You are on page 1of 76

Work front availability Mechanical and Electrical

Date: 27-Feb-22 Date


SN Location WBS1 Activity Civil Handover
1 AST-1 AST-1 Diffuser Gid Air test Ready available
AST-1 Header Installation Ready available
AST-1 Header Air testing Ready available
AST-1 Gate Side bracket and drive installation Ready available
AST-1 Gate Water leak test Ready available
2 RAS 1 RAS 1 RAS pipe and Pump installation 17-Oct-17
RAS 1 Mono rail Installation After Pump installation
RAS 1 Internal SS piping and valve installation Ready available
RAS 1 Gate Water leak test After Pump installation
3 SST Zone 1 SST Zone 1 Final competion for walk thru Ready available
4 DC 1 DC 1 Gate shaft and drive installation Ready available
DC 1 Gate Water leak test Ready available
5 AST-2 AST-2 Diffuser Gid Air test Ready available
AST-2 MLR Pump Installation Ready available
AST-2 Header Installation Ready available
AST-2 Header Air testing Ready available
AST-2 Gate Side bracket and drive installation Ready available
AST-2 Davit Installation Ready available
AST-2 Gate Water leak test Ready available
6 RAS 2 RAS 2 RAS Pump installation 15-Nov-21
RAS 2 Penstock Installation Ready available
RAS 2 Mono rail Installation After Pump installation
RAS 2 SAS Pump Installation 05-Nov-21
RAS 2 Internal SS piping and valve installation 05-Nov-21
RAS 2 Gate Water leak test After Pump installation
7 SST Zone 2 SST Zone 2 SST 7 Scrapper bridge Installation Ready available
SST Zone 2 SST 7 weir plate installation 30-Oct-21
SST Zone 2 SST 5 Scrapper bridge Installation Ready available
SST Zone 2 SST 5 weir plate installation 10-Nov-21
SST Zone 2 SST 6 Scrapper bridge Installation 21-Oct-21
SST Zone 2 SST 6 weir plate installation 15-Nov-21
SST Zone 2 SST 8 Scrapper bridge Installation 30-Oct-21
SST Zone 2 SST 8 weir plate installation 20-Nov-21
8 SPS 2 SPS 2 Internal SS piping and valve installation Ready available
9 DC 2 DC 2 Gate Installation 30-Oct-21
DC 2 Gate shaft and drive installation After gate installation
DC 2 Gate Water leak test After installation
6 AST-3 AST-3 Installation of Mixers 20-Oct-21
AST-3 Installation of MLR pumps Ready available
AST-3 Gate grouting Ready available
AST-3 South tank diffuser installation Ready available
AST-3 North tank diffuser installation Ready available
AST-3 Branch header installation Ready available
AST-3 Diffuser Gid Air test Ready available
AST-3 Header Installation Ready available
AST-3 Header Air testing Ready available
AST-3 Davit Installation Ready available
AST-3 Gate Water leak test Ready available
6 RAS 3 RAS 3 RAS Pump installation 10-Nov-21
RAS 3 Mono rail Installation After Pump installation
RAS 3 SAS Pump Installation 30-Oct-21
RAS 3 Internal SS piping and valve installation 30-Oct-21
RAS 3 Gate Water leak test After Pump installation
7 SST Zone 3 SST Zone 3 SST 12 weir plate completion Ready available
SST Zone 3 SST 10 weir plate completion -----------

