You are on page 1of 3

10 Key

Considerations:
Hydropower Projects in Indonesia

Indonesia's ambitious promotion of renewable energy projects with an emphasis on hydropower has sparked
interest from local and international investors, developers and financiers. As of May 2020, the installed
hydropower plant capacity in Indonesia had reached 6.095 GW. It is targeted to reach 9.7 GW or around 17% of
national power generation in 20281. In a bid to further boost private investment, the government has issued
several regulations on renewable energy (including hydropower) and the parliament has finally passed the
Omnibus Law, which (among other things) seek to simplify and clarify procedures relating to licenses and
renewable tariff frameworks.

Foreign Investment Pre-Feasibility Study ("Pre-FS")


1 Restrictions 3 and Feasibility Study ("FS")

The maximum foreign ownership thresholds for electricity


generation (including hydropower projects) in Indonesia vary
depending on the capacity of the power plant, as indicated below. A Pre-FS and FS are part of the "pre-development"
stage of a hydropower project (similar to other power
projects). The "pre-development" stage refers to the
Maximum foreign period before execution of the Letter of Intent ("LOI")
Capacity KBLI No. Ref.
ownership by PLN, which is done before the execution
of the PPA. As with other power projects, the right to develop a
Less than 1 MW Closed power plant is only secured when the PPA is executed by PLN
and the IPP. However, once the LOI is signed (i.e., after the
1 - 10 MW 35111 49% project developer is declared the winning bidder), the IPP will
have a document in writing stipulating PLN's intention to execute
the PPA with the IPP.
Above 10 MW 95%2
Indonesia's regulatory framework does not prescribe the types of
Please refer to our publication on Joint Venture Projects in activities that must be covered in a Pre-FS and FS. The
Indonesia for further details on foreign investment in Indonesia regulations are silent on the requirement for consents, permits or
more generally. licenses to be obtained for Pre-FS and FS. Instead, the
requirements should be assessed on a case-by-case basis,
depending on the types of activities within Pre-FS and FS that will
be carried out. For example, if the site survey shows that the

2 Licenses targeted project location is in a protected or production forest


area, an approval for forest area utilization (i.e., survey activities)
may be required.
In general, the main license required for Independent Power However, some licenses can only be obtained after the IPP has
Producers ("IPP") is an electricity supply business license (Izin passed certain steps and obtained other licenses as pre-requisite
Usaha Penyediaan Tenaga Listrik or "IUPTL"). An IPP must documents. One example is an IUPTL, which requires a copy of a
obtain an IUPTL for power generation in order to sell electricity to PPA and several documents (e.g., financial close document from
the state-owned utility PT Perusahaan Listrik Negara ("PLN"). PLN).
Specifically for hydro projects, an IPP is required to obtain a water
resources business permit and to pay the water charge to the
government.
One of the key licenses that a hydro IPP needs is the location
permit (izin lokasi), which gives its holder an exclusive right to
acquire land and develop the project at a certain location. Given
the site-specific nature of hydro projects, this is one of the first
licenses that an IPP will need to obtain in order to secure its
project, even at the pre-development stage.

2
If the project is developed under the Public Private Partnership (PPP)
1
Based on PLN's 2019-2028 Electricity Supply Business Plan ("RUPTL"). scheme, the investment is open 100% for foreign ownership during the
concession period.

page 1
10 Key
Considerations:
Hydropower Projects in Indonesia

4 Procurement Process 5 Tariffs

Direct Appointment vs Limited Tender MEMR Regulation 50/2017 sets a ceiling tariff on hydropower plants
where the electricity produced is sold to PLN. The same concept
The procurement of renewable projects by PLN is regulated in applies to other renewable power sources. Briefly, the ceiling tariff is
Minister of Energy and Mineral Resources ("MEMR") Regulation determined based on PLN's average cost of generation in a specific
No. 50 of 2017, as lastly amended by MEMR Regulation No. 4 of region (biaya pokok penyediaan pembangkitan or "BPP") in the
2020 on Utilization of Renewable Energy for Electricity Supply previous year, as follows:
("MEMR Regulation 50/2017").
a) If the local BPP is higher than the average national BPP, the
ceiling tariff is the amount of the local BPP.
For existing hydro projects for which an IPP obtained a location
permit before 26 February 2020, PLN can procure the projects by b) For projects in Sumatra, Java and Bali islands, or in other
way of direct appointment. In addition, as a general rule, PLN can local systems where the local BPP is equal to or lower than
also do direct appointment under certain conditions, including if the average national BPP, the tariff is determined based on
there is an electricity supply crisis in the local system, or if the mutual agreement between PLN and the seller.
project is an expansion of an existing project at the same location. The current national BPP is 7.86 USD cents/kWh, while the local
For hydro projects utilizing water resources from state assets BPP ranges from 6.91 USD cents/kWh to 21.34 USD cents/kWh.
(e.g., dams owned by the Ministry of Public Works and Housing),
The BPP figure reflects PLN's cost of generation, excluding
the developer will have to participate in the selection process transmission and distribution costs. The transmission costs (i.e.,
carried out by the government institution holding the asset, but the tariff component charged by IPP to PLN for the construction of
PLN then will no longer need to do any tender. In this case, the
transmission lines to connect the plant to PLN's existing grid) is
MEMR will assign PLN to buy electricity from the project. determined based on business to business negotiation.

