Professional Documents
Culture Documents
INSTALLATION
VIGERSLEV ALLÉ 77 - 2500 VALBY - DENMARK 2040 AVENUE C - PA 18017-2188 BETHLEHEM – USA CAPITAL TOWERS 180. KODAMBAKKAM HIGH ROAD, NUNGAMBAKKAM,- CHENNAI 600 034 - INDIA
2 70000393-1
CONTENTS: PAGE:
APPENDICES:
Installation procedure V
4 70000393-1
Note!
The present instruction manual is concerned with the situations
which, according to the experience of FLS, are the most likely to
occur. An exhaustive enumeration of all conceivable situations
which may occur during the installation, operation and
maintenance of the lining cannot be provided.
1. GENERAL NOTES
The DucroBar lining for the fine-grinding compartment of ball mills is a
semi-boltless lining, the primary purpose of which is to protect the mill
shell against wear and, due to the shape of the lining, to enhance the
grinding efficiency of the mill.
The lining which is made of cast iron with a high chromium content is
extremely wear-resistant, but its impact strength characteristics are
limited due to the high hardness level. For this reason, it is of
paramount importance to ensure that these relatively brittle lining
plates are handled with extreme care in connection with the handling
and installation at site. The lining plates must never be thrown about
or thrown randomly onto a pile atop one another since pressures
resulting from impacting and stress loading may result in breakage of
the plates. This applies particularly to the long and relatively thin bars.
Furthermore, the lining plates must never be subjected to bending
stresses while tightening of the bolts is being carried out.
However, if properly handled and installed the DucroBar lining will
normally have a long service life in comparison with most other types
of linings and materials.
Any minor cracks incurred by the lining plates due to rough handling
may cause the lining plates to crack during operation, resulting in
dislodgement (drop-out) of the plates. This will lead to a situation
where the heavy lining fragments will inflict damage to the remaining
lining plates, and the unprotected mill shell will be subjected to wear
exposure/damage.
70000393-1 5
Fixation of the rods at the diaphragm and outlet grate can be done in
different ways, dependent upon the design of the mill. Appendix III
shows different methods. Fig. A and B are the methods most
commonly used for modern UMS-mills. Reference is made to the
specific erection drawing for the method applied in the specific case.
3. INSTALLATION
SAFETY!
In order to provide a safe working environment for the erection
personnel, it is essential to ensure – regardless of the method
of erection – that stable scaffolding and platforms with railing are
provided around the worksite throughout the erection process.
In connection with the performance of any activities in, on
or under the mill, the main motor, the auxiliary drive or any
other temporary drive mechanism MUST be de-energized
through switching-off and lockout of the high-voltage
circuit breaker. It must only be possible for the supervisor
in charge of operations to cancel the lockout.
Locked safety guards etc. must always be fitted around
rotating parts such as auxiliary drive or any other
temporary drive mechanism.
IMPORTANT!
Extreme care is needed when handling and installing the
heavy mill parts in order to avoid a situation where such
parts are dumped or dropped onto the unprotected mill
shell and the slide rings. Indentation marks on the
dynamically stressed mill body is liable to give rise to
crack formations at subsequent point in time.
8 70000393-1
The bolted-on type of retaining ring (13) at the outlet head (Fig. F) is
often mounted on the supporting plate of the outlet grate by means of
T-head bolts (17). First, these bolts are placed in the hole of the
retaining ring, and the retaining ring can then be mounted using a
special tool attached to the bolt end, turning/pulling the T-head bolt to
its proper position on the supporting plate. The notch in the threaded
end of the bolt indicates the direction on the bolt head. It is very
important to ensure that the bolt head is correctly
positioned relative to the hole in the supporting plate,
i.e. at right angles to the hole, since, otherwise, the
retaining ring will fall off.
3.6 Installation of lining. First third.
With the manhole at the outlet end in lowermost position, the operation
is started by mounting the lining rods (03) in the belt section nearest
the outlet grate by pushing the rods under the lining plate (12) at the
outlet slide ring (UMS-mills). The rods must be absolutely parallel to
the mill axis. Gradually as the rods are fitted, the bolted-on retaining
ring segments (01,02) must be mounted at the other end of the rods.
The individual retaining ring segments must be centered exactly above
the bolt holes in the mill shell and must be flush in the circumferential
direction. Mount, wherever possible, the supplied angle irons,
25x25x3, in the recesses at the end of the retainer ring segments. This
must be done to prevent excessive movements of the segments during
operation. DO NOT FORGET to check constantly the axial clearance
of the rods. If the clearance is more than 4mm, the supplied 70° angle
irons (04) must be fitted in the recess at one end of the rods. If the
clearance is still more than 4mm, it will be necessary to tack-weld a
thin plate to the angle iron in order to reduce the clearance as much
as possible. If the rod cannot be accommodated due to inadequate
space, i.e. if the rod is too long or if the distance between the last row
of bolts and the outlet slide ring is too short, it will be necessary to
grind off - exercising due caution - some of the 5mm high crusts at one
end of the rod.
NOTE! Orientation of classifying retaining rings to be
such that the oblique face is pointing towards the mill
inlet. See Appendix II and separate erection drawing.
Lining plates are mounted on about one-third of the circumference
(Fig. A in Appendix V). The bolts for the retaining ring must be
provided with sealing discs (07). On older mills, the size of the bolt
holes in the mill shell may be larger than actually required, and in such
cases a combined guide bushing and sealing disc must be used (see
separate erection drawing).