Final survey Ready available


SST Zone 3
SST Zone 3 Final competion for walk thru Ready available
8 SPS 3 SPS 3 Internal SS piping and valve installation Ready available
9 DC 3 DC 3 Gate Installation 17-Nov-21
DC 3 Gate shaft and drive installation After gate installation
DC 3 Gate Water leak test After gate installation
10 ES 7 ES 7 Penstock Installation 28-Oct-21
ES 7 Shaft and drive installation After gate installation
ES 7 Grouting After gate installation
11 RSF RSF Stop log installation North 1 No Ready available
RSF Stop log installation South 3 Nos Ready available
RSF Blower room SS piping Ready available
RSF Pipe gallery piping 02-Nov-21
RSF Drain Pump installation 18-Oct-21
RSF Stop log grouting 10 Nos Ready available
RSF North side penstock grouting Ready available
12 CCT CCT Gallery penstock shaft and drive installation Ready available
CCT Penstock grouting Ready available
14 CDS CDS Scrubber stack installation Ready available
CDS Recirculation Pump and piping works Ready available
CDS Final completion for walk thru Ready available
15 TSE PS TSE PS EOT crane beam installation 20-Oct-21
TSE PS Booster pump installation Ready available
TSE PS Service water pump installation Ready available
TSE PS Drain Pump installation 05-Nov-21
TSE PS TSE pump final alignment Ready available
TSE PS TSE pump grouting Ready available
TSE PS SS piping works 10-Nov-21
16 TOS TOS Penstock grouting Ready available
TOS Stoplog installation Ready available
TOS Screen installation Ready available
TOS Pump installation 19-Oct-21
TOS SS piping and valve works After Pump installation
17 OCU 1 OCU 1 Pump installation Ready available
OCU 1 Interconnecting piping works Ready available
OCU 1 GRP pipe supports Ready available
OCU 1 Blower installation Ready available
18 OCU 2 OCU 2 Pump installation Ready available
OCU 2 Interconnecting piping works Ready available
OCU 2 GRP pipe supports Ready available
OCU 2 Blower installation Ready available
19 Blower building Blower building Blower enclosure installation Ready available
Blower building blower SS piping works 28-Oct-21
20 Dewatering building Dewatering buildiSS piping works Ready available
21 Inlet splitter boxx Inlet splitter boxx Penstock Installation 26-Oct-21
Inlet splitter boxx Stop log installation 26-Oct-21
22 Inlet chamber Inlet chamber Penstock Installation 12-Nov-21
Inlet chamber Stop log installation 12-Nov-21
Inlet chamber Crane beam installation 12-Nov-21
Inlet chamber Launder installation 12-Nov-21
Inlet chamber Conveyor installation 12-Nov-21
Inlet chamber SS piping works 20-Nov-21
23 Grit and grease chamber Grit and grease Penstock Installation 12-Nov-21
