Professional Documents
Culture Documents
Key Considerations:: Hydropower Projects in Indonesia
Key Considerations:: Hydropower Projects in Indonesia
Considerations:
Hydropower Projects in Indonesia
Indonesia's ambitious promotion of renewable energy projects with an emphasis on hydropower has sparked
interest from local and international investors, developers and financiers. As of May 2020, the installed
hydropower plant capacity in Indonesia had reached 6.095 GW. It is targeted to reach 9.7 GW or around 17% of
national power generation in 20281. In a bid to further boost private investment, the government has issued
several regulations on renewable energy (including hydropower) and the parliament has finally passed the
Omnibus Law, which (among other things) seek to simplify and clarify procedures relating to licenses and
renewable tariff frameworks.
2
If the project is developed under the Public Private Partnership (PPP)
1
Based on PLN's 2019-2028 Electricity Supply Business Plan ("RUPTL"). scheme, the investment is open 100% for foreign ownership during the
concession period.
page 1
10 Key
Considerations:
Hydropower Projects in Indonesia
Direct Appointment vs Limited Tender MEMR Regulation 50/2017 sets a ceiling tariff on hydropower plants
where the electricity produced is sold to PLN. The same concept
The procurement of renewable projects by PLN is regulated in applies to other renewable power sources. Briefly, the ceiling tariff is
Minister of Energy and Mineral Resources ("MEMR") Regulation determined based on PLN's average cost of generation in a specific
No. 50 of 2017, as lastly amended by MEMR Regulation No. 4 of region (biaya pokok penyediaan pembangkitan or "BPP") in the
2020 on Utilization of Renewable Energy for Electricity Supply previous year, as follows:
("MEMR Regulation 50/2017").
a) If the local BPP is higher than the average national BPP, the
ceiling tariff is the amount of the local BPP.
For existing hydro projects for which an IPP obtained a location
permit before 26 February 2020, PLN can procure the projects by b) For projects in Sumatra, Java and Bali islands, or in other
way of direct appointment. In addition, as a general rule, PLN can local systems where the local BPP is equal to or lower than
also do direct appointment under certain conditions, including if the average national BPP, the tariff is determined based on
there is an electricity supply crisis in the local system, or if the mutual agreement between PLN and the seller.
project is an expansion of an existing project at the same location. The current national BPP is 7.86 USD cents/kWh, while the local
For hydro projects utilizing water resources from state assets BPP ranges from 6.91 USD cents/kWh to 21.34 USD cents/kWh.
(e.g., dams owned by the Ministry of Public Works and Housing),
The BPP figure reflects PLN's cost of generation, excluding
the developer will have to participate in the selection process transmission and distribution costs. The transmission costs (i.e.,
carried out by the government institution holding the asset, but the tariff component charged by IPP to PLN for the construction of
PLN then will no longer need to do any tender. In this case, the
transmission lines to connect the plant to PLN's existing grid) is
MEMR will assign PLN to buy electricity from the project. determined based on business to business negotiation.
3
Note, each consortium member will need to prequalify. required to obtain an AMDAL approval or to provide a statement letter
4
Under the Omnibus Law, an environmental permit (which was a undertaking to comply with the UKL-UPL standards before they can obtain
prerequisite to obtaining a business license) is removed as this will be a business license.
integrated in the business license. Consequently, companies are only
page 2
10 Key
Considerations:
Hydropower Projects in Indonesia
Government Guarantee
7 Run of River vs Peaker 8
Under MEMR Regulation 50/2017, electricity can be purchased Business Viability Guarantee Letters ("BVGL") are
from a hydropower plant that utilizes power from the available for certain projects that are listed in the
stream/waterfall of river water or one that utilizes power from Second Fast Track Program launched by the
dams/reservoirs or irrigation channels, whose construction is government in 2010. The Minister of Finance will
multipurpose. This may be known as a "conventional hydropower guarantee certain PLN payment obligations under
plant" or "run of river". the PPA. However, a number of projects under the Second Fast
Track Program have been successfully developed and have
However, Indonesia is also adopting the internationally obtained international project financing without BVGL.
recognized model of "peaking power plant" (or 'peakers') which
will operate during times of high demand of electricity. Commonly, A similar model of guarantee is also theoretically available for any
peakers are ramped up to 100% capacity as quickly as possible, IPP projects under Presidential Regulation No. 4 of 2016, as lastly
operated during high-demand periods, and then shut down. amended by Presidential Regulation No. 14 of 2017 on
However, recent trends have popularized peakers as the local Acceleration of Power Infrastructure Development. However, in
market attempts to shift to diversified renewable energy, in order the past five years, developers and international lenders have
to deal with intermittency issues. been willing to do IPP projects without asking for government
guarantees.
Categories
Sanctions
Failure to meet the local content requirements may result in
various administrative sanctions, including penalties and
blacklisting.
page 3