You are on page 1of 159

begesting

Jumlah bobot. total


dia. Tul. dia. Pjg sat. jarak jmlh bobot bobot
No. Nama beton b h panjang / tul. Tul dibulatka lebar begesting
Pokok Begel Begel begel begel begel total/m3
m3 Pokok pokok n

Strous 25cm 0.25 20.36 10 6.00 6.00 0.79 0.20 102.00 75.33 17.79 93.11 94 kg/m3

pondasi 50x50 0.50 0.15 0.59 12 4.00 12.00 0.59 4.00 2.10 2.10 4.19 111.74 kg/m3
pondasi 70x70 0.70 0.15 0.79 12 6.00 12.00 0.79 6.00 4.21 4.21 8.42 114.50 kg/m3
pondasi 150x60x35 1.50 0.35 1.79 13 5.00 - 1.79 5.00 9.32 - 9.32 11.84 kg/m3
0.60 0.35 0.89 13 12.00 - 0.89 12.00 11.13 - 11.13 88.31 kg/m3
pondasi 60x60x35 0.60 0.35 0.89 13 5.00 13.00 0.89 5.00 4.64 4.64 9.27 73.59 kg/m3

sloof 15x20 0.15 0.20 33.33 12 4.00 8.00 0.62 0.15 223.00 118.37 54.55 172.92 173 kg/m3 0.40 4.444
sloof 15x25 0.15 0.25 26.67 12 4.00 8.00 0.72 0.15 178.00 94.69 50.57 145.26 146 kg/m3 0.50 6.667
sloof 20x30 0.20 0.30 16.67 12 6.00 8.00 0.92 0.15 112.00 88.78 40.66 129.43 130 kg/m3 0.60 5.000
sloof 12x15 0.12 0.15 55.56 10 4.00 8.00 0.46 0.15 371.00 137.00 67.34 204.34 205 kg/m3 0.30 5.556

kolom 20x25 0.20 0.25 20.00 12 6.00 8.00 0.82 0.15 134.00 106.53 43.35 149.89 150 kg/m3 0.90 9.000
kolom15x15 0.15 0.15 44.44 12 4.00 8.00 0.52 0.15 297.00 157.82 60.94 218.76 219 kg/m3 0.60 13.333
kolom12x12 0.12 0.12 69.44 12 4.00 8.00 0.40 0.15 463.00 246.60 73.07 319.67 320 kg/m3 0.24 8.333
kolom 30x30 0.30 0.30 11.11 10 6.00 8.00 1.12 0.15 75.00 41.10 33.14 74.24 75 kg/m3 1.20 6.667
kolom 15x25 0.15 0.25 26.67 12 6.00 8.00 0.72 0.15 178.00 142.04 50.57 192.61 193 kg/m3 0.80 10.667
kolom 20x20 0.30 0.30 11.11 10 4.00 8.00 1.12 0.15 75.00 27.40 33.14 60.54 61 kg/m3 1.20 6.667

balok 15x15 0.15 0.15 44.44 12 4.00 8.00 0.52 0.15 297.00 157.82 60.94 218.76 219 kg/m3 0.45 10.000
ring balok 12x15 0.12 0.15 55.56 10 4.00 8.00 0.46 0.15 371.00 137.00 67.34 204.34 205 kg/m3 0.30 5.556
latei balok 12x15 0.12 0.15 55.56 10 4.00 8.00 0.46 0.15 371.00 137.00 67.34 204.34 205 kg/m3 0.42 11.667
balok 20x40 0.20 0.40 12.50 12 6.00 8.00 1.12 0.15 84.00 66.58 37.12 103.70 104 kg/m3 1.00 12.500
balok 20x25 0.20 0.25 20.00 12 6.00 8.00 0.82 0.15 134.00 106.53 43.35 149.89 150 kg/m3 0.46 9.200
balok 15x20 0.15 0.20 33.33 12 6.00 8.00 0.62 0.15 223.00 177.55 54.55 232.10 233 kg/m3 0.55 9.167
balok 30x60 0.30 0.60 5.56 16 12.00 8.00 1.72 0.15 38.00 105.22 25.79 131.00 132 kg/m3 1.26 7.000
0.30 0.60 5.56 13 2.00 11.58 11.58 12 kg/m3
balok 30x40 0.30 0.40 8.33 16 10.00 8.00 1.32 0.15 56.00 131.52 29.17 160.69 161 kg/m3 0.86 7.167
balok 20x30 0.20 0.30 16.67 16 5.00 8.00 0.92 0.15 112.00 131.52 40.66 172.18 173 kg/m3 0.56 9.333
balok 15x25 0.15 0.25 26.67 13 6.00 8.00 0.72 0.15 178.00 166.70 50.57 217.27 218 kg/m3 0.53 14.133

plat lantai besi 10 3.50 0.12 2.25 10 10.00 10 3.50 0.15 19.00 13.87 41.00 54.87 -
2.25 6 20.00 6 3.50 20.00 9.99 15.54 25.52
0.66 10 20.00 10 0.66 38.00 8.17 15.52 23.69
104.08 124.170 kg/m3 1.00 8.333
m2 3.00 x pakai
m2 2.00 x pakai
m2 2.00 x pakai
m2 3.00 x pakai

m2 2.00 x pakai
m2 2.00 x pakai
m2 2.00 x pakai
m2 2.00 x pakai
m2 2.00 x pakai
m2 2.00 x pakai

m2 2.00 x pakai
m2 3.00 x pakai
m2 2.00 x pakai
m2 1.00 x pakai
m2 1.00 x pakai
m2 2.00 x pakai
m2 1.00 x pakai

m2 1.00 x pakai
m2 1.00 x pakai
m2 1.00 x pakai

m2 1.00 x pakai

m2 1 x pakai
SD SEPANJANG 2
WF
JUMLAH
PANJANG DUBEL / BOBOT/ BOBOT
NOMOR BATANG JUMLAH KUDA- SATUAN KODE PLAT LUASAN TEBAL BOBOT/M2
BATANG SINGGEL M' TOTAL
KUDA
batang 4.223 1.000 2.00 2.00 14.00 236.49 plendes 0.0500 10 80.90
tiang 0.328 1.000 2.00 2.00 14.00 18.37 kopel bawah 0.0246 8 64.93
voute 0.450 0.500 2.00 2.00 14.00 12.60 kopel atas 0.0257 8 64.93
voute atas 0.212 0.500 2.00 2.00 14.00 5.94 tutup wf kolom 0.0137 8 64.93
plat rip 0.0048 6 48.61
273.39 kg plat penyangga gording 0.0075 8 64.93

PANJANG
LAS NOMOR BATANG JUMLAH UKURAN
BATANG
jmlh / jmlh panjang
KODE PLAT Panjang Las SATUAN 9.660 12.00
kuda2 kuda2 total gording CNP 125.50.20.2,3
plendes 52.00 2 2 208.00 3.336 4.00 CNP 125.50.20.2,3
kopel bawah 90.00 2 2 360.00
kopel atas 90.00 2 2 360.00
dudukan gording 10.00 12 2 240.00 Trektang GORDING 1.00 60 10
1168.00 cm
DIBAGI 4 1168 10 116.80 cm Trektang KUDA-KUDA 6.95 2 16

Ikatan angin kuda-kuda 5.27 4 12

jarum keras
angkur baut 16mm 8
Draf & Mur M10 Trekstank gording 60
Baut M12 A-325 30
JUMLAH
JUMLAH KUDA- BOBOT SAT
KUDA
2 2 16.18
2 2 6.39
2 2 6.66
2 2 3.56
10 2 4.63
12 2 11.69
49.11 kg

BOBOT/ BOBOT
SATUAN
M' TOTAL

4.51 522.80
4.51 60.18
582.98 kg

0.616 36.97
36.97 kg
1.577 21.93
21.93 kg
0.887 18.70
18.70 kg
6.00 buah
2.000 16 bh
1 60 bh
2 60 bh
PERHITUNGAN VOLUME
Nama Program : PENINGKATAN SARANA DAN PRASARANA APARATUR
Nama Kegiatan : PEMELIHARAAN RUTIN / BERKALA GEDUNG KANTOR
Nama Pekerjaan : REHAB PAGAR KANTOR & KAMAR MANDI/WC/GUDANG/R.RAPAT
Lokasi Kegiatan : KANTOR DISPORA SIDOARJO

NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat


1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
A PAGAR
I PEKERJAAN PERSIAPAN
1. Pembersihan lokasi x x x = - = 64.87 m2
DEPAN SISI TIMUR 56.80 x 1.00 x x 0.50 = 28.40
LENGKUNG 6.64 x 1.00 x x 0.50 = 3.32
SAMPING SISI UTARA 66.30 x 1.00 x x 0.50 = 33.15
2. Pembongkaran dinding x x x = - = 1.00 ls
bongkar sloof lama 129.74 x 0.28 x 0.15 x = 5.45
kolom lama 1.20 x 0.35 x 1.50 x 1.00 = 0.63
2.00 x 1.20 x 0.40 x 1.00 = 0.96
3. Pembongkaran besi pagar x x x = 129.74 = 129.74 m1

II PEKERJAAN TANAH
1. Galihan tanah pondasi x x x = - = 7.31 m3
sepatu 250x150x30 2.50 x 1.50 x 0.35 x 2.00 = 2.63
sepatu 50x50x15 0.50 x 0.50 x 0.20 x 35.00 = 1.75
sloof pintu masuk 48.90 x 0.40 x 0.15 x 1.00 = 2.93
2. Urugan tanah kembali 7.31 x 0.25 x x = 1.83 = 1.83 m3
3. Urugan pasir bawah pondasi x x x = - = 0.81 m3
sepatu 250x150x30 2.50 x 1.50 x 0.05 x 2.00 = 0.38
sepatu 50x50x15 0.50 x 0.50 x 0.05 x 35.00 = 0.44

III PEKERJAAN PONDASI


1. Pekerjaan Pengeboran Pondasi Strous Ø(25x25)cm 3.00 x 12.00 x x = 36.00 = 36.00 m1
2. Pekerjaan Beton Pondasi Strous Ø(30x30)cm 3.00 x 0.05 x x 12.00 = 1.77 = 1.77 m3
3. Pas. Pondasi beton plat 250x150x30 cm 2.50 x 1.50 x 0.30 x 2.00 = 2.25 = 2.25 m3
4. Pas. Pondasi beton plat 50x50x15 cm 0.50 x 0.50 x 0.15 x 35.00 = 1.31 = 1.31 m3
5. Pas. Beton rabat bawah pondasi K-100 x x x = - = 0.81 m3
sepatu 250x150x30 2.50 x 1.50 x 0.05 x 2.00 = 0.38
sepatu 50x50x15 0.50 x 0.50 x 0.05 x 35.00 = 0.44

IV PEKERJAAN BETON
1. Beton Sloof 15/20 K-175 = 3.02 m3
sisi timur 23.55 x 0.15 x 0.20 x = 0.71
20.08 x 0.15 x 0.20 x = 0.60
lengkung 6.64 x 0.15 x 0.20 x = 0.20
sisi utara 50.40 x 0.15 x 0.20 x = 1.51
2. Beton kolom 20/20 K-175 x x x = - = 0.64 m3
utama 2.77 x 0.20 x 0.20 x 4.00 = 0.44
atas 1.21 x 0.20 x 0.20 x 4.00 = 0.19
3. Beton kolom 15/15 K-175 2.10 x 0.15 x 0.15 x 35.00 = 1.65 = 1.65 m3
4. Beton plat lantai t=10 cm x x x = - = 0.44 m3
bawah 1.03 x 2.14 x 0.10 x 2.00 = 0.44
5. Beton plat lantai t=10 cm x x x = - = 0.44 m3
atas 1.04 x 2.12 x 0.10 x 2.00 = 0.44
6. Beton ring balok 12/15 K-175 0.12 x 0.15 x 100.67 x 1.00 = 1.81 = 1.81 m3
7. Pas. Beton rabat dudukan rel pintu masuk K-100 48.90 x 0.15 x 0.15 x 1.00 = 1.10 = 1.10 m3

V PEKERJAAN PASANGAN
1. Pasangan bata Merah Gapura Utama 1PC : 5Ps
gapura utama 3.50 x 2.50 x x 2.00 = 17.50 = 15.98 m3
volume kolom dalam 0.64 x x x = 0.64
volume plat lantai dalam 0.44 + 0.44 x x = 0.88
total volume gapura utama 17.50 - 0.64 - 0.88 x = 15.98
2. Pasangan bata Merah Pilar 1PC : 5Ps
pilar 0.60 x 0.70 x x 35.00 = 14.70 = 13.05 m3
volume kolom dalam x x x = 1.65
total volume pilar 14.70 - 1.65 x x = 13.05
3. Pasangan bata Merah 1 bata 1PC : 5Ps
0.40 x 100.67 x x = 40.27 = 40.27 m2
4. Pasangan bata Merah 1/2 bata 1PC : 5Ps
pagar 0.55 x 100.67 x x = 55.37 = 61.97 m2
rong 0.15 x 0.40 x x 124.00 = 7.44
papan nama 0.70 x 2.68 x 2.00 x = 3.75
0.30 x 9.50 x x = 2.85
total volume bata 69.41 - 7.44 x x = 61.97
5. Plesteran dinding baru 1Pc : 5Ps x x = 60.40 m2
sloof 0.20 x 100.67 x x 2.00 = 40.27
list atas 0.10 x 100.67 x x 2.00 = 20.13
6. Pekerjaan Acian = 60.40 m2
7. Pasang Granite 60x60 cm = 326.93 m2
Pilar bawah 1.80 x 0.30 x x 35.00 = 18.90
list kecil atasnya 1.66 x 0.05 x x 35.00 = 2.91
1.52 x 0.05 x x 35.00 = 2.66
badan pilar 1.40 x 0.70 x x 35.00 = 34.30
list kecil atas badan pilar 1.52 x 0.05 x x 35.00 = 2.66
1.66 x 0.05 x x 35.00 = 2.91
1.80 x 0.05 x x 35.00 = 3.15
1.66 x 0.05 x x 35.00 = 2.91
topi miring 0.48 x 0.26 x 4.00 x 35.00 = 17.29
topi pilar 1.32 x 0.10 x x 35.00 = 4.62
1.20 x 0.05 x x 35.00 = 2.10
1.04 x 0.05 x x 35.00 = 1.82
NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat
1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
Gapura bawah 2.20 x 4.80 x x 2.00 = 21.12
tengah 0.80 x 3.08 x x 2.00 = 4.93
atas 3.30 x 3.08 x x 2.00 = 20.33
bawah pagar 100.67 x 0.30 x x 2.00 = 60.40
pagar 61.97 x x x 2.00 = 123.94
8. Pasang Pintu Pagar besi hollow finishing cat isian kayu = 52.79 m2
4.50 x 2.05 x x 2.00 = 18.45
4.75 x 2.05 x x 1.00 = 9.74
3.75 x 2.05 x x 2.00 = 15.38
4.50 x 2.05 x x 1.00 = 9.23
9. Pasang rel pintu besi siku 40.40.4 15.40 + 9.50 + 15.00 + 9.00 = 48.90 = 48.90 m1

VI PEKERJAAN CAT
1. Cat dinding baru x x x = 60.40 = 60.40 m2
2. Cat Kayu x x x = - = 23.88 m2
pintu utama 1.29 x 0.15 x 2.00 x 26.00 = 10.06
pintu samping kua 0.94 x 0.15 x 2.00 x 14.00 = 3.95
pintu samping tengah 0.94 x 0.15 x 2.00 x 22.00 = 6.20
pintu paling barat 0.94 x 0.15 x 2.00 x 13.00 = 3.67
3. Cat besi hollow x x x = - = 54.67 m2
pintu utama 18.00 x 0.20 x 2.00 x = 7.20
3.90 x 0.20 x 2.00 x = 1.56
50.70 x 0.12 x 2.00 x = 12.17
pintu samping kua 18.64 x 0.20 x 1.00 x = 3.73
3.20 x 0.20 x 1.00 x = 0.64
41.60 x 0.12 x 1.00 x = 4.99
pintu samping tengah 15.00 x 0.20 x 2.00 x = 6.00
3.20 x 0.20 x 2.00 x = 1.28
33.60 x 0.12 x 2.00 x = 8.06
pintu paling barat 18.00 x 0.20 x 1.00 x = 3.60
3.20 x 0.20 x 1.00 x = 0.64
40.00 x 0.12 x 1.00 x = 4.80
VII PEKERJAAN TAMAN
1. Urugan tanah malang x x x = 1.00 = 1.00 truck
2. Penanaman pucuk merah h=100 cm x x x = 2.00 = 2.00 bh
3. Penanaman rumput gajah mini 4.65 x 1.32 x x = 6.14 = 6.14 m2
4. Perawatan dan jaminan hidup 1 bulan x x x = = 1.00 ls
5. Instalasi listrik lampu taman x x x = = 3.00 ttk
6. Pasang lampu LED Sorot 20 watt x x x = = 3.00 unit
7. Pas. Saklar ganda x x x = = 1.00 unit

KAMAR MANDI/WC/GUDANG/R.RAPAT
I PEKERJAAN PERSIAPAN
1. Pembersihan lokasi 67.90 x 1.00 x x 0.50 = 33.95 = 33.95 m2
2. Pembongkaran dinding 3.00 x 3.00 x 0.15 x 0.50 = 0.68 = 0.68 m3

II PEKERJAAN TANAH
1. Urugan sirtu bawah lantai = 27.06 m3
1 3.15 x 3.65 x 0.20 x 1.00 = 2.30
2 5.15 x 3.65 x 0.20 x 1.00 = 3.76
km/wc 3.15 x 1.50 x 0.17 x 1.00 = 0.80
depan km/wc 3.15 x 2.15 x 0.20 x 1.00 = 1.35
3 3.20 x 3.65 x 0.20 x 1.00 = 2.34
4 3.10 x 3.65 x 0.20 x 1.00 = 2.26
5 3.65 x 5.05 x 0.20 x 1.00 = 3.69
teras besar 3.13 x 14.09 x 0.20 x 1.00 = 8.82
teras kecil 8.71 x 1.00 x 0.20 x 1.00 = 1.74

III PEKERJAAN BETON


1. Beton kolom 12/12 K-175 = 0.85 m3
depan 0.12 x 0.12 x 3.85 x 12.00 = 0.67
belakang 0.12 x 0.12 x 1.05 x 12.00 = 0.18
2. Beton balok latei 12/15 K-175 0.12 x 0.15 x 24.10 x 1.00 = 0.43 = 0.43 m3
3. Beton ring balok 12/15 K-175 0.12 x 0.15 x 97.05 x 1.00 = 1.75 = 1.75 m3
4. Pas. Beton rabat bawah lantai K-100 x x = 4.08 m3
1 3.15 x 3.65 x 0.03 x 1.00 = 0.34
2 5.15 x 3.65 x 0.03 x 1.00 = 0.56
km/wc 3.15 x 1.50 x 0.03 x 1.00 = 0.14
depan km/wc 3.15 x 2.15 x 0.03 x 1.00 = 0.20
3 3.20 x 3.65 x 0.03 x 1.00 = 0.35
4 3.10 x 3.65 x 0.03 x 1.00 = 0.34
5 3.65 x 5.05 x 0.03 x 1.00 = 0.55
teras besar 3.13 x 14.09 x 0.03 x 1.00 = 1.32
teras kecil 8.71 x 1.00 x 0.03 x 1.00 = 0.26
5. Pas. Beton plat tutup saluran t=7cm 14.09 x 1.00 x 0.07 x 1.00 = 0.99 = 0.99 m3

IV PEKERJAAN PASANGAN
1. Pasangan bata Merah 1PC : 5Ps
depan 21.40 x 3.85 x x = 82.39 = 191.00 m2
belakang 21.40 x 1.70 x x = 36.38
horisontal 3.65 x 1.05 x 8.00 x = 30.66
sumur 17.80 x 2.39 x x = 42.54
gewel 0.50 x 3.65 x 1.42 x 8.00 = 20.73
= 212.70
p1 0.91 x 2.14 x 5.00 x = 9.74
p2 0.70 x 2.00 x 2.00 x = 2.80
p3 1.29 x 2.10 x 1.00 x = 2.71
j1 0.39 x 1.84 x 9.00 x = 6.46
= 21.70
total 212.70 - 21.70 = 191.00
2. Plesteran dinding baru 1Pc : 5Ps = 382.00 m2
dinding baru 191.00 x 2.00 = 382.00
3. Plesteran dinding lama 1Pc : 5Ps = 53.50 m2
dinding lama dalam 21.40 x 2.50 x x = 53.50
NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat
1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
3. Pekerjaan Acian 382.00 + = 382.00 m2

V PEKERJAAN ATAP
1. Pasang rangka atap galvalume x x x = = 115.64 m2
besar 16.60 x 4.80 x x = 79.68
kecil 5.80 x 6.20 x x = 35.96
2. Pasang genteng kodok ex. Karangpilang x x x = = 130.33 m2
besar belakang 20.88 x 2.14 x x = 44.67
besar depan 18.79 x 3.06 x x = 57.48
kecil samping kiri 1.40 x 3.54 x x = 4.96
kecil samping kanan 3.75 x 3.54 x x = 13.28
kecil depan 0.50 x 5.80 x 3.43 x = 9.94
3. Pasang genteng bubung ex. Karangpilang 20.10 + 1.30 + 9.98 + 3.54 = 34.92 = 34.92 m1
4. Pasang talang seng galvalume 21.65 + 14.74 + 5.21 x = 41.60 = 41.60 m1
5. Pasang rangka canopy besi hollow 4x4 cm 2.55 x 14.09 x x = 35.93 = 35.93 m2
6. Pasang atap zincalume 2.55 x 14.09 x x = 35.93 = 35.93 m2
7. Pasang listplank Kalsiplank l=30cm 17.25 + 1.40 + 5.80 + 6.20 = 30.65 = 30.65 m1

VI PEKERJAAN PLAFOND
1. Pasang rangka plafond hollow galvalume = 105.14 m2
1 3.15 x 3.65 x x 1.00 = 11.50
2 5.15 x 3.65 x x 1.00 = 18.80
km/wc 3.15 x 1.50 x x 1.00 = 4.73
depan km/wc 3.15 x 2.15 x x 1.00 = 6.77
3 3.20 x 3.65 x x 1.00 = 11.68
4 3.10 x 3.65 x x 1.00 = 11.32
5 3.65 x 5.05 x x 1.00 = 18.43
teras besar 0.50 x 14.74 x x 1.00 = 7.37
1.00 x 3.15 x x 1.00 = 3.15
1.00 x 1.40 x x 1.00 = 1.40
teras besar 1.00 x 3.80 x x 1.00 = 3.80
1.00 x 6.20 x x 1.00 = 6.20

2. Pasang penutup plafond gypsumboard 9mm = 105.14 m2


3. List gypsum kecil = 95.70 m'
1 3.15 + 3.65 x 2.00 x 1.00 = 13.60
2 5.15 + 3.65 x 2.00 x 1.00 = 17.60
km/wc 3.15 + 1.50 x 2.00 x 1.00 = 9.30
depan km/wc 3.15 + 2.15 x 2.00 x 1.00 = 10.60
3 3.20 + 3.65 x 2.00 x 1.00 = 13.70
4 3.10 + 3.65 x 2.00 x 1.00 = 13.50
5 3.65 + 5.05 x 2.00 x 1.00 = 17.40

VI PEKERJAAN PINTU JENDELA


1. Pasang kusen alumunium 4" Brown = 73.60 m'
P1 5 2.14 x 2.00 x x 5.00 = 21.40
0.82 x 2.00 x x 5.00 = 8.20
P3 1 2.14 x 2.00 x x 1.00 = 4.28
1.20 x 1.00 x x 1.00 = 1.20
J1 9 1.84 x 2.00 x x 9.00 = 33.12
0.30 x 2.00 x x 9.00 = 5.40

2. Pasang daun pintu board WPC


- daun pintu board WPC 0,5cm = 5.00 bh
- Engsel pintu 5.00 x 3.00 = 15.00 bh
- Pasang slot pintu 2x putar = 5.00 bh
3. Pasang Daun Jendela alumunium lengkap (coklat)
- daun jendela aluminium brown model casement = 6.46 m2
J1 0.39 x 1.84 x 9.00 x = 6.46
- kaca bening 5mm = 4.75 m2
J1 0.30 x 1.76 x 9.00 x = 4.75
- Engsel Casement uk. 12" = 18.00 bh
J1 2.00 x 9.00 x = 18.00
- Pasang Rambuncis = 9.00 bh
4. Pasang daun pintu aluminium isi kaca ryben
- daun aluminium isi kaca ryben 0.60 x 2.10 x x 2.00 = 2.52 = 2.52 m2
- Engsel pintu 1.00 x 6.00 x x = = 6.00 bh
- Pasang slot pintu 2x putar 1.00 x x x = = 1.00 bh
- Grendel pintu 1.00 x x x = = 1.00 bh
5. Pasang kaca ryben 2.00 x 0.50 x x 2.00 = 2.00 = 2.00 m2
NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat
1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
VII PEKERJAAN KERAMIK
1. Pasang lantai keramik 40x40cm = 129.81 m2
1 3.15 x 3.65 x 1.00 = 11.50
2 5.15 x 3.65 x 1.00 = 18.80
depan km/wc 3.15 x 2.15 x 1.00 = 6.77
3 3.20 x 3.65 x 1.00 = 11.68
4 3.10 x 3.65 x 1.00 = 11.32
5 3.65 x 5.05 x 1.00 = 18.43
teras depan 14.10 x 3.05 x 1.00 = 43.01
1.00 x 3.51 x 1.00 = 3.51
1.00 x 4.80 x 1.00 = 4.80

VIII PEKERJAAN KM / WC
1. Pasang daun pintu kamar mandi
- Pasang kusen alumunium 4" Coklat 2.00 + 2.00 + 0.60 x 2.00 = 9.20 = 9.20 m1
- daun pintu aluminium 0.60 x 2.00 x 2.00 = 2.40 = 2.40 m2
- Engsel pintu 2.00 x 2.00 x = 4.00 bh
- Pasang slot pintu 2x putar 1.00 x 2.00 x = 2.00 bh
2. Pasang Kloset jongkok = 2.00 bh
3. Pasang Floor drain = 2.00 bh
4. Pasang Kran air = 2.00 bh
5. Pasang lantai keramik 20x20cm 1.30 x 1.50 = 1.95 = 4.73 m2
1.85 x 1.50 = 2.78
6. Pasang keramik dinding 20x25cm 5.85 x 1.50 x = 8.78 = 15.98 m2
4.80 x 1.50 x = 7.20
7. Instalasi Pipa air bersih 3/4" = 8.00 m'
8. Instalasi Pipa air kotor 3" = 12.00 m'
9. Instalasi Pipa air kotor 4" = 12.00 m'
10. Pekerjaan septiktank Batu bata = 1.00 unit
11. Pekerjaan resapan buis beton Ø 80cm (3bh) = 1.00 unit

IX PEKERJAAN INSTALASI LISTRIK


1. Instalasi titik lampu = 16.00 titik
2. Pasang lampu SL tornado 24 watt ex. Philips = 12.00 bh
3. Pasang lampu SL tornado 15 watt ex. Philips = 4.00 bh
4. Pasang Instalasi Stop kontak = 6.00 bh
5. Pasang saklar ganda = 6.00 bh
6. Pasang saklar tunggal = 3.00 bh

X PEKERJAAN CAT
1. Cat dinding baru = 382.00 m2
2. Cat dinding lama = 53.50 m2
3. Cat plafond = 105.14 m2
4. Cat listplank 0.35 x 30.65 = 10.73 m2