Grit and grease Scraper installation 12-Nov-21
Grit and grease Classifier Installation 12-Nov-21
Grit and grease Pump installation 12-Nov-21
24 PDPS PDPS Pump installation 22-Oct-21
PDPS Mixer installation 22-Oct-21
PDPS Davit Installation 22-Oct-21
l and Electrical
Date FLOAT
Start Finish Start Finish Issue/Remarks
17-Oct-21 27-Oct-21 (133) (123)
23-Oct-21 29-Oct-21 (127) (121)
30-Oct-21 06-Nov-21 (120) (113)
16-Oct-21 17-Oct-21 (134) (133)
23-Oct-21 27-Oct-21 (127) (123)
20-Oct-21 22-Oct-21 (130) (128)
23-Oct-21 25-Oct-21 (127) (125)
16-Oct-21 19-Oct-21 (134) (131)
23-Oct-21 27-Oct-21 (127) (123)
10-Oct-21 17-Oct-21 (140) (133)
completed
completed
28-Oct-21 07-Nov-21 (122) (112)
Completed
30-Oct-21 05-Nov-21 (120) (114)
06-Nov-21 11-Nov-21 (113) (108)
18-Oct-21 19-Oct-21 (132) (131)
On hold
18-Oct-21 21-Oct-21 (132) (129)
17-Nov-21 20-Nov-21 (102) (99)
13-Oct-21 18-Oct-21 (137) (132)
21-Nov-21 24-Nov-21 (98) (95)
12-Nov-21 15-Nov-21 (107) (104)
16-Nov-21 21-Nov-21 (103) (98)
21-Nov-21 24-Nov-21 (98) (95)
07-Oct-21 22-Oct-21 (143) (128)
02-Nov-21 09-Nov-21 (117) (110)
12-Oct-21 27-Oct-21 (138) (123)
10-Nov-21 17-Nov-21 (109) (102)
25-Oct-21 09-Nov-21 (125) (110)
18-Nov-21 25-Nov-21 (101) (94)
03-Nov-21 18-Nov-21 (116) (101)
26-Nov-21 03-Dec-21 (93) (86)
12-Oct-21 19-Oct-21 (138) (131)
05-Nov-21 13-Nov-21 (114) (106)
14-Nov-21 18-Nov-21 (105) (101)
19-Nov-21 22-Nov-21 (100) (97)
23-Oct-21 27-Oct-21 (127) (123)
21-Oct-21 25-Oct-21 (129) (125)
17-Oct-21 20-Oct-21 (133) (130)
08-Oct-21 26-Oct-21 (142) (124)
17-Oct-21 04-Nov-21 (133) (115)
20-Oct-21 28-Oct-21 (130) (122)
29-Oct-21 05-Nov-21 (121) (114)
06-Nov-21 12-Nov-21 (113) (107)
13-Nov-21 18-Nov-21 (106) (101)
On hold
24-Oct-21 28-Oct-21 (126) (122)
12-Nov-21 15-Nov-21 (107) (104)
16-Nov-21 20-Nov-21 (103) (99)
02-Nov-21 05-Nov-21 (117) (114)
06-Nov-21 11-Nov-21 (113) (108)
16-Nov-21 18-Nov-21 (103) (101)
completed
--------- -----------
After SST-10 Weir
24-Oct-21 26-Oct-21 (126) (124)
plate
29-Oct-21 02-Nov-21 (121) (117) After inspection
20-Oct-21 27-Oct-21 (130) (123)
19-Nov-21 27-Nov-21 (100) (92)
28-Nov-21 30-Nov-21 (91) (89)
02-Dec-21 03-Dec-21 (87) (86)
31-Oct-21 04-Nov-21 (119) (115)
05-Nov-21 06-Nov-21 (114) (113)
05-Nov-21 07-Nov-21 (114) (112)
16-Oct-21 19-Oct-21 (134) (131)
18-Oct-21 21-Oct-21 (132) (129)
15-Oct-21 21-Oct-21 (135) (129)
04-Nov-21 18-Nov-21 (115) (101)
22-Oct-21 28-Oct-21 (128) (122)
13-Oct-21 19-Oct-21 (137) (131)
15-Oct-21 17-Oct-21 (135) (133)
16-Oct-21 18-Oct-21 (134) (132)
18-Oct-21 21-Oct-21 (132) (129)
16-Oct-21 21-Oct-21 (134) (129)
18-Oct-21 24-Oct-21 (132) (126)
