CONCRETING WORKS (BEAMS AND TIE BEAMS)

BEAMS
BEAMS LENGTH AREA VOLUME
1 15.103 m 0.06 m2 0.90618 m3
2 12.05242 m 0.06 m2 0.723145 m3
3 12.05242 m 0.06 m2 0.723145 m3
4 5.40948 m 0.06 m2 0.324569 m3
5 3.10059 m 0.06 m2 0.186035 m3
6 9.30151 m 0.06 m2 0.558091 m3
7 9.30151 m 0.06 m2 0.558091 m3
8 7.90154 m 0.06 m2 0.474092 m3
9 4.50089 m 0.06 m2 0.270053 m3
10 3.40066 m 0.06 m2 0.20404 m3
11 2.82399 m 0.06 m2 0.169439 m3
TOTAL 5.096881 m3

TIE BEAMS
BEAMS LENGTH AREA VOLUME CONCRETING WORKS (CLASS AA)
1 15.103 m 0.06 m2 0.90618 m3
2 6.74294 m 0.06 m2 0.404576 m3 QUANTITY TAKE-OFF
3 6.74294 m 0.06 m2 0.404576 m3 MATERIALS MULTIPLIER TOTAL VOLUME (m3) QTY. WASTAGE (10%) TOTAL UNIT
4 12.05242 m 0.06 m2 0.723145 m3 CEMENT (40 KG) 12 10.5708186 126.8498 12.68498232 140 BAGS
5 5.40948 m 0.06 m2 0.324569 m3 SAND 0.5 10.5708186 5.2854093 0.52854093 5.8140 m3
6 3.10059 m 0.06 m2 0.186035 m3 GRAVEL 1 10.5708186 10.5708186 1.05708186 11.6279 m3
7 9.30151 m 0.06 m2 0.558091 m3
8 9.30151 m 0.06 m2 0.558091 m3
9 6.47752 m 0.06 m2 0.388651 m3
10 3.1006 m 0.06 m2 0.186036 m3
11 3.40066 m 0.06 m2 0.20404 m3
11 2.59759 m 0.06 m2 0.155855 m3
12 7.90154 m 0.06 m2 0.474092 m3
TOTAL 5.473938 m3

TOTAL VOLUME BEAMS + TIE BEAMS 10.57082 m3