B PEKERJAAN GASEBO
1. Pasang gasebo lengkap = 1.00 unit

C PEKERJAAN LAMPU HALAMAN


1. Galihan tanah pondasi 0.60 x 0.60 x 1.00 x 3.00 = 1.08 = 1.08 m3
2. Urugan tanah kembali 0.25 x 1.08 x x = 0.27 = 0.27 m3
3. Urugan pasir bawah pondasi 0.60 x 0.60 x 0.10 x 3.00 = 0.11 = 0.11 m3
4. Pas. Pondasi beton plat 0.45 x 0.60 x 0.90 x 3.00 = 0.73 = 0.73 m3
5. Pas. Ankur dia. 16mm P=500mm 4.00 x 3.00 x x = 12.00 = 12.00 bj
6. Pas. Base plat 12mm 0.09 x 4.00 x 303.82 x = 109.38 = 109.38 kg
7. Pas. Tiang lampu x x x = = 3.00 unit
8. Pas. Lampu LED 200watt x x x = = 3.00 unit
9. Pas. Panel lampu x x x = = 3.00 unit
10. Pas. Kabel tanam NYY 3X2,5 x x x = = 110.00 m1
11. Pas. Saklar ganda x x x = = 2.00 unit
12. Pekerjaan cat besi 0.63 x 10.00 x x 3.00 = 18.84 = 18.84 m2

D PEKERJAAN TIANG BENDERA


1. Galihan tanah pondasi 0.70 x 0.70 x 0.50 x 1.00 = 0.25 = 0.25 m3
2. Urugan tanah kembali 0.25 x 0.25 x x = 0.06 = 0.06 m3
3. Urugan pasir bawah pondasi 0.70 x 0.70 x 0.10 x 1.00 = 0.05 = 0.05 m3
4. Pekerjaan Pengeboran Pondasi Strous Ø(30x30)cm 2.00 x 1.00 x x = 2.00 = 2.00 m1
5. Pekerjaan Beton Pondasi Strous Ø(30x30)cm 3.00 x 0.07 x x 1.00 = 0.21 = 0.21 m3
6. Pas. Pondasi beton plat 70x70x25cm 0.70 x 0.70 x 0.25 x 1.00 = 0.12 = 0.12 m3
7. Pasangan bata Merah 1PC : 5Ps 1.50 x 1.50 = 2.25 = 2.25 m2
8. Plesteran dinding baru 1Pc : 5Ps x = 2.25 m2
9. Pasang ornamen bunga x = 1.00 unit
10. Pas. Ankur dia. 16mm P=500mm 4.00 x 1.00 x x = 4.00 = 4.00 bj
11. Pas. Base plat 12mm 0.09 x 1.00 x 303.82 x = 27.34 = 27.34 kg
12. Pas. Tiang bendera x x x = = 1.00 unit
13. Pekerjaan cat besi 0.63 x 9.00 x x 1.00 = 5.65 = 5.65 m2

F PEKERJAAN LAMPU LED PENDOPO


1. Instalasi lampu x x x = - = 1.00 titik
2. Pas. Lampu LED selang x x x = - = 108.02 m1
lisplank 13.40 x 4.00 x x = 53.60
nok 9.07 x 1.50 x 4.00 x = 54.42
3. Pas. Saklar x x x = = 1.00 unit
NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat
1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
PERHITUNGAN VOLUME
Nama Program : PENINGKATAN SARANA DAN PRASARANA APARATUR
Nama Kegiatan : PEMELIHARAAN RUTIN / BERKALA GEDUNG KANTOR
Nama Pekerjaan : REVITASI KANTOR EX. KANTOR CAPIL
Lokasi Kegiatan : KANTOR DISPORA SIDOARJO

NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat


1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
A GEDUNG
I PEKERJAAN PERSIAPAN
1. Pembersihan lokasi 23.00 x 1.50 x = 34.50 = 34.50 m2
2. Pekerjaan bongkaran partisi x x = 1.00 = 1.00 ls

II PEKERJAAN CAT
1. Cat dinding lama = 1,165.09 m2
horisontal paling timur 10.80 x 3.50 x x = 37.80
7.20 x 3.50 x x = 25.20
3.00 x 3.50 x x = 10.50
3.60 x 3.50 x x = 12.60
5.60 x 3.50 x x = 19.60
7.10 x 3.50 x x = 24.85
5.60 x 3.50 x x = 19.60
5.70 x 3.50 x x = 19.95
5.75 x 3.50 x x = 20.13
15.80 x 3.50 x x = 55.30
2.00 x 3.50 x x = 7.00
7.25 x 3.50 x x = 25.38
2.00 x 3.50 x x = 7.00
paling barat 7.20 x 3.50 x x = 25.20
vertical paling utara 12.00 x 3.50 x x = 42.00
4.75 x 3.50 x x = 16.63
3.50 x 3.50 x x = 12.25
3.50 x 3.50 x x = 12.25
10.75 x 3.50 x x = 37.63
6.00 x 3.50 x x = 21.00
8.50 x 3.50 x x = 29.75
5.25 x 3.50 x x = 18.38
6.50 x 3.50 x x = 22.75
6.00 x 3.50 x x = 21.00
2.00 x 3.50 x x = 7.00
6.00 x 3.50 x x = 21.00
4.50 x 3.50 x x = 15.75
4.00 x 3.50 x x = 14.00
paling selatan 13.50 x 3.50 x x = 47.25
kolom teras 1.60 x 3.30 x 2.00 x = 10.56
gewel teras 0.50 x 7.75 x 1.41 x = 5.46
bata bawah gewel 10.75 x 0.68 x x = 7.31
= 672.06
rong kusen x x x = -
p1 1 2.00 x 2.10 x 1.00 x = 4.20
p2 16 0.90 x 2.10 x 16.00 x = 30.24
p3 1 2.00 x 2.10 x 1.00 x = 4.20
p4 3 0.80 x 2.00 x 3.00 x = 4.80
j1 2 1.00 x 2.80 x 2.00 x = 5.60
j2 6 0.42 x 2.50 x 6.00 x = 6.30
j3 10 1.78 x 1.92 x 10.00 x = 34.18
= 89.52
total 672.06 - 89.52 x x 2.00 = 1,165.09

2. Cat listplank = 42.32 m2


0.35 x 34.50 x x 2.00 = 24.15
0.35 x 25.95 x x 2.00 = 18.17

3. Cat plafond = 331.90 m2


lokasi 1 4.20 x 4.75 x x = 19.95
lokasi 2 x x x = 72.34
lokasi 3 5.60 x 4.60 x x = 25.76
1.25 x 2.85 x x = 3.56
lokasi 4 5.60 x 4.60 x x = 25.76
1.25 x 2.85 x x = 3.56
lokasi 5 3.60 x 3.50 x x = 12.60
lokasi 6 3.60 x 3.50 x x = 12.60
lokasi 7 2.75 x 1.25 x x = 3.44
lokasi 8 2.50 x 3.75 x x = 9.38
lokasi 9 1.25 x 2.00 x x = 2.50
lokasi 10 1.25 x 2.00 x x = 2.50
lokasi 11 1.25 x 2.00 x x = 2.50
lokasi 12 1.50 x 2.00 x x = 3.00
lokasi 13 3.70 x 4.50 x x = 16.65
2.00 x 3.25 x x = 6.50
lokasi 14 6.00 x 3.60 x x = 21.60
lokasi 15 7.10 x 6.50 x x = 46.15
3.50 x 4.50 x x = 15.75
lokasi 16 4.00 x 5.20 x x = 20.80
lokasi 17 2.50 x 2.00 x x = 5.00
NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat
1 2 3.00 4.00 5.00 6.00 7.00 8.00 9
III PEKERJAAN INSTALASI LISTRIK
1. Instalasi titik lampu = 57.00 titik
2. Pasang lampu SL tornado 24 watt ex. Philips = 32.00 bh
3. Pasang lampu SL tornado 15 watt ex. Philips = 3.00 bh
4. Pasang lampu SL tornado 15 watt DOWNLIGHT = 22.00 bh

IV PEKERJAAN PINTU JENDELA


1. Pasang Daun pintu board WPC 0,5cm 9.00 x x x = = 9.00 bh
2. Pasang Engsel pintu 27.00 x x x = = 27.00 bh
3. Pasang slot pintu 2x putar x x x = = 9.00 bh

B KANTIN
I PEKERJAAN PERSIAPAN
1. Pembersihan lokasi 27.10 x 1.00 x = 27.10 = 27.10 m2
2. Pekerjaan Bongkaran atap 3.75 x 9.80 x x 1.00 = 36.75 = 36.75 m2

II PEKERJAAN BETON
1. Beton balok latei 12/15 K-175 0.12 x 0.15 x 11.40 x 1.00 = 0.21 = 0.21 m3
2. Pas. Beton rabat bawah lantai K-100 x x x = - = 0.85 m3
4.50 x 2.50 x 0.03 x 1.00 = 0.34
2.50 x 3.75 x 0.03 x 1.00 = 0.28
2.80 x 2.80 x 0.03 x 1.00 = 0.24
III PEKERJAAN PASANGAN
1. Pasangan bata Merah 1PC : 5Ps
PENINGGIAN 0.50 x 27.10 x x = 13.55 = 13.55 m2
2. Plesteran dinding baru 1Pc : 5Ps = 27.10 m2
dinding baru 13.55 x 2.00 = 27.10
3. Pekerjaan Acian 27.10 + = 27.10 m2

IV PEKERJAAN ATAP
1. Pasang rangka atap galvalume x x x = = 56.05 m2
besar 4.75 x 11.80 x x = 56.05
2. Pasang atap zincalume x x x = - = 92.38 m2
kantin 4.75 x 11.80 x x = 56.05
canopy 1.50 x 7.15 x x = 10.73
4.50 x 4.75 x x = 21.38
1.30 x 3.25 x x = 4.23
3. Pasang rangka canopy besi hollow 3,5x3,5 cm x x x = 92.38 = 92.38 m2

V PEKERJAAN PLAFOND
1. Pasang rangka plafond hollow galvalume = 10.13 m2
kantin 2.25 x 4.50 x x 1.00 = 10.13
2. Pasang penutup plafond gypsumboard 9mm = 10.13 m2
3. List gypsum kecil = 13.50 m'
kantin 2.25 + 4.50 x 2.00 x 1.00 = 13.50

VI PEKERJAAN PINTU JENDELA


1. Pasang kusen alumunium 4" Brown = 19.13 m'
P1 2 2.14 x 2.00 x x 2.00 = 8.56
0.82 x 2.00 x x 2.00 = 3.28
P2 1 2.14 x 2.00 x x 1.00 = 4.28
0.87 x 1.00 x x 1.00 = 0.87
0.82 x 1.00 x x 1.00 = 0.82
0.66 x 2.00 x x 1.00 = 1.32

2. Pasang daun pintu board WPC


- daun pintu board WPC 0,5cm = 3.00 bh
- Engsel pintu 3.00 x 3.00 = 9.00 bh
- Pasang slot pintu 2x putar = 3.00 bh
3. Pasang Daun Jendela alumunium lengkap (coklat)
- daun jendela aluminium brown model casement = 0.47 m2
P2 0.62 x 0.76 x 1.00 x = 0.47
- kaca bening 5mm = 0.34 m2
P2 0.52 x 0.66 x 1.00 x = 0.34
- Engsel Casement uk. 12" = 2.00 bh
J1 2.00 x 1.00 x = 2.00
- Pasang Rambuncis = 1.00 bh
4. Pasang pintu harmonika = 1.00 unit

VII PEKERJAAN KERAMIK


1. Pasang lantai keramik 40x40cm = 28.47 m2
4.50 x 2.50 x 1.00 = 11.25
2.50 x 3.75 x 1.00 = 9.38
2.80 x 2.80 x 1.00 = 7.84

VIII PEKERJAAN INSTALASI LISTRIK


1. Instalasi titik lampu = 9.00 titik
2. Pasang lampu SL tornado 24 watt ex. Philips = 9.00 bh
4. Pasang Instalasi Stop kontak = 6.00 bh
5. Pasang saklar ganda = 3.00 bh
6. Pasang saklar tunggal = 2.00 bh

IX PEKERJAAN CAT
1. Cat dinding baru = 27.10 m2
2. Cat dinding lama = 149.68 m2
21.05 x 2.76 = 58.16
9.80 x 2.76 = 27.08
= 85.24
pintu harmonika 2.00 x 2.00 x x 1.00 = 4.00
p1 2.14 x 0.91 x x 2.00 = 3.89
p2 2.14 x 0.91 x x 1.00 = 1.95
0.66 x 0.84 x x 1.00 = 0.55
= 10.40
total cat 85.24 - 10.40 x 2.00 = 149.68
3. Cat plafond = 10.13 m2
PERHITUNGAN VOLUME
Nama Program : PENDIDIKAN DASAR
Nama Kegiatan : PEMBANGUNAN DAN REHABILITASI BANGUNAN SD
Nama Pekerjaan : REHABILITASI SD NEGERI KEMANTREN I
Lokasi Kegiatan : KEC. TULANGAN KAB. SIDOARJO

NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat


1 2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN
1. Pembersihan Lokasi 37.36 x 1.00 x x 1.00 = 37.36 = 37.36 m2
2. Pekerjaan Bongkaran dinding 0.50 x 0.15 x 3.00 x 4.00 = 0.90 = 0.90 m3

II PEKERJAAN TANAH
1. Galian tanah untuk pondasi 0.60 x 0.60 x 0.75 x 15.00 = 4.05 = 4.05 m3
2. Urugan Tanah Kembali 0.25 x 4.05 x x = 1.01 = 1.01 m3
3. Urugan pasir bawah pondasi 0.60 x 0.60 x 0.05 x 15.00 = 0.27 = 0.27 m3

III PEKERJAAN PONDASI


1. Pas. Pondasi beton plat 50x50x15 0.50 x 0.50 x 0.15 x 15.00 = 0.56 = 0.56 m3
2. Pas. Beton rabat bawah pondasi 1Pc : 3PS : 6Kr 0.50 x 0.50 x 0.05 x 15.00 = 0.19 = 0.19 m3

IV PEKERJAAN BETON
2. Beton Kolom K2 15/15 0.15 x 0.15 x 3.50 x 5.00 = 0.39 = 0.39 m3
3. Beton Kolom K3 20/20 0.20 x 0.20 x 3.50 x 2.00 = 0.28 = 0.28 m3
4. Beton Kolom KP 12/12 0.12 x 0.12 x 3.50 x 4.00 = 0.20 = 0.20 m3
5. Beton balok latei 12/15 0.12 x 0.15 x 12.00 x 1.00 = 0.22 = 0.56 m3
0.12 x 0.15 x 6.00 x 1.00 = 0.11
0.12 x 0.15 x 2.00 x 4.00 = 0.14
0.12 x 0.15 x 5.00 x 1.00 = 0.09
6. Beton Balok 15/15 0.15 x 0.15 x 15.00 x 1.00 = 0.34 = 0.34 m3
7. Beton plat canopy t=5 cm K-175 0.91 x 0.50 x 0.05 x 1.00 = 0.02 = 0.02 m3
8. Beton ring balok 12/15 0.12 x 0.15 x 55.85 x 1.00 = 1.01 = 1.52 m3
ring gewel 0.12 x 0.15 x 6.28 x 4.00 = 0.45
0.12 x 0.15 x 3.66 x 1.00 = 0.07

V PEKERJAAN PASANGAN
1. Pasangan Bata Merah 1pc : 6ps 0.80 x 55.85 x x = = 19.62 m2
gewel utama 0.50 x 5.00 x 1.80 x 4.00 = 18.00
gewel teras 0.50 x 2.85 x 1.14 x 1.00 = 1.62
= 19.62
2. Plesteran dinding 1pc : 6ps baru - x 2.00 x x = - = 19.62 m2
gewel utama 18.00 x 1.00 x x = 18.00
gewel teras 1.62 x 1.00 x x = 1.62

3. Plesteran dinding 1pc : 6ps lama x x x = = 86.56 m2


tembok lama 55.85 x 1.35 x x = 75.40
luasan kusen
pj1 3 2.59 x 0.91 x 3.00 x 1.00 = 7.07
1.29 x 1.29 x 3.00 x 1.00 = 4.99
p1 1 1.32 x 2.15 x 1.00 x 1.00 = 2.84
p2 3 0.91 x 2.14 x 3.00 x 1.00 = 5.84
p3 1 0.81 x 2.14 x 1.00 x 1.00 = 1.73
j1 3 1.29 x 1.98 x 3.00 x 1.00 = 7.66
j2 2 1.65 x 0.60 x 2.00 x 1.00 = 1.98
= 32.12
total 75.40 - 32.12 x 2.00 = 86.56

4. Plesteran beton 1pc : 3ps x x x = - = 42.75 m2


Beton kolom K1 15/25 3.90 x 0.50 x x 10.00 = 19.50
Beton Kolom K2 15/15 2.83 x 0.60 x x 5.00 = 8.49
Beton Kolom K3 20/20 3.90 x 0.70 x x 2.00 = 5.46
Beton balok latei 12/15 12.00 x 0.30 x x 1.00 = 3.60
6.00 x 0.30 x x 1.00 = 1.80
2.00 x 0.30 x x 4.00 = 2.40
5.00 x 0.30 x x 1.00 = 1.50
5. Plesteran Acian 19.62 + 86.56 + 42.75 + = 148.93 = 148.93 m2

VI PEKERJAAN PENUTUP ATAP x x x = =


1. Pasang rangka atap galvalume 8.16 x 14.15 x x = 115.46 = 125.46 m2
2.50 x 4.00 x x = 10.00
2. Pasang genteng kodok ex. Karangpilang 4.36 x 14.15 x x = 61.69 = 152.99 m2
5.59 x 14.15 x x = 79.10
2.44 x 2.50 x 2.00 x = 12.20
3. Pasang genteng bubung ex. Karangpilang 14.15 + 2.50 x x = 16.65 = 16.65 m1
4. flashing seng 4.36 + 5.59 x x 2.00 = 19.90 = 29.66 m1
2.44 + 2.44 x x 2.00 = 9.76

5. Pasang listplank woodplank 1/25 19.90 + 28.30 + 9.76 + = 57.96 = 57.96 m1


VII PEKERJAAN PLAFOND x x x = =
1. Pasang plafond gypsumboard t=9mm rangka hollow x x x = = 113.61 m2
R. Guru 6.00 x 5.00 x x 1.00 = 30.00
R. Kepsek 3.00 x 5.00 x x 1.00 = 15.00
UKS 3.00 x 3.00 x x 1.00 = -
Pantry 2.00 x 1.75 x x 1.00 = 3.50
Km/wc 2.00 x 1.25 x x 1.00 = 2.50
teras depan kepsek 1.85 x 2.85 x x 1.00 = 5.27
0.50 x 2.00 x x 2.00 = 2.00
0.50 x 2.44 x x 2.00 = 2.44
teras depan besar 1.50 x 12.00 x x 1.00 = 18.00
0.25 x 12.00 x x 1.00 = 3.00
teras belakang besar 1.00 x 12.00 x x 1.00 = 12.00
overstek samping 1.00 x 19.90 x x 1.00 = 19.90
2. List gypsum kecil + x x = = 85.00 m1
R. Guru 6.00 + 5.00 x 2.00 x 1.00 = 22.00
R. Kepsek 3.00 + 5.00 x 2.00 x 1.00 = 16.00
UKS 3.00 + 3.00 x 2.00 x 1.00 = -
Pantry 2.00 + 1.75 x 2.00 x 1.00 = 7.50
Km/wc 2.00 + 1.20 x 2.00 x 1.00 = 6.40
teras depan kepsek 1.85 + 1.20 x 2.00 x 1.00 = 6.10
teras depan besar 1.50 + 12.00 x 2.00 x 1.00 = 27.00

VIII PEKERJAAN PINTU JENDELA


1. Pasang kusen alumunium 4" Coklat x x x = = 70.37 m1
pj1 1 2.59 x 2.00 x x 1.00 = 5.18
1.29 x 1.00 x x 1.00 = 1.29
1.55 x 2.00 x x 1.00 = 3.10
0.62 x 1.00 x x 1.00 = 0.62
p1 1 2.15 x 2.00 x x 1.00 = 4.30
1.22 x 1.00 x x 1.00 = 1.22
p2 4 2.14 x 2.00 x x 4.00 = 17.12
0.82 x 1.00 x x 4.00 = 3.28
j1 2 1.29 x 3.00 x x 2.00 = 7.74
1.98 x 3.00 x x 2.00 = 11.88
j2 2 1.65 x 2.00 x x 2.00 = 6.60
0.50 x 2.00 x x 2.00 = 2.00
bv 1 2.04 x 2.00 x x 1.00 = 4.08
0.49 x 4.00 x x 1.00 = 1.96
2. Pasang daun pintu board WPC x x x = =
- daun pintu board WPC 0,5cm 5.00 x x x = 5.00 = 5.00 unit
- Engsel pintu 5.00 x 3.00 x x = 15.00 = 15.00 bh
- Pasang slot pintu 2x putar 5.00 x x x = 5.00 = 5.00 unit
3. Pasang daun pintu aluminium isi kaca x x x = =
- daun pintu aluminium 2.00 x x x = 2.00 = 2.00 unit
- Engsel pintu 2.00 x 3.00 x x = 6.00 = 6.00 bh
- Pasang slot pintu 2x putar 1.00 x x x = 1.00 = 1.00 unit
4. Pasang Daun Jendela alumunium lengkap (coklat) x x x = =
- Slimar daun jendela brown model casement = 3.42 m1
j1 0.60 x 0.76 x 2.00 x 2.00 = 1.82
j2 0.51 x 1.56 x 1.00 x 2.00 = 1.59
- Kaca bening 5mm = 2.52 m2
j1 0.50 x 0.66 x 2.00 x 2.00 = 1.32
j2 0.41 x 1.46 x 1.00 x 2.00 = 1.20

- Engsel Casement uk. 12" 4.00 + 1.00 + 2.00 x 2.00 = 14.00 = 14.00 BH
- Pasang Rambuncis 7.00 x x x = 7.00 = 7.00 bh
5. Pasang kaca Bening t=5mm = 4.18 m2
pj1 0.60 x 0.76 x 1.00 = 0.46
0.82 x 0.50 x 1.00 = 0.41
0.60 x 0.50 x 2.00 = 0.60
j1 0.60 x 0.76 x 2.00 = 0.91
0.60 x 0.50 x 3.00 x 2.00 = 0.90
bv1 0.60 x 0.50 x 3.00 x 1.00 = 0.90
IX PEKERJAAN LANTAI
1. Pasang lantai keramik 40x40 x x x = - = 89.31 m2
R. Guru 6.00 x 5.00 x x 1.00 = 30.00
R. Kepsek 3.00 x 5.00 x x 1.00 = 15.00
UKS 3.00 x 3.00 x x 1.00 = -
Pantry 2.00 x 1.75 x x 1.00 = 3.50
teras depan kepsek 1.85 x 2.85 x x 1.00 = 5.27
1.00 x 2.50 x x 1.00 = 2.50
1.00 x 2.08 x x 1.00 = 2.08
teras besar 1.50 x 12.00 x x 1.00 = 18.00
teras kecil 1.08 x 12.00 x x 1.00 = 12.96

2. Pasang lantai keramik 20x20 x x x = - = 2.50 m2


Km/wc 2.00 x 1.25 x x 1.00 = 2.50
3. Pasang dinding keramik 20x25 5.80 x 1.25 x x 1.00 = 7.25 = 7.25 m2

X PEKERJAAN INSTALASI LISTRIK


1. Instalasi titik lampu x x x = = 9.00
2. Pasang lampu SL tornado 24 watt x x x = 4.00 = 4.00
3. Pasang lampu SL tornado 15 watt x x x = 5.00 = 5.00
4. Pasang Stop kontak x x x = 4.00 = 4.00
5. Pasang saklar ganda x x x = 4.00 = 4.00

XI PEKERJAAN CAT
1. Cat dinding baru 19.62 + 42.75 + 86.56 x = 148.93 = 148.93 m2
2. Cat listplank 0.30 x 57.96 x x = 17.39 = 17.39 m2
3. Cat plafon 113.61 x x x = 113.61 = 113.61 m2
PEMERINTAH KABUPATEN SIDOARJO
DINAS KESEHATAN
UPTD PUSKESMAS TROSOBO
Jl. Raya Trosobo Taman - Sidoarjo, Kode Pos 61257
Telp. 031-7873664 Email : pkmtrosobo@gmail.com

PROGRAM :

Program Upaya Kesehatan Masyarakat di Puskesmas

KEGIATAN :

Penyediaan Biaya Operasional dan Pemeliharaan Puskesmas Trosobo

E.E
( Engineer Estimate)
 

PEKERJAAN :

Renovasi Gapura Puskesmas

LOKASI PEKERJAAN :

Puskesmas Trosobo Kec. Taman Kab. Sidoarjo

TAHUN ANGGARAN :

2018
KONSULTAN PERENCANA
DAFTAR HARGA BAHAN BANGUNAN
SEBELUM PPN UNTUK TAHUN ANGGARAN 2018 SEMESTER I

No. Nama / Jenis Bahan Satuan Harga Bahan

1 Pasir Urug/sirtu M3 283,333.33


2 Pasir Pasang M3 271,600.00
3 Pasir beton M3 313,333.00
4 Pasir Beton (kg) Kg 223.81
5 Sirtu Ayak M3 185,000.00
6 Batu belah M3 283,333.00
7 Bata merah Bh 750.00
8 Koral beton M3 280,000.00
9 koral beton (kg) kg 207.41
10 Bata ringan tebal 7,5 cm M3 849,150.00
11 Bata ringan tebal 10 cm M3 670,889.00
12 Semen portland sak 46,000.00
13 Semen portland (kg) Kg 1,150.00
14 Mortar siap pakai (MSP) Kg 6,100.00
15 Semen warna Kg 7,750.00
16 Besi beton polos Kg 10,650.00
17 Besi beton ulir Kg 11,650.00
18 Kawat beton Kg 21,200.00
19 Dinabolt Bh 2,300.00
20 Besi baja WF Kg 13,000.00
21 Besi profil siku Kg 13,000.00
22 Besi CNP Kg 13,500.00
23 Besi plat Kg 13,500.00
24 Besi Strip (2x3)cm Kg 11,200.00
25 Stak trektang Bh 1,100.00
26 Kawat las Kg 57,000.00
27 Maintruss C 70.30.0,75 M 13,500.00
28 Maintruss C 80.30.0,75 M 15,833.33
29 Reng UK 3.2.0,45 M 5,500.00
30 Screw 12 - 14 x 20 BJ 300.00
31 Screw 12 - 14 x 16 BJ 300.00
32 Kusen Alumunium Profil 4" M 110,000.00
33 Slimar Alumunium Profil 3/8" model casement 3 Profil M 110,000.00
34 Sealant Tube 36,000.00
35 Profil kaca M 32,000.00
36 Kalsiplang l=30cm t=9mm M 21,800.00
37 Kalsiplang l=20cm t=9mm M 16,300.00
38 Besi hollow 4x4 plafon M 8,000.00
39 Besi hollow 2x4 plafon M 5,500.00
40 Gypsumboard 9mm Lbr 62,500.00
41 kalsiboard (1200x2400x4)mm Lbr 67,900.00
42 List gypsum profil M 14,000.00
43 List kayu profil M 7,000.00
44 Kawat Ram M 22,600.00
45 Sekrup gypsumboard kg 45,000.00
No. Nama / Jenis Bahan Satuan Harga Bahan

