Professional Documents
Culture Documents
180. SAGS Work Scope Requirements regarding the SAGS Work set forth in this
Agreement, Sections 1 to 5 and 7 to 18 of Exhibit A
(except those portions expressly identified within such
Sections as applying to the Plant Work Scope), Exhibit AD
(except those portions expressly identified within such
Parts as applying to the Plant Work Scope), as such
requirements may be changed from time to time in
accordance with Article 4.9.
181. Scoping Estimate A detailed written scope of work and an estimate relating
to a contemplated change in the Work, including:
(a) the proposed change in the Contract Price
(including a breakdown of the proposed change
in the Offshore Portion or the Onshore Portion, if
any) resulting from such change (computed in
accordance with Section 4.9.6) and a detailed
presentation of the computation of such
proposed change in the Contract Price;
(b) the effect such change could be expected to have
on the Project Schedule, the Project Milestone
Payment Schedule or any other Exhibit or
schedule;
(c) the proposed change in any Project Deadline
made necessary by such change (computed in
accordance with Section 4.9.7); and
(d) the potential effect of such change on
Contractor's ability to comply with any of its
obligations hereunder, including, without
limitation, warranties and the Performance
Guarantees and the Emissions Guarantees.
182. Scoping Letter The term Scoping Letter shall have the meaning set forth
in Section 4.9.4.4
183. Second Bond The term Second Bond shall have the meaning set forth in
Section 4.5.2.
184. Steam Usage The term Steam Usage shall have the meaning set forth in
Section 10.8 of Exhibit AE.
185. Steam Rate The term Steam Rate shall have the meaning given such
term in Section 10.8 of Exhibit AE.
186. Steamfield That portion of the Job Site where the SAGS is to be
constructed and where Wells are located.
205. Warranty Period With respect to each item constituting a portion of Work,
the period commencing at 12:01 a.m. local time on the
first (1st) day following the Performance Test Completion
Date or the Deemed Final Completion Date and
terminating:
(a) in the case of SAGS Equipment and SAGS Work,
sixty five (65) Weeks after the Final Completion
Date or Deemed Final Completion Date, as the
case may be, as modified by Section 4.18 2.6; and
(b) in the case of Plant Equipment and Plant Work,
sixty five (65) Weeks after the Final Completion
Date or Deemed Final Completion Date, as the
case may be, as modified by Section 4.18.2.6.
206. Wayang Windu Power The Wayang Windu geothermal power development
Development located in West Java comprising:
(a) Wayang Windu Phase 1;
(b) the Plant, as specified in the Plant Work Scope,
and SAGS as specified in the SAGS Work Scope;
(c) the Wells and associated civil works.
207. Wayang Windu Phase 1 Existing Wayang Windu geothermal power development,
comprising Unit 1 and associated wells, steamfield above
ground system, power station building and switchyard,
together with all supporting plant structures, facilities,
interconnections and works for the generation of electric
outputs from Unit 1 and transmission to the point of
interconnection with the PLN system.
208. Wayang Windu Phase 2 The second generating unit at the Wayang Windu Power
Development, comprising Plant, SAGS, Wells and
supporting facilities, improvements and works necessary
to generate and transmit electric outputs to the point of
Electrical Interconnection.
1.2 INTERPRETATION
In the Agreement:
(a) the words "include" and "including" are to be construed without limitation;
(b) any reference to a "person" shall be construed as including reference to any individual,
corporation, firm, partnership, joint venture, association, organization, trust or Public
Sector Entity (in each case whether or not having separate legal personality);
(d) references to contracts, agreements and instruments concluded between Owner, MNL and
any other person shall be treated as including reference to such contracts, agreements or
instruments as amended, supplemented, substituted, novated or assigned from time to
time;
(e) any reference to: "day" means a calendar day (including Saturday, Sunday and holidays); a
"week" means any period of seven days; a "month" means a calendar month of the
Gregorian Calendar; a “Business Day" means any day other than:
i. Saturday or Sunday; or
ii. a day on which banking institutions in Singapore, Jakarta or New York are authorized
or obligated by law or executive order to remain closed;
(f) the headings titles and references thereto in the Contract Documents are included for ease
of reference and shall not constitute a part of the Contract, nor affect its interpretation;
(g) unless inconsistent with any other provision of the Contract, the meaning of any term or
abbreviation used in the Contract relating to the sale and carriage of goods is defined by
the 2000 edition of the "Incoterms". International rules for the interpretation of trade
terms published by the International Chamber of Commerce shall be as so defined and the
rights and obligations of the Parties in respect of the relevant matter, shall be as so
ascribed; and
Contractor shall procure that all Subcontractors in Exhibit R shall include a term in their
respective
subcontracts with Contractor allowing Owner to purchase direct from a Subcontractor the said
recommended
spare parts.
4.12.2 Availability of Spare Parts.
Contractor agrees to use good faith efforts to include in each subcontract and purchase order
relating to any item of the Equipment or other component of the Project a requirement that
the Subcontractor notify Contractor and Owner in the event Subcontractor intends to
discontinue supplying any functional spare parts and permit Owner to order any quantity of any
of such parts at the prices therefor prevailing prior to such discontinuance of supply.
4.13.1.2 Functional Tests. Contractor shall perform the Functional Tests in accordance with
Section 10.5 of Exhibit AE only after all of the following conditions have been satisfied:
(a) Contractor has met all the requirements of Section 2.2.1 and submitted the certificate
required by Section 2.2.1.1;
(b) Contractor has met all the requirements of Section 3.2.1 and submitted the certificate
required by Section 3.2.1.1;
(c) Owner has approved or been deemed to approve the Functional Test Procedures; and
(d) Contractor has provided the corresponding turnover submittal(s) to Owner as required by
Parts 1 and 2 of Exhibit T.
SCHEDULE OF MAJOR SUBCONTRACTORS
Part 1 - SAGS
Note: All parameters shall be at the design point conditions in Exhibit AE - Section 2, unless
otherwise stated
1.2.2 SAGS
1.2.2.1 General
This SAGS Work Scope includes the detailed engineering, procurement, construction,
commissioning and testing of Steamfield Above Ground System (SAGS) to collect fluid
from geothermal production wells, separate any water phase, transport the resultant
steam to the Power Station and dispose of brine, all in accordance with the conceptual
and preliminary design and minimum requirements of the SAGS as provided by the
Owner and described in this Technical Specification.
The Contractor shall study and check the existing installation for pipeline, electrical
power cables and control cables and earthing conductors to be considered in their
design. The modification or relocation of existing installation shall be the Contractor's
responsibility. Contractor shall locate all existing 6.3 kV cabling and earthing conductors
before commencing earthworks.
3.4.1 Materials
The stone for masonry lined walls, lined drains and other work shall consist of clean,
hard durable stone (batu belah) of 75 mm to 200 mm size.
The cement mortar shall consist of 1 part of cement to 3 parts of sand with the
minimum amount of water required to obtain workability. The proportions of the
mortar shall be measured in proper gauge boxes.
3.4.2 Construction
The masonry work shall be constructed with tightly-packed, well-bonded stone to the
best standard of workmanship.
Contractor shall provide drainage from behind all masonry walls by means of 40 mm
PVC or bamboo pipes spaced at 1.0 m centres vertically and horizontally.
Backfilling behind masonry walls shall be carried out in thin layers using light
compaction equipment and taking care to avoid overstressing or displacing the wall.
SECTION 4
SAGS PROCESS DESIGN
TABLE OF CONTENT
TABLE OF CONTENT
SECTION 8
DISTRIBUTED CONTROL SYSTEM
TABLE OF CONTENT