25-Oct-21 28-Oct-21 (125) (122)
25-Oct-21 04-Nov-21 (125) (115)
17-Oct-21 21-Oct-21 (133) (129)
22-Oct-21 27-Oct-21 (128) (123)
28-Oct-21 30-Oct-21 (122) (120)
16-Oct-21 18-Oct-21 (134) (132)
19-Oct-21 21-Oct-21 (131) (129)
13-Nov-21 23-Nov-21 (106) (96)
17-Oct-21 19-Oct-21 (133) (131)
14-Oct-21 18-Oct-21 (136) (132)
25-Oct-21 30-Oct-21 (125) (120)
22-Oct-21 29-Oct-21 (128) (121)
30-Oct-21 08-Nov-21 (120) (111)
13-Oct-21 19-Oct-21 (137) (131)
09-Oct-21 18-Oct-21 (141) (132)
11-Oct-21 17-Oct-21 (139) (133)
Completed
20-Oct-21 23-Oct-21 (130) (127)
24-Oct-21 28-Oct-21 (126) (122)
24-Oct-21 28-Oct-21 (126) (122)
Completed
09-Oct-21 17-Oct-21 (141) (133)
08-Nov-21 25-Nov-21 (111) (94)
21-Oct-21 06-Nov-21 (129) (113)
05-Nov-21 13-Nov-21 (114) (106)
14-Nov-21 22-Nov-21 (105) (97)
14-Nov-21 27-Nov-21 (105) (92)
28-Nov-21 10-Dec-21 (91) (79)
14-Nov-21 04-Dec-21 (105) (85)
30-Nov-21 08-Dec-21 (89) (81)
16-Nov-21 23-Nov-21 (103) (96)
24-Nov-21 05-Dec-21 (95) (84)
15-Nov-21 30-Nov-21 (104) (89)
16-Nov-21 06-Dec-21 (103) (83)
29-Nov-21 09-Dec-21 (90) (80)
13-Nov-21 26-Nov-21 (106) (93)
24-Oct-21 02-Nov-21 (126) (117)
03-Nov-21 12-Nov-21 (116) (107)
13-Nov-21 26-Nov-21 (106) (93)
SWTP-9 PROJECT COMMISSIONING ACTION and ISSUE TRACKER
As of: 27-Feb-22
SN Description No. Type ActionBy Latest Date Action date Status Remarks (Marafiq) Wabag Response
Raised
1 Biomass
2 Food and mass ration for Ast tank
3 Diffuser and MLR pumps
4 Fine screen and grit and grease
5 To start 1/3 of capacity
6 Velocity is an important factor to have a good result
7 Effluent Quality
8
Lagoon must be ready for emergency by pass as per RC
72 hours storage lagoon is needed
9 Control Phylosopy Program
10
11
12
13
14
15
16
17
18
19
20
21
22
SWTP-9 PROJECT HSE ACTION and ISSUE TRACKER
As of: 27-Feb-22
SN Description No. Type ActionBy Location Latest Date Action date Status Remarks (Marafiq) Wabag Response
Raised
6 meter away from fence requirement by MASA ISD
5 1 Action Wabag 30-Sep-21 Open
department
47 Grading roads 1 Action NSH 11-Oct-21 Open
61 TSE removal of unwanted material 1 Action Ajyal 25-Nov-21 Open
Refresh the workers in regarding the emergency and
72 Action NSH 1-Dec-21 Open
rescue.
73 Takanah and T4 to provide additional safety officer Action Takanah/T4 1-Dec-21 5-Dec-21 Closed
75 Al Batin to improve scaffolding storage management Action Al Batin 1-Dec-21 Open
78 Lagoon Electrical works APR Action T4 5-Dec-21 Open
79 Additional HSE officer for takanah Action Takanah 6-Dec-21 Open
81
Marafiq comment on safety officers on site to be Action Wabag 6-Dec-21 Open
monitored (Advice all safety officer)