46 Paku sekrup Bh 1,100.00


47 Skrup Fixer Bh 950.00
48 Paku Sekrup 1 cm-2,5 cm Bh 900.00
49 Paku skrup 10 cm Bh 2,000.00
50 Paku 1 cm - 2,5 cm Kg 19,500.00
51 Paku 5 cm - 10 cm Kg 19,660.00
52 Paku tripleks Kg 18,400.00
53 Triplek 9 mm Lbr 175,000.00
54 Tripleks 6 mm Lbr 113,000.00
55 Plywood tebal 9 mm Lbr 144,500.00
56 Dolken kayu f 8-10/400 cm Bh 21,000.00
57 Kayu meranti (papan) M3 4,861,111.11
58 Kaso-kaso (5 × 7) cm kayu meranti M3 3,500,000.00
59 Kaso-kaso (4 × 6) cm kayu meranti M3 3,500,000.00
60 Reng 2/3 kayu meranti M3 3,500,000.00
61 Kayu kelas II M3 5,890,000.00
62 Kayu kelas III M3 4,978,000.00
63 Kayu meranti (balok) M3 4,861,111.11
64 Lem kayu Kg 45,000.00
65 Plamir kayu Kg 28,400.00
66 Plamir tembok Kg 15,000.00
67 Amplas Bh 6,850.00
68 Kuwas Bh 23,000.00
69 Rool Bh 25,000.00
70 Cat tembok Kg 31,600.00
71 Cat Kayu Kg 56,350.00
72 Cat meni Kg 41,500.00
73 Cat meni besi Kg 41,500.00
74 Minyak cat Ltr 24,500.00
75 Genteng kaca Bh 98,700.00
76 Genteng karang pilang Kw 1 Bh 7,700.00
77 Bubungan Genteng karang pilang Bh 9,700.00
78 Asbes Gelombang kecil Lbr 94,000.00
79 Seng plat bjls 30 M 46,000.00
80 keramik (30x30) cm M2 55,000.00
81 keramik (40x40) cm M2 70,000.00
82 keramik (40x40) cm (Rock Tile) M2 47,500.00
83 Keramik dinding (20x25) cm M2 80,000.00
84 Keramik lantai (20x20) cm M2 40,000.00
85 Kabel NYA 500 Volt 2 x 2,5 mm2 M 9,000.00
86 Pipa Paralon 5/8" btg 11,500.00
87 T Doos Pvc Bh 3,450.00
88 L Bow Bh 1,000.00
89 Klem Bh 130.00
90 Mongkok Bh 1,000.00
91 Stop Kontak ex Broco Bh 24,500.00
92 Fitting Plafon ex Broco Bh 20,000.00
93 Saklar Tunggal ex Broco Bh 12,000.00
No. Nama / Jenis Bahan Satuan Harga Bahan

94 Saklar Ganda ex Broco Bh 14,700.00


95 MCB Bh 50,000.00
96 Lampu SL model tornado 24 Watt ex Philips Bh 45,400.00
97 Lampu SL model tornado 15 Watt ex Philips Bh 37,900.00
98 Lampu LED 13 Watt ex Philips Bh 51,300.00
99 Kaca tebal bening 5 mm M2 88,000.00
100 Kaca tebal bening 8 mm M2 190,000.00
101 Kaca tebal raiben 5 mm M2 125,000.00
102 Kunci pintu tanam 2x putar Bh 189,800.00
103 Engsel pintu 4" Bh 75,000.00
104 Engsel jendela 3" Bh 22,550.00
105 engsel Casement uk. 8" Bh 12,000.00
106 Rambuncis Bh 12,200.00
107 Grendel Bh 12,500.00
108 Hak angin Bh 12,000.00
109 Klosed Duduk Bh 473,000.00
110 Kloset jongkok porselen Bh 205,000.00
111 Wastefel bh 408,333.00
112 Pipa PVC 1/2" m 5,675.00
113 Pipa PVC 3/4" m' 7,233.25
114 Pipa PVC D 3" m' 48,750.00
115 Pipa PVC D 4" m' 71,250.00
116 Kran air 1/2 " Bh 42,125.00
117 Kran air 3/4 " Bh 33,350.00
118 Seal tape Bh 7,000.00
119 Floor drain Bh 60,000.00
120 Air ltr 100.00
121 Minyak pelumas ltr 30,000.00
122 Minyak bekisting ltr 25,000.00
123 Print out lapis vinyl m2 20,000.00
124 Pintu KM PVC Bh 200,000.00
125 Pintu Kaka MD 82 x210 cm Bh 1,092,000.00
126 Pintu Board WPC 82 x210 cm Bh 1,110,000.00
127 Bahan tambahan kimia liter 60,000.00
128 Solar ltr 10,000.00
129 Sewa alat Las Jam 50,000.00
130 Profil pintu alumunium m 42,325.00
131 MSP (plesteran) kg 3,675.00
132 MSP (acian) kg 2,750.00
133 Keramik border 7,5x20 cm bh 8,000.00
134 Batu tempel hitam m2 120,000.00
135 Paving block 6 cm m2 55,000.00
136 Eternit 100x100 tebal 5mm m2 22,500.00
137 Soda api kg 10,000.00
138 Cat dasar kayu Kg 56,350.00
139 Pengencer Kg 28,000.00
140 Ampelas lbr 6,850.00
141 Politur ltr 71,000.00
No. Nama / Jenis Bahan Satuan Harga Bahan

142 Politur jadi ltr 71,000.00


143 Cat dasar tembok kg 20,000.00
144 Hollow Galvanis 3,5x3,5 t. 1 mm m' 30,500.00
145 Hollow Galvanis 1,5x3,5 t. 1 mm m' 8,566.67
146 hollow 5x5 galvanis Fsl 38,333.33
147 Flashing Seng m' 30,000.00
148 Lis siku aluminium 3 cm m 10,000.00
149 Holow aluminium 1" x 2" m' 11,700.00
150 Jendela alluminium casement 3 profil m' 46,000.00
151 Seng galvalum 0,3 lebar 90 cm m' 41,400.00
152 Seng galvalum 0,3 lebar 60 cm m' 33,500.00
153 Atap galvalum 2,68x1,00x0,4 m 45,000.00
154 Jarum keras Ø 16 mm bh 72,000.00
155 Besi Angkur Ø 16 mm bh 35,000.00
156 Mur baut HTB 12 bh 5,000.00
157 Mur baut Trektang HTB 10 bh 5,000.00
158 Grendel pintu kamar mandi bh 13,000.00
159 Alluminium strip M 32,000.00
160 Karet m 1,800.00
161 Spigot m 8,100.00
162 Beton alur m2 80,000.00
163 Granit Lokal 60 x 60 m2 134,191.20
164 Bata expose kelas A bh 1,100.00
165 Coating kg 65,000.00
166 Topi uskup bh 5,750.00
167 Kanstin (DT 21) K 300 bh 17,250.00
168 U-DITH 400 X 500 X 1200 mm Gandar 5 Ton Unit 940,000.00
169 U-DITH 400 X 600 X 1200 mm Gandar 5 Ton Unit 954,043.20
170 U-DITH 400 X 500 X 1200 mm Gandar 10 Ton Unit 959,463.90
171 U-DITH 400 X 600 X 1200 mm Gandar 10 Ton Unit 1,078,719.30
172 U-DITH 400 X 500 X 1200 mm Gandar 20 Ton Unit 1,349,754.30
173 U-DITH 400 X 600 X 1200 mm Gandar 20 Ton Unit 1,517,796.00
174 COVER U-DITH 400 - 80 / 1200 mm Gandar 5 Ton Unit 346,000.00
175 COVER U-DITH 500 - 80 / 1200 mm Gandar 5 Ton Unit 435,000.00
176 COVER U-DITH 400 - 110 / 1200 mm Gandar 10 Ton Unit 584,000.00
177 COVER U-DITH 500 - 110 / 1200 mm Gandar 10 Ton Unit 628,000.00
178 COVER U-DITH 400 - 110 / 1200 mm Gandar 20 Ton Unit 986,000.00
179 COVER U-DITH 500 - 150 / 1200 mm Gandar 20 Ton Unit 1,386,000.00
180 Alat Bantu Ls. 120,000.00
181 Atap formax l=1,05m m2 215,000.00
182 Tanah Taman Terolah m3 85,000.00
183 #REF! #REF! 26,000.00
184 #REF! #REF! 70,000.00
185 #REF! #REF! 85,000.00
186 #REF! #REF! 2,500.00
187 #REF! #REF! 9,000.00
188 #REF! #REF! 25,000.00
189 #REF! #REF! 2,500.00
No. Nama / Jenis Bahan Satuan Harga Bahan

190 #REF! #REF! 3,000.00


191 #REF! #REF! 6,500.00
192 #REF! #REF! 8,000.00
193 #REF! #REF! 7,000.00
194 #REF! #REF! 25,000.00
195 #REF! #REF! 17,000.00
196 #REF! #REF! 12,000.00
197 #REF! #REF! 19,000.00
PERHITUNGAN VOLUME

Nama Program : Program Upaya Kesehatan Masyarakat di Puskesmas


Nama Kegiatan : Penyediaan Biaya Operasional dan Pemeliharaan Puskesmas Trosobo
Nama Pekerjaan : Renovasi Gapura Puskesmas
Lokasi : Puskesmas Trosobo Kec. Taman Kab. Sidoarjo

NO URAIAN Panjang Lebar Tinggi Jumlah Total Volume Sat


1 2 3 4 5 6 7 8 9

I PEKERJAAN PERSIAPAN
1. Pembersihan Lokasi Awal & Akhir Kegiatan = 1.00 Ls.

2. Pembongkaran Gapura Existing = 1.00 Ls.

II PEKERJAAN TANAH
1. Penggalian Tanah Biasa Untuk Pondasi 0.90 x 0.90 x 1.20 x 2.00 = 1.94 = 1.94 m3

2. Urugan Tanah Kembali 0.25 x 1.94 = 0.49 m3

3. Urugan Pasir 5cm 0.90 x 0.90 x 0.05 x 2.00 = 0.08 = 0.08 m3

III PEKERJAAN PONDASI


1. Pekerjaan Pengeboran Pondasi Strous Ø(30x30)cm 2.00 x 2.00 = 4.00 = 4.00 m1

2. Pekerjaan Beton Pondasi Strous Ø(30x30)cm 0.15 x 3.14 x 2.00 x 2.00 = 1.88 = 1.88 m3

3. Plat Sepatu 100x100x20cm 1.00 x 1.00 x 0.20 x 2.00 = 0.40 = 0.40 m3

4. Beton rabat 1Pc : 3Ps : 6Kr Tebal. 10cm 1.10 x 1.10 x 0.10 x 2.00 = 0.24 = 0.24 m3

IV PEKERJAAN STRUKTUR UTAMA


1. Kolom Beton 60/40 0.60 x 0.40 x 4.30 x 1.00 = 1.03 = 1.03 m3

2. Kolom Beton 100/40 1.00 x 0.40 x 4.75 x 1.00 = 1.90 = 1.04 m3


Pengurangan Beton 0.70 x 0.30 x 4.10 x 1.00 = - 0.86

3. Penebalan Plesteran Beton 1Pc : 4Ps 4.30 x 0.60 x 2.00 = 5.16 = 28.76 m2
4.30 x 0.40 x 2.00 = 3.44
4.75 x 0.40 x 2.00 = 3.80
0.50 x 0.08 x 10.00 = 0.40
7.00 x 0.60 x 2.00 = 8.40
4.75 x 1.00 x 2.00 = 9.50
4.75 x 0.40 x 2.00 = 3.80
Pengurangan Plesteran 4.10 x 0.70 x 2.00 = - 5.74

4. Finishing Granit Lokal 60 x 60 cm 4.30 x 0.60 x 2.00 = 5.16 = 8.60 m2


4.30 x 0.40 x 2.00 = 3.44

5. Plat Beton 12cm (Untuk Penutup Saluran) 4.00 x 0.80 x 0.12 x 1.00 = 0.38 = 0.38 m3

V PEKERJAAN FINISHING
1. Font Akrilik Mirror Cutting Laser (Warna Gold) Size 12 cm = 41.00 = 41.00 bh
2. Font Akrilik Mirror Cutting Laser (Warna Gold) Size 20 cm = 20.00 = 20.00 bh
3. Font Akrilik Mirror Cutting Laser (Warna Gold) Size 8 cm = 38.00 = 38.00 bh
4. Logo Sidoarjo Bahan Akrilik Sticker = 1.00 = 1.00 bh
5. Logo UPT Puskesmas Bahan Akrilik Sticker = 1.00 = 1.00 bh
6. Pasangan Batu Alam Andesit Finishing Countting 4.75 x 1.00 x 2.00 = 9.50 = 7.56 m2
4.75 x 0.40 x 2.00 = 3.80
Pengurangan Batu Alam 4.10 x 0.70 x 2.00 = - 5.74

7. Lampu Sorot LED 30 Watt 2.00 = 2.00 bh

VI PEKERJAAN BESI
1. Pipa Bulat Stainless Steel ∅ 2" Tebal 0.8mm 1.00 x 25.00 = 25.00 = 25.00 m1
2. Plat Besi Baja Hitam Tebal 1.4 mm (Untuk Papan Nama) 7.60 x 0.70 x 2.00 = 10.64 = 10.85 m2
0.70 x 0.15 x 2.00 = 0.21
3. Rangka Hollow 40x40x1.2 mm (Untuk Papan Nama)
Vertikal 0.70 x 4.00 = 2.80 = 38.85 m1
0.70 x 7.00 = 4.90
Horisontal 7.60 x 4.00 = 30.40
0.15 x 5.00 = 0.75
4. Finishing Cat Besi = 10.85 m2
REKAPITULASI
ENGINEER ESTIMATE

Nama Program : Program Upaya Kesehatan Masyarakat di Puskesmas


Nama Kegiatan : Penyediaan Biaya Operasional dan Pemeliharaan Puskesmas Trosobo
Nama Pekerjaan : Renovasi Gapura Puskesmas
Lokasi Kegiatan : Puskesmas Trosobo Kec. Taman Kab. Sidoarjo
Tahun Anggaran : 2018

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp.)

PEMBANGUNAN GAPURA BARU PUSKESMAS TROSOBO

I PEKERJAAN PERSIAPAN 5,000,000.00

II PEKERJAAN TANAH 255,850.86

III PEKERJAAN PONDASI 500,508,194.46

IV PEKERJAAN STRUKTUR UTAMA 781,887,640.67

V PEKERJAAN FINISHING 10,047,870.26

VI PEKERJAAN BESI #VALUE!

SUB TOTAL #VALUE!


PPn 10% #VALUE!
JUMLAH TOTAL #VALUE!
DIBULATKAN #VALUE!
TERBILANG :

#VALUE!

Sidoarjo, Oktober 2018


Dibuat oleh :
Menyetujui : Konsultan Perencana
Pejabat Pelaksana Teknis Kegiatan (PPTK) CV. KARYA ANUGRAH KONSULTAN
UPTD Puskesmas Trosobo

dr. B.IRAWATYRATNA.K, MM Ir. MARTOJO


NIP. 19741019 200701 2 008 Direktur
Mengetahui :
Pejabat Pembuat Komitmen (PPKom)
UPTD Puskesmas Trosobo

dr. MUHAMMAD ATHO'ILLAH, MM


NIP. 19761007 200801 1 009
HARGA UPAH TENAGA KERJA KOTA SIDOARJO TAHUN 2018

HARGA
NO URAIAN SAT.
JAM HARI
1 Mandor org 19,749.00 157,992.00
2 Kepala tukang org 18,499.00 147,992.00
3 Tukang org 17,124.00 136,992.00
4 Pekerja org 15,374.00 122,992.00
5 Operator org 17,124.00 136,992.00
6 Pembantu operator org 15,374.00 122,992.00
7 Sopir org 17,124.00 136,992.00
8 Pembantu sopir org 15,374.00 122,992.00
9 Mekanik org 17,124.00 136,992.00
10 Pembantu mekanik org 15,374.00 122,992.00

HARGA BAHAN KOTA SIDOARJO TAHUN 2018

NO URAIAN SAT. HARGA KETERANGAN

1 Asbes gelombang besar tebal 5 mm (2,50 x 0,92 m) Lbr 95,000.00


2 Asbes gelombang kecil tebal 5 mm (2,25 x 0,92 m) Lbr
3 Asbes gelombang kecil tebal 5 mm (2,00 x 0,92 m) Lbr 55,000.00
4 Asbes wuwung stel gelombang 0,92 mm Lbr -
5 Genteng Karang Pilang / wisma bj -
6 Genteng wuwung karang pilang / wisma bj -
7 Genteng Nglayur/Trenggalek bj -
8 Genteng nok palentong bj -
9 Genteng nok Nglayur/Trenggalek bh -
10 Genteng Beton bj -
11 Genteng Galvalum lbr -
12 Genteng Glazzur lbr -
13 Nok genteng beton bj -
14 Nok genteng Galvalum bj -
15 Sisalation / alluminium foil m2 -
16 Seng gelombang 3" X 6" bkls 28 lbr -
17 Seng plat 3' x 6' Bjls 28 lbr 70,000.00
18 Seng Datar lbr -
19 Triplek tebal 4 mm (1,20 x 2,40) lbr 75,000.00
20 Triplek tebal 4 mm (0,90 x 2,00) lbr 55,000.00
21 Triplek tebal 4 mm (1,22 x 2,44) lbr 70,000.00
22 Triplek tebal 4 mm (1,10 x 2,10) lbr -
23 Formite/ Penjaga jarak bekisting / spacer bh -
24 Formika m' -
25 Plastik Aerator bh -
26 Rolling door alluminium m2 -
27 Pintu Harmonika m2 -
28 pintu aluminium m' -
29 Gypsum board (120X240X9mm) lbr 58,750.00
30 Profil alluminium "T" m -
NO URAIAN SAT. HARGA KETERANGAN

31 Aluminium strip m -
32 Roof light fibreglass kg -
33 Tepung Gypsum kg 4,125.00
34 Ramset bh -
35 BAHAN MENGGUNAKAN KAYU -
36 Dolken kayu Ø 8-10/400 cm bh 21,000.00
37 Kayu jati balok 8/12, 6/12 m3 -
38 Kayu jati usuk 5/7, 4/6, 3/5 m3 -
39 Kayu jati papan 2/20 x 2 m m3 -
40 Kayu jati reng 2/3, 3/5 m3 -
41 Kayu kamper (balok) m3 7,250,000.00
NO URAIAN SAT. HARGA KETERANGAN

42 Kayu kamper (papan) m3 8,000,000.00


43 Kayu kamper (usuk) m3 5,000,000.00
44 Kayu kamper (reng) m3 5,000,000.00
45 Kayu meranti (balok) m3 4,750,000.00
46 Kayu meranti (papan) m3 4,500,000.00
47 Kayu meranti (usuk) m3 3,625,000.00
48 Kayu meranti (begesting) m3 3,375,000.00
49 Kayu kruing (balok) m3 6,500,000.00
50 Kayu kruing (papan) m3 -
51 Kayu kruing (usuk) m3 5,500,000.00
52 List Kayu 2/4 m' 6,000.00
53 List Kayu profil m' 12,500.00
54 Perancah Kayu m3 -
55 Kayu terentang m3 -
56 Ijuk kg -
57 Kaso 5/7 m3 -
58 Kayu papan tebal 9 mm lbr -
59 Bambu Ø6 - 10 / 600 cm btg -
60 Bilik Bambu m' -
61 Minyak Bekisting liter 30,000.00
62 Gedeg Guling 1X3 bh -
63 Gedeg Guling 2X3 bh -
64 Glangsing bh -
65 Tali Rafia roll 17,500.00
66 BAHAN MENGGUNAKAN BATU/PASIR & SEMEN -
67 Batu Bata merah kelas 1 bh 571.00
68 Bata berongga ekspose bh -
69 Batu kali pecah 15/20 m3 223,750.00
70 Batu pecah 5/7 m3 -
71 Batu pecah 2/3 m3
72 Batu pecah 1/2 m3 296,250.00
73 Batu kali pecah 3/5 m3 -
74 Batu tempel m2 -
75 Batu kerikil beton m3 -
76 Pasir cor/beton m3 216,666.67
77 Pasir Pasang m3 192,917.00
78 Pasir urug m3 90,000.00
79 Semen berwarna Yiyitan kg 7,750.00
80 Semen PC (Portland Cement)/Semen Gresik ( 40 Kg) kg 1,145.00
81 Semen Tiga Roda (40 Kg) zak
82 Semen Holcim 40 Kg zak
83 Tanah Urug m3 85,000.00
84 Tanah sirtu (Ngoro) m3 187,000.00
85 Tanah liat m3 -
86 Air liter 25.00
87 BAHAN MENGGUNAKAN BESI/LOGAM -
88 Besi begel/ baut kg
89 Besi beton polos kg 9,000.00
90 Besi beton ulir kg 9,350.00
NO URAIAN SAT. HARGA KETERANGAN

91 Keni bh -
92 Besi pipa galvanis medium 1 1/2, 6m ljr 380,000.00
93 Besi pipa galvanis medium 1 1/4, 6m ljr 402,500.00
94 Besi pipa galvanis medium 1 , 6m ljr 305,000.00
95 Besi pipa galvanis medium 1/2, 6m ljr 160,000.00
96 Besi pipa galvanis medium 2 1/2, 6m ljr 415,000.00
97 Besi pipa galvanis medium 2, 6m ljr 476,666.67
98 Besi pipa galvanis medium 3, 6m ljr 975,000.00
99 Besi pipa galvanis medium 4, 6m ljr -
100 Besi pipa galvanis medium 5, 6m ljr -
101 Besi pipa galvanis medium 6, 6m ljr -
NO URAIAN SAT. HARGA KETERANGAN

102 Besi pipa galvanis medium 3/4, 6m ljr 190,000.00


103 Besi pipa galvanis medium 3/8, 6m ljr -
104 Besi plat 4 x 8 tebal 2 mm, kg 11,349.04
105 Besi Plat bordes 4" x 8" tebal 3mm kg
106 Besi profil WF < 200 mm kg 12,900.00
107 Besi profil WF 200 s/d 400 mm kg 12,900.00
108 Besi profil WF 400 s/d 500 mm kg 13,500.00
109 Besi siku L 60.60.6 kg 9,225.09
110 Besi siku L 30.30.3 kg 7,598.04
111 Besi strip tebal 5 mm kg
112 Kawat ikat beton kg 18,625.00
113 Kawat nyamuk kasa aluminium m2 23,500.00
114 Kawat harmonika m 34,833.33
115 Kawat las listrik kg 28,250.00
116 Rel pintu dorong bh 225,000.00
117 Pengelasan cm -
118 BAHAN UNTUK LANTAI -
119 Paving stone persegi abu-abu tebal 6 cm kasar m2 55,000.00
120 Paving stone persegi abu-abu tebal 8 cm kasar m2 -
121 Paving stone persegi abu-abu tebal 10 cm kasar m2 -
122 Tegel keramik 30 x 30 cm bh 4,000.00
123 Tegel keramik 33 x 33 cm bh -
124 Tegel keramik 40 x 40 cm bh -
125 Tegel keramik 10 x 30 cm bh -
126 Keramik artistik (5 x 20) cm bh -
127 Plint abu-abu 15 x 20 cm bh 7,000.00
128 Plint abu-abu 10 x 30 cm bh -
129 Plint abu-abu 10 x 40 cm bh -
130 Ubin granit 20 x 20 cm bh -
131 Ubin granit 30 x 30 cm bh -
132 Ubin granit 40 x 40 cm bh -
133 Plint Keramik artistik bh -
134 Plint keramik (10 x 20) cm bh -
135 Plint keramik (10 x 10) cm bh -
136 Plint keramik (5 x 20) cm bh -
137 Tegel keramik dinding (20 x 25) cm bh 2,200.00
138 BAHAN UNTUK PENGECATAN -
139 Cat besi Emco kg 73,250.00
140 Cat kayu Emco kg 70,000.00
141 Cat meni (besi/kayu) cap Pedang kg 25,500.00
142 Cat residu liter 14,250.00
143 Meni A kg -
144 Cat tembok Vinilek, (sejenis) 5 kg 117,500.00
145 Cat tembok Decolith dan yg setara 5 kg 98,900.00
146 Vernis jenis lainnya lt 87,500.00
147 Minyak cat/ afduner jenis lainnya lt 14,500.00
148 Kertas gosok/ Ampelas lbr 3,700.00
149 Plamur tembok kg 16,500.00
150 Plamur kayu kg 29,100.00
NO URAIAN SAT. HARGA KETERANGAN

151 Plamur Besi kg 31,800.00


152 Lem kayu kg 21,100.00
153 Lem kayu jenis lainnya 27,250.00
154 Thinner B / minyak cat liter 18,400.00
155 Kuas besar bh 23,100.00
156 Water Proff lbr 4,500.00
157 BAHAN PENGGANTUNG DAN PENGUNCI -
158 Engsel H stl 18,500.00
159 Engsel Kuningan arch asli stl 25,000.00
160 Engsel jendela bh 12,500.00
161 Engsel angin bh 14,000.00
NO URAIAN SAT. HARGA KETERANGAN

162 Engsel pintu bh 32,500.00


163 Engsel pintu viper dan yg setara bh 31,500.00
164 Grendel bj 8,000.00
165 Grendel biasa (besar) bh 14,500.00
166 Grendel biasa (kecil) bh 7,000.00
167 Grendel Tanam bh 105,000.00
168 Grendel Tanam jenis lainnya bh 85,000.00
169 Kunci tanam antik bh 25,000.00
170 Kunci tanam (808) bj 17,500.00
171 Kunci tanam besar kuda terbang 2 x putar bj 81,000.00
172 Kunci tanam kamar mandi bh 53,000.00
173 Door closer bh 200,000.00
174 Door stop bh 26,500.00
175 Door holder bh -
176 Kunci selot bh 15,000.00
177 Hak angin bj 14,500.00
178 Kait angin bh 6,500.00
179 Pegangan pintu bh 100,000.00
180 Kunci tanam biasa bh 21,250.00
181 BAHAN UNTUK KM/WC/URINOIR -
182 Closet duduk putih porselin komplit single blok bh 1,250,000.00
183 Closet duduk putih porselin komplit double blok bh -
184 Closet jongkok porselin warna putih bh 212,500.00
185 Bak cuci stainless steel bh 195,000.00
186 Seal tape bh 3,400.00
187 Wastafel bh 350,000.00
188 Kran air bh 35,000.00
189 Urinoir bh -
190 Floor drain bh 45,000.00
191 Roof Drain bh -
192 Bak fibreglass bh 262,500.00
193 Air ltr -
194 BAHAN JENIS KACA -
195 Kaca polos tb. 3 mm m2 30,000.00
196 Kaca polos tb. 5 mm m2 45,000.00
197 Kaca rayban tb 5 mm m2 50,000.00
198 Sealant bh 35,000.00
199 Kaca buram m2 -
200 kaca cermin 5 mm m2 85,000.00
201 Kaca Tempered 12 mm (tanpa frame) m2 -
202 BAHAN BETON CETAKAN -
203 Buis beton diameter 15 cm bh -
204 Buis beton diameter 20 cm bh -
205 Buis beton diameter 30 cm bh -
206 Buis beton diameter 40 cm bh -
207 Buis beton diameter 50 cm bh -
208 Buis beton U 15 cm bh 32,000.00
209 Buis beton U 20 cm bh 36,000.00
210 Buis beton U 30 cm bh 41,000.00
NO URAIAN SAT. HARGA KETERANGAN

211 Buis beton U 40 cm bh 47,000.00


212 Buis beton U 50 cm bh 50,000.00
213 Curbig beton type A pj. 60 cm bh -
214 Curbig beton type B pj. 50 cm bh -
215 Beton K225 m3 -
216 U Gutter bh 583,000.00
217 Box Culvert bh 725,000.00
218 BAHAN PLASTIK PIPA PVC -
219 Keni PVC 1/2" bh 1,750.00
220 Keni PVC 3/4" bh 2,200.00
221 Keni PVC 2" bh 4,000.00
NO URAIAN SAT. HARGA KETERANGAN

