, I. Gutman, L. Carlshem, J. Bartsch, R. Kleveborn: “Development of the
Water Drop Induced Corona WDIC Test Method for Composite Insulators”, IEEE
Electrical Insulation Magazine, November/December 2015, Vol. 31, No. 6, p.p. 43-
51
7. I. Gutman, A. Dernfalk: “Innovative testing techniques for veri cation of corona,
pollution and ice/snow performance of insulation structures”, World Congress &
Exhibition on Insulators, Arresters & Bushings, Barcelona-Sitges, Spain, 5-8
November 2017
8. P. Sidenvall, I. Gutman, L. Carlshem, J. Bartsch: “A Round Robin Test of the Water
Induced Corona Test”, ICOLIM-2017, Strasbourg, France, 26-28 April 2017, paper
0017
9. CIGRE WG B2.03: “Use of corona rings to control the electrical eld along
transmission line composite insulators”, Brochure 284, December 2005
10. A.J. Phillips, J. Kuffel, A. Baker, J. Burnham, A. Carreira, E. Cherney, W. Chisholm,
M. Farzaneh, R. Gemignani, A. Gillespie, T. Grisham, R. Hill, T. Saha, B. Vancia, J.
Yu: “Electric Fields on AC Composite Transmission Line Insulators”, IEEE
Transactions on Power Delivery, Vol. 23, No. 2, April 2008, p.p. 823-830
11. I. Gutman, J. Lundquist, V. Dubickas, L. Carlshem, R. Kleveborn: “Design of
corona/arcing rings when replacing cap-and-pin insulators by composite
insulators”, 17th ISH-2011, Hannover, Germany, 22-26 August, 2011, A-007
12. P. Sidenvall, I. Gutman, J. Schulte-Fischedick, J. Seifert, J-F. Gof net:
“Methodology of Modern E- eld Calculations - Case Study for Insulated Cross-
Arm”, CEIDP-2013, p.p. 334-337
13. M. Radosavljevic, I. Gutman, C. Ahlholm, P. Sidenvall: “Ageing and deterioration of
composite post insulators exposed to high electric eld in 220 kV and 400 kV
switchyards in Swedish network”, 2017 CIGRE SC B3 Colloquium, Recife, Brazil,
18-20 September 2017
14. P. Sidenvall, I. Gutman, J.-F. Gof net: “Application of new test procedure for
veri cation of water drop corona on innovative insulation cross-arms”, 19th ISH-
2015, Pilsen, Czech Republic, 23-28 August, 2015, paper 262
15. I. Gutman, J. Lundengård, S. Bucan, P. Sidenvall, J.-F. Gof net: “Trends in
pollution/corona testing for compact insulation systems in the form of insulated
AUTHORS
Summary
NordLink is the rst HVDC interconnector between Norway and Germany. In this
paper we will explain how a dedicated Market & Operations (M&O) project for
NordLink was planned and organized in addition to the joint construction project.
Rather than working towards a common goal of constructing a new asset, the tasks of
the M&O project of NordLink can be viewed as building a bridge between the existing
market solutions and operational principles of the two TSOs. Key success factors
were the dedicated set-up of the M&O project, its early start and a structured and
faithful collaboration. In this way, all planned market solutions and operational
procedures were in place when the asset was ready for use. Thus, commercial
operation of NordLink could start as planned and has been going successfully to
date.
KEYWORDS
NordLink enables the exchange of renewable energy between Germany and Norway.
When Germany has surplus of wind and solar power this can be exported to Norway
while production from the Norwegian hydro power reservoirs is stopped or reduced.
Norwegian hydro and wind power can be exported to Germany when there is surplus
in Norway and/or low wind and solar generation in Germany.
Furthermore and independently from each other, the converters have the capability
to support the AC network with reactive power. This property is available from the
VSC converters independent of the amount of active power transmitted.
Alternatively, the converters can operate in the static synchronous compensator
(STATCOM) mode at zero active power. In this way, NordLink provides exible
reactive power control at the connection points of the converters.
Due to good planning and cooperation on all levels, the NordLink project was
completed on time and within budget in the middle of the Covid-19 pandemic. In this
paper, we will not elaborate on the construction of the interconnector but on the
market and operation parts of the project. In Section 2 we will explain how the
dedicated Market & Operations (M&O) Project for NordLink was planned and
organized. In Section 3 we will present the market solutions and operational
procedures that are currently implemented for NordLink. In Section 4 we will
present operational experiences to date, and nally, in Section 5 we conclude with
the main lessons learned and upcoming challenges.
