New York State Department of Transportation

QUALITY CONTROL CHECKLIST


SIGNS
D#
CHECKBOX
Inspectors Equipment YES NO

Inspectors should have an engineers rule, 25' tape, measuring wheel, 100’ steel tape and a
clearance rod.

Preliminary Review YES NO

Review Contract Plans, Specs.and Standard Sheets for SIGNS (Sections 644, 645, 646 & 647).
Review Pay Items in Contract for SIGNS - (Overhead Structures, New Signs, Removals).
Study Tables in Plans for all sign removals and installations.
Determine locations in Plans and on Site for all signs. Look for obstructions, interferences, etc.

Review the NYSDOT Standard Sheets 645-01 thru 645-14 and 646-11 thru 646-16. You can
find the Standard Sheets on the "IntraDOT" page by clicking the "Site Index" tab and scrolling
down to "Standard Sheets- US Customary link.
Become familiar with; NYSDOT Standard Specification Sections 644 - OVERHEAD SIGN
STRUCTURES and 645 - SIGNS (Wind Load, Post Sizing and Bolt Torque tables)
Become familiar with the Federal MUTCD; This publication can be found through the IntraDot
site index by using the “MUTCD (Federal)” link.

Become familiar with the Standard Highway Signs (Supplement to the Federal MUTCD)This
publication can also be found through the IntraDot site index by using the “MUTCD (Federal)”
link.

Become familiar with the NYS supplemental; This publication can be found through the IntraDot
site index by using the “Construction Division (Gateway external site)” and clicking on the
“Connect with Office of Construction Internet page” this takes you to the “Engineering Division
Office of Construction page. Now click the “General Information, Guidance, Manuals and
Computer Applications” scroll to the bottom and click on “Manual of on Uniform Traffic Control
Devices (MUTCD)”.
Become familiar with the Steel Construction Manual This publication can be found through the
IntraDot site index by using the “Office Of Structures ” link.Choose "Manuals / Publications" and
click on the 'Steel Construction Manual".

Review the Reference Marker Manual; this publication can be found through the IntraDOT page
by choosing
Check the "SiteEngineering
for applicable Index" tab and selecting
Bulletins and"Refernce Markers"
Engineering Instructions. You can find the
Engineering Bulletins and Instructions by using the Intradot Site Index "Engineering Instructions
and Bulletins (EI’s and EB’s)" link.
The MURK Part 1B Construction Inspection Manual (C.I.M.) can be found by opening the
IntraDOT page, clicking on the “Site Index” tab and choosing “Construction Division (Gateway to
external site.)” and then Click on “General Information, Guidance, Manuals and Computer
Applications”.

Sign Related Computer Links YES NO


This SIGN Maps
GIS SIGN checkare
list available.
can be found by using
Contact Ruththe ProjectWise
VanPutten, Explorer
Regional GISapplication
Specialist found
at on your
desktop under the "Region 8 "tab choose the "Resource Information" Folder.Bus:845-431-5845,
Cell:607-238-9673 or by Email: Ruth.VanPutten@dot.ny.gov.
You can find guide rail information by using the IntradDot page and cnoosing the "Site Index#
tab and clicking on "GUIDE RAIL" .
You can find links related to guide rail information by using the IntradDot site index and .
Google Earth can be useful in obtaining field information. Keep in mind that Google Eearth data
may not always be current.

Materials - Overhead Sign Structures, Signs, Delineators and Removals YES NO

Review Material Specifications for Signs (Section 700).


Check with OE for Certifications and Testing of all Steel Components (644-2.01).
Anchor Bolts, Nuts and Washers (644-2.02C).
Hi-Strength Steel Bolts, Nuts and Washers (644-2.02D).
U-Bolts (644-2.02E).

The MURK Part2A Materials Inspection Manual (M.I.M.) can be found by opening the IntraDOT
page, clicking on the “Site Index” tab and choosing “Construction Division (Gateway to external
site.)” and then Click on “General Information, Guidance, Manuals and Computer Applications”.

Construction Details YES NO

Review the contract plans, proposal and ammendments.

If a crane is used for lifting, check for a valid crane operator's license and attach copy to DWR

Review Shop Drawings and check for acceptance by DOT (644-3.01).

Check for pole markings (Sign Structure ID No.) white on green 12" X 6"on Posts (644-3.01).

Check Hi-Strength Bolt tightening as per NYS Steel Constr.Manual, Table 1001.5b (644-3.02F).
Review Lifting Plan and check for acceptance by DOT (644-3.06C).
Conduct visual inspection of sign components (644-3.06D).
Check Anchor Bolt placement and tightening as per Table 644-2 (644-3.06E).
Check Type A posts in final location for number and strength as per Table 645-1 (645-3.03).
Check Type B posts in final location for number and strength as per Table 645-1 (645-3.04).

Check Type B breakaway bases and hinge assemblies as per Standard Sheets (645-3.04B).
Check sign panel installations for bearing pad separations to prevent corrosion (645-3.02).
Check installation interval for reference markers (161m =1/10th mile) (646-3.02). Verify locations
and offsets with the Project Design Manager
Check delineator installations for pad separations to prevent corrosion (646-2.06).
Inspect delineator installations during day for proper location, line and grade (646-3.04).
Inspect delineator installations during night for proper orientation and reflection (646-3.04).
Check that all concrete sign footings removed are cut to 1' below ground surface (647-3.03).
Check existing signs during relocation to prevent damage to panels (647-3.04).
NYSDOT

Revised: March 9, 2018