222 Keni PVC 3" bh 7,900.00


223 Keni PVC 4" bh 13,800.00
224 Keni PVC 5" bh 25,000.00
225 Keni PVC 1/2" TS bh 2,000.00
226 Keni PVC 3/4" TS bh 2,500.00
227 Keni PVC 2" TS bh 9,250.00
228 Keni PVC 3" TS bh 24,000.00
229 Keni PVC 4" TS bh 47,500.00
230 Keni PVC 5" TS bh 125,000.00
231 Klem PVC bh 5,000.00
232 Pipa paralon 5/8" panjang 4.00 mt (Maspion) ljr 8,000.00
233 Pipa PVC 1/2" panjang 4.00 mt (Maspion) ljr 28,500.00
234 Pipa PVC 2" panjang 4.00 mt (Maspion) ljr 46,000.00
235 Pipa PVC 3" panjang 4.00 mt (Maspion) ljr 67,000.00
236 Pipa PVC 3/4" panjang 4.00 mt (Maspion) ljr -
237 Pipa PVC 4" panjang 4.00 mt (Maspion) ljr 91,500.00
238 Pipa PVC 5" panjang 4.00 mt (Maspion) ljr 261,500.00
239 Pipa PVC 3/4" tipe AW panjang 4.00 mt ljr 31,100.00
240 Pipa PVC 1/2" tipe AW panjang 4.00 mt ljr 25,600.00
241 Pipa PVC 1" tipe AW panjang 4.00 mt ljr 40,000.00
242 Pipa PVC 1 1/2" tipe AW panjang 4.00 mt ljr 67,950.00
243 Pipa PVC 2" tipe AW panjang 4.00 mt ljr 100,000.00
244 Pipa PVC 2 1/2" tipe AW panjang 4.00 mt ljr 130,500.00
245 Pipa PVC 3" tipe AW panjang 4.00 mt ljr 176,875.00
246 Pipa PVC 4" tipe AW panjang 4.00 mt ljr 257,625.00
247 Pipa PVC 5" tipe AW panjang 4.00 mt ljr 360,000.00
248 Pipa PVC 3/4" tipe AW panjang 6.00 mt ljr 40,500.00
249 Pipa PVC 1/2" tipe AW panjang 6.00 mt ljr 34,000.00
250 Pipa PVC 1" tipe AW panjang 6.00 mt ljr 51,250.00
251 Pipa PVC 1 1/2" tipe AW panjang 6.00 mt ljr 118,500.00
252 Pipa PVC 2" tipe AW panjang 6.00 mt ljr 176,000.00
253 Pipa PVC 2 1/2" tipe AW panjang 6.00 mt ljr 226,000.00
254 Pipa PVC 3" tipe AW panjang 6.00 mt ljr 322,500.00
255 Pipa PVC 4" tipe AW panjang 6.00 mt ljr 470,000.00
256 Pipa PVC 5" tipe AW panjang 6.00 mt ljr 741,000.00
257 BAHAN JENIS PAKU -
258 Paku asbes kg 51,500.00
259 Paku reng kg 15,400.00
260 Paku triplek kg 18,000.00
261 Paku usuk kg 15,400.00
262 Paku pancing bj 1,250.00
263 Paku sekrup 3,5" bj 500.00
264 Paku sekrup 2" bj 250.00
265 Dinaboult BJ 1,750.00
266 BAHAN PERALATAN LISTRIK -
267 Stop kontak (Broco) bh 13,500.00
268 Skakelar tunggal (Broco) bh 13,000.00
269 Skakelar / hendel (switch) bh 35,000.00
270 Zekering lengkap bh -
NO URAIAN SAT. HARGA KETERANGAN

271 Zekering SPA 60 Amp. bh -


272 Panel box bh -
273 Lampu pijar 25, 40, 75 / 220 V bh -
274 Lampu TL 20 W / 220 V komplit balas, kaca (Philips) bh 90,000.00
275 Lampu TL 40 W / 220 V komplit balas, kaca (Philips) bh 100,000.00
276 Lampu LED 15 Watt bh 57,500.00
277 Lampu LED 10 Watt bh 41,000.00
278 BAHAN BETON PRECAST -
279 Paving stone abu-abu persegi t=6cm k.300 m2 55,000.00
280 Topi uskup t=6 cm, k.300 bj 3,500.00
281 Kanstin 10.20.40, bj 14,400.00
NO URAIAN SAT. HARGA KETERANGAN

282 U-DITCH Gandar 5 T


283 U 30.30.120 bh 300,000.00
284 U 30.40.120 bh 355,000.00
285 U 30.50.120 bh 413,000.00
286 U 40.40.120 bh 456,000.00
287 U 40.40.120 bh -
288 U 40.50.120 bh 521,000.00
289 U 40.60.120 bh 586,000.00
290 U 50.50.120 bh 553,000.00
291 U 50.60.120 bh 619,000.00
292 U 50.70.120 bh 682,000.00
293 U 60.60.120 bh 808,000.00
294 U 60.70.120 bh 882,000.00
295 U 60.80.120 bh 955,000.00
296 U 60.100.120 bh 1,101,000.00
297 U 80.80.120. bh 1,243,000.00
298 U 80.90.120. bh 1,335,000.00
299 U 80.100.120 bh 1,426,000.00
300 U 80.120.120 bh 1,610,000.00
301 U 100.100.120 bh 1,518,000.00
302 U 100.120.120 bh 2,268,000.00
303 U 100.150.120 bh 2,385,000.00
304 U 120.100.120 bh 2,161,000.00
305 U 120.120.120 bh 2,987,000.00
306 U 120.150.120 bh 3,363,000.00
307 U 150.150.120 bh 3,492,000.00
308 U 150.170.120 bh 3,769,000.00
309 U-DITCH Gandar 10 T
310 U 30.30.120 bh 340,000.00
311 U 30.40.120 bh 402,000.00
312 U 30.50.120 bh 464,000.00
313 U 40.40.120 bh 516,000.00
314 U 40.50.120 bh 587,000.00
315 U 40.60.120 bh 660,000.00
316 U 50.50.120 bh -
317 U 50.50,120 bh 624,000.00
318 U 50.60.120 bh 697,000.00
319 U 50.70.120 bh 771,000.00
320 U 60.60.120 bh 911,000.00
321 U 60.70.120 bh 993,000.00
322 U 60.80.120 bh 1,077,000.00
323 U 60.100.120 bh 1,243,000.00
324 U 80.80.120 bh 1,401,000.00
325 U 80.90.120 bh 1,505,000.00
326 U 80.100.120 bh 1,608,000.00
327 U 80.120.120 bh 1,815,000.00
328 U 100.100.120 bh 1,711,000.00
329 U 100.120.120 bh 1,920,000.00
330 U 120.100.120 bh 3,042,000.00
NO URAIAN SAT. HARGA KETERANGAN

331 U 120.120.120 bh 3,370,000.00


332 U 120.150.120 bh 3,795,000.00
333 U 150.150.120 bh 3,941,000.00
334 U 150.170.120 bh 4,251,000.00
335 Cover U-DITCH Gandar 5 T
336 cover 30.6.120 bh 150,000.00
337 cover 40.8.120 bh 192,000.00
338 cover 50.8.120 bh 321,000.00
339 cover 60.10.120 bh 380,000.00
340 cover 80.10.120 bh 600,000.00
341 cover 100.12.120 bh 720,000.00
NO URAIAN SAT. HARGA KETERANGAN

342 cover 120.12.120 bh 883,000.00


343 cover 150.15.120 bh 1,348,000.00
344 Cover 42.120.8 bh -
345 Cover 52.120.10 bh -
346 Cover 60.120.10 bh -
347 Cover 52.120.10 bh -
348 Cover 52.120.10 bh -
349 Cover 62.120.10 bh -
350 Cover 62.120.10 bh -
351 Cover 62.120.10 bh -
352 Cover 72.120.10 bh -
353 Cover 76.120.10 bh -
354 Cover 100.120.12 bh -
355 Cover 100.120.12 bh -
356 Cover 124.120.12 bh -
357 Cover 124.120.12 bh -
358 Cover 146.120.14 bh -
359 Cover 146.120.14 bh -
360 Cover 174.120.14 bh -
361 Cover U-DITCH Gandar 10 T
362 cover 30.6.120 bh 228,000.00
363 cover 40.8.120 bh 323,000.00
364 cover 50.8.120 bh 347,000.00
365 cover 60.10.120 bh 493,000.00
366 cover 80.10.120 bh 648,000.00
367 cover 100.12.120 bh 970,000.00
368 cover 120.12.120 bh 1,229,000.00
369 cover 150.15.120 bh 1,938,000.00
370 Sewa Crane jam 599,629.55
371 Plat Bordes 2,4m x 1,2m x 3mm lbr 1,005,000.70
372 Waterproofing kg 45,750.00
373 Serat fiber m2 8,500.00
374 Besi Profil (Baja Konstruksi) kg 22,200.00
375 Besi profil WF kg 21,000.00
376 Kanal C + pabrikasi kg 23,500.00
377 Pipa Bulat Stainless Steel ∅ 2" Tebal 0.8mm m1 60,833.33
378 Besi Hollow 40x40x2mm m2 29,833.33
379 Roda Bubut Pagar bh 70,000.00
380 Pengunci Pagar bh 50,000.00
381 Granit Lokal 60 x 60 cm m2 313,500.00
382 Font Akrilik Mirror Cutting Laser (Warna Gold) Size 12 cm bh 67,000.00
383 Font Akrilik Mirror Cutting Laser (Warna Gold) Size 20 cm bh 80,000.00
384 Font Akrilik Mirror Cutting Laser (Warna Gold) Size 8 cm bh 50,000.00
385 Logo Sidoarjo Bahan Akrilik bh 500,000.00
386 Logo UPT Puskesmas Bahan Akrilik bh 500,000.00
387 Batu Alam Andesit Finishing Countting 20x40cm m2 185,250.00
388 Lampu Sorot LED 30 Watt bh 250,000.00
388 Plat Besi Baja Hitam Tebal 1.4 mm m2 113,218.75
NO URAIAN SAT. HARGA KETERANGAN
RENCANA ANGGARAN BIAYA
ENGINEER ESTIMATE

Nama Program : Program Upaya Kesehatan Masyarakat di Puskesmas


Nama Kegiatan : Penyediaan Biaya Operasional dan Pemeliharaan Puskesmas Trosobo
Nama Pekerjaan : Renovasi Gapura Puskesmas
Lokasi Kegiatan : Puskesmas Trosobo Kec. Taman Kab. Sidoarjo
Tahun Anggaran : 2018

NO URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN (Rp) JUMLAH HARGA (Rp.)

1 2 3 4 5 6
PEMBANGUNAN GAPURA BARU PUSKESMAS TROSOBO
I PEKERJAAN PERSIAPAN
1. Pembersihan Lokasi Awal & Akhir Kegiatan 1.00 Ls. 1,500,000.00 1,500,000.00
2. Pembongkaran Gapura Existing 1.00 Ls. 3,500,000.00 3,500,000.00
Jumlah I 5,000,000.00
II PEKERJAAN TANAH
1. Penggalian Tanah Biasa Untuk Pondasi 1.94 m3 105,813.18 205,700.82
2. Urugan Tanah Kembali 0.49 m3 76,335.16 37,098.89
3. Urugan Pasir 5cm 0.08 m3 161,125.27 13,051.15
Jumlah II 255,850.86
III PEKERJAAN PONDASI
1. Pekerjaan Pengeboran Pondasi Strous Ø(30x30)cm 4.00 m1 215,252.29 861,009.18
2. Pekerjaan Beton Pondasi Strous Ø(30x30)cm 1.88 m3 264,232,665.95 497,814,342.65
3. Plat Sepatu 100x100x20cm 0.40 m3 4,036,829.16 1,614,731.66
4. Beton rabat 1Pc : 3Ps : 6Kr Tebal. 10cm 0.24 m3 901,284.98 218,110.97
Jumlah III 500,508,194.46
IV PEKERJAAN STRUKTUR UTAMA
1. Kolom Beton 60/40 1.03 m3 264,232,665.95 272,688,111.26
2. Kolom Beton 100/40 1.04 m3 264,232,665.95 274,537,739.92
3. Penebalan Plesteran Beton 1Pc : 4Ps 28.76 m2 7,932,612.78 228,141,943.69
4. Finishing Granit Lokal 60 x 60 cm 8.60 m2 547,725.54 4,710,439.61
5. Plat Beton 12cm (Untuk Penutup Saluran) 0.38 m3 4,711,995.29 1,809,406.19
Jumlah IV 781,887,640.67
V PEKERJAAN FINISHING
1. Font Akrilik Mirror Cutting Laser (Warna Gold) Size 12 cm 41.00 buah 67,000.00 2,747,000.00
2. Font Akrilik Mirror Cutting Laser (Warna Gold) Size 20 cm 20.00 buah 80,000.00 1,600,000.00
3. Font Akrilik Mirror Cutting Laser (Warna Gold) Size 8 cm 38.00 buah 50,000.00 1,900,000.00
4. Logo Sidoarjo Bahan Akrilik Sticker 1.00 buah 500,000.00 500,000.00
5. Logo UPT Puskesmas Bahan Akrilik Sticker 1.00 buah 500,000.00 500,000.00
6. Pasangan Batu Alam Andesit Finishing Countting 7.56 m2 304,347.92 2,300,870.26
7. Lampu Sorot LED 30 Watt 2.00 buah 250,000.00 500,000.00
Jumlah V 10,047,870.26
VI PEKERJAAN BESI
1. Pipa Bulat Stainless Steel ∅ 2" Tebal 0.8mm 25.00 m1 100,445.54 2,511,138.51
2. Plat Besi Baja Hitam Tebal 1.4 mm (Untuk Papan Nama) 10.85 m2 212,482.43 2,305,434.39
3. Rangka Hollow 40x40x1.2 mm (Untuk Papan Nama) 38.85 m1 62,935.54 2,445,045.74
4. Finishing Cat Besi 10.85 m2 #VALUE! #VALUE!
Jumlah VI #VALUE!
TOTAL #VALUE!
PPn 10% #VALUE!
JUMLAH TOTAL #VALUE!
DIBULATKAN #VALUE!
ANALISA HARGA SATUAN PEKERJAAN TAHUN 2018

Jenis Pekerjaan : Penggalian 1 m3 tanah biasa sedalam 1 m


Satuan Pembayaran : 1 m3
Referensi : AHSP PU-CK 2013; A. 2.3.1.1 ; Hal: 377

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.75 122,992.00 92,244.00
Mandor L.04 OH 0.03 157,992.00 3,949.80
JUMLAH TENAGA KERJA 96,193.80
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 96,193.80


E Overhead & Profit (Contoh 15 %) 10% x D 9,619.38
F Harga Satuan Pekerjaan (D+E) 105,813.18

Jenis Pekerjaan : Pengurugan kembali 1 m3 galian tanah ( 1/3 kali koefisien pekerjaan galian)
Satuan Pembayaran : 1 m3
Referensi : AHSP PU-CK 2013; A. 2.3.1.9 ; Hal: 380

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.50 122,992.00 61,496.00
Mandor L.04 OH 0.05 157,992.00 7,899.60
JUMLAH TENAGA KERJA 69,395.60
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 69,395.60
E Overhead & Profit (Contoh 15 %) 10% x D 6,939.56
F Harga Satuan Pekerjaan (D+E) 76,335.16

Jenis Pekerjaan : Pengurugan 1 m3 dengan pasir urug


Satuan Pembayaran : 1 m3
Referensi : AHSP PU-CK 2013; A. 2.3.1.11 ; Hal: 381

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.30 122,992.00 36,897.60
Mandor L.04 OH 0.01 157,992.00 1,579.92
JUMLAH TENAGA KERJA 38,477.52
B BAHAN
Pasir urug 1.20 90,000.00 108,000.00
JUMLAH HARGA BAHAN 108,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 146,477.52
E Overhead & Profit (Contoh 15 %) 10% x D 14,647.75
F Harga Satuan Pekerjaan (D+E) 161,125.27
Jenis Pekerjaan : Pengurugan 1 m3 sirtu padat
Satuan Pembayaran : 1 m3
Referensi : AHSP PU-CK 2013; A. 2.3.1.14 ; Hal: 382

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.25 122,992.00 30,748.00
Mandor L.04 OH 0.03 157,992.00 3,949.80
JUMLAH TENAGA KERJA 34,697.80
B BAHAN
Sirtu m3 1.20 187,000.00 224,400.00
JUMLAH HARGA BAHAN 224,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 259,097.80


E Overhead & Profit (Contoh 15 %) 10% x D 25,909.78
F Harga Satuan Pekerjaan (D+E) 285,007.58

: Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),


Jenis Pekerjaan
slump (3-6) cm, w/c = 0,87
Satuan Pembayaran : 1 m3
Referensi : AHSP PU-CK A.4.1.1.4
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1.20 122,992.00 147,590.40
Tukang Batu L.02 OH 0.20 136,992.00 27,398.40
Kepala Tukang L.03 OH 0.02 147,992.00 2,959.84
Mandor L.04 OH 0.06 157,992.00 9,479.52
JUMLAH TENAGA KERJA 187,428.16
B BAHAN
Semen Portland kg 230.00 1,145.00 263,350.00
Pasir beton (BD Pasir = 1.400 Kg/m3) kg 893.00 154.76 138,202.38
Batu kerikil beton (BD Kerikil = 1.350 Kg/m3) kg 1027.00 219.44 225,369.44
Air (beton) Liter 200.00 25.00 5,000.00
JUMLAH HARGA BAHAN 631,921.83
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 819,349.99
E Overhead & Profit 10% x D 81,935.00
F Harga Satuan Pekerjaan (D+E) 901,284.98
Jenis Pekerjaan : Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Satuan Pembayaran : 1 m3
Referensi : AHSP PU-CK A.4.1.1.8
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1.65 122,992.00 202,936.80
Tukang Batu L.02 OH 0.28 136,992.00 37,672.80
Kepala Tukang L.03 OH 0.03 147,992.00 4,143.78
Mandor L.04 OH 0.08 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
Semen Portland kg 384.00 1,145.00 439,680.00
Pasir beton (BD Pasir = 1.400 Kg/m3) kg 692.00 154.76 107,095.24
Batu kerikil beton (BD Kerikil = 1.350 Kg/m3) kg 1039.00 219.44 228,002.78
Air (beton) Liter 215.00 25.00 5,375.00
JUMLAH HARGA BAHAN 780,153.02
C PERALATAN
- -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,038,019.73


E Overhead & Profit 10% x D 103,801.97
F Harga Satuan Pekerjaan (D+E) 1,141,821.70

Jenis Pekerjaan : Pembesian 10 kg dengan besi polos atau besi ulir


Satuan Pembayaran : 10 Kg
Referensi : AHSP PU-CK A.4.1.1.17
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.07 122,992.00 8,609.44
Tukang Besi L.02 OH 0.07 136,992.00 9,589.44
Kepala Tukang L.03 OH 0.01 147,992.00 1,035.94
Mandor L.04 OH 0.00 157,992.00 631.97
JUMLAH TENAGA KERJA 19,866.79
B BAHAN
Besi beton kg 10.50 9,000.00 94,500.00
Kawat beton kg 0.15 18,625.00 2,793.75
JUMLAH HARGA BAHAN 97,293.75
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 117,160.54


E Overhead & Profit 10% x D 11,716.05
F Harga Satuan Pekerjaan (D+E) 128,876.60
F Harga Satuan Pekerjaan (D+E) 140,592.65
Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk pondasi
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.1.1.20
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.52 122,992.00 63,955.84
Tukang Kayu L.02 OH 0.26 136,992.00 35,617.92
Kepala Tukang L.03 OH 0.03 147,992.00 3,847.79
Mandor L.04 OH 0.03 157,992.00 4,107.79
JUMLAH TENAGA KERJA 107,529.34
B BAHAN
Usuk Kayu kelas III m3 0.04 3,375,000.00 135,000.00
Paku biasa 2” – 5” kg 0.30 15,400.00 4,620.00
Minyak bekisting Liter 0.10 30,000.00 3,000.00
JUMLAH HARGA BAHAN 142,620.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 250,149.34


E Overhead & Profit 10% x D 25,014.93
F Harga Satuan Pekerjaan (D+E) 275,164.28
Begisting 3 x Pakai 91,721.43

Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk kolom


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.1.1.22
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.66 122,992.00 81,174.72
Tukang Kayu L.02 OH 0.33 136,992.00 45,207.36
Kepala Tukang L.03 OH 0.03 147,992.00 4,883.74
Mandor L.04 OH 0.03 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Usuk Kayu kelas III m3 0.04 3,625,000.00 145,000.00
Paku biasa 2” – 5” kg 0.40 15,400.00 6,160.00
Minyak bekisting Liter 0.20 30,000.00 6,000.00
Balok kayu kelas II m3 0.02 4,750,000.00 71,250.00
Plywood tebal 9 mm Lbr 0.35 75,000.00 26,250.00
Dolken kayu diameter 8-10/400 cm Batang 2,000 21,000.00 42,000,000.00
JUMLAH HARGA BAHAN 42,254,660.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,391,139.55


E Overhead & Profit 10% x D 4,239,113.96
F Harga Satuan Pekerjaan (D+E) 46,630,253.51
Begisting 3 x Pakai 15,543,417.84
Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk balok
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.1.1.23
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.66 122,992.00 81,174.72
Tukang Kayu L.02 OH 0.33 136,992.00 45,207.36
Kepala Tukang L.03 OH 0.03 147,992.00 4,883.74
Mandor L.04 OH 0.03 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Usuk Kayu kelas III m3 0.04 3,625,000.00 145,000.00
Paku biasa 2” – 5” kg 0.40 15,400.00 6,160.00
Minyak bekisting Liter 0.20 30,000.00 6,000.00
Balok kayu kelas II m3 0.02 4,750,000.00 85,500.00
Plywood tebal 9 mm Lbr 0.35 75,000.00 26,250.00

Dolken kayu diameter 8-10/400 cm Batang 2.00 21,000.00 42,000.00

JUMLAH HARGA BAHAN 310,910.00


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 447,389.55
E Overhead & Profit 10% x D 44,738.96
F Harga Satuan Pekerjaan (D+E) 492,128.51
Begisting 3 x Pakai 164,042.84

Jenis Pekerjaan : Pemasangan 1 m2 bekisting untuk lantai


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.1.1.24
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.66 122,992.00 81,174.72
Tukang Kayu L.02 OH 0.33 136,992.00 45,207.36
Kepala Tukang L.03 OH 0.03 147,992.00 4,883.74
Mandor L.04 OH 0.03 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Usuk Kayu kelas III m3 0.04 3,625,000.00 145,000.00
Paku biasa 2” – 5” kg 0.40 15,400.00 6,160.00
Minyak bekisting Liter 0.20 30,000.00 6,000.00
Balok kayu kelas II m3 0.02 4,750,000.00 71,250.00
Plywood tebal 9 mm Lbr 0.35 75,000.00 26,250.00

Dolken kayu diameter 8-10/400 cm Batang 6.00 21,000.00 126,000.00

JUMLAH HARGA BAHAN 380,660.00


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 517,139.55
E Overhead & Profit 10% x D 51,713.96
F Harga Satuan Pekerjaan (D+E) 568,853.51
Begisting 3 x Pakai 189,617.84
Jenis Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.1.3
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.30 122,992.00 36,897.60
Tukang Batu L.02 OH 0.10 136,992.00 13,699.20
Kepala Tukang L.03 OH 0.01 147,992.00 1,479.92
Mandor L.04 OH 0.02 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah bh 140.00 571.00 79,940.00
Semen Portland Kg 26.55 1,145.00 30,399.75
Pasir Pasang m3 0.09 192,917.00 17,941.28
JUMLAH HARGA BAHAN 128,281.03
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 182,727.63


E Overhead & Profit 10% x D 18,272.76
F Harga Satuan Pekerjaan (D+E) 201,000.39

Jenis Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 4Pasir Pasang tebal 15 mm


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.4
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.30 122,992.00 36,897.60
Tukang Batu L.03 OH 0.15 136,992.00 20,548.80
Kepala Tukang L.03 OH 0.02 147,992.00 2,219.88
Mandor L.04 OH 0.02 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen Portland Kg 6,240 1,145.00 7,144,800.00
Pasir pasang m3 0.02 192,917.00 4,630.01
JUMLAH HARGA BAHAN 7,149,430.01
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 7,211,466.17


E Overhead & Profit 10% x D 721,146.62
F Harga Satuan Pekerjaan (D+E) 7,932,612.78
Jenis Pekerjaan : Pemasangan 1 m2 finishing siar pasangan bata merah
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.24
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.15 122,992.00 18,448.80
Tukang Batu L.03 OH 0.08 136,992.00 10,274.40
Kepala Tukang L.03 OH 0.01 147,992.00 1,183.94
Mandor L.04 OH 0.01 157,992.00 1,263.94
JUMLAH TENAGA KERJA 31,171.07
B BAHAN
Semen Portland Kg 3,108 1,145.00 3,558,660.00
JUMLAH HARGA BAHAN 3,558,660.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,589,831.07


E Overhead & Profit 10% x D 358,983.11
F Harga Satuan Pekerjaan (D+E) 3,948,814.18

Jenis Pekerjaan : Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2Pasir Pasang.
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.26
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.30 122,992.00 36,897.60
Tukang Batu L.03 OH 0.15 136,992.00 20,548.80
Kepala Tukang L.03 OH 0.02 147,992.00 2,219.88
Mandor L.04 OH 0.02 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen Portland Kg 6.34 1,145.00 7,259.30
Pasir pasang m3 0.01 192,917.00 2,315.00
JUMLAH HARGA BAHAN 9,574.30
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 71,610.46


E Overhead & Profit 10% x D 7,161.05
F Harga Satuan Pekerjaan (D+E) 78,771.51

Jenis Pekerjaan : Pemasangan 1 m2 acian dinding.


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.27
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.20 122,992.00 24,598.40
Tukang Batu L.03 OH 0.10 136,992.00 13,699.20
Kepala Tukang L.03 OH 0.01 147,992.00 1,479.92
Mandor L.04 OH 0.01 157,992.00 1,579.92
JUMLAH TENAGA KERJA 41,357.44
B BAHAN
Semen Portland Kg 3.25 1,145.00 3,721.25
JUMLAH HARGA BAHAN 3,721.25
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 45,078.69


E Overhead & Profit 10% x D 4,507.87
F Harga Satuan Pekerjaan (D+E) 49,586.56
Jenis Pekerjaan : Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.2.1.4
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1,050 122,992.00 129,141,600.00
Tukang Las Biasa L.03 OH 1,050 136,992.00 143,841,600.00
Kepala tukang L.03 OH 0.11 147,992.00 15,539.16
Mandor L.04 OH 0.05 157,992.00 8,215.58
JUMLAH TENAGA KERJA 273,006,954.74
B BAHAN
lbr 1.00 1,005,000.70 1,005,000.70
Plat Bordes 2,4m x 1,2m x 3mm
JUMLAH HARGA BAHAN 1,005,000.70
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 274,011,955.44


E Overhead & Profit 10% x D 27,401,195.54
F Harga Satuan Pekerjaan (D+E) 301,413,150.99

Jenis Pekerjaan
: Pengecatan 1 m2 tembok baru EXTERIOR ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.7.1.10
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.02 122,992.00 2,459.84
Tukang cat L.02 OH 0.06 136,992.00 8,630.50
Kepala tukang L.03 OH 0.01 147,992.00 932.35
Mandor L.04 OH 0.00 157,992.00 473.98
JUMLAH TENAGA KERJA 12,496.66
B BAHAN
Plamur tembok Kg 0.10 16,500.00 1,650.00
Cat dasar Kg 0.10 23,500.00 2,350.00
Cat tembok Kg 0.26 23,500.00 6,110.00
JUMLAH HARGA BAHAN 10,110.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,606.66


E Overhead & Profit 10% x D 2,260.67
F Harga Satuan Pekerjaan (D+E) 24,867.33
Jenis Pekerjaan : Pengecatan 1 m2 permukaan baja dengan menie besi
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.7.1.16
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,02 122,992.00 #VALUE!
Tukang cat L.02 OH 0,2 136,992.00 #VALUE!
Kepala tukang L.03 OH 0,02 147,992.00 #VALUE!
Mandor L.04 OH 0,0025 157,992.00 #VALUE!
JUMLAH TENAGA KERJA #VALUE!
B BAHAN
Meni besi/kayu Kg 0,10 25,500.00 #VALUE!
Kuas Bh 0,01 23,100.00 #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #VALUE!


E Overhead & Profit 10% x D #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

Jenis Pekerjaan : Pemasangan Benangan 1 Pc : 2 Ps.