The rst phase is the Market & Systems Concepts phase where the teams come
together for the rst time to create a platform of common understanding and
joint purpose to agree on a high level concept for WHAT to use the link for. The
main deliverable of this phase is the System Operation Agreement (SOA),
describing the high-level principles of market solutions and operational
procedures including the responsibilities and liabilities of the parties with
respect to system operation.
In the second phase, called Market & Systems Processes, the teams go deeper
into the agreed concepts to agree on HOW to implement the various
functionalities of the link. There are two sets of deliverables from this phase: The
Functional Process Descriptions (FPD) and the Common and Internal Operational
Naturally, there were a number of feedback loops between the phases. E. g. several
concepts that were agreed in the SOA had to be changed due to improved
understanding of common challenges and needs that were discovered during the
development of FPDs and COPs. Similarly, many of the FPDs had to be updated when
the ICT development started, both due to improvements discovered in the
implementation and due to new challenges that occurred.
The ve phases described above are the main content of the M&O project. In the nal
stages of the NordLink project, the deliverables from the M&O project and the
construction project come together in the Commissioning and Trial Operation Phases
as illustrated in Figure 3. These phases are de ned in the various construction
contracts to verify that the assets work as speci ed. However, these phases are also
important for the TSOs to verify that all the market systems, operational procedures
and IT solutions work as intended.
During the Transmission Test Phase, the link is operating according to a planned
schedule. The TSOs buy and sell the necessary test energy in the energy market, but
the market does not in uence the volumes that are used. Only during high load
testing did the parties consider the price differences in the Norwegian and German
market, and test power was transmitted in the optimal direction from low to high
price areas when possible.
To manage this phase a dedicated test management plan and a concept for
procurement of test energy were established as a harmonized common guideline
between the TSOs. This included also detailed descriptions of roles and
responsibilities, a communication plan (weekly/daily meeting agenda) and
procedures for the actual test execution. A dedicated support team with extra staff
for the test energy procurement and a proactive information of stakeholders like
neighboring TSOs have greatly contributed to a successful test phase.
In parallel to the link testing, also the connections to external systems are tested in
this phase. This includes the Single Day-Ahead Coupling (SDAC), the Single Intraday
Coupling (SIDC) market XBID, Nominated Electricity Market Operators (NEMOs), the
Nordic Operations Information System (NOIS) and the Joint Allocation Of ce (JAO),
see chapter 3.1.
From the market player perspective there is no difference between the Trial
Operation and the Normal Operation phases. The difference is mainly in the
contractual structure, as the asset is still the responsibility of the contractors during
Trial Operation. The TSOs do not take over full responsibility and ownership until the
Trial Operation is successfully completed. The Operation & Maintenance Agreement
does not come into force until the TSOs have taken over the asset.
Balancing services are currently not implemented on NordLink. The link shall
join the European platforms for manual and automatic balancing reserves (MARI
and PICASSO) when these become available between the Nordic and Core
synchronous systems [6], [7].
3.2.1. Agreements
The System Operation Agreement (SOA) that regulates all aspects of the use of
the link, including system operation governance, liabilities and responsibilities
between the parties. The SOA also takes into account the European regulations
and agreements that are applicable for the operations of the link both technically
and commercially. An important example for this framework is the ramping
limitations de ned for the two relevant synchronous systems Nordic and CE,
which NordLink must always comply with. The lowest value of the ramping
limitation given by the two systems will prevail.
The Operation and Maintenance Agreement (OMA) that regulates the operation
and maintenance of the asset itself, including maintenance, repairs, governance,
liabilities, insurance and general responsibilities between the parties.
The day-to-day operation of the link is set out in 11 Common Operational Procedures
(COP) and further individual procedures at Statnett and TenneT. The operational
procedures are based on 8 Functional Process Descriptions (FPD) that go deeper into
the technical processes that are needed to support the operations, and thus serve
also as major input for ICT speci cations and development. Altogether the COP and
FPD describe the operational phases from outage planning over real-time operations
of the HVDC system and disturbance management to reporting and transparency:
As the reactive power capabilities of both converters are independent from each
other and cause negligible losses in the converters, there is no need for common
procedures or processes on reactive power management. Both TSOs can use the
reactive power in control modes like reactive power control, QU-control and AC
voltage (droop) control. This is an important added value for AC grid operations in
the vicinity of the converter connection points.
3.2.3. IT solutions
Naturally, the established IT architectures within TenneT and Statnett look different.
