Professional Documents
Culture Documents
Purpose:
Study of Single Busbar Scheme with respect to Main-Transfer scheme in perspective of Gas Insulated
Switchgear.
For the study the Substation is considered with One (1) no. of 220kV Evacuation line, two (2) nos. of
Transformer bays.
The comparisons are done at equipment level, as we compare the operation mechanism and inherent
characteristics of each physical character of equipment to understand differences.
1. Circuit Breaker:
The internal arc-quenching/interrupter (puffer type) mechanism of AIS and GIS breakers are both
fundamentally same. Hence, the reliability of Breaker may be considered same except environmental
faults due to rain water etc. on AIS bushings.
Line Bay
Line Bay
In M+T scheme, any of the feeder CB can be taken into maintenance without shutdown of power flow and
thus, M+T scheme is more reliable than SB scheme. However, since the M+T scheme implementation includes
additional 1 Isolator per bay, addition of Bus Transfer /Bus Coupler Bay the cost of M+T scheme is higher than
BC Bay
SB scheme.
The M+T scheme also provides higher flexibility to the operator to adjust Main Busbar load, by shifting some
load on the transfer bus. This flexibility is not applicable with busbars without sectionalizer and hence, not
applicable for our case.
Trafo Bay Trafo Bay
Considerations:
As OHL travels through different geography and areas, the probability of fault on the lines are comparatively
high. It may be noted that 80-90% of line faults are temporary L-G faults and self-clearing in nature. Only 10-
20% faults are Permanent faults which requires maintenance/replacements such as insulator flash-over and
conductor break etc. As per statistics majority of faults in lines are likely to occur during rainy seasons.
Hence, it can be safely concluded that probability of line faults requiring maintenance is around 3-5%
considering a 12 months cycle.
As OHL are beyond the scope of the substation and probability of major fault is less hence lines are not
considered as part of Substation bus configuration study.
Un-interrupted power evacuation cannot be achieved during break down / fault at Line Circuit Breaker, as no
option for Transfer of the line CB function is available in SB scheme. This short coming can be over come by the
M+T scheme.
In SB scheme, future expansion (if any) needs to be envisaged at present, as there will not be any flexibility of
load shifting between the buses as available in M+T scheme.
As discussed above in section “AIS vs GIS equipment”, the Circuit Breaker interrupter designs for AIS CB and
GIS CB are fundamentally same and hence, probability of fault occurrence in CB of both AIS/GIS are same.
Thus, although GIS system is a high reliability system at main switching equipment (CB) level the reliability is
almost same without any added advantage.
It must also be noted that GIS CB pole/interrupter removal for maintenance can only be undertaken by skilled
workers certified by OEM. Hence, fault detected on CB - Call raised to OEM – CB Pole change / Maintenance
complete, this cycle may take more than 2-4 days. In contrast in a AIS system, the CB pole removal can be
done by Substation OEM personnel within 2-3 hours if the spare is available.
Conclusion:
Based on above considerations it can be concluded that whether a GIS or AIS is implemented, Main and
Transfer scheme is a recommended scheme for a power evacuation switchyard of a Generation system as
down time would lead to loss of revenue.