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.28
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.20 122,992.00 24,598.40
Tukang Batu L.03 OH 0.10 136,992.00 13,699.20
Kepala Tukang L.03 OH 0.01 147,992.00 1,479.92
Mandor L.04 OH 0.01 157,992.00 1,579.92
JUMLAH TENAGA KERJA 41,357.44
B BAHAN
Semen Portland Kg 0.50 1,145.00 572.50
Pasir Pasang m3 0.01 192,917.00 2,507.92
JUMLAH HARGA BAHAN 3,080.42
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 44,437.86


E Overhead & Profit 10% x D 4,443.79
F Harga Satuan Pekerjaan (D+E) 48,881.65
Jenis Pekerjaan : Pelapisan Waterproofing
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.7.1.16
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.05 122,992.00 6,149.60
Tukang cat L.02 OH 0.0750 136,992.00 10,274.40
Kepala tukang L.03 OH 0.01 147,992.00 1,183.94
Mandor L.04 OH 0.0 157,992.00 473.98
JUMLAH TENAGA KERJA 18,081.91
B BAHAN
Waterproofing Kg 0.35 45,750.00 16,012.50
Serat fiber m2 1.00 8,500.00 8,500.00
JUMLAH HARGA BAHAN 24,512.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,594.41


E Overhead & Profit 10% x D 4,259.44
F Harga Satuan Pekerjaan (D+E) 46,853.85

Jenis Pekerjaan : Pembongkaran Bekisting


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.7.1.19
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.053 122,992.00 6,518.58
Tukang kayu L.02 OH 0.0180 136,992.00 2,465.86
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 9,774.39
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 9,774.39


E Overhead & Profit 10% x D 977.44
F Harga Satuan Pekerjaan (D+E) 10,751.83

Jenis Pekerjaan : Pondasi Plat Sepatu 100x100x30 K-250


Satuan Pembayaran : 1 m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A Pekerjaan
Pekerjaan Bekisting Pondasi m2 5.52 91,721.43 506,651.69
Pekerjaan Pembesian kg 165.65 14,059.27 2,328,964.70
Pekerjaan Beton K-250 m3 1.00 1,141,821.70 1,141,821.70
Pembongkaran Begesting m2 5.52 10,751.83 59,391.07
JUMLAH 4,036,829.16

B Jumlah (A+B+C) 4,036,829.16


C Overhead & Profit 10% x D
D Harga Satuan Pekerjaan (B+C) 4,036,829.16
Jenis Pekerjaan : Pekerjaan Sloof Beton 15x20cm K-250
Satuan Pembayaran : 1 m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A Pekerjaan
Pekerjaan Bekisting Pondasi m2 8.00 91,721.43 733,771.41
Pekerjaan Pembesian kg 181.60 14,059.27 2,553,188.24
Pekerjaan Beton K-250 m3 1.00 1,141,821.70 1,141,821.70
Pembongkaran Begesting m2 8.00 10,751.83 86,014.65
JUMLAH 4,514,796.00

B Jumlah (A+B+C) 4,514,796.00


C Overhead & Profit 10% x D
D Harga Satuan Pekerjaan (B+C) 4,514,796.00

Jenis Pekerjaan : Pedestal 35x35x80 K-250


Satuan Pembayaran : 1 m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A Pekerjaan
Pekerjaan Bekisting Pondasi m2 8.00 91,721.43 733,771.41
Pekerjaan Pembesian kg 182.60 14,059.27 2,567,247.50
Pekerjaan Beton K-250 m3 1.00 1,141,821.70 1,141,821.70
Pembongkaran Begesting m2 8.00 10,751.83 86,014.65
JUMLAH 4,528,855.26

B Jumlah (A+B+C) 4,528,855.26


C Overhead & Profit 10% x D
D Harga Satuan Pekerjaan (B+C) 4,528,855.26

Jenis Pekerjaan : Ring Balok 15x20 K-250


Satuan Pembayaran : 1 m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A Pekerjaan
Pekerjaan Bekisting Balok m2 10.00 164,042.84 1,640,428.36
Pekerjaan Pembesian kg 189.00 14,059.27 2,657,201.09
Pekerjaan Beton K-250 m3 1.00 1,141,821.70 1,141,821.70
Pembongkaran Begesting m2 10.00 10,751.83 107,518.31
JUMLAH 5,546,969.46

B Jumlah (A+B+C) 5,546,969.46


C Overhead & Profit 10% x D
D Harga Satuan Pekerjaan (B+C) 5,546,969.46
Jenis Pekerjaan : Kolom Praktis 12/12 cm
Satuan Pembayaran : 1 m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A Pekerjaan
Pekerjaan Bekisting Kolom m2 16.67 15,543,417.84 259,056,963.93
Pekerjaan Pembesian kg 291.28 14,059.27 4,095,219.85
Pekerjaan Beton K-100 m3 1.00 901,284.98 901,284.98
Pembongkaran Begesting m2 16.67 10,751.83 179,197.19
JUMLAH 264,232,665.95

B Jumlah (A+B+C) 264,232,665.95


C Overhead & Profit 10% x D
D Harga Satuan Pekerjaan (B+C) 264,232,665.95

Jenis Pekerjaan : Plat Beton 12cm K-250


Satuan Pembayaran : 1 m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A Pekerjaan
Pekerjaan Bekisting Lantai m2 8.33 189,617.84 1,580,148.63
Pekerjaan Pembesian kg 135.17 14,059.27 1,900,426.37
Pekerjaan Beton K-250 m3 1.00 1,141,821.70 1,141,821.70
Pembongkaran Begesting m2 8.33 10,751.83 89,598.59
JUMLAH 4,711,995.29

B Jumlah (A+B+C) 4,711,995.29


C Overhead & Profit 10% x D
D Harga Satuan Pekerjaan (B+C) 4,711,995.29

Jenis Pekerjaan : Pekerjaan Fabrikasi dan Elektroda Baja


Satuan Pembayaran : 1 kg
Referensi : AHSP PU-CK A.4.2.1.1
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.06 122,992.00 7,379.52
Tukang Las Biasa L.03 OH 0.060 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 16,960.97
B BAHAN
Besi Profil (Baja Konstruksi) kg 1.15 22,200.00 25,530.00

JUMLAH HARGA BAHAN 25,530.00


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,490.97


E Overhead & Profit 10% x D 4,249.10
F Harga Satuan Pekerjaan (D+E) 46,740.06
Jenis Pekerjaan : Pekerjaan Kuda kuda WF
Satuan Pembayaran : 1 kg
Referensi : AHSP PU-CK A.4.2.1.5
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.04 122,992.00 4,919.68
Tukang Las Biasa L.03 OH 0.006 136,992.00 821.95
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 7,103.56
B BAHAN
Besi profil WF kg 1.10 21,000.00 23,100.00
Elektroda kg 0.04 46,740.06 1,869.60
JUMLAH HARGA BAHAN 24,969.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 32,073.16


E Overhead & Profit 10% x D 3,207.32
F Harga Satuan Pekerjaan (D+E) 35,280.48

Jenis Pekerjaan : Pekerjaan Gording Kanal C 100.50.20.2,3


Satuan Pembayaran : 1 kg
Referensi : AHSP PU-CK A.4.2.1.6
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.04 122,992.00 4,919.68
Tukang Las Biasa L.03 OH 0.006 136,992.00 821.95
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 7,103.56
B BAHAN
Kanal C + pabrikasi kg 1.15 23,500.00 27,025.00
Elektroda kg 0.04 46,740.06 1,869.60
JUMLAH HARGA BAHAN 28,894.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,998.16


E Overhead & Profit 10% x D 3,599.82
F Harga Satuan Pekerjaan (D+E) 39,597.98

Jenis Pekerjaan : Pembuatan Lubang Strous Pile diameter 30 cm kedalaman 2 m


Satuan Pembayaran : 1 m'
Referensi : AHSP PU-CK 2013; A. 2.3.1.4 ; Hal: 377

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1.44 122,992.00 177,108.48
Mandor L.04 OH 0.07 157,992.00 11,375.42
JUMLAH TENAGA KERJA 188,483.90
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Alat bantu Strouss Pile jam 1.20 6,000.00 7,200.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 195,683.90


E Overhead & Profit (Contoh 15 %) 10% x D 19,568.39
F Harga Satuan Pekerjaan (D+E) 215,252.29
Jenis Pekerjaan : Pemasangan 1m1 Pipa Bulat Stainless Steel ∅ 2" Tebal 0.8mm
Satuan Pembayaran : 1 m1
Referensi : AHSP PU-CK A.4.4.1.6
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.043 122,992.00 5,288.66
Tukang Batu L.02 OH 0.043 136,992.00 5,890.66
Kepala Tukang L.03 OH 0.004 147,992.00 636.37
Mandor L.04 OH 0.002 157,992.00 331.78
JUMLAH TENAGA KERJA 12,147.46
B BAHAN
Pipa Bulat Stainless Steel ∅ 2" Tebal 0.8mm m1 1.10 60,833.33 66,916.67
Perlengkapan set 0.35 35,000.00 12,250.00
JUMLAH HARGA BAHAN 79,166.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 91,314.13


E Overhead & Profit 10% x D 9,131.41
F Harga Satuan Pekerjaan (D+E) 100,445.54

Jenis Pekerjaan : Pemasangan 1m1 Besi Hollow 40x40x2mm


Satuan Pembayaran : 1 m1
Referensi : AHSP PU-CK A.4.4.1.6
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.043 122,992.00 5,288.66
Tukang Batu L.02 OH 0.043 136,992.00 5,890.66
Kepala Tukang L.03 OH 0.004 147,992.00 636.37
Mandor L.04 OH 0.002 157,992.00 331.78
JUMLAH TENAGA KERJA 12,147.46
B BAHAN
Besi Hollow 40x40x2mm m1 1.10 29,833.33 32,816.67
Perlengkapan set 0.35 35,000.00 12,250.00
JUMLAH HARGA BAHAN 45,066.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 57,214.13


E Overhead & Profit 10% x D 5,721.41
F Harga Satuan Pekerjaan (D+E) 62,935.54

Jenis Pekerjaan
: Pemasangan 1m2 lantai granit ukuran lokal 60 cm x 60 cm

Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.7.1.35
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.70 122,992.00 86,094.40
Tukang batu L.02 OH 0.35 136,992.00 47,947.20
Kepala tukang L.03 OH 0.04 147,992.00 5,179.72
Mandor L.04 OH 0.04 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
Granit Lokal 60 x 60 cm Doos 1.05 313,500.00 329,175.00
Semen portland (kg) Kg 10.00 1,145.00 11,450.00
Pasir pasang M3 0.05 192,917.00 8,681.27
Semen warna Kg 0.50 7,750.00 3,875.00
JUMLAH HARGA BAHAN 353,181.27
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 497,932.31


E Overhead & Profit 10% x D 49,793.23
F Harga Satuan Pekerjaan (D+E) 547,725.54
Jenis Pekerjaan : Pemasangan 1 m2 Pasangan Batu Alam Finishing Countting
Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.46
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.30 122,992.00 36,897.60
Tukang Batu L.03 OH 0.15 136,992.00 20,548.80
Kepala Tukang L.03 OH 0.02 147,992.00 2,219.88
Mandor L.04 OH 0.02 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Batu Alam Andesit Finishing Countting 20x40cm m2 1.05 185,250.00 194,512.50
Semen Portland Kg 10.00 1,145.00 11,450.00
Pasir pasang M3 0.05 192,917.00 8,681.27
JUMLAH HARGA BAHAN 214,643.77
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 276,679.93


E Overhead & Profit 10% x D 27,667.99
F Harga Satuan Pekerjaan (D+E) 304,347.92

Jenis Pekerjaan : Pemasangan 1 m2 Plat Besi Baja Hitam Tebal 1.4 mm


Satuan Pembayaran : 1 m2
Referensi : AHSP PU-CK A.4.4.2.46
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.30 122,992.00 36,897.60
Tukang Batu L.03 OH 0.15 136,992.00 20,548.80
Kepala Tukang L.03 OH 0.02 147,992.00 2,219.88
Mandor L.04 OH 0.02 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Plat Besi Baja Hitam Tebal 1.4 mm m2 1.05 113,218.75 118,879.69
Perlengkapan set 0.35 35,000.00 12,250.00
JUMLAH HARGA BAHAN 131,129.69
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 193,165.85


E Overhead & Profit 10% x D 19,316.58
F Harga Satuan Pekerjaan (D+E) 212,482.43
A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Upah % 75 199,980.00 149,985.00
JUMLAH TENAGA KERJA 149,985.00
B BAHAN
Pipa Paralon 5/8" btg 2.000 11,500.00 23,000.00
Kabel NYA 500 Volt 2 x 2,5 mm2 m 16.000 9,000.00 144,000.00
T Doos Pvc buah 2.000 3,450.00 6,900.00
L Bow buah 4.000 1,000.00 4,000.00
Klem buah 16.000 130.00 2,080.00
Fitting Plafon ex Broco buah 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 199,980.00
C PERALATAN

JUMLAH
D Jumlah (A+B+C) HARGA 349,965.00
ALAT
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 34,996.50
F Harga Satuan Pekerjaan (D+E) 384,961.50

A.8.4.6.1 (K3) Pemasangan 1 buah MCB


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Upah % 75 228,070.00 171,052.50
JUMLAH TENAGA KERJA 171,052.50
B BAHAN
Pipa Paralon 5/8" btg 3.000 11,500.00 34,500.00
Kabel NYA 500 Volt 2 x 2,5 mm2 m 15.000 9,000.00 135,000.00
T Doos Pvc buah 1.000 3,450.00 3,450.00
L Bow buah 2.000 1,000.00 2,000.00
Klem buah 24.000 130.00 3,120.00
MCB buah 1.000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 228,070.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 399,122.50
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 39,912.25
F Harga Satuan Pekerjaan (D+E) 439,034.75

A.8.4.6.1 (K3) Pemasangan 1 buah titik stopkontak


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Upah % 75 130,490.00 97,867.50
JUMLAH TENAGA KERJA 97,867.50
B BAHAN
Pipa Paralon 5/8" btg 1.000 11,500.00 11,500.00
Kabel NYA 500 Volt 2 x 2,5 mm2 m 10.000 9,000.00 90,000.00
T Doos Pvc buah 1.000 3,450.00 3,450.00
Klem buah 8.000 130.00 1,040.00
Stop Kontak ex Broco buah 1.000 24,500.00 24,500.00
JUMLAH HARGA BAHAN 130,490.00
C PERALATAN

JUMLAH
D Jumlah (A+B+C) HARGA 228,357.50
ALAT
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 22,835.75
F Harga Satuan Pekerjaan (D+E) 251,193.25
Pasang Usuk reng galvalume jarak 60cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang besi L.02 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.002 157,992.00 315.98
JUMLAH TENAGA KERJA 59,982.26
B BAHAN
Maintruss C 70.30.0,75 m' 2.300 13,500.00 31,050.00
Reng UK 3.2.0,45 m' 4.770 5,500.00 26,235.00
Screw 12 - 14 x 20 bh 8.000 300.00 2,400.00
Screw 12 - 14 x 16 bh 16.000 300.00 4,800.00
JUMLAH HARGA BAHAN 64,485.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 124,467.26
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 12,446.73
F Harga Satuan Pekerjaan (D+E) 136,913.99

A.4.1.1.17 Pembesian 10 kg dengan besi Ulir


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 122,992.00 8,609.44
Tukang besi L.02 OH 0.070 136,992.00 9,589.44
Kepala tukang L.03 OH 0.007 147,992.00 1,035.94
Mandor L.04 OH 0.004 157,992.00 631.97
JUMLAH TENAGA KERJA 19,866.79
B BAHAN
Besi Beton Ulir kg 10.500 11,650.00 122,325.00
Kawat beton kg 0.150 21,200.00 3,180.00
JUMLAH HARGA BAHAN 125,505.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 145,371.79


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 14,537.18
F Harga Satuan Pekerjaan (D+E) 159,908.97
Harga Per Kg 15,990.90

Pemasangan 1 kg besi profil Siku


Harga Jumlah
No Uraian Kode Satuan Koefisien
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.06 122,992.00 7,379.52
Tukang las konstruksi L.03 OH 0.06 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 16,960.97
B BAHAN
Besi profil siku Kg 1.150 13,000.00 14,950.00
JUMLAH HARGA BAHAN 14,950.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 31,910.97


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,191.10
F Harga Satuan Pekerjaan (D+E) 35,102.06
Pemasangan 1 kg besi plat baja
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.06 122,992.00 7,379.52
Tukang las konstruksi L.03 OH 0.06 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 16,960.97
B BAHAN
Besi plat Kg 1.150 13,500.00 15,525.00
JUMLAH HARGA BAHAN 15,525.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 32,485.97


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,248.60
F Harga Satuan Pekerjaan (D+E) 35,734.56

Pengelasan pagar hollow 1m2


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 122,992.00 98,393.60
Tukang las L.03 OH 0.500 136,992.00 68,496.00
Kepala tukang L.03 OH 0.050 147,992.00 7,399.60
Mandor L.04 OH 0.025 157,992.00 3,949.80
JUMLAH TENAGA KERJA 178,239.00
B BAHAN
Hollow Galvanis 3,5x3,5 t. 1 mm m1 3.250 30,500.00 99,125.00
Hollow Galvanis 1,5x3,5 t. 1 mm m1 11.600 8,566.67 99,373.33
Kawat las Kg 0.4 57,000.00 22,800.00
JUMLAH HARGA BAHAN 221,298.33
C PERALATAN
Sewa alat Las jam 0.170 50,000.00 8,500.00
JUMLAH HARGA ALAT 8,500.00

D Jumlah (A+B+C) 408,037.33


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 40,803.73
F Harga Satuan Pekerjaan (D+E) 448,841.07

Pengelasan pintu pagar hollow 1m2


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 122,992.00 98,393.60
Tukang las L.03 OH 0.500 136,992.00 68,496.00
Kepala tukang L.03 OH 0.050 147,992.00 7,399.60
Mandor L.04 OH 0.025 157,992.00 3,949.80
JUMLAH TENAGA KERJA 178,239.00
B BAHAN
hollow 5x5 galvanis m1 3.210 38,333.33 123,050.00
Hollow Galvanis 1,5x3,5 t. 1 mm m1 9.600 8,566.67 82,240.00
Kawat las Kg 0.400 57,000.00 22,800.00
Besi profil siku Kg 4.600 13,000.00 59,800.00
Besi beton polos Kg 0.616 10,650.00 6,562.53
Kayu kelas II M3 0.023 5,890,000.00 132,525.00
JUMLAH HARGA BAHAN 426,977.53
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 605,216.53


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 60,521.65
F Harga Satuan Pekerjaan (D+E) 665,738.18
A.4.6.1.21. Pemasangan 1 m’ lisplank Kalsiplang l=30cm t=9mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Tukang kayu L.03 OH 0.050 136,992.00 6,849.60
Kepala tukang L.03 OH 0.005 147,992.00 739.96
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 20,678.72
B BAHAN
Kalsiplang l=30cm t=9mm m1 1.100 21,800.00 23,980.00
Sekrup gypsumboard kg 0.050 45,000.00 2,250.00
Besi hollow 2x4 plafon m' 2.500 5,500.00 13,750.00
JUMLAH HARGA BAHAN 39,980.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 60,658.72


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 6,065.87
F Harga Satuan Pekerjaan (D+E) 66,724.59

A.4.4.3.1. Pemasangan 1 m2 Keramik lantai 30x30


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 122,992.00 86,094.40
Tukang batu L.02 OH 0.350 136,992.00 47,947.20
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.035 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
keramik (30x30) cm buah 1.050 55,000.00 57,750.00
Semen portland (kg) kg 8.190 1,150.00 9,418.50
Pasir pasang M3 0.045 271,600.00 12,222.00
Semen warna kg 0.500 7,750.00 3,875.00
JUMLAH HARGA BAHAN 83,265.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 228,016.54


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 22,801.65
F Harga Satuan Pekerjaan (D+E) 250,818.19

A.4.4.3.1. Pemasangan 1 m2 Keramik lantai 40x40 (rocktile)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 122,992.00 86,094.40
Tukang batu L.02 OH 0.350 136,992.00 47,947.20
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.035 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
keramik (40x40) cm (Rock Tile) buah 1.050 47,500.00 49,875.00
Semen portland (kg) kg 8.190 1,150.00 9,418.50
Pasir pasang M3 0.045 271,600.00 12,222.00
Semen warna kg 0.500 7,750.00 3,875.00
JUMLAH HARGA BAHAN 75,390.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 220,141.54


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 22,014.15
F Harga Satuan Pekerjaan (D+E) 242,155.69
A.4.2.1.13. Pemasangan 1 m jalusi holow aluminium 1" x 2" brown
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.045 122,992.00 5,534.64
Tukang alumunium L.03 OH 0.045 136,992.00 6,164.64
Kepala tukang L.03 OH 0.0045 147,992.00 665.96
Mandor L.04 OH 0.0045 157,992.00 710.96
JUMLAH TENAGA KERJA 13,076.21
B BAHAN
Holow aluminium 1" x 2" m 1.100 11,700.00 12,870.00
Paku Sekrup 1 cm-2,5 cm bh 2.000 900.00 1,800.00
JUMLAH HARGA BAHAN 14,670.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,746.21


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 2,774.62
F Harga Satuan Pekerjaan (D+E) 30,520.83

A.4.2.1.13. Pemasangan 1 m2 jendela kaca rangka alluminium casement 3 profil


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang alumunium L.03 OH 0.300 136,992.00 41,097.60
Kepala tukang L.03 OH 0.030 147,992.00 4,439.76
Mandor L.04 OH 0.030 157,992.00 4,739.76
JUMLAH TENAGA KERJA 87,174.72
B BAHAN

Jendela alluminium casement 3 profil m 4.400 46,000.00 202,400.00

Spigot m 0.800 8,100.00 6,480.00


Paku Sekrup 1 cm-2,5 cm bh 16.000 900.00 14,400.00
Karet m 4.400 1,800.00 7,920.00
Sealant Tube 0.270 36,000.00 9,720.00
JUMLAH HARGA BAHAN 240,920.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 328,094.72


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 32,809.47
F Harga Satuan Pekerjaan (D+E) 360,904.19
Pasang kuda kuda galvalume jarak 70cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.540 122,992.00 66,415.68
Tukang besi L.02 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.002 157,992.00 315.98
JUMLAH TENAGA KERJA 89,500.34
B BAHAN
Maintruss C 80.30.0,75 m' 9.570 15,833.33 151,525.00
Reng UK 3.2.0,45 m' 5.950 5,500.00 32,725.00
Screw 12 - 14 x 20 bh 14.000 300.00 4,200.00
Screw 12 - 14 x 16 bh 16.000 300.00 4,800.00
Dinabolt bh 1.000 2,300.00 2,300.00
JUMLAH HARGA BAHAN 195,550.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 285,050.34
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 28,505.03
F Harga Satuan Pekerjaan (D+E) 313,555.38
Pemasangan 1 m2 usuk reng genteng kodok, kayu kelas II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Tukang kayu L.03 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 28,268.28
B BAHAN
Kaso-kaso (5 × 7) cm kayu meranti m3 0.014 3,500,000.00 49,000.00
Reng 2/3 kayu meranti m3 0.004 3,500,000.00 12,600.00
Paku 5 cm - 10 cm kg 0.250 19,660.00 4,915.00
JUMLAH HARGA BAHAN 66,515.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 94,783.28


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 9,478.33
F Harga Satuan Pekerjaan (D+E) 104,261.61

Pemasangan 1 m2 reng genteng kodok, kayu kelas II


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 122,992.00 6,149.60
Tukang kayu L.03 OH 0.050 136,992.00 6,849.60
Kepala tukang L.03 OH 0.005 147,992.00 739.96
Mandor L.04 OH 0.003 157,992.00 394.98
JUMLAH TENAGA KERJA 14,134.14
B BAHAN
Kaso-kaso (5 × 7) cm kayu meranti m3 - 3,500,000.00 -
Reng 2/3 kayu meranti m3 0.004 3,500,000.00 12,600.00
Paku 5 cm - 10 cm kg 0.250 19,660.00 4,915.00
JUMLAH HARGA BAHAN 17,515.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 31,649.14


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,164.91
F Harga Satuan Pekerjaan (D+E) 34,814.05

Pemasangan 1 m2 atap genteng lama


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Tukang kayu L.03 OH 0.075 136,992.00 10,274.40
Kepala tukang L.11 OH 0.008 147,992.00 1,183.94
Mandor L.15 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 31,171.07
B BAHAN
Genteng karang pilang Kw 1 buah 22.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 31,171.07


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,117.11
F Harga Satuan Pekerjaan (D+E) 34,288.18

Pemasangan 1 m2 paving block natural tebal 6 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang batu L.03 OH 0.030 136,992.00 4,109.76
Kepala tukang L.11 OH 0.040 147,992.00 5,919.68
Mandor L.15 OH 0.030 157,992.00 4,739.76
JUMLAH TENAGA KERJA 39,367.60
B BAHAN
Paving block 6 cm buah 1.010 55,000.00 55,550.00
Pasir Urug m3 0.050 283,333.33 14,166.67
JUMLAH HARGA BAHAN 69,716.67
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 109,084.27


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 10,908.43
F Harga Satuan Pekerjaan (D+E) 119,992.69
1 m1 Pasangan Uskup/Stoper Uk. Tebal 6cm (HSPK 2009 Surabaya) 24.08.01.27
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang batu L.03 OH 0.100 136,992.00 13,699.20
Kepala tukang L.11 OH 0.010 147,992.00 1,479.92
Mandor L.15 OH 0.001 157,992.00 157.99
JUMLAH TENAGA KERJA 39,935.51
B BAHAN
Uskup paving stone buah 3.340 5,750.00 19,205.00
Pasir Urug m3 0.013 283,333.33 3,683.33
JUMLAH HARGA BAHAN 22,888.33
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 62,823.85


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 6,282.38
F Harga Satuan Pekerjaan (D+E) 69,106.23

Pemasangan 1 m3 dinding bata Expose kelas a (bata pres) 1Pc : 5 Ps


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 122,992.00 110,692.80
Tukang batu L.03 OH 0.300 136,992.00 41,097.60
Kepala tukang L.11 OH 0.030 147,992.00 4,439.76
Mandor L.15 OH 0.045 157,992.00 7,109.64
JUMLAH TENAGA KERJA 163,339.80
B BAHAN
Bata expose kelas A bh 770.000 1,100.00 847,000.00
Semen portland (kg) kg 168.000 1,150.00 193,200.00
Pasir Pasang m3 0.384 271,600.00 104,294.40
JUMLAH HARGA BAHAN 1,144,494.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,307,834.20


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 130,783.42
F Harga Satuan Pekerjaan (D+E) 1,438,617.62

Pemasangan 1 m3 dinding bata 1Pc : 5 Ps


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 122,992.00 110,692.80
Tukang batu L.03 OH 0.300 136,992.00 41,097.60
Kepala tukang L.11 OH 0.030 147,992.00 4,439.76
Mandor L.15 OH 0.045 157,992.00 7,109.64
JUMLAH TENAGA KERJA 163,339.80
B BAHAN
Bata merah bh 770.000 750.00 577,500.00
Semen portland (kg) kg 168.000 1,150.00 193,200.00
Pasir Pasang m3 0.384 271,600.00 104,294.40
JUMLAH HARGA BAHAN 874,994.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,038,334.20


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 103,833.42
F Harga Satuan Pekerjaan (D+E) 1,142,167.62
Pekerjaan 1 m2 pengecatan Dinding exterior coating (modif)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 122,992.00 2,459.84
Tukang batu L.03 OH 0.063 136,992.00 8,630.50
Kepala tukang L.11 OH 0.006 147,992.00 932.35
Mandor L.15 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 12,496.66
B BAHAN
coating kg 0.100 65,000.00 6,500.00
JUMLAH HARGA BAHAN 6,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 18,996.66


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 1,899.67
F Harga Satuan Pekerjaan (D+E) 20,896.33