But within the parts relevant for NordLink the same hierarchy levels are visible:
The Market & Scheduling systems, which facilitate all market activities,
communicate with the external connections and give the required input to the
SCADA/EMS and Settlement & Reporting systems.
The SCADA/EMS systems, which control the operation of the link and give further
input to Settlement & Reporting. A crucial step here is to transfer the Set Point
Schedule matched between both parties to the power order sent to the HVDC
controller.
The Settlement & Reporting systems, which facilitate reporting and transparency
requirements and in the end also the nancial settlement of energy exchanged
via the link.
The particular challenge for the IT implementation was not to build one new stand-
alone solution but to adapt in parallel the existing IT systems embedded in the
established process landscape. This entailed an extensive coordination effort with
respect to speci cations of the interfaces, different IT providers involved,
simultaneous non-NordLink adaptions affecting the same systems, management of
test cases and timing of end-to-end tests. Nonetheless the whole IT landscape could
be tested successfully prior to the beginning of the transmission test phase.
These measures proved to be very valuable for a smooth transition into the
commercial operations and to gain rst operational experience. As a result, the full
link capacity could be released from January 5th, 2021. However, the capacity that is
offered on the German-Norwegian bidding zone border to the Day-ahead and
Intraday markets is always the lowest of three values: The technical capacity of the
link itself, the maximum export/import capacity in the German AC grid and the
maximum import/export capacity in the Norwegian AC grid. Events like planned and
unplanned outages in the connected AC grids may reduce a system's ability to both
import and export power in periods. Similarly, high levels of wind and solar
generation may also limit available capacity in the connected systems. These
capacities are calculated for all bidding zone borders in the common European
market each day and may result in an available market capacity that is lower than
the technical capacity of the link itself.
There may also be periods where the price difference between the Norwegian and
German bidding zones is too small to transmit energy pro tably (i. e. the value of the
price difference is less than the cost of losses on the link). Thus, the resulting ow
pattern as shown in Figure 6 features a high degree of volatility.
The ramping limitations for the Nordic HVDC interconnectors are based on common
Nordic stability criteria and agreed in the Nordic Synchronous Area Operational
Agreement. The purpose of these limitations is to reduce the deterministic frequency
deviations when several interconnectors need to change setpoint from one market
time unit to another. Up to now, a total Nordic limit has been shared equally between
all HVDC interconnectors with 600 MW per hour each, but with the introduction of
owbased market clearing this will become a dynamic limit to be allocated to the
border(s) with the highest social welfare gain.
It is worth noting there was a longer planned outage with further tests in March 2021
due to nal construction works at the end of the Trial Operation period. Apart from
some shorter outages, successful operation has continued to date.
Key factors for this success were the set-up of a dedicated M&O project, its early start
and a structured and faithful collaboration. In this way, it was possible in a timely
fashion to overcome the challenges of connecting different synchronous systems and
for TSO operations to act on eye-level to the construction work. Furthermore, it has
been of great value to involve the best process, ICT and HVDC-specialists of both
TSOs. Some resources where fully allocated to the project, while other key experts
were involved when needed. In particular, the involvement of these experienced
experts has ensured that NordLink solutions are not stand-alone but t into the
existing process landscape as good as possible. In this way, it was ensured that
adding new assets compatible to market and regulatory requirements was done
within a manageable effort for TSO control centers.
Some further lessons learned include the importance of clarifying the roles and
responsibilities between the M&O project and the construction project. For future
projects it could also be helpful to improve the coordination between the project
phases developing the agreements and the FPDs/COPs to avoid some of the above-
mentioned feedback loops and enable an earlier start of the ICT phase.
There is also a common working group together with the Danish and Dutch TSOs
looking to implement new ramping rules for all HVDC interconnectors from Southern
Norway. Currently, there is an individual limit to how fast each interconnector can
ramp from one hour to the next, independent from what other interconnectors may
need to do. A more ef cient solution will be to implement an aggregated area limit
where one interconnector may ramp faster if the others do not need to ramp,
dependent on the price difference between the different bidding zones.