Other than in the above circumstances, PLN will have to do direct


selection or limited tender to procure hydro projects. MEMR
Regulation 50/2017 requires a direct appointment process to be
completed within 90 days, and a direct selection process to be
completed within 180 days.

Mandatory Prequalification Process

Hydro developers need to be prequalified and shortlisted in PLN's


6 Environmental Considerations
list of selected developers (daftar penyedia terseleksi or "DPT").
The general perception is that hydropower plants are cleaner than
Only developers that have been included in the DPT can
coal-sourced power generation. However, the environmental
participate in PLN's procurement process. Since 2017, PLN has
impact can be significant and there are material environmental
carried out two rounds of DPT process for hydro developers.
concerns in relation to the implementation of hydro power plants,
Specifically for the hydro DPT process, as well as the developers
e.g., large land area required, safety of fish and other biota in the
(who can be in a consortium3) having to prequalify, the specific
water. Therefore, certain companies operating in Indonesia
project (which already has a feasibility study) has to prequalify.
(including IPPs) are required by the prevailing laws and
This is slightly different from the DPT process for non-hydro
regulations to observe key obligations with respect to
developers, where each company must individually prove its
environmental protection and management, including by
financial and technical capability in order to pass the DPT
preparing an environmental impact study (AMDAL or UKL-UPL) in
process.
order to obtain a business license (i.e., IUPTL).4
Export credit agencies, multilateral lenders and development
finance institutions will also typically require environmental
reporting and compliance obligations that are up to international
standards, as a condition to financing. Likewise, investors and
lenders, under pressure from shareholders to deliver more
sustainable investments, will require greater accountability and
transparency with regard to environmental and sustainability
studies.

3
Note, each consortium member will need to prequalify. required to obtain an AMDAL approval or to provide a statement letter
4
Under the Omnibus Law, an environmental permit (which was a undertaking to comply with the UKL-UPL standards before they can obtain
prerequisite to obtaining a business license) is removed as this will be a business license.
integrated in the business license. Consequently, companies are only

page 2
10 Key
Considerations:
Hydropower Projects in Indonesia

Government Guarantee
7 Run of River vs Peaker 8
Under MEMR Regulation 50/2017, electricity can be purchased Business Viability Guarantee Letters ("BVGL") are
from a hydropower plant that utilizes power from the available for certain projects that are listed in the
stream/waterfall of river water or one that utilizes power from Second Fast Track Program launched by the
dams/reservoirs or irrigation channels, whose construction is government in 2010. The Minister of Finance will
multipurpose. This may be known as a "conventional hydropower guarantee certain PLN payment obligations under
plant" or "run of river". the PPA. However, a number of projects under the Second Fast
Track Program have been successfully developed and have
However, Indonesia is also adopting the internationally obtained international project financing without BVGL.
recognized model of "peaking power plant" (or 'peakers') which
will operate during times of high demand of electricity. Commonly, A similar model of guarantee is also theoretically available for any
peakers are ramped up to 100% capacity as quickly as possible, IPP projects under Presidential Regulation No. 4 of 2016, as lastly
operated during high-demand periods, and then shut down. amended by Presidential Regulation No. 14 of 2017 on
However, recent trends have popularized peakers as the local Acceleration of Power Infrastructure Development. However, in
market attempts to shift to diversified renewable energy, in order the past five years, developers and international lenders have
to deal with intermittency issues. been willing to do IPP projects without asking for government
guarantees.

9 Local Content Requirements

Categories

The Electricity Law and its implementing regulations require that


electricity business services prioritize the use of local content.
This requirement is intended to maximize the utilization of local
content in the construction of electricity infrastructure for public
use. 10 Future prospects
Minister of Industry Regulation No. 54/M-IND/PER/3/2012 on
Guidelines on Use of Local Content for the Construction of
Electricity Infrastructure, as amended by Minister of Industry Based on PLN's 2019-2028 RUPTL, there will be an additional
Regulation No. 05/M-IND/PER/2/2017, regulates specific local 56.395 GW of power plants installed in the period from 2019 to
content provisions for a non-storage pump hydropower plant – 2028, whereby a total of 9.7 GW or 17.2% of the total target is
these content requirements apply to three categories: goods, projected to be taken up by hydropower plants. Indonesia has
services, and goods and services combined. The initial also set a target that 23% of the country's energy mix should be
assessment of whether the requirement for local content for a from renewable sources by 2025.
hydropower plant has been fulfilled is conducted by the
goods/services provider (i.e., by way of self-assessment). Since mid-2019, the government has been preparing a draft
presidential regulation on procurement of renewable energy by
Procurement of Imported Goods PLN. One of the changes expected in the presidential regulation
is from a BPP-based tariff to a feed-in-tariff and a ceiling tariff
MOI Regulation 54/2012 allows the procurement of imported without any tie-in to PLN's BPP. It is expected that a feed-in-tariff
goods only in the following circumstances: will only be available for smaller scale projects. The draft
a) The goods cannot yet be produced in Indonesia. regulation is still under discussion and should be issued in the
near future. Once issued, we expect that MEMR Regulation
b) Technical specifications of domestically produced goods 50/2017 will be amended to conform with the presidential
do not meet the requirements. regulation.
c) The quantity of domestic production is insufficient to fulfil the
need.

Sanctions
Failure to meet the local content requirements may result in
various administrative sanctions, including penalties and
blacklisting.

page 3

You might also like