1 m1 Pasang Kansteen
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Tukang batu L.03 OH 0.200 136,992.00 27,398.40
Kepala tukang L.11 OH 0.020 147,992.00 2,959.84
Mandor L.15 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 50,386.96
B BAHAN
Kanstin (DT 21) K 300 buah 1.660 17,250.00 28,635.00
Semen portland sak 0.120 46,000.00 5,520.00
Pasir Pasang m3 0.008 271,600.00 2,172.80
JUMLAH HARGA BAHAN 36,327.80
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 86,714.76


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 8,671.48
F Harga Satuan Pekerjaan (D+E) 95,386.24
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Tukang kayu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 28,268.28
B BAHAN
Kaso-kaso (5 × 7) cm kayu meranti m3 0.012 3,500,000.00 42,000.00
Paku 5 cm - 10 cm Kg 0.020 19,660.00 393.20
Kayu meranti (papan) m3 0.007 4,861,111.11 34,027.78
JUMLAH HARGA BAHAN 76,420.98
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 104,689.26


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 10,468.93
F Harga Satuan Pekerjaan (D+E) 115,158.18

A. 2.2.1.9. (K3) Pembersihan 1 m2 lapangan dan perataan


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Mandor L.04 OH 0.050 157,992.00 7,899.60
JUMLAH TENAGA KERJA 20,198.80
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,198.80


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 2,019.88
F Harga Satuan Pekerjaan (D+E) 22,218.68

A. 2.2.1.13. Pembongkaran 1 m3 beton bertulang


Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 13.334 122,992.00 1,639,975.33
Mandor L.04 OH 0.666 157,992.00 105,222.67
JUMLAH TENAGA KERJA 1,745,198.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,745,198.00
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 174,519.80
F Harga Satuan Pekerjaan (D+E) 1,919,717.80
A. 2.2.1.14. Pembongkaran 1 m3 dinding tembok bata
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.667 122,992.00 819,987.66
Mandor L.04 OH 0.333 157,992.00 52,611.34
JUMLAH TENAGA KERJA 872,599.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 872,599.00


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 87,259.90
F Harga Satuan Pekerjaan (D+E) 959,858.90

A. 2.2.1.14. Pembongkaran 1 m2 Pembongkaran atap + rangka


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Mandor L.04 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 19,712.74
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 19,712.74


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 1,971.27
F Harga Satuan Pekerjaan (D+E) 21,684.01

A. 2.2.1.15. Pembuatan dan Pemasangan 1 unit papan nama proyek


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 122,992.00 184,488.000
Tukang kayu L.02 OH 1.000 136,992.00 136,992.000
Kepala tukang L.03 OH 0.050 147,992.00 7,399.600
Mandor L.04 OH 0.050 157,992.00 7,899.600
JUMLAH TENAGA KERJA 336,779.200
B BAHAN
Triplek 12 mm M2 0.960 57,600.00 55,296.00
Print out lapis vinyl M2 0.960 20,000.00 19,200.00
Kaso-kaso (4 × 6) cm kayu M3 0.020 3,500,000.00 70,000.00
meranti
Lis siku aluminium 3 cm M 4.000 10,000.00 40,000.00
Cat tembok Kg 0.900 31,600.00 28,440.00
JUMLAH HARGA BAHAN 212,936.000
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 549,715.20


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 54,971.52
F Harga Satuan Pekerjaan (D+E) 604,686.72
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.75 122,992.00 92,244.00
Mandor L.04 OH 0.025 157,992.00 3,949.80
JUMLAH TENAGA KERJA 96,193.80
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 96,193.80


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 9,619.38
F Harga Satuan Pekerjaan (D+E) 105,813.18

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m


Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.900 122,992.00 110,692.80
Mandor L.04 OH 0.045 157,992.00 7,109.64
JUMLAH TENAGA KERJA 117,802.44
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 117,802.44
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 11,780.24
F Harga Satuan Pekerjaan (D+E) 129,582.68

A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.050 122,992.00 129,141.60
Mandor L.04 OH 0.067 157,992.00 10,585.46
JUMLAH TENAGA KERJA 139,727.06
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 139,727.06


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 13,972.71
F Harga Satuan Pekerjaan (D+E) 153,699.77

A.2.3.1.6. Menggali 1 m3 tanah lumpur sedalam 1 m

Harga Satuan (Rp) Jumlah Harga (Rp)


Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.200 122,992.00 147,590.40
Mandor L.04 OH 0.045 157,992.00 7,109.64
JUMLAH TENAGA KERJA 154,700.04
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 154,700.04


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 15,470.00
F Harga Satuan Pekerjaan (D+E) 170,170.04

A.2.3.1.8. (K3) Pembuangan 1 m3 tanah sejauh 30 meter


Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.330 122,992.00 40,587.36
Mandor L.04 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 42,167.28
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 42,167.28
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 4,216.73
F Harga Satuan Pekerjaan (D+E) 46,384.01

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 122,992.00 61,496.00
Mandor L.04 OH 0.050 157,992.00 7,899.60
JUMLAH TENAGA KERJA 69,395.60
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 69,395.60
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 6,939.56
F Harga Satuan Pekerjaan (D+E) 76,335.16

A.2.3.1.10. (K3) Pemadatan tanah 1 m3 tanah ( per 20 cm)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 122,992.00 61,496.00
Mandor L.04 OH 0.050 157,992.00 7,899.60
JUMLAH TENAGA KERJA 69,395.60
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 69,395.60
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 6,939.56
F Harga Satuan Pekerjaan (D+E) 76,335.16

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Mandor L.04 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 38,477.52
B BAHAN
Pasir Urug/sirtu 1.200 283,333.33 340,000.00
JUMLAH HARGA BAHAN 340,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 378,477.52
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 37,847.75
F Harga Satuan Pekerjaan (D+E) 416,325.27
A.2.3.1.14. Pengurugan 1 m3 sirtu padat
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 122,992.00 30,748.00
Mandor L.04 OH 0.025 157,992.00 3,949.80
JUMLAH TENAGA KERJA 34,697.80
B BAHAN
Pasir Urug/sirtu m3 1.200 283,333.33 340,000.00
JUMLAH HARGA BAHAN 340,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 374,697.80


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 37,469.78
F Harga Satuan Pekerjaan (D+E) 412,167.58
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 122,992.00 184,488.00
Tukang batu L.02 OH 0.750 136,992.00 102,744.00
Kepala tukang L.03 OH 0.075 147,992.00 11,099.40
Mandor L.04 OH 0.075 157,992.00 11,849.40
JUMLAH TENAGA KERJA 310,180.80
B BAHAN
Batu belah m3 1.200 283,333.00 339,999.60
Semen portland (kg) Kg 202.000 1,150.00 232,300.00
Pasir pasang m3 0.485 271,600.00 131,726.00
JUMLAH HARGA BAHAN 704,025.60
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,014,206.40
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 101,420.64
F Harga Satuan Pekerjaan (D+E) 1,115,627.04

A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 122,992.00 184,488.00
Tukang batu L.02 OH 0.750 136,992.00 102,744.00
Kepala tukang L.03 OH 0.075 147,992.00 11,099.40
Mandor L.04 OH 0.075 157,992.00 11,849.40
JUMLAH TENAGA KERJA 310,180.80
B BAHAN
Batu belah m3 1.200 283,333.00 339,999.60
Semen portland (kg) Kg 163.000 1,150.00 187,450.00
Pasir pasang m3 0.520 271,600.00 141,232.00
JUMLAH HARGA BAHAN 668,681.60
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 978,862.40
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 97,886.24
F Harga Satuan Pekerjaan (D+E) 1,076,748.64

A.3.2.1.3. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 122,992.00 184,488.00
Tukang batu L.02 OH 0.750 136,992.00 102,744.00
Kepala tukang L.03 OH 0.075 147,992.00 11,099.40
Mandor L.04 OH 0.075 157,992.00 11,849.40
JUMLAH TENAGA KERJA 310,180.80
B BAHAN
Batu belah m3 1.200 283,333.00 339,999.60
Semen portland (kg) Kg 136.000 1,150.00 156,400.00
Pasir pasang m3 0.544 271,600.00 147,750.40
JUMLAH HARGA BAHAN 644,150.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 954,330.80
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 95,433.08
F Harga Satuan Pekerjaan (D+E) 1,049,763.88
A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 122,992.00 184,488.00
Tukang batu L.02 OH 0.750 136,992.00 102,744.00
Kepala tukang L.03 OH 0.075 147,992.00 11,099.40
Mandor L.04 OH 0.075 157,992.00 11,849.40
JUMLAH TENAGA KERJA 310,180.80
B BAHAN
Batu belah m3 1.200 283,333.00 339,999.60
Semen portland (kg) Kg 117.000 1,150.00 134,550.00
Pasir pasang m3 0.561 271,600.00 152,367.60
JUMLAH HARGA BAHAN 626,917.20
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 937,098.00
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 93,709.80
F Harga Satuan Pekerjaan (D+E) 1,030,807.80

A.3.2.1.5. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8PP


Harga Satuan (Rp) Jumlah Harga
No Uraian Kode Satuan Koefisien (Rp)
A TENAGA
Pekerja L.01 OH 1.500 122,992.00 184,488.00
Tukang batu L.02 OH 0.750 136,992.00 102,744.00
Kepala tukang L.03 OH 0.075 147,992.00 11,099.40
Mandor L.04 OH 0.075 157,992.00 11,849.40
JUMLAH TENAGA KERJA 310,180.80
B BAHAN
Batu belah m3 1.200 283,333.00 339,999.60
Semen portland (kg) Kg 91.000 1,150.00 104,650.00
Pasir pasang m3 0.584 271,600.00 158,614.40
JUMLAH HARGA BAHAN 603,264.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 913,444.80


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 91,344.48
F Harga Satuan Pekerjaan (D+E) 1,004,789.28

A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)


Harga Satuan (Rp) Jumlah Harga
No Uraian Kode Satuan Koefisien (Rp)
A TENAGA
Pekerja L.01 OH 0.780 122,992.00 95,933.76
Tukang batu L.02 OH 0.390 136,992.00 53,426.88
Kepala tukang L.03 OH 0.039 147,992.00 5,771.69
Mandor L.04 OH 0.039 157,992.00 6,161.69
JUMLAH TENAGA KERJA 161,294.02
B BAHAN
Batu belah m3 1.200 283,333.00 339,999.60
Pasir urug/sirtu m3 0.432 283,333.33 122,400.00
JUMLAH HARGA BAHAN 462,399.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 623,693.62


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 62,369.36
F Harga Satuan Pekerjaan (D+E) 686,062.98
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 Mpa (K100)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 247 1,150.00 284,050.00
2 Pasir Beton (kg) kg 869 223.81 194,490.27
3 koral beton (kg) kg 999 207.41 207,200.00
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 707,240.27
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 965,106.98


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 96,510.70
F Harga Satuan Pekerjaan (D+E) 1,061,617.68

A.4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 Mpa (K125)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 276 1,150.00 317,400.00
2 Pasir Beton (kg) kg 828 223.81 185,314.09
3 koral beton (kg) kg 1012 207.41 209,896.30
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 734,110.38
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 991,977.10


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 99,197.71
F Harga Satuan Pekerjaan (D+E) 1,091,174.81
A.4.1.1.3 Membuat 1 m3 beton mutu f’c = 12,2 Mpa (K150)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 299 1,150.00 343,850.00
2 Pasir Beton (kg) kg 799 223.81 178,823.62
3 koral beton (kg) kg 1017 207.41 210,933.33
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 755,106.95
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,012,973.66


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 101,297.37
F Harga Satuan Pekerjaan (D+E) 1,114,271.03
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) (K100)
cm, w/c = 0,87
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.200 122,992.00 147,590.40
2 Tukang batu L.02 OH 0.200 136,992.00 27,398.40
3 Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
4 Mandor L.04 OH 0.060 157,992.00 9,479.52
JUMLAH TENAGA KERJA 187,428.16
B BAHAN
1 Semen portland (kg) kg 230 1,150.00 264,500.00
2 Pasir Beton (kg) kg 893 223.81 199,861.69
3 koral beton (kg) kg 1027 207.41 213,007.41
4 Air Liter 200 100.00 20,000.00
JUMLAH HARGA BAHAN 697,369.10
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 884,797.26
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 88,479.73
F Harga Satuan Pekerjaan (D+E) 973,276.99

A. A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, slump (120 ± 20) mm (K175)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 326 1,150.00 374,900.00
2 Pasir Beton (kg) kg 760 223.81 170,095.06
3 koral beton (kg) kg 1029 207.41 213,422.22
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 779,917.28
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,037,783.99


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 103,778.40
F Harga Satuan Pekerjaan (D+E) 1,141,562.39

A.4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 Mpa (K200)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 352 1,150.00 404,800.00
2 Pasir Beton (kg) kg 731 223.81 163,604.59
3 koral beton (kg) kg 1031 207.41 213,837.04
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 803,741.62
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,061,608.34


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 106,160.83
F Harga Satuan Pekerjaan (D+E) 1,167,769.17

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 Mpa (K225)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 371 1,150.00 426,650.00
2 Pasir Beton (kg) kg 698 223.81 156,218.88
3 koral beton (kg) kg 1047 207.41 217,155.56
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 821,524.44
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,079,391.15


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 107,939.11
F Harga Satuan Pekerjaan (D+E) 1,187,330.26

A.4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 Mpa (K250)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 384 1,150.00 441,600.00
2 Pasir Beton (kg) kg 692 223.81 154,876.03
3 koral beton (kg) kg 1039 207.41 215,496.30
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 833,472.32
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,091,339.03


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 109,133.90
F Harga Satuan Pekerjaan (D+E) 1,200,472.94

A.4.1.1.9. Membuat 1 m3 beton mutu f’c = 24,0 Mpa (K275)


Harga Jumlah
Uraian Kode Satuan Koefisien Satuan Harga
No (Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 406 1,150.00 466,900.00
2 Pasir Beton (kg) kg 684 223.81 153,085.55
3 koral beton (kg) kg 1026 207.41 212,800.00
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 854,285.55
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,112,152.26


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 111,215.23
F Harga Satuan Pekerjaan (D+E) 1,223,367.49

A.4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 Mpa (K300)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.650 122,992.00 202,936.80
2 Tukang batu L.02 OH 0.275 136,992.00 37,672.80
3 Kepala tukang L.03 OH 0.028 147,992.00 4,143.78
4 Mandor L.04 OH 0.083 157,992.00 13,113.34
JUMLAH TENAGA KERJA 257,866.71
B BAHAN
1 Semen portland (kg) kg 413 1,150.00 474,950.00
2 Pasir Beton (kg) kg 681 223.81 152,414.12
3 koral beton (kg) kg 1021 207.41 211,762.96
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 860,627.09
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,118,493.80


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 111,849.38
F Harga Satuan Pekerjaan (D+E) 1,230,343.18

A.4.1.1.11. Membuat 1 m3 beton mutu f’c = 28,8 Mpa (K325)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 2.100 122,992.00 258,283.20
2 Tukang batu L.02 OH 0.35 136,992.00 47,947.20
3 Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
4 Mandor L.04 OH 0.105 157,992.00 16,589.16
JUMLAH TENAGA KERJA 327,999.28
B BAHAN
1 Semen portland (kg) kg 439 1,150.00 504,850.00
2 Pasir Beton (kg) kg 670 223.81 149,952.22
3 koral beton (kg) kg 1006 207.41 208,651.85
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 884,954.07
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,212,953.35


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 121,295.34
F Harga Satuan Pekerjaan (D+E) 1,334,248.69

A.4.1.1.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa, slump (120 ± 20) mm (K350)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 2.100 122,992.00 258,283.20
2 Tukang batu L.02 OH 0.350 136,992.00 47,947.20
3 Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
4 Mandor L.04 OH 0.105 157,992.00 16,589.16
JUMLAH TENAGA KERJA 327,999.28
B BAHAN
1 Semen portland (kg) kg 448 1,150.00 515,200.00
2 Pasir Beton (kg) kg 667 223.81 149,280.79
3 koral beton (kg) kg 1000 207.41 207,407.41
4 Air Liter 215 100.00 21,500.00
JUMLAH HARGA BAHAN 893,388.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,221,387.48


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 122,138.75
F Harga Satuan Pekerjaan (D+E) 1,343,526.23

Untuk pekerjaan beton pracetak yang bisa diangkat 24 jam diperlukan


penambahan bahan tambahan sesuai Tabel berikut:

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 2.100 122,992.00 258,283.20
2 Tukang batu L.02 OH 0.350 136,992.00 47,947.20
3 Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
4 Mandor L.04 OH 0.105 157,992.00 16,589.16
JUMLAH TENAGA KERJA 327,999.28
B BAHAN
1 Semen portland (kg) kg 448 1,150.00 515,200.00
2 Pasir Beton (kg) kg 667 223.81 149,280.79
3 koral beton (kg) kg 1000 207.41 207,407.41
4 Bahan tambahan kimia Liter 4.5 60,000.00 270,000.00
5 Air Liter 200 100.00 20,000.00
JUMLAH HARGA BAHAN 1,161,888.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,489,887.48


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 148,988.75
F Harga Satuan Pekerjaan (D+E) 1,638,876.23
CATATAN: Bobot isi pasir = 1400 kg/m3, Bobot isi kerikil = 1350 kg/m3, Buckling factor pasir 20%

A.4.1.1.17 Pembesian 10 kg dengan besi polos


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 122,992.00 8,609.44
Tukang besi L.02 OH 0.070 136,992.00 9,589.44
Kepala tukang L.03 OH 0.007 147,992.00 1,035.94
Mandor L.04 OH 0.004 157,992.00 631.97
JUMLAH TENAGA KERJA 19,866.79
B BAHAN
Besi Beton Polos kg 10.500 10,650.00 111,825.00
Kawat beton kg 0.150 21,200.00 3,180.00
JUMLAH HARGA BAHAN 115,005.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 134,871.79


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 13,487.18
F Harga Satuan Pekerjaan (D+E) 148,358.97
Harga Per Kg 14,835.90
A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 122,992.00 63,955.84
Tukang kayu L.02 OH 0.260 136,992.00 35,617.92
Kepala tukang L.03 OH 0.026 147,992.00 3,847.79
Mandor L.04 OH 0.026 157,992.00 4,107.79
JUMLAH TENAGA KERJA 107,529.34
B BAHAN
Kayu kelas III m3 0.040 4,978,000.00 199,120.00
Paku 5 cm - 10 cm kg 0.300 19,660.00 5,898.00
Minyak bekisting Liter 0.100 25,000.00 2,500.00
JUMLAH HARGA BAHAN 207,518.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 315,047.34


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 31,504.73
F Harga Satuan Pekerjaan (D+E) 346,552.08

A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 122,992.00 63,955.84
Tukang kayu L.02 OH 0.260 136,992.00 35,617.92
Kepala tukang L.03 OH 0.026 147,992.00 3,847.79
Mandor L.04 OH 0.026 157,992.00 4,107.79
JUMLAH TENAGA KERJA 107,529.34
B BAHAN
Kayu kelas III m3 0.045 4,978,000.00 224,010.00
Paku 5 cm - 10 cm kg 0.300 19,660.00 5,898.00
Minyak bekisting Liter 0.100 25,000.00 2,500.00
JUMLAH HARGA BAHAN 232,408.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 339,937.34


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 33,993.73
F Harga Satuan Pekerjaan (D+E) 373,931.08
A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 122,992.00 81,174.72
Tukang kayu L.02 OH 0.33 136,992.00 45,207.36
Kepala tukang L.03 OH 0.033 147,992.00 4,883.74
Mandor L.04 OH 0.033 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Kayu kelas III m3 0.040 4,978,000.00 199,120.00
Paku 5 cm - 10 cm kg 0.400 19,660.00 7,864.00
Minyak bekisting Liter 0.200 25,000.00 5,000.00
Plywood tebal 9 mm Lbr 0.350 144,500.00 50,575.00
JUMLAH HARGA BAHAN 262,559.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 399,038.55


E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 39,903.86
F Harga Satuan Pekerjaan (D+E) 438,942.41

A.4.1.1.23 (K3) Pemasangan 1 m2 bekisting untuk balok


Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.660 122,992.00 81,174.72
Tukang kayu L.02 OH 0.330 136,992.00 45,207.36
Kepala tukang L.03 OH 0.033 147,992.00 4,883.74
Mandor L.04 OH 0.033 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Kayu kelas III m3 0.040 4,978,000.00 199,120.00
Paku 5 cm - 10 cm kg 0.400 19,660.00 7,864.00
Minyak bekisting Liter 0.200 25,000.00 5,000.00
Plywood tebal 9 mm Lbr 0.350 144,500.00 50,575.00
Dolken kayu f 8-10/400 cm Batang 2.000 21,000.00 42,000.00
JUMLAH HARGA BAHAN 304,559.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 441,038.55
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 44,103.86
F Harga Satuan Pekerjaan (D+E) 485,142.41

A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk lantai


Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.660 122,992.00 81,174.72
Tukang kayu L.02 OH 0.330 136,992.00 45,207.36
Kepala tukang L.03 OH 0.033 147,992.00 4,883.74
Mandor L.04 OH 0.033 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Kayu kelas III m3 0.040 4,978,000.00 199,120.00
Paku 5 cm - 10 cm kg 0.400 19,660.00 7,864.00
Minyak bekisting Liter 0.200 25,000.00 5,000.00
Plywood tebal 9 mm Lbr 0.350 144,500.00 50,575.00
Dolken kayu f 8-10/400 cm Batang 6.000 21,000.00 126,000.00
JUMLAH HARGA BAHAN 388,559.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 525,038.55
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 52,503.86
F Harga Satuan Pekerjaan (D+E) 577,542.41
A.4.1.1.26 (K3) Pemasangan 1 m2 bekisting untuk tangga
Harga Satuan (Rp) Jumlah Harga (Rp)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.660 122,992.00 81,174.72
Tukang kayu L.02 OH 0.330 136,992.00 45,207.36
Kepala tukang L.03 OH 0.033 147,992.00 4,883.74
Mandor L.04 OH 0.033 157,992.00 5,213.74
JUMLAH TENAGA KERJA 136,479.55
B BAHAN
Kayu kelas III m3 0.030 4,978,000.00 149,340.00
Paku 5 cm - 10 cm kg 0.400 19,660.00 7,864.00
Minyak bekisting Liter 0.150 25,000.00 3,750.00
Plywood tebal 9 mm Lbr 0.350 144,500.00 50,575.00
Dolken kayu f 8-10/400 cm Batang 2.000 21,000.00 42,000.00
JUMLAH HARGA BAHAN 253,529.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 390,008.55
E Overhead & Profit (Contoh 15 %) 10% x D (maksimum) 39,000.86
F Harga Satuan Pekerjaan (D+E) 429,009.41

Membuat 1m3 Beton Strous Diameter 25cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 93.112 14,835.90 1,381,400.00
JUMLAH 2,522,962.39

Membuat 1m3 Beton Pondasi 50x50

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 111.739 14,835.90 1,657,754.12
JUMLAH 2,799,316.51

Membuat 1m3 Beton Pondasi 70x70

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 114.503 14,835.90 1,698,753.58
JUMLAH 2,840,315.97

Membuat 1m3 Beton Pondasi 150x60x35

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 100.153 14,835.90 1,485,863.50
JUMLAH 2,627,425.89

Membuat 1m3 Beton Pondasi 60x60x35

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
Beton K-175 M3 1.000 1,141,562.39 1,141,562.39
Pekerjaan besi polos Kg 73.593 14,835.90 1,091,825.06
JUMLAH 2,233,387.46

Membuat 1m3 Beton sloof 12x15

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 204.336 14,835.90 3,031,502.08
Begesting sloof 2x pakai m2 5.556 373,931.08 2,077,394.88
JUMLAH 6,250,459.35
Membuat 1m3 Beton sloof 15x20

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 172.920 14,835.90 2,565,421.34
Begesting sloof 2x pakai m2 4.444 373,931.08 1,661,915.90
JUMLAH 5,368,899.63

Membuat 1m3 Beton sloof 15x25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 145.261 14,835.90 2,155,080.36
Begesting sloof 2x pakai m2 6.667 373,931.08 2,492,873.86
JUMLAH 5,789,516.61

Membuat 1m3 Beton sloof 20x30

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 129.431 14,835.90 1,920,231.86
Begesting sloof 2x pakai m2 5.000 373,931.08 1,869,655.39
JUMLAH 4,931,449.64

Membuat 1m3 Beton kolom 20x25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 149.885 14,835.90 2,223,685.16
Begesting kolom 2x pakai m2 9.000 438,942.41 3,950,481.66
JUMLAH 7,315,729.21

Membuat 1m3 Beton kolom 15x15

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 218.760 14,835.90 3,245,498.58
Begesting kolom 2x pakai m2 13.333 438,942.41 5,852,565.43
JUMLAH 10,239,626.40

Membuat 1m3 Beton kolom 12x12

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 319.673 14,835.90 4,742,628.50
Begesting kolom 2x pakai m2 8.333 438,942.41 3,657,853.39
JUMLAH 9,542,044.28

Membuat 1m3 Beton kolom 30x30

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 74.243 14,835.90 1,101,462.10
Begesting kolom 2x pakai m2 6.667 438,942.41 2,926,282.71
JUMLAH 5,169,307.21

Membuat 1m3 Beton kolom 20x20

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 60.543 14,835.90 898,210.31
Begesting kolom 2x pakai m2 6.667 438,942.41 2,926,282.71
JUMLAH 4,966,055.42
Membuat 1m3 Beton kolom 15x25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 192.608 14,835.90 2,857,518.55
Begesting kolom 2x pakai m2 10.667 438,942.41 4,682,052.34
JUMLAH 8,681,133.28

Membuat 1m3 Beton balok 15x15

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 204.336 14,835.90 3,031,502.08
Begesting balok 2x pakai m2 10.000 485,142.41 4,851,424.07
JUMLAH 9,024,488.54

Membuat 1m3 Beton balok 12x15

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 204.336 14,835.90 3,031,502.08
Begesting balok 2x pakai m2 5.556 485,142.41 2,695,235.60
JUMLAH 6,868,300.07

Membuat 1m3 Beton balok latei 12x15

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 204.336 14,835.90 3,031,502.08
Begesting balok 2x pakai m2 11.667 485,142.41 5,659,994.75
JUMLAH 9,833,059.22

Membuat 1m3 Beton balok 20x40

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 103.702 14,835.90 1,538,515.24
Begesting balok 1x pakai m2 12.500 485,142.41 6,064,280.09
JUMLAH 8,790,125.60

Membuat 1m3 Beton balok 20x25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 149.885 14,835.90 2,223,685.16
Begesting balok 1x pakai m2 9.200 485,142.41 4,463,310.15
JUMLAH 7,874,325.57

Membuat 1m3 Beton balok 15x20

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
Beton K-175 M3 1.000 1,141,562.39 1,141,562.39
Pekerjaan besi polos Kg 232.104 14,835.90 3,443,469.07
Begesting balok 2x pakai m2 9.167 485,142.41 4,447,138.73
JUMLAH 9,032,170.19

Membuat 1m3 Beton balok 30x60

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 25.788 14,835.90 382,594.67
Pekerjaan besi ulir Kg 116.793 15,990.90 1,867,616.85
Begesting balok 1x pakai m2 7.000 485,142.41 3,395,996.85
JUMLAH 6,833,538.63

Membuat 1m3 Beton balok 30x40

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 29.166 14,835.90 432,701.92
Pekerjaan besi ulir Kg 160.686 15,990.90 2,569,511.30
Begesting balok 1x pakai m2 7.167 485,142.41 3,476,853.92
JUMLAH 7,666,397.40

Membuat 1m3 Beton balok 20x30

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 40.655 14,835.90 603,160.26
Pekerjaan besi ulir Kg 172.175 15,990.90 2,753,240.11
Begesting balok 1x pakai m2 9.333 485,142.41 4,527,995.80
JUMLAH 9,071,726.43

Membuat 1m3 Beton balok 15x25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 50.567 14,835.90 750,203.98
Pekerjaan besi ulir Kg 217.268 15,990.90 3,474,316.79
Begesting balok 1x pakai m2 14.133 485,142.41 6,856,679.36
JUMLAH 12,268,530.39