References
1. https://www.europarl.europa.eu/factsheets/en/sheet/45/internal-energy-market,
https://www.entsoe.eu/network_codes/
2. https://www.entsoe.eu/network_codes/cacm/implementation/sdac/
3. https://www.jao.eu/
4. https://www.nordpoolgroup.com/trading/Day-ahead-trading/loss-functionality/
5. https://www.entsoe.eu/network_codes/cacm/implementation/sidc/
6. https://www.entsoe.eu/network_codes/eb/mari/
7. https://www.entsoe.eu/network_codes/eb/picasso/
AUTHORS
Summary
Increasing penetration of inverter-based resources (IBR) has expedited the
retirement of conventional synchronous generators (SGs) in power systems
worldwide. This has reduced levels of synchronous inertia and frequency control
provided by synchronous generators, which in turn increases the complexity of
primary and secondary frequency control. Synchronous inertia plays a key role in
slowing the rate of change of frequency (RoCoF) after a disturbance, providing time
for primary frequency control to act, and thereby maintain frequency within required
limits. Under low inertia conditions RoCoF can increase, reducing the available time
for primary frequency control to act.
Fast frequency response (FFR) can provide the necessary frequency control quickly
and can potentially help avoid undesired system frequency outcomes such as under-
frequency load shedding or over-frequency generation shedding. While to date
battery energy storage systems (BESSs) have been considered the most promising
technology to provide FFR, solar farms (SFs) have also demonstrated the capability
of providing FFR.
This paper present real-life example of FFR from SFs in the Australia’s National
Electricity Market (NEM) power system. Real-time measurements have been used to
benchmark a SF model, to con rm the accuracy of the model. The effect of varying
droop in the model has been assessed and its response is compared with response
from a BESS. This comparison demonstrates the capability of SF in providing FFR
that is similar to that from a BESS. The contribution of FFR from BESSs and SFs
toward overall power system security is demonstrated through a simulation of a NEM
region. The impact of droop and dead-band settings of SFs and BESSs on their FFR
provision, and their impact on power system security, are also assessed.
frequency control - synchronous inertia - rate of change of frequency - fast frequency response - solar
farm - battery energy storage - droop and dead-band
1. Introduction
The National Electricity Market (NEM) of Australia is experiencing an unprecedented
increase in the penetration of renewables and inverter-based resources (IBR) at both
transmission and distribution levels. The South Australian (SA) power system, in
particular, has witnessed operating periods with the instantaneous penetration of
IBR-generated electricity exceeding 140% of the region’s operational demand, with
the balance exported to neighbouring regions. The increasing level of IBR in the NEM
power system has accelerated the retirement of synchronous generators (SGs), which
has been a factor in reduced frequency control performance in the NEM [1]. The
Australian Energy Market Operator (AEMO) has been intervening to maintain a
minimum number of SGs online in several regions of the NEM, to maintain the
required level of system strength needed for stable operation of IBR [2]. While these
online SGs contribute to power system inertia, a steady decline in the inertia level
has been observed in the past few years[1].
Fast frequency response (FFR) has been gaining increasing attention to support
power system operation with low inertia, assisting in limiting the RoCoF, and
providing suf cient time for primary frequency control. Here, FFR acts as a rapid
The NEM has one of the highest penetrations of distributed photovoltaic (DPV)
systems worldwide, causing signi cant operational demand reduction during sunny
periods [5]. Output from this DPV cannot be readily curtailed. Under low demand
conditions driven by DPV, and particularly for an islanded region, output from
transmission-connected SFs (and wind farms [WFs]) may have to be curtailed
instead, due to both insuf cient demand and as a result of other technical network
constraints [2]. This creates headroom, providing an opportunity for SFs to provide
FFR to the grid during these periods. Instances of relatively fast generation change
to correct frequency deviation by SFs have been observed in some real-life operating
conditions in the NEM power system, which is discussed later in this paper.
FFR has been investigated [6] from an energy viewpoint, where the energy
delivered after a frequency event is decoupled, based on the timeframe the
energy is released into the grid.
The capability of FFR supplied by a BESS, in replacing SGs’ inertia and primary
frequency response (PFR), has been evaluated [7], measuring the energy
provided by SGs to estimate the required size of BESS to deliver the same
amount of energy during the rst 6 seconds after the event.
FFR has been contrasted against synthetic inertia, where the former is de ned as
any type of fast active power change based on frequency deviation, while the
latter is the mimicked response of SGs’ rotational masses which is in proportion
to the RoCoF [8]. The reference shows that FFR leads to a better overall frequency
performance compared to synthetic inertia.
An SF has been modelled to simultaneously provide FFR and oscillations
damping to the grid [9]. The proposed model is evaluated on a two-area test
power system.
The frequency support capability of a curtailed grid-scale SF, among its other grid
support services, has been tested by the National Renewable Energy laboratory
(NREL), as reported in [10] and [11]. A ramp-rate limit of 10 MW/sec, however, is
applied in [10] to the SF’s response which could prevent the SF from delivering
its full response before the frequency nadir/peak and hence contributing to
arresting the frequency nadir/peak.