83
Excess soil in the street light foundation must be Action T4 8-Dec-21 Open
removed
86 Debris from the SST-2 North side needs jack hammer ` Action NSH 8-Dec-21 Open
87 Porta cabins not operational Action T4 8-Dec-21 Open
88 APR nominations Action General 8-Dec-21 Open
Removal of Empty Cable drums and cables and place
89 Action T4 15-Dec-21 Open
hard barricade

90
Unusable material near Catch pit and foundation storage Action NSH 15-Dec-21 Open
(planks, Plywoods and etc.)

91
Al Batin office foundation needs to be change (Unsafe Action Al Batin 15-Dec-21 Open
for human occupancy)
92 SAS no garbage bin Action SAS 15-Dec-21 Open
93 SAS office needs to rectify the stair Action SAS 15-Dec-21 Open
94 Office tags for SAS must be in placed Action SAS 15-Dec-21 Open
Parking area for table 4 needs to be with proper isolation
95 Action T4 15-Dec-21 Open
and sign boards
96 Toilet as requested to be near the generator Action T4 15-Dec-21 Open
97 Exhaust fan must be installed in AJYAL storage room Action AJYAL 15-Dec-21 Open
98 Garbage disposal must be manage properly Action Takanah 15-Dec-21 Open
Zone 5 risk assesment for thrust block is with Marafiq for
100 Action NSH 15-Dec-21 Open
approval
To complete the concrete trench from RSF to Aeration
101 Action NSH 15-Dec-21 25-Dec-21 Open
tank
102 Excavation fire water line between SSt 11 and RSf Action NSH 15-Dec-21 Open
103 Manhole near RAS-2 and 3 Action NSH 15-Dec-21 22-Dec-21 Open
104 Splitter box material removal Action NSH 15-Dec-21 Open
106 NIC cabins and materials must be remove from the site. Action Wabag 15-Dec-21 Open
107 Hard Barricade for Amaco portable cabin Action Amaco 15-Dec-21 Open
108 Unwanted HDPE liners must be removed on site. Action Fanar 15-Dec-21 Open
SWTP-9 L4 SCHEDULE
2/27/2022 7:49
Activity ID Activity Name WBS WBS-1 Original Duration
BL Project Start BL Project Finish Start Finish Float Status No
MARAFIQ COMM SWTP 9 PROJECT - L4 PREC COM AND COMM SCHEDULE 167 9-Sep-21 1-May-22 9-Sep-21 1-May-22 63 On schedule
MARAFIQ COMM.1 MILESTONES 167 9-Sep-21 1-May-22 9-Sep-21 1-May-22 63 On schedule
MARAFIQ COMM.1.1 UTILITY DATES 42 21-Nov-21 8-Jan-22 21-Nov-21 8-Jan-22 (50) Behind Schedule
STPPCC15480 Availability of Fiber Optic System 3 5-Jan-22 8-Jan-22 5-Jan-22 8-Jan-22 (50) Behind Schedule
STPSMC1000 Availability of Power from Owner 3 21-Nov-21 23-Nov-21 21-Nov-21 23-Nov-21 (96) Behind Schedule
Availability of Utility from Owner - PW / FW
STPSMC1010 3 30-Dec-21 2-Jan-22 30-Dec-21 2-Jan-22 (56) Behind Schedule
MARAFIQ COMM.1.2 CONSTRUCTION COMPLETION 132 9-Sep-21 13-Mar-22 9-Sep-21 13-Mar-22 14 Very Critical
MARAFIQ COMM.1.2.7 GREENFIELD 122 9-Sep-21 30-Jan-22 9-Sep-21 30-Jan-22 (28) Behind Schedule
MARAFIQ COMM.1.2.7.1 TRAIN1 93 9-Sep-21 28-Dec-21 9-Sep-21 28-Dec-21 (61) Behind Schedule
MARAFIQ COMM.1.2.7.1.1 TRAIN1 PRETREATMENT AREA TRAIN1 PRETREATMENT AREA 23 30-Nov-21 28-Dec-21 30-Nov-21 28-Dec-21 (61) Behind Schedule
Civil completion - Pre treatment area -
Train1(Inlet con, splitterbox, Flowmsmt, Inlet TRAIN1 PRETREATMENT AREA

STPSMC1020 chamber, FIne scr, GG1A/1B,DC) 0 30-Nov-21 30-Nov-21 (89) Behind Schedule
Mech completion - Pre treatment area -
Train1(Inlet con, splitterbox, Flow msmt, Inlet TRAIN1 PRETREATMENT AREA
STPSMC1030 chamber, FIne scr, GG1A/1B,DC) 0 23-Dec-21 23-Dec-21 (66) Behind Schedule
Piiping Completion - Pre treatment area -
Train1 (Inlet con, splitterbox,Flow msmt, Inlet TRAIN1 PRETREATMENT AREA
STPSMC1040 chamber, FIne scr, GG1A/1B,DC) 0 15-Dec-21 15-Dec-21 (74) Behind Schedule
Elect completion - Pre treatment area -
Train1 (Inlet con, splitterbox, Flow msmt, TRAIN1 PRETREATMENT AREA

STPSMC1050 Inlet chamber, FIne scr, GG1A/1B,DC) 0 25-Dec-21 25-Dec-21 (64) Behind Schedule
Instrument completion - Pre treat area -
Train1(Inlet con, splitterbox,Flow msmt, Inlet TRAIN1 PRETREATMENT AREA

STPSMC1060 chamber, FIne scr, GG1A/1B,DC) 0 28-Dec-21 28-Dec-21 (61) Behind Schedule
TRAIN1 SECONDARY
MARAFIQ COMM.1.2.7.1.2 TRAIN1 SECONDARY TREATMENT A TREATMENT AREA 25 30-Sep-21 30-Oct-21 30-Sep-21 30-Oct-21 (120) Behind Schedule
Civil completion Train1 - Secondary
Treatment area (AST1,SST 1to 4, RAS1, TRAIN1 SECONDARY
TREATMENT AREA

STPSMC1070 SPS1&2, DC1,ES) 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1


Mechanical completion Train1 - Secondary
Treatment area (AST1,SST 1to 4, RAS1, TRAIN1 SECONDARY
TREATMENT AREA

STPSMC1080 SPS1&2, DC1,ES) 0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1