Membuat 1m3 Beton plat lantai t=12cm k-225

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 124.170 14,835.90 1,842,171.15
Begesting plat 1x pakai m2 8.333 577,542.41 4,812,853.39
JUMLAH 7,842,354.81

Membuat 1m3 Beton plat tangga

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-225 M3 1.000 1,187,330.26 1,187,330.26


Pekerjaan besi polos Kg 113.025 14,835.90 1,676,827.27
Begesting tangga 1x pakai m2 8.333 577,542.41 4,812,853.39
JUMLAH 7,677,010.93

Membuat 1m3 Beton plat lantai t=12cm k-175

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

Beton K-175 M3 1.000 1,141,562.39 1,141,562.39


Pekerjaan besi polos Kg 124.170 14,835.90 1,842,171.15
Begesting plat 1x pakai m2 8.333 577,542.41 4,812,853.39
JUMLAH 7,796,586.93
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.1. Pemasangan 1 kg besi profil CNP


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.06 122,992.00 7,379.52
Tukang las konstruksi L.03 OH 0.06 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 16,960.97
B BAHAN
Besi CNP Kg 1.150 13,500.00 15,525.00
JUMLAH HARGA BAHAN 15,525.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 32,485.97


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,248.60
F Harga Satuan Pekerjaan (D+E) 35,734.56

A.4.2.1.2. Pemasangan 1 kg rangka kuda-kuda baja WF


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.06 122,992.00 7,379.52
Tukang las konstruksi L.03 OH 0.06 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 16,960.97
B BAHAN
Besi baja WF Kg 1.150 13,000.00 14,950.00
JUMLAH HARGA BAHAN 14,950.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 31,910.97


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,191.10
F Harga Satuan Pekerjaan (D+E) 35,102.06

A.4.2.1.3. Pengerjaan 100 kg pekerjaan perakitan


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1 122,992.00 12,299.20
Tukang besi L.03 OH 0.1 136,992.00 13,699.20
Kepala tukang L.03 OH 0.001 147,992.00 147.99
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 26,936.35
B BAHAN
Solar Liter 1.000 10,000.00 10,000.00
Minyak pelumas Liter 0.100 30,000.00 3,000.00
JUMLAH HARGA BAHAN 13,000.00
C PERALATAN
Sewa alat las Jam 0.800 50,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

D Jumlah (A+B+C) 79,936.35


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,993.64
F Harga Satuan Pekerjaan (D+E) 87,929.99
Pekerjaan perakitan /kg 879.30
A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.040 122,992.00 4,919.68
Tukang las konstruksi L.03 OH 0.020 136,992.00 2,739.84
Kepala tukang L.03 OH 0.002 147,992.00 295.98
Mandor L.04 OH 0.002 157,992.00 315.98
JUMLAH TENAGA KERJA 8,271.49
B BAHAN
Kawat las Kg 0.400 57,000.00 22,800.00
Solar Liter 0.300 10,000.00 3,000.00
Minyak pelumas Liter 0.040 30,000.00 1,200.00
JUMLAH HARGA BAHAN 27,000.00
C PERALATAN
Sewa alat las Jam 0,170 50,000.00 8,500,000.00
JUMLAH HARGA ALAT 8,500,000.00

D Jumlah (A+B+C) 8,535,271.49


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 853,527.15
F Harga Satuan Pekerjaan (D+E) 9,388,798.64
Pekerjaan perakitan /cm 938,879.86

A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 122,992.00 5,288.66
Tukang alumunium L.03 OH 0.043 136,992.00 5,890.66
Kepala tukang L.03 OH 0.0043 147,992.00 636.37
Mandor L.04 OH 0.0021 157,992.00 331.78
JUMLAH TENAGA KERJA 12,147.46
B BAHAN
Kusen Alumunium Profil 4" m 1.100 110,000.00 121,000.00
Skrup fixer buah 2.000 950.00 1,900.00
Sealant Tube 0.060 36,000.00 2,160.00
JUMLAH HARGA BAHAN 125,060.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 137,207.46


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,720.75
F Harga Satuan Pekerjaan (D+E) 150,928.21

A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3 122,992.00 36,897.60
Tukang alumunium L.03 OH 0.3 136,992.00 41,097.60
Kepala tukang L.03 OH 0.03 147,992.00 4,439.76
Mandor L.04 OH 0.03 157,992.00 4,739.76
JUMLAH TENAGA KERJA 87,174.72
B BAHAN
Profil pintu alumunium m 4.400 42,325.00 186,230.00
Spigot m 1.200 8,100.00 9,720.00
Paku Sekrup 1 cm-2,5 cm m 24.000 900.00 21,600.00
Sealant Tube 0.270 36,000.00 9,720.00
JUMLAH HARGA BAHAN 227,270.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 314,444.72


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 31,444.47
F Harga Satuan Pekerjaan (D+E) 345,889.19
A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai Seng galvalum 0,3 lebar 90 cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang besi L.03 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.001 157,992.00 157.99
JUMLAH TENAGA KERJA 55,114.63
B BAHAN
Seng galvalum 0,3 lebar 90 cm m 1.050 41,400.00 43,470.00
Paku 1 cm - 2,5 cm kg 0.015 19,500.00 292.50
Kayu meranti (papan) m3 0.019 4,861,111.11 92,361.11
JUMLAH HARGA BAHAN 136,123.61
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 191,238.24


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 19,123.82
F Harga Satuan Pekerjaan (D+E) 210,362.07

A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, Seng galvalum 0,3 lebar 60 cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Tukang besi L.03 OH 0.300 136,992.00 41,097.60
Kepala tukang L.03 OH 0.030 147,992.00 4,439.76
Mandor L.04 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 65,250.10
B BAHAN
Seng galvalum 0,3 lebar 60 cm m 1.050 33,500.00 35,175.00
Paku 1 cm - 2,5 cm kg 0.010 19,500.00 195.00
Besi Strip (2x3)cm kg 0.500 11,200.00 5,600.00
JUMLAH HARGA BAHAN 40,970.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 106,220.10


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 10,622.01
F Harga Satuan Pekerjaan (D+E) 116,842.11

A.4.2.1.20.Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk partisi
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 122,992.00 30,748.00
Tukang besi L.02 OH 0.250 136,992.00 34,248.00
Kepala tukang L.03 OH 0.025 147,992.00 3,699.80
Mandor L.04 OH 0.013 157,992.00 2,053.90
JUMLAH TENAGA KERJA 70,749.70
B BAHAN
Besi hollow 4x4 plafon M1 3.50 8,000.00 28,000.00
Assesoris (perkuatan, las dll) Ls 100% xrangka 28,000.00 28,000.00
JUMLAH HARGA BAHAN 56,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 126,749.70


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 12,674.97
F Harga Satuan Pekerjaan (D+E) 139,424.67
A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow galvalume 1x40.40.2mm, modul 60 x 60 cm, untuk plafon
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 122,992.00 30,748.00
Tukang besi L.02 OH 0.250 136,992.00 34,248.00
Kepala tukang L.03 OH 0.025 147,992.00 3,699.80
Mandor L.04 OH 0.013 157,992.00 2,053.90
JUMLAH TENAGA KERJA 70,749.70
B BAHAN
Besi hollow 4x4 plafon M1 4.00 8,000.00 32,000.00
Assesoris (perkuatan,las dll) Ls 100%xrangka 32,000.00 32,000.00
JUMLAH HARGA BAHAN 64,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 134,749.70


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,474.97
F Harga Satuan Pekerjaan (D+E) 148,224.67

A.4.2.1.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.734 122,992.00 90,276.13
Tukang besi L.02 OH 0.734 136,992.00 100,552.13
Kepala tukang L.03 OH 0.073 147,992.00 10,803.42
Mandor L.04 OH 0.037 157,992.00 5,845.70
JUMLAH TENAGA KERJA 207,477.38
B BAHAN
Maintruss C 70.30.0,75 kg 3.065 13,500.00 41,377.50
JUMLAH HARGA BAHAN 41,377.50
C PERALATAN
Peralatan % 10.000 41,377.50 4,137.750
JUMLAH HARGA ALAT 4,137.750

D Jumlah (A+B+C) 252,992.63


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 25,299.26
F Harga Satuan Pekerjaan (D+E) 278,291.89

A.4.2.1.22. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.7604 122,992.00 93,523.12
Tukang besi L.02 OH 0.7604 136,992.00 104,168.72
Kepala tukang L.03 OH 0.076 147,992.00 11,247.39
Mandor L.04 OH 0.038 157,992.00 6,003.70
JUMLAH TENAGA KERJA 214,942.92
B BAHAN
Maintruss C 70.30.0,75 kg 4.050 13,500.00 54,675.00
JUMLAH HARGA BAHAN 54,675.00
C PERALATAN
Peralatan % 10.000 54,675.00 5,467.500
JUMLAH HARGA ALAT 5,467.500

D Jumlah (A+B+C) 275,085.42


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 27,508.54
F Harga Satuan Pekerjaan (D+E) 302,593.96
A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.085 122,992.00 10,454.32
Tukang alumunium L.03 OH 0.085 136,992.00 11,644.32
Kepala tukang L.03 OH 0.0085 147,992.00 1,257.93
Mandor L.04 OH 0.0042 157,992.00 663.57
JUMLAH TENAGA KERJA 24,020.14
B BAHAN
Profil pintu alumunium m 4.400 42,325.00 186,230.00
Alluminium strip m 14.600 32,000.00 467,200.00
JUMLAH HARGA BAHAN 653,430.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 677,450.14


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 67,745.01
F Harga Satuan Pekerjaan (D+E) 745,195.15
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A. 4.4.1.4. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 122,992.00 73,795.20
Tukang batu L.02 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.030 157,992.00 4,739.76
JUMLAH TENAGA KERJA 108,893.20
B BAHAN
Bata merah buah 140.000 750.00 105,000.00
Semen portland (kg) Kg 22.200 1,150.00 25,530.00
Pasir pasang m3 0.102 271,600.00 27,703.20
JUMLAH HARGA BAHAN 158,233.20
C PERALATAN 46,000.00

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 267,126.40


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 26,712.64
F Harga Satuan Pekerjaan (D+E) 293,839.04

A. 4.4.1.5 Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 122,992.00 73,795.20
Tukang batu L.02 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.030 157,992.00 4,739.76
JUMLAH TENAGA KERJA 108,893.20
B BAHAN
Bata merah buah 140.000 750.00 105,000.00
Semen portland (kg) Kg 18.500 1,150.00 21,275.00
Pasir pasang m3 0.122 271,600.00 33,135.20
JUMLAH HARGA BAHAN 159,410.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 268,303.40


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 26,830.34
F Harga Satuan Pekerjaan (D+E) 295,133.74

A. 4.4.1.7 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah buah 70.000 750.00 52,500.00
Semen portland (kg) Kg 18.950 1,150.00 21,792.50
Pasir pasang m3 0.038 271,600.00 10,320.80
JUMLAH HARGA BAHAN 84,613.30
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 139,059.90


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,905.99
F Harga Satuan Pekerjaan (D+E) 152,965.89
A. 4.4.1.8 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah buah 70.000 750.00 52,500.00
Semen portland (kg) Kg 14.370 1,150.00 16,525.50
Pasir pasang m3 0.040 271,600.00 10,864.00
JUMLAH HARGA BAHAN 79,889.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 134,336.10


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,433.61
F Harga Satuan Pekerjaan (D+E) 147,769.71

A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah buah 70.000 750.00 52,500.00
Semen portland (kg) Kg 11.500 1,150.00 13,225.00
Pasir pasang m3 0.043 271,600.00 11,678.80
JUMLAH HARGA BAHAN 77,403.80
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 131,850.40


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,185.04
F Harga Satuan Pekerjaan (D+E) 145,035.44

A. 4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :5PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah buah 70.000 750.00 52,500.00
Semen portland (kg) Kg 9.680 1,150.00 11,132.00
Pasir pasang m3 0.045 271,600.00 12,222.00
JUMLAH HARGA BAHAN 75,854.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 130,300.60


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,030.06
F Harga Satuan Pekerjaan (D+E) 143,330.66
A. 4.4.1.11 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 6PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah buah 70.000 750.00 52,500.00
Semen portland (kg) Kg 8.320 1,150.00 9,568.00
Pasir pasang m3 0.049 271,600.00 13,308.40
JUMLAH HARGA BAHAN 75,376.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 129,823.00


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 12,982.30
F Harga Satuan Pekerjaan (D+E) 142,805.30

A. 4.4.1.12 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :8PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 54,446.60
B BAHAN
Bata merah buah 70.000 750.00 52,500.00
Semen portland (kg) Kg 6.500 1,150.00 7,475.00
Pasir pasang m3 0.050 271,600.00 13,580.00
JUMLAH HARGA BAHAN 73,555.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 128,001.60


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 12,800.16
F Harga Satuan Pekerjaan (D+E) 140,801.76

A. 4.4.1.26 Pemasangan 1m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.26 122,992.00 31,977.92
Tukang batu L.02 OH 0.130 136,992.00 17,808.96
Kepala tukang L.03 OH 0.013 147,992.00 1,923.90
Mandor L.04 OH 0.0003 157,992.00 47.40
JUMLAH TENAGA KERJA 51,758.17
B BAHAN
Bata ringan tebal 10 cm m3 0.100 670,889.00 67,088.90
Mortar siap pakai (MSP) Kg 4.000 6,100.00 24,400.00
JUMLAH HARGA BAHAN 91,488.90
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 143,247.07


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 14,324.71
F Harga Satuan Pekerjaan (D+E) 157,571.78
52.4
95.6

228 83333.3
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 7.776 1,150.00 8,942.40
Pasir pasang m3 0.023 271,600.00 6,246.80
JUMLAH HARGA BAHAN 15,189.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,225.36


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,722.54
F Harga Satuan Pekerjaan (D+E) 84,947.90

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 6.240 1,150.00 7,176.00
Pasir pasang m3 0.024 271,600.00 6,518.40
JUMLAH HARGA BAHAN 13,694.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 75,730.56


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,573.06
F Harga Satuan Pekerjaan (D+E) 83,303.62

A.4.4.2.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 5.184 1,150.00 5,961.60
Pasir pasang m3 0.026 271,600.00 7,061.60
JUMLAH HARGA BAHAN 13,023.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 75,059.36


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,505.94
F Harga Satuan Pekerjaan (D+E) 82,565.30
A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 4.416 1,150.00 5,078.40
Pasir pasang m3 0.027 271,600.00 7,333.20
JUMLAH HARGA BAHAN 12,411.60
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 74,447.76


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,444.78
F Harga Satuan Pekerjaan (D+E) 81,892.54

A.4.4.2.7. Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 3.936 1,150.00 4,526.40
Pasir pasang m3 0.028 271,600.00 7,604.80
JUMLAH HARGA BAHAN 12,131.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 74,167.36


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,416.74
F Harga Satuan Pekerjaan (D+E) 81,584.10

A.4.4.2.8. Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 3.456 1,150.00 3,974.40
Pasir pasang m3 0.029 271,600.00 7,876.40
JUMLAH HARGA BAHAN 11,850.80
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 73,886.96


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,388.70
F Harga Satuan Pekerjaan (D+E) 81,275.66
A.4.4.2.24 Pemasangan 1 m2 finishing siar pasangan bata merah
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Tukang batu L.03 OH 0.075 136,992.00 10,274.40
Kepala tukang L.03 OH 0.008 147,992.00 1,183.94
Mandor L.04 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 31,171.07
B BAHAN
Semen portland (kg) Kg 3.108 1,150.00 3,574.20
JUMLAH HARGA BAHAN 3,574.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 34,745.27


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,474.53
F Harga Satuan Pekerjaan (D+E) 38,219.80

A.4.4.2.26. Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 122,992.00 36,897.60
Tukang batu L.03 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.015 157,992.00 2,369.88
JUMLAH TENAGA KERJA 62,036.16
B BAHAN
Semen portland (kg) Kg 6.340 1,150.00 7,291.00
Pasir pasang m3 0.012 271,600.00 3,259.20
JUMLAH HARGA BAHAN 10,550.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 72,586.36


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,258.64
F Harga Satuan Pekerjaan (D+E) 79,845.00

A.4.4.2.27. Pemasangan 1 m2 acian


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang batu L.03 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 41,357.44
B BAHAN
Semen portland (kg) Kg 3.250 1,150.00 3,737.50
JUMLAH HARGA BAHAN 3,737.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 45,094.94


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 4,509.49
F Harga Satuan Pekerjaan (D+E) 49,604.43
A.4.4.2.28. Pemasangan 1 m2 plesteran dengan mortar siap pakai (MSP)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang batu L.03 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 41,357.44
B BAHAN
MSP (plesteran) Kg 20 3,675.00 73,500.00
JUMLAH HARGA BAHAN 73,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 114,857.44


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 11,485.74
F Harga Satuan Pekerjaan (D+E) 126,343.18

A.4.4.2.29. Pemasangan 1 m2 plesteran acian mortar siap pakai (MSP)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang batu L.03 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 41,357.44
B BAHAN
MSP (acian) Kg 2.5 2,750.00 6,875.00
JUMLAH HARGA BAHAN 6,875.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 48,232.44


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 4,823.24
F Harga Satuan Pekerjaan (D+E) 53,055.68
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.35. Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 122,992.00 86,094.40
Tukang batu L.02 OH 0.350 136,992.00 47,947.20
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.035 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
keramik (30x30) cm Doos 1.050 55,000.00 57,750.00
Semen portland (kg) Kg 10.000 1,150.00 11,500.00
Pasir pasang M3 0.045 271,600.00 12,222.00
Semen warna Kg 0.500 7,750.00 3,875.00
JUMLAH HARGA BAHAN 85,347.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 230,098.04


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 23,009.80
F Harga Satuan Pekerjaan (D+E) 253,107.84

A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20 cm x 20 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 122,992.00 86,094.40
Tukang batu L.02 OH 0.350 136,992.00 47,947.20
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.035 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
Keramik lantai (20x20) cm Doos 1.050 40,000.00 42,000.00
Semen portland (kg) Kg 10.400 1,150.00 11,960.00
Pasir pasang M3 0.045 271,600.00 12,222.00
Semen warna Kg 0.500 7,750.00 3,875.00
JUMLAH HARGA BAHAN 70,057.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 214,808.04


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 21,480.80
F Harga Satuan Pekerjaan (D+E) 236,288.84

A.4.4.3.39. Pemasangan 1 m’ plint keramik ukuran 7,5 cm x 20 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.090 122,992.00 11,069.28
Tukang batu L.02 OH 0.090 136,992.00 12,329.28
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 29,368.24
B BAHAN
Keramik border 7,5x20 cm Bh 5.300 8,000.00 42,400.00
Semen portland (kg) Kg 1.140 1,150.00 1,311.00
Pasir pasang M3 0.003 271,600.00 814.80
Semen warna Kg 0.025 7,750.00 193.75
JUMLAH HARGA BAHAN 44,719.55
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 74,087.79


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,408.78
F Harga Satuan Pekerjaan (D+E) 81,496.57

A.4.4.3.54.Pemasangan 1 m2 dinding keramik 20 cm x 25 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 122,992.00 110,692.80
Tukang batu L.02 OH 0.450 136,992.00 61,646.40
Kepala tukang L.03 OH 0.045 147,992.00 6,659.64
Mandor L.04 OH 0.045 157,992.00 7,109.64
JUMLAH TENAGA KERJA 186,108.48
B BAHAN
Keramik dinding (20x25) cm buah 1.050 80,000.00 84,000.00
Semen portland (kg) Kg 9.300 1,150.00 10,695.00
Pasir pasang M3 0.018 271,600.00 4,888.80
Semen warna Kg 1.940 7,750.00 15,035.00
JUMLAH HARGA BAHAN 114,618.80
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 300,727.28


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 30,072.73
F Harga Satuan Pekerjaan (D+E) 330,800.01

A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel hitam


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 122,992.00 86,094.40
Tukang batu L.02 OH 0.350 136,992.00 47,947.20
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.035 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
Batu tempel hitam m2 1.100 120,000.00 132,000.00
Semen portland (kg) Kg 11.750 1,150.00 13,512.50
Pasir pasang M3 0.035 271,600.00 9,506.00
JUMLAH HARGA BAHAN 155,018.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 299,769.54
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 29,976.95
F Harga Satuan Pekerjaan (D+E) 329,746.49

A.4.4.3.64. Pemasangan 1 m2 paving block natural tebal 6 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 122,992.00 30,748.00
Tukang batu L.02 OH 0.500 136,992.00 68,496.00
Kepala tukang L.03 OH 0.050 147,992.00 7,399.60
Mandor L.04 OH 0.001 157,992.00 205.39
JUMLAH TENAGA KERJA 106,848.99
B BAHAN
Paving block 6 cm M2 1.010 55,000.00 55,550.00
Pasir pasang M3 0.050 271,600.00 13,580.00
JUMLAH HARGA BAHAN 69,130.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 175,978.99


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 17,597.90
F Harga Satuan Pekerjaan (D+E) 193,576.89

A.4.4.3.9. Pemasangan 1 m2 lantai ubin granit ukuran 60 cm x 60 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 122,992.00 30,748.00
Tukang batu L.02 OH 0.125 136,992.00 17,124.00
Kepala tukang L.03 OH 0.013 147,992.00 1,923.90
Mandor L.04 OH 0.013 157,992.00 2,053.90
JUMLAH TENAGA KERJA 51,849.79
B BAHAN
Granit Lokal 60 x 60 m2 1.050 134,191.20 140,900.76
Semen portland (kg) kg 9.800 1,150.00 11,270.00
Semen warna Kg 1.300 7,750.00 10,075.00
Pasir pasang M3 0.045 271,600.00 12,222.00
JUMLAH HARGA BAHAN 174,467.76
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 226,317.55


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 22,631.76
F Harga Satuan Pekerjaan (D+E) 248,949.31

A.4.4.3.58.1 Pemasangan 1 m2 dinding batu tempel hitam


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 122,992.00 86,094.40
Tukang batu L.02 OH 0.350 136,992.00 47,947.20
Kepala tukang L.03 OH 0.035 147,992.00 5,179.72
Mandor L.04 OH 0.035 157,992.00 5,529.72
JUMLAH TENAGA KERJA 144,751.04
B BAHAN
Beton alur m2 1.100 80,000.00 88,000.00
Semen portland (kg) Kg 11.750 1,150.00 13,512.50
Pasir pasang M3 0.035 271,600.00 9,506.00
JUMLAH HARGA BAHAN 111,018.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 255,769.54


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 25,576.95
F Harga Satuan Pekerjaan (D+E) 281,346.49
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.1. Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.030 122,992.00 3,689.76
Tukang kayu L.02 OH 0.070 136,992.00 9,589.44
Kepala tukang L.03 OH 0.007 147,992.00 1,035.94
Mandor L.04 OH 0.004 157,992.00 631.97
JUMLAH TENAGA KERJA 14,947.11
B BAHAN
Eternit 100x100 tebal 5mm m2 1.100 22,500.00 24,750.00
Paku tripleks kg 0.010 18,400.00 184.00
JUMLAH HARGA BAHAN 24,934.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 39,881.11


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,988.11
F Harga Satuan Pekerjaan (D+E) 43,869.22

A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9)


mm, tebal 9 mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Tukang kayu L.02 OH 0.050 136,992.00 6,849.60
Kepala tukang L.03 OH 0.005 147,992.00 739.96
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 20,678.72
B BAHAN
Gypsumboard 9mm Lembar 0.364 62,500.00 22,750.00
Sekrup gypsumboard kg 0.110 45,000.00 4,950.00
JUMLAH HARGA BAHAN 27,700.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 48,378.72


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 4,837.87
F Harga Satuan Pekerjaan (D+E) 53,216.59

A.4.5.1.9. Pemasangan 1 m’ list langit-langit gypsum


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 122,992.00 6,149.60
Tukang kayu L.02 OH 0.050 136,992.00 6,849.60
Kepala tukang L.03 OH 0.005 147,992.00 739.96
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 14,213.14
B BAHAN
List gypsum profil m 1.050 14,000.00 14,700.00
Paku 1 cm - 2,5 cm kg 0.010 19,500.00 195.00
JUMLAH HARGA BAHAN 14,895.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 29,108.14


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 2,910.81
F Harga Satuan Pekerjaan (D+E) 32,018.95

A.4.5.1.10 Pemasangan 1 m2 rangka langit-langit besi hollow 40.40


Lihat pada kelompok Pekerjaan Besi dan Alumunium (A.9.21)
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1. (K3) Pemasangan 1 buah closet duduk/monoblock


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.300 122,992.00 405,873.60
Tukang batu L.02 OH 1.100 136,992.00 150,691.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.160 157,992.00 25,278.72
JUMLAH TENAGA KERJA 583,323.44
B BAHAN
Klosed Duduk Unit 1.000 473,000.00 473,000.00
Perlengkapan Ls 6% x closet 28,380.00 28,380.00
JUMLAH HARGA BAHAN 501,380.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,084,703.44


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 108,470.34
F Harga Satuan Pekerjaan (D+E) 1,193,173.78

A.5.1.1 2. Pemasangan 1 buah closet jongkok porselen


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
TENAGA
Pekerja L.01 OH 1.000 122,992.00 122,992.00
Tukang batu L.02 OH 1.500 136,992.00 205,488.00
Kepala tukang L.03 OH 0.150 147,992.00 22,198.80
Mandor L.04 OH 0.160 157,992.00 25,278.72
JUMLAH TENAGA KERJA 375,957.52
B BAHAN
Kloset jongkok porselen Unit 1.000 205,000.00 205,000.00
Semen Portland (kg) Kg 6.000 1,150.00 6,900.00
Pasir pasang M3 0.010 271,600.00 2,716.00
JUMLAH HARGA BAHAN 214,616.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 590,573.52


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 59,057.35
F Harga Satuan Pekerjaan (D+E) 649,630.87

A.5.1.1 5. (K3) Pemasangan 1 buah wastafel


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 122,992.00 147,590.40
Tukang batu L.02 OH 1.450 136,992.00 198,638.40
Kepala tukang L.03 OH 0.150 147,992.00 22,198.80
Mandor L.04 OH 0.060 157,992.00 9,479.52
JUMLAH TENAGA KERJA 377,907.12
B BAHAN
Wastefel Unit 1.200 408,333.00 489,999.60
Semen Portland (kg) Kg 6.000 1,150.00 6,900.00
Pasir pasang M3 0.010 271,600.00 2,716.00
Perlengkapan % 12.000 4,083.33 48,999.96
JUMLAH HARGA BAHAN 548,615.56
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,038,615.16


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 103,861.52
F Harga Satuan Pekerjaan (D+E) 1,142,476.68

A.5.1.1 14. Pemasangan 1 buah floor drain


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 122,992.00 1,229.92
Tukang batu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 17,199.00
B BAHAN
Floor drain Unit 1.000 60,000.00 60,000.00
JUMLAH HARGA BAHAN 60,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,199.00


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 7,719.90
F Harga Satuan Pekerjaan (D+E) 84,918.90

A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.160 122,992.00 265,662.72
Tukang batu L.02 OH 0.720 136,992.00 98,634.24
Kepala tukang L.03 OH 0.072 147,992.00 10,655.42
Mandor L.04 OH 0.011 157,992.00 1,737.91
JUMLAH TENAGA KERJA 376,690.30
B BAHAN
Bata merah buah 40.000 750.00 30,000.00
Semen portland (kg) Kg 44.000 1,150.00 50,600.00
Pasir pasang M3 0.070 271,600.00 19,012.00
Pasir beton M3 0.060 313,333.00 18,799.98
Koral beton M3 0.070 280,000.00 19,600.00
Besi beton polos Kg 1.600 10,650.00 17,040.00
JUMLAH HARGA BAHAN 155,051.98
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 531,742.28


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 53,174.23
F Harga Satuan Pekerjaan (D+E) 584,916.50

A.5.1.1 19. Pemasangan 1 buah kran diameter ½”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.010 122,992.00 1,229.92
Tukang batu L.02 OH 0.400 136,992.00 54,796.80
Kepala tukang L.03 OH 0.040 147,992.00 5,919.68
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 62,736.36
B BAHAN
Kran air 1/2 " M 1.000 42,125.00 42,125.00
Seal tape Buah 0.025 7,000.00 175.00
JUMLAH HARGA BAHAN 42,300.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 105,036.36