To date not much study has been carried out focusing on FFR provision from grid-
scale SFs and BESSs and their impact on the frequency stability of an actual large-
scale power system, supported by real-life observations. Also, the extent to which the
droop and dead-band settings of FFR providers can impact the frequency
performance of the grid has not been paid due attention in the past.
This paper rst presents the real-life responses from an SF and a BESS in the NEM
power system during frequency events. The measured responses of the SF and BESS
during the events are then replicated through electromagnetic transient (EMT)-type
simulations, via injecting the frequency signals measured during the events into the
EMT model of a SF and BESS. Through this exercise it is demonstrated that properly
con gured SF can provide FFR similar to BESS. A detailed wide area EMT model of a
gigawatt-scale NEM region is then used to demonstrate the potential bene ts of FFR
provision by SFs in addition to BESSs for frequency control of the grid. Additional
The received data also con rmed that some SFs in the NEM had provided similar
rapid change in the generation to control the frequency change, again in line with
their control design. In this section, examples of real-life response provided by a
transmission-connected BESS and a SF during a few frequency events are presented.
Figure 1(b) shows the response of the same SF to an over-frequency event, where the
frequency increased to around 51.1 Hz. As seen, the SF rapidly reduced its output
from around 90 MW to 52 MW, which is well aligned with its known droop (5%) and
dead-band (± 0.15 Hz) settings. The rapid reduction in the generation occurred prior
to the peak frequency, and therefore contributed towards arresting the over-
frequency.
Figure 1 - Measured SF responses to (a) an under-frequency event and (b) an over-frequency event
Another point to be noticed in Figure 1(a) is that the response provided by the SF is
as per its 5% droop setting. Therefore, even though larger headroom was available
for the SF during the event, only a small portion of it was used in line with its droop
setting. It is, however, observed that the SF has withdrawn its FFR after t=12s, while
frequency has not yet returned within the ± 0.15 Hz dead-band. The sooner-than-
expected FFR withdrawal could be associated with the fast variations in the
irradiance level observed over the time of the event, given the small size of active
power change (less than 3 MW). It could also be caused by the hysteresis-like dead-
band re-entering limit in the control system of the SF.
Figure 2(b) shows the BESS response to the same over-frequency event as in Figure
1(b), where the frequency rose to 51.1 Hz. As seen, the BESS has responded to the
event by reducing its output to -87 MW in less than 2 seconds according to its droop
(1.7%) and dead-band (± 0.15 Hz) settings.
Figure 2 - Measured BESS responses to (a) an under-frequency event and (b) and over-frequency event
The active power response of the EMT model of the SF to the over-frequency event is
shown in Figure 4(b). Again, the simulated response closely matches the measured
response when the droop is set to 5% (green trace), consistent with the known
control system settings in the SF model. Also, the gure shows that changing the
droop setting of the model to 3% and 1.7% signi cantly increases the FFR capability
of the SF.
Table 1 - Simulated case studies on the wide area EMT model of a NEM sub-network
The results of the rst three cases are shown in Figure 6. The key ndings are:
For a contingency size of 190 MW, when only the BESS provides FFR, the
frequency nadir is 49.25 Hz compared to 49.48 Hz when FFR is also available
from SF. The availability of FFR from an SF is dependent on headroom availability
via pre-curtailment.
Other things being equal, availability of FFR from an SF allows an additional 60
MW contingency size, while still maintaining the frequency nadir above the
frequency operating standards. This clearly demonstrates a bene t of the SF’s
FFR for frequency stability of the future grid.
It is observed that in case 3 (the red curves), SF has hit its maximum active
power limit, while BESS has not, while the same droop setting of 1.7% has been
Figure 6 - Wide area results: (a) frequency (b) FFR from SFs (c) FFR from BESS
The results of cases 2, 4 and 5 are shown in Figure 7. The key ndings are:
Using a wider dead-band of ±150 mHz, the FFR responses of both the SF and
BESS start with around 300 ms delay, compared to when a ±20 mHz dead-band is
used. This leads to a 0.1 Hz lower frequency nadir when a larger dead-band is
applied, for the same contingency size.
When a droop of 3% is used, the frequency nadir is 0.15 Hz lower compared to
when a 1.7% droop is used, keeping all other conditions unchanged.