14 70000393-1
Bolts must not be inserted in the retaining ring segments at the ends
of the mounted area since these bolt holes must be used for the
bolting-on of erection irons (20) for retention of the rods (03) when the
mill is turned.
In the second-but-last belt section before the outlet head, rods (03)
and retaining ring segments (01,02) must also be mounted on about
one-third of the circumference.
The lining plates (08) must be mounted on each side of the manhole in
the belt section with manhole. The plates must be mounted so that
they are absolutely parallel to the axis, and the bolts must be equipped
with sealing discs (07).
The erection irons (20) must be mounted so that the pressure screws
(21) force the rods together, preventing them from being dislocated or
falling out when the mill is turned (see Appendices IV and V as well as
separate erection drawing for application of erection irons).
3.7 Installation of lining. Second third.
The mill must now be turned through 1/3 revolution. DO NOT
FORGET the lubrication of bearings! There must never be
any persons or heavy parts in or on the mill while the mill is being
turned. The lining parts for the next one-third of the mill circumference
in the two belt sections nearest the outlet end must be mounted as
described in sub-section 3.6, again terminating the operation by
means of erection irons (20). See Fig. B in Appendix V.
ERECTION CHECK
3.8 Installation of lining. Last third.
Again, the mill must be turned 1/3 revolution so that the last unlined
part of mill shell is now facing downwards. See Fig. C in Appendix V.
The rods (03) must be fitted in their proper positions, with the
exception of the last rod. The entire lining section must be forced
lightly together, using the small jack – included in the supply – placed
in the last opening. Place a steel plate between jack and rods in order
to distribute the pressure exerted on the rods. Then determine the
exact distance between the contact faces of the rods. If the distance is
more than 235mm, a three-wave rod (25) must be used along with
intermediate plates (05) in order to fill out the last gap. If there is
inadequate space to accommodate the three-wave rod, a normal rod
should be used along with intermediate plates (05) for filling out the
gap. Simultaneously with the measuring of the distance, it must also
be checked that the distance is the same across the two sets of
contact faces, i.e. whether the rods are positioned in parallel. If not,
compensation is needed by welding on a thin plate at one end of one
or several intermediate plates.
70000393-1 15
4. OPERATION
Prior to grinding media being charged to the fine-grinding
compartment, it must be checked that the lining has been installed in
correct manner, that all bolts have been tightened to the specified
torque level, and that all erection tools and other items used during the
installation procedure have been removed from the mill. Presence
of heavy foreign objects in the mill may lead to the
destruction of the lining after a short period of
operation.
ERECTION CHECK
Close all manholes, except one manhole which must be placed in top
position; this manhole must be used for the charging the grinding
media. Do not charge all the balls through the same manhole, but
distribute the grinding balls to both ends of the compartment. Do not
forget to mount the manhole covers (09) with the supplied rubber
packings. The tightening torque for the bolts for covers, M42x3: 1200
Nm
The compartment must be filled with the specified quantity of grinding
media. The full quantity of grinding balls is not normally charged into
new mills at the initial stage. Hence it will be possible to adjust the
composition of balls during the running-in of the mill. To safeguard the
mill gear unit, the mill must not under normal circumstances be
operated at less than 80% of its installed power.
70000393-1 17
5. MAINTENANCE
Alter all lining bolts have been re-tightened until the specified torque
level remains constant, the lining does not require any particular
maintenance. However, the lining plates must be checked, on a
regular monthly basis, for wear, cracks and dislodgement. The
wear, or the residual thickness, on the single lining patterns must be
measured and recorded on an ongoing basis to allow an assessment
of the residual service life to be made, so that a new lining can be
ordered at an early stage. In principle, the lining can be used up to the
point of lining breakage or wear-through occurring. In case of lining
plate breakage and if a part of the plate has dropped out, it is of the
utmost importance to locate the fragments in the charge load;
otherwise such fragments will damage the other lining plates in the
compartment. Furthermore, the unprotected zone of the mill body will
be subjected to wear exposure/damage, involving risk of subsequent
crack formations. So, gradually as the lining parts are being worn
down, the inspection intervals should be narrowed or the lining should
be replaced before the mill body sustains damage.
For a full-scale inspection of the entire lining to be conducted, it will be
necessary to close the mill and to turn it through 180º in order to
inspect that part of the lining which was previously hidden under the
charge load in the mill.
Dismantling of worn lining parts.
The bolt head in the worn-out lining plates will normally be deformed to
such an extent that it will not be possible to dismantle the bolts from
the plates in normal manner. Since the bolts cannot be re-used, we
would recommend that the nut is screwed off, with subsequent
removal of the entire lining plates with the embedded bolt.
70000393-1 19
6. APPENDICES
Appendix I
01 Retaining ring, standard corrugated lining
03 Boltless lining plate (rod)
04 70 o angle iron
05 Intermediate
06 25x25x3 mm angle iron
07 Sealing discs
08 Lining plates at manhole
09 Manhole cover
70000393-1 21
I
22 70000393-1
Appendix II
02 Retaining ring, classifying lining
03 Boltless lining plate (rod)
04 70 o angle
05 Intermediate
06 25x25x3 mm angle iron
07 Sealing discs
08 Lining plate at manhole
09 Manhole cover
70000393-1 23
II
24 70000393-1
Appendix III
III
26 70000393-1
Appendix IV
01 Retaining ring
03 Boltless lining plate (rod)
20 Erection iron
21 Pressure screw
22 Jack
70000393-1 27
IV
28 70000393-1
Appendix V
05 Intermediate
25 boltless lining plate with three-wave pattern (rod)
70000393-1 29