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 10,503.64
F Harga Satuan Pekerjaan (D+E) 115,540.00

A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter ½ ”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 122,992.00 4,427.71
Tukang batu L.02 OH 0.060 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.002 157,992.00 315.98
JUMLAH TENAGA KERJA 13,851.17
B BAHAN
Pipa PVC 1/2" M 1.200 5,675.00 6,810.00
Perlengkapan % 35.000 5,675.00 1,986.25
JUMLAH HARGA BAHAN 8,796.25
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,647.42


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 2,264.74
F Harga Satuan Pekerjaan (D+E) 24,912.16

A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter ¾ ”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 122,992.00 4,427.71
Tukang batu L.02 OH 0.060 136,992.00 8,219.52
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.002 157,992.00 315.98
JUMLAH TENAGA KERJA 13,851.17
B BAHAN
Pipa PVC 3/4" M 1.200 7,233.25 8,679.90
Perlengkapan % 35.000 7,233.25 2,531.64
JUMLAH HARGA BAHAN 11,211.54
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 25,062.71


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 2,506.27
F Harga Satuan Pekerjaan (D+E) 27,568.98

A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe D diameter 3”


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 122,992.00 9,962.35
Tukang batu L.02 OH 0.135 136,992.00 18,493.92
Kepala tukang L.03 OH 0.014 147,992.00 1,997.89
Mandor L.04 OH 0.004 157,992.00 631.97
JUMLAH TENAGA KERJA 31,086.13
B BAHAN
Pipa PVC D 3" M 1.200 48,750.00 58,500.00
Perlengkapan % 35.000 48,750.00 17,062.50
JUMLAH HARGA BAHAN 75,562.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 106,648.63


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 10,664.86
F Harga Satuan Pekerjaan (D+E) 117,313.50
A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe D diameter 4”
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 122,992.00 9,962.35
Tukang batu L.02 OH 0.135 136,992.00 18,493.92
Kepala tukang L.03 OH 0.014 147,992.00 1,997.89
Mandor L.04 OH 0.004 157,992.00 631.97
JUMLAH TENAGA KERJA 31,086.13
B BAHAN
Pipa PVC D 4" M 1.200 71,250.00 85,500.00
Perlengkapan % 35.000 71,250.00 24,937.50
JUMLAH HARGA BAHAN 110,437.50
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 141,523.63


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 14,152.36
F Harga Satuan Pekerjaan (D+E) 155,676.00
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.2. Pemasangan 1 m2 atap genteng kodok


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Tukang kayu L.03 OH 0.075 136,992.00 10,274.40
Kepala tukang L.11 OH 0.008 147,992.00 1,183.94
Mandor L.15 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 31,171.07
B BAHAN
Genteng karang pilang Kw 1 buah 22.000 7,700.00 169,400.00
JUMLAH HARGA BAHAN 169,400.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 200,571.07


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 20,057.11
F Harga Satuan Pekerjaan (D+E) 220,628.18

A.4.5.2.5. Pemasangan 1 m’ bubung genteng kodok


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 122,992.00 49,196.80
Tukang kayu L.03 OH 0.200 136,992.00 27,398.40
Kepala tukang L.11 OH 0.020 147,992.00 2,959.84
Mandor L.15 OH 0.002 157,992.00 315.98
JUMLAH TENAGA KERJA 79,871.02
B BAHAN
Bubungan Genteng karang pilang buah 3.500 9,700.00 33,950.00
Semen Portland (kg) Kg 8.000 1,150.00 9,200.00
Pasir pasang M3 0.032 271,600.00 8,691.20
JUMLAH HARGA BAHAN 51,841.20
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 131,712.22


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,171.22
F Harga Satuan Pekerjaan (D+E) 144,883.45

A.4.5.2.39. Pemasangan 1 m2 atap galvalum


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 122,992.00 14,759.04
Tukang kayu L.03 OH 0.060 136,992.00 8,219.52
Kepala tukang L.11 OH 0.006 147,992.00 887.95
Mandor L.15 OH 0.006 157,992.00 947.95
JUMLAH TENAGA KERJA 24,814.46
B BAHAN
Atap galvalum 2,68x1,00x0,4 Lbr 0.700 45,000.00 31,500.00
Sekrup gypsumboard Kg 0.020 45,000.00 900.00
JUMLAH HARGA BAHAN 32,400.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 57,214.46


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 5,721.45
F Harga Satuan Pekerjaan (D+E) 62,935.91
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.2.Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.000 122,992.00 737,952.00
Tukang kayu L.03 OH 18.000 136,992.00 2,465,856.00
Kepala tukang L.03 OH 1.800 147,992.00 266,385.60
Mandor L.04 OH 0.300 157,992.00 47,397.60
JUMLAH TENAGA KERJA 3,517,591.20
B BAHAN
Kayu kelas II m3 1.200 5,890,000.00 7,068,000.00
Paku 5 cm - 10 cm Kg 1.250 19,660.00 24,575.00
Lem kayu Kg 1.000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 7,137,575.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 10,655,166.20


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 1,065,516.62
F Harga Satuan Pekerjaan (D+E) 11,720,682.82

A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 122,992.00 122,992.00
Tukang kayu L.03 OH 3.000 136,992.00 410,976.00
Kepala tukang L.03 OH 0.300 147,992.00 44,397.60
Mandor L.04 OH 0.050 157,992.00 7,899.60
JUMLAH TENAGA KERJA 586,265.20
B BAHAN
Kayu kelas II m3 0.040 5,890,000.00 235,600.00
Lem kayu Kg 0.500 45,000.00 22,500.00
JUMLAH HARGA BAHAN 258,100.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 844,365.20


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 84,436.52
F Harga Satuan Pekerjaan (D+E) 928,801.72

A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 122,992.00 98,393.60
Tukang kayu L.03 OH 2.400 136,992.00 328,780.80
Kepala tukang L.03 OH 0.240 147,992.00 35,518.08
Mandor L.04 OH 0.040 157,992.00 6,319.68
JUMLAH TENAGA KERJA 469,012.16
B BAHAN
Kayu kelas II m3 0.024 5,890,000.00 141,360.00
Lem kayu Kg 0.300 45,000.00 13,500.00
JUMLAH HARGA BAHAN 154,860.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 623,872.16


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 62,387.22
F Harga Satuan Pekerjaan (D+E) 686,259.38
A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas II
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 122,992.00 122,992.00
Tukang kayu L.03 OH 3.000 136,992.00 410,976.00
Kepala tukang L.03 OH 0.300 147,992.00 44,397.60
Mandor L.04 OH 0.050 157,992.00 7,899.60
JUMLAH TENAGA KERJA 586,265.20
B BAHAN
Kayu kelas II m3 0.064 5,890,000.00 376,960.00
Lem kayu Kg 0.500 45,000.00 22,500.00
JUMLAH HARGA BAHAN 399,460.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 985,725.20
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 98,572.52
F Harga Satuan Pekerjaan (D+E) 1,084,297.72

A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas III Bentang 6M'

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.000 122,992.00 491,968.00
Tukang kayu L.03 OH 12.000 136,992.00 1,643,904.00
Kepala tukang L.03 OH 1.200 147,992.00 177,590.40
Mandor L.04 OH 0.200 157,992.00 31,598.40
JUMLAH TENAGA KERJA 2,345,060.80
B BAHAN
Kayu meranti (balok) m3 1.100 4,861,111.11 5,347,222.22
Besi Strip (2x3)cm kg 15.000 11,200.00 168,000.00
Paku 5 cm - 10 cm kg 5.600 19,660.00 110,096.00
JUMLAH HARGA BAHAN 5,625,318.22
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 7,970,379.02
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 797,037.90
F Harga Satuan Pekerjaan (D+E) 8,767,416.92

A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas III


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.700 122,992.00 824,046.40
Tukang kayu L.03 OH 20.100 136,992.00 2,753,539.20
Kepala tukang L.03 OH 2.010 147,992.00 297,463.92
Mandor L.04 OH 0.335 157,992.00 52,927.32
JUMLAH TENAGA KERJA 3,927,976.84
B BAHAN
Kayu meranti (balok) m3 1.100 4,861,111.11 5,347,222.22
Besi Strip (2x3)cm kg 15.000 11,200.00 168,000.00
Paku 5 cm - 10 cm kg 3.000 19,660.00 58,980.00
JUMLAH HARGA BAHAN 5,574,202.22
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 9,502,179.06


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 950,217.91
F Harga Satuan Pekerjaan (D+E) 10,452,396.97
A.4.6.1.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Tukang kayu L.03 OH 0.300 136,992.00 41,097.60
Kepala tukang L.03 OH 0.030 147,992.00 4,439.76
Mandor L.04 OH 0.075 157,992.00 11,849.40
JUMLAH TENAGA KERJA 75,835.56
B BAHAN
Kaso-kaso (5 × 7) cm kayu mera m3 0.015 3,500,000.00 53,900.00
Paku 5 cm - 10 cm kg 0.200 19,660.00 3,932.00
JUMLAH HARGA BAHAN 57,832.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 133,667.56


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,366.76
F Harga Satuan Pekerjaan (D+E) 147,034.32

A.4.6.1.20.Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 122,992.00 24,598.40
Tukang kayu L.03 OH 0.300 136,992.00 41,097.60
Kepala tukang L.03 OH 0.030 147,992.00 4,439.76
Mandor L.04 OH 0.010 157,992.00 1,579.92
JUMLAH TENAGA KERJA 71,715.68
B BAHAN
Kaso-kaso (5 × 7) cm kayu mera m3 0.016 3,500,000.00 57,050.00
Paku 5 cm - 10 cm kg 0.250 19,660.00 4,915.00
JUMLAH HARGA BAHAN 61,965.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 133,680.68


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 13,368.07
F Harga Satuan Pekerjaan (D+E) 147,048.75

A.4.6.1.21. Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas III


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Tukang kayu L.03 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 43,447.40
B BAHAN
Kayu meranti (papan) m3 0.011 4,861,111.11 52,500.00
Paku 5 cm - 10 cm kg 0.100 19,660.00 1,966.00
JUMLAH HARGA BAHAN 54,466.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 97,913.40


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 9,791.34
F Harga Satuan Pekerjaan (D+E) 107,704.74
A.4.6.1.22. Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas III
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 122,992.00 12,299.20
Tukang kayu L.03 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 43,447.40
B BAHAN
Kayu meranti (papan) m3 0.011 4,861,111.11 53,472.22
Paku 5 cm - 10 cm kg 0.050 19,660.00 983.00
JUMLAH HARGA BAHAN 54,455.22
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 97,902.62


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 9,790.26
F Harga Satuan Pekerjaan (D+E) 107,692.88
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.010 122,992.00 1,229.92
Tukang kayu L.02 OH 0.500 136,992.00 68,496.00
Kepala tukang L.03 OH 0.050 147,992.00 7,399.60
Mandor L.04 OH 0.005 157,992.00 789.96
JUMLAH TENAGA KERJA 77,915.48
B BAHAN
Kunci pintu tanam 2x putar buah 1.000 189,800.00 189,800.00
JUMLAH HARGA BAHAN 189,800.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 267,715.48


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 26,771.55
F Harga Satuan Pekerjaan (D+E) 294,487.03

A.4.6.2.5. Pemasangan 1 buah engsel pintu


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 122,992.00 1,844.88
Tukang kayu L.02 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.001 157,992.00 126.39
JUMLAH TENAGA KERJA 24,739.95
B BAHAN
Engsel pintu 4" buah 1.000 75,000.00 75,000.00
JUMLAH HARGA BAHAN 75,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 99,739.95


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 9,974.00
F Harga Satuan Pekerjaan (D+E) 109,713.95

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 122,992.00 1,229.92
Tukang kayu L.02 OH 0.100 136,992.00 13,699.20
Kepala tukang L.03 OH 0.010 147,992.00 1,479.92
Mandor L.04 OH 0.001 157,992.00 79.00
JUMLAH TENAGA KERJA 16,488.04
B BAHAN
Engsel jendela 3" buah 1.000 22,550.00 22,550.00
JUMLAH HARGA BAHAN 22,550.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 39,038.04


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,903.80
F Harga Satuan Pekerjaan (D+E) 42,941.84
A.4.6.2.6. Pemasangan 1 buah engsel casement
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 122,992.00 1,844.88
Tukang kayu L.02 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 25,877.50
B BAHAN
engsel Casement uk. 8" buah 1.000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 37,877.50


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,787.75
F Harga Satuan Pekerjaan (D+E) 41,665.25

A.4.6.2.9. Pemasangan 1 buah kait angin


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 122,992.00 1,844.88
Tukang kayu L.02 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.008 157,992.00 1,263.94
JUMLAH TENAGA KERJA 25,877.50
B BAHAN
Hak angin buah 1.000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 37,877.50


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,787.75
F Harga Satuan Pekerjaan (D+E) 41,665.25

A.4.6.2.11. Pemasangan 1 buah Rabuncis


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 122,992.00 2,459.84
Tukang kayu L.02 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.001 157,992.00 157.99
JUMLAH TENAGA KERJA 32,976.07
B BAHAN
Rambuncis buah 1.000 12,200.00 12,200.00
JUMLAH HARGA BAHAN 12,200.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 45,176.07


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 4,517.61
F Harga Satuan Pekerjaan (D+E) 49,693.68
A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 122,992.00 1,844.88
Tukang kayu L.02 OH 0.150 136,992.00 20,548.80
Kepala tukang L.03 OH 0.015 147,992.00 2,219.88
Mandor L.04 OH 0.001 157,992.00 126.39
JUMLAH TENAGA KERJA 24,739.95
B BAHAN
Kaca tebal bening 5 mm m2 1.100 88,000.00 96,800.00
Sealant Kg 0.050 36,000.00 1,800.00
JUMLAH HARGA BAHAN 98,600.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 123,339.95


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 12,334.00
F Harga Satuan Pekerjaan (D+E) 135,673.95

A.4.6.2.18. Pemasangan 1 m2 kaca tebal 8 mm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.017 122,992.00 2,090.86
Tukang kayu L.02 OH 0.170 136,992.00 23,288.64
Kepala tukang L.03 OH 0.017 147,992.00 2,515.86
Mandor L.04 OH 0.001 157,992.00 142.19
JUMLAH TENAGA KERJA 28,037.56
B BAHAN
Kaca tebal bening 8 mm m2 1.100 190,000.00 209,000.00
Sealant Kg 0.070 36,000.00 2,520.00
JUMLAH HARGA BAHAN 211,520.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 239,557.56


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 23,955.76
F Harga Satuan Pekerjaan (D+E) 263,513.32
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 122,992.00 18,448.80
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 18,922.78
B BAHAN
Soda api Kg 0.050 10,000.00 500.00
JUMLAH HARGA BAHAN 500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 19,422.78


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 1,942.28
F Harga Satuan Pekerjaan (D+E) 21,365.05

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 122,992.00 8,609.44
Tukang cat L.02 OH 0.009 136,992.00 1,232.93
Kepala tukang L.03 OH 0.006 147,992.00 887.95
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 11,204.30
B BAHAN
Cat meni Kg 0.200 41,500.00 8,300.00
Plamir kayu Kg 0.150 28,400.00 4,260.00
Cat dasar kayu Kg 0.170 56,350.00 9,579.50
Cat kayu Kg 0.260 56,350.00 14,651.00
Kuwas buah 0.010 23,000.00 230.00
Pengencer Kg 0.030 28,000.00 840.00
Ampelas Lbr 0.200 6,850.00 1,370.00
JUMLAH HARGA BAHAN 39,230.50
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 50,434.80
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 5,043.48
F Harga Satuan Pekerjaan (D+E) 55,478.28

A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 122,992.00 8,609.44
Tukang cat L.02 OH 0.105 136,992.00 14,384.16
Kepala tukang L.03 OH 0.004 147,992.00 591.97
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 24,059.54
B BAHAN
Cat meni Kg 0.200 41,500.00 8,300.00
Plamir kayu Kg 0.150 28,400.00 4,260.00
Cat dasar kayu Kg 0.170 56,350.00 9,579.50
Cat kayu Kg 0.350 56,350.00 19,722.50
Kuwas buah 0.010 23,000.00 230.00
Pengencer Kg 0.030 28,000.00 840.00
Ampelas Lbr 0.200 6,850.00 1,370.00
JUMLAH HARGA BAHAN 44,302.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 68,361.54
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 6,836.15
F Harga Satuan Pekerjaan (D+E) 75,197.70

A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.040 122,992.00 4,919.68
Tukang cat L.02 OH 0.060 136,992.00 8,219.52
Kepala tukang L.03 OH 0.016 147,992.00 2,367.87
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 15,981.05
B BAHAN
Politur L 0.150 71,000.00 10,650.00
Politur jadi L 0.372 71,000.00 26,412.00
Ampelas Lbr 2.000 6,850.00 13,700.00
JUMLAH HARGA BAHAN 50,762.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 66,743.05


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 6,674.30
F Harga Satuan Pekerjaan (D+E) 73,417.35

A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 122,992.00 2,459.84
Tukang cat L.02 OH 0.063 136,992.00 8,630.50
Kepala tukang L.03 OH 0.006 147,992.00 932.35
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 12,496.66
B BAHAN
plamir tembok Kg 0.100 15,000.00 1,500.00
Cat dasar tembok Kg 0.100 20,000.00 2,000.00
Cat tembok Kg 0.260 31,600.00 8,216.00
JUMLAH HARGA BAHAN 11,716.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 24,212.66
E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 2,421.27
F Harga Satuan Pekerjaan (D+E) 26,633.93

A.4.7.1.11.Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.028 122,992.00 3,443.78
Tukang cat L.02 OH 0.042 136,992.00 5,753.66
Kepala tukang L.03 OH 0.004 147,992.00 621.57
Mandor L.04 OH 0.003 157,992.00 473.98
JUMLAH TENAGA KERJA 10,292.98
B BAHAN
Cat dasar tembok Kg 0.120 20,000.00 2,400.00
Cat tembok Kg 0.180 31,600.00 5,688.00
JUMLAH HARGA BAHAN 8,088.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 18,380.98


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 1,838.10
F Harga Satuan Pekerjaan (D+E) 20,219.08
A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 122,992.00 2,459.84
Tukang cat L.02 OH 0.200 136,992.00 27,398.40
Kepala tukang L.03 OH 0.020 147,992.00 2,959.84
Mandor L.04 OH 0.003 157,992.00 394.98
JUMLAH TENAGA KERJA 33,213.06
B BAHAN
Cat meni besi Kg 0.100 41,500.00 4,150.00
kuwas buah 0.010 23,000.00 230.00
JUMLAH HARGA BAHAN 4,380.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 37,593.06


E Overhead & Profit (Contoh 10%) 10% x D (maksimum) 3,759.31
F Harga Satuan Pekerjaan (D+E) 41,352.37
DAFTAR HARGA BAHAN BANGUNAN
SEBELUM PPN UNTUK TAHUN ANGGARAN 2018 SEMESTER I

No. Nama / Jenis Bahan Satuan Harga Bahan


1 Pasir Urug/sirtu M3 141,500.00
2 Pasir Pasang M3 197,400.00
3 Pasir beton M3 318,700.00
4 Pasir Beton (kg) Kg 227.64
5 Sirtu Ayak M3 162,700.00
6 Batu belah M3 167,500.00
7 Bata merah Bh 600.00
8 Koral beton M3 298,900.00
9 koral beton (kg) kg 221.41
10 Bata ringan tebal 7,5 cm M3 646,700.00
11 Bata ringan tebal 10 cm M3 646,700.00
12 Semen portland sak 45,000.00
13 Semen portland (kg) Kg 1,125.00
14 Mortar siap pakai (MSP) Kg 2,100.00
15 Semen warna Kg 12,100.00
16 Besi beton polos Kg 9,200.00
17 Besi beton ulir Kg 9,500.00
18 Kawat beton Kg 21,200.00
19 Dinabolt Bh 2,300.00
20 Besi baja WF Kg 12,700.00
21 Besi profil siku Kg 10,000.00
22 Besi CNP Kg 8,400.00
23 Besi plat Kg 9,900.00
24 Besi Strip (2x3)cm Kg 9,500.00
25 Stak trektang Bh 1,100.00
26 Kawat las Kg 35,300.00
27 Maintruss C 70.30.0,75 M 12,500.00
28 Maintruss C 80.30.0,75 M 12,800.00
28 Reng UK 3.2.0,45 M 6,200.00
29 Screw 12 - 14 x 20 BJ 300.00
30 Screw 12 - 14 x 16 BJ 300.00
31 Kusen Alumunium Profil 4" M 64,000.00
32 Slimar Alumunium Profil 3/8" model casement 3 Profil M 46,000.00
33 Sealant Tube 29,700.00
34 Profil kaca M 32,000.00
35 Kalsiplang l=30cm t=9mm M 21,800.00
36 Kalsiplang l=20cm t=9mm M 16,300.00
37 Besi hollow 4x4 plafon M 8,000.00
38 Besi hollow 2x4 plafon M 5,500.00
39 Gypsumboard 9mm Lbr 54,400.00
40 kalsiboard (1200x2400x4)mm Lbr 52,400.00
No. Nama / Jenis Bahan Satuan Harga Bahan
41 List gypsum profil M 6,000.00
42 List kayu profil M 7,000.00
43 Kawat Ram M 23,500.00
44 Sekrup gypsumboard kg 45,000.00
45 Paku sekrup Bh 200.00
46 Skrup Fixer Bh 700.00
47 Paku Sekrup 1 cm-2,5 cm Bh 400.00
48 Paku skrup 10 cm Bh 2,000.00
49 Paku 1 cm - 2,5 cm Kg 45,000.00
50 Paku 5 cm - 10 cm Kg 15,800.00
51 Paku tripleks Kg 18,400.00
52 Triplek 9 mm Lbr 120,300.00
53 Tripleks 6 mm Lbr 85,000.00
54 Plywood tebal 9 mm Lbr 144,500.00
55 Dolken kayu f 8-10/400 cm Bh 5,300.00
56 Kayu meranti (papan) M3 4,925,000.00
57 Kaso-kaso (5 × 7) cm kayu meranti M3 4,428,571.43
58 Kaso-kaso (4 × 6) cm kayu meranti M3 4,791,666.67
59 Reng 2/3 kayu meranti M3 5,625,000.00
60 Kayu kelas II M3 4,875,000.00
61 Kayu kelas III M3 2,938,000.00
62 Kayu meranti (balok) M3 4,875,000.00
63 Lem kayu Kg 12,300.00
64 Plamir kayu Kg 28,400.00
65 Plamir tembok Kg 5,600.00
66 Amplas Bh 8,500.00
67 Kuwas Bh 20,100.00
68 Rool Bh 31,200.00
69 Cat tembok Kg 23,600.00
70 Cat Kayu Kg 60,500.00
71 Cat meni Kg 33,100.00
72 Cat meni besi Kg 33,100.00
73 Minyak cat Ltr 27,500.00
74 Genteng kaca Bh 50,000.00
75 Genteng karang pilang Kw 1 Bh 4,500.00
76 Bubungan Genteng karang pilang Bh 16,000.00
77 Asbes Gelombang kecil Lbr 90,000.00
78 Seng plat bjls 30 M 41,400.00
79 keramik (30x30) cm M2 34,500.00
80 keramik (40x40) cm M2 45,000.00
81 keramik (40x40) cm (Rock Tile) M2 53,500.00
82 Keramik dinding (20x25) cm M2 49,000.00
83 Keramik lantai (20x20) cm M2 44,500.00
84 Kabel NYA 500 Volt 2 x 2,5 mm2 M 3,400.00
85 Pipa Paralon 5/8" btg 10,400.00
No. Nama / Jenis Bahan Satuan Harga Bahan
86 T Doos Pvc Bh 1,400.00
87 L Bow Bh 1,200.00
88 Klem Bh 900.00
89 Mongkok Bh 1,000.00
90 Stop Kontak ex Broco Bh 15,000.00
91 Fitting Plafon ex Broco Bh 12,100.00
92 Saklar Tunggal ex Broco Bh 14,500.00
93 Saklar Ganda ex Broco Bh 17,800.00
94 MCB Bh 50,000.00
95 Lampu SL model tornado 24 Watt ex Philips Bh 45,400.00
96 Lampu SL model tornado 15 Watt ex Philips Bh 37,900.00
97 Lampu LED 13 Watt ex Philips Bh 51,300.00
98 Kaca tebal bening 5 mm M2 92,500.00
99 Kaca tebal bening 8 mm M2 145,000.00
100 Kaca tebal raiben 5 mm M2 78,000.00
101 Kunci pintu tanam 2x putar Bh 205,000.00
102 Engsel pintu 4" Bh 24,250.00
103 Engsel jendela 3" Bh 20,000.00
104 engsel Casement uk. 8" Bh 12,000.00
105 Rambuncis Bh 12,200.00
106 Grendel Bh 13,000.00
107 Hak angin Bh 11,900.00
108 Klosed Duduk Bh 463,000.00
109 Kloset jongkok porselen Bh 137,300.00
110 Wastefel bh 450,000.00
111 Pipa PVC 1/2" m 25,800.00
112 Pipa PVC 3/4" m' 29,500.00
113 Pipa PVC D 3" m' 103,000.00
114 Pipa PVC D 4" m' 139,800.00
115 Kran air 1/2 " Bh 70,333.33
116 Kran air 3/4 " Bh 42,500.00
117 Seal tape Bh 3,400.00
118 Floor drain Bh 19,000.00
119 Air ltr 100.00
120 Minyak pelumas ltr 45,000.00
121 Minyak bekisting ltr 7,000.00
122 Print out lapis vinyl m2 20,000.00
123 Pintu KM PVC Bh 190,000.00
124 Pintu Kaka MD 82 x210 cm Bh 1,092,000.00
125 Pintu Board WPC 82 x210 cm Bh 1,250,000.00
126 Bahan tambahan kimia liter 60,000.00
127 Solar ltr 8,550.00
128 Sewa alat Las Jam 40,000.00
129 Profil pintu alumunium m 42,325.00
130 MSP (plesteran) kg 3,675.00
No. Nama / Jenis Bahan Satuan Harga Bahan
131 MSP (acian) kg 2,750.00
132 Keramik border 7,5x20 cm bh 3,000.00
133 Batu tempel hitam m2 120,000.00
134 Paving block 6 cm m2 55,000.00
135 Eternit 100x100 tebal 5mm m2 22,500.00
136 Soda api kg 10,000.00
137 Cat dasar kayu Kg 57,000.00
138 Pengencer Kg 28,000.00
139 Ampelas lbr 8,500.00
140 Politur ltr 54,000.00
141 Politur jadi ltr 54,000.00
142 Cat dasar tembok kg 23,600.00
143 hollow 4x4 galvanis m' 15,400.00
144 hollow 2x4 galvanis m' 11,200.00
145 hollow 5x5 galvanis m' 15,416.67
146 Lis siku aluminium 3 cm m 10,000.00
147 Holow aluminium 1" x 2" m' 11,700.00
148 Jendela alluminium casement 3 profil m' 46,000.00
149 Seng galvalum 0,3 lebar 90 cm m' 41,400.00
150 Seng galvalum 0,3 lebar 60 cm m' 33,500.00
151 Atap galvalum 2,68x1,00x0,4 m 45,000.00
152 Jarum keras Ø 16 mm bh 72,000.00
153 Besi Angkur Ø 16 mm bh 35,000.00
154 Mur baut HTB 12 bh 5,000.00
155 Mur baut Trektang HTB 10 bh 5,000.00
156 Grendel pintu kamar mandi bh 13,000.00
157 Alluminium strip M 32,000.00
158 Karet m 1,800.00
159 Spigot m 8,100.00
160 Beton alur m2 80,000.00
161 Granit Lokal 60 x 60 m2 126,000.00
162 Topi uskup bh 3,000.00
163 Kanstin (DT 21) K 300 bh 10,000.00

You might also like