Figure 7 - Wide area results: (a) frequency (b) FFR from SFs (c) FFR from BESS
In the NEM, FFR from BESS has been implemented both at the individual inverter
level and at the central PPC level, depending on the site. In SFs, frequency response
has been implemented at the PPC level only to date.
6.1. ERCOT (Texas)
ERCOT (in Texas) has FFR services implemented from 1 March 2020. Under this
service FFR must be delivered within 0.25 seconds once the frequency is below
59.85 Hz (i.e. 0.15 Hz below nominal frequency of 60 Hz) [13]. Figure 8 shows an
expected response from FFR providers. Earlier, ERCOT already had a type of fast
frequency response product provided by load resources with under-frequency relays
set to trip within 0.5 seconds of frequency reaching or falling below 59.7 Hz. This
service still remains, even after implementation of FFR. At this stage, all of the new
FFR service is provided by storage resources. Resources providing FFR shall be also
capable of governor-like response with ±17 mHz dead-band, and droop setting of
5.0%. Once FFR is deployed, it should sustain for up to 15 minutes or until frequency
recovers to 59.98 Hz (whichever happens rst). Once FFR is recalled, it should
restore within 15 minutes.
As the majority of FFR resources is provided by wind generators, EirGrid also limits
energy extracted from wind generators. The extra energy provided in the 2-10
second timeframe by the increase in MW output must be greater than the loss of
energy in the 10-20 second timeframe due to a reduction in output power. As shown
in Figure 9, in order to be eligible for FFR, the amount indicated by the blue hatched
area (Power provided) shall be greater than the green hatched area (Power drawn)
[14].
7. Conclusion
This paper provides real-life evidence that SFs have capability to provide FFR. The
response is con gurable and can closely align with that of BESSs. Responses from an
SF during frequency events have been analysed. The real-time observations show
that grid-scale SFs have the potential to provide FFR to the grid, contingent on the
availability of active power headroom when responding to under-frequency. Using
the benchmarked model of a SF, it was shown that SFs can provide similar FFR to
that from a BESS, if they are properly tuned for this purpose and subject to resource
(i.e. headroom) availability. A detailed wide area EMT model of a NEM region was
used to evaluate the impact of FFR from SFs on overall frequency control of the
power system. The results verify that the frequency response of the grid can be
signi cantly improved when the FFR from SFs is available. It was also shown that the
improved frequency stability allows for larger contingency sizes. Besides, it was
shown that the FFR control settings, such as droop and frequency dead-band, are
crucial for determining the effectiveness of the response, where a tighter dead-band
and a smaller droop noticeably improve the frequency stability of the grid.
References
1. IEEE, “Renewables in Australia”, IEEE Power & Energy Magazine, Vol 19, n. 5,
September/ October 2021
2. AEMO, “Transfer Limit Advice, System Strength in SA and Victoria”, Australian
Energy Market Operator, July 2021
3. NERC, "Fast frequency response concepts and bulk power system reliability
needs." NERC Inverter-Based Resource Performance Task Force (IRPTF), March
2020.
4. AEMO, "Fast frequency response in the NEM", Australian Energy Market Operator,
2017.
5. AEMO, “South Australian Electricity Report”, Australian Energy Market Operator,
November 2020.
6. D. Stenclik, M. Richwine, N. Miller, L. Hong, “The Role of Fast Frequency Response
in Low Inertia Power Systems”, CIGRE PARIS 2018.
7. Brogan, P., et al. "Fast frequency response requirements for replacement of
observed generator response during under frequency transients." CIGRE
Symposium, Dublin, 2017.
8. Eriksson, Robert, Niklas Modig, and Katherine Elkington. "Synthetic inertia
versus fast frequency response: a de nition." IET Renewable Power
Generation 12.5 (2018): 507-514.
9. Varma, Rajiv K., and Mohammad Akbari. "Simultaneous fast frequency control
and power oscillation damping by utilizing PV solar system as PV-
STATCOM." IEEE Transactions on Sustainable Energy 11.1 (2019): 415-425.
10. C. Loutan, P. Klauer, S. Chowdhury, S. Hall. “Demonstration of Essential Reliability
Services by a 300-MW Solar Photovoltaic Power Plant”, NREL/TP-5D00-67799.
National Renewable Energy Lab. (NREL), Golden, CO (United States), 2017.
11. V. Gevorgian, B. O’Neill, “Demonstration of Active Power Controls by Utility-Scale
PV Power Plant in an Island Grid”, NREL/CP-5D00-67255. National Renewable
Energy Lab. (NREL), Golden, CO (United States), 2017.