Piiping Completion Train1 - Secondary
Treatment area (AST1,SST 1to 4, RAS1, TRAIN1 SECONDARY
TREATMENT AREA

STPSMC1090 SPS1&2, DC1,ES) 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1


Electrical completion Train 1 - Secondary
Treatment area (AST1,SST 1to 4, RAS1, TRAIN1 SECONDARY
TREATMENT AREA

STPSMC1100 SPS1&2, DC1,ES) 0 20-Oct-21 20-Oct-21 (130) Behind Schedule 1


Instrument completion Train1 - Secondary
Treatment area (AST1,SST 1to 4, RAS1, TRAIN1 SECONDARY
TREATMENT AREA

STPSMC1110 SPS1&2, DC1,ES) 0 30-Oct-21 30-Oct-21 (120) Behind Schedule 1


TRAIN1 TERTIARY TREATMENT
MARAFIQ COMM.1.2.7.1.3 TRAIN1 TERTIARY TREATMENT AREA AREA 41 10-Nov-21 28-Dec-21 10-Nov-21 28-Dec-21 (61) Behind Schedule 1
Civil completion - Tertiary treatment area
Train 1 (RSF 1,2,3 & 4 , BW Tank/ Pumps, CCT TRAIN1 TERTIARY TREATMENT
AREA

STPSMC1120 tank1,Blowers, CDS,TSE Ps, ) 0 10-Nov-21 10-Nov-21 (109) Behind Schedule 1

Mechanical completion - Tertiary treatment


area Traiin1 (RSF 1,2,3 & 4 , BW Tank/ TRAIN1 TERTIARY TREATMENT
AREA
Pumps,CCT tank1,Blowers, CDS,TSE Ps, )
STPSMC1130 0 11-Dec-21 11-Dec-21 (78) Behind Schedule 1
Piiping Completion - Tertiary treatment area
Train1 (RSF 1,2,3 & 4 , BW Tank/ Pumps,CCT TRAIN1 TERTIARY TREATMENT
AREA

STPSMC1140 tank1,Blowers, CDS,TSE Ps, ) 0 10-Nov-21 10-Nov-21 (109) Behind Schedule 1


Electrical completion - Tertiary treatment
area Train1 (RSF 1,2,3 & 4 , BW Tank/ TRAIN1 TERTIARY TREATMENT
AREA

STPSMC1150 Pumps,CCT tank1,Blowers, CDS,TSE Ps, ) 0 23-Dec-21 23-Dec-21 (66) Behind Schedule 1
Inst completion - Tertiary treatment area
Traiin1 (RSF 1,2,3 & 4 , BW Tank/ Pumps,CCT TRAIN1 TERTIARY TREATMENT
AREA

STPSMC1160 tank1,Blowers, CDS,TSE Ps, ) 0 28-Dec-21 28-Dec-21 (61) Behind Schedule 1


TRAIN1 SLUDGE TREATMENT
MARAFIQ COMM.1.2.7.1.4 TRAIN1 SLUDGE TREATMENT AREA AREA 48 30-Oct-21 25-Dec-21 30-Oct-21 25-Dec-21 (64) Behind Schedule 1
Civil completion- Sludge trt area -
Train1(Sludge thickener 130- TRAIN1 SLUDGE TREATMENT
1/2,TT,Decan140-1/2/7,Lime dosing, CS, Poly AREA

dsg 1/2/6/7)
STPSMC1170 0 30-Oct-21 30-Oct-21 (120) Behind Schedule 1
Mech completion - Sludge trt area -
Train1(Sludge thickener 130-1/2, Decan140- TRAIN1 SLUDGE TREATMENT
AREA

STPSMC1180 1/2/7,Lime dosing,CS, Poly dsg 1/2/6/7) 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
Piiping Completion - Sludge trt area- Train1
(Sludge thickener 130-1/2, Decan140- TRAIN1 SLUDGE TREATMENT
AREA

STPSMC1190 1/2/7,Lime dosing,CS, Poly dsg 1/2/6/7) 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
Electcompletion - Sludge trt area - Train1
(Sludge thickener 130-1/2, Decan140- TRAIN1 SLUDGE TREATMENT
AREA

STPSMC1200 1/2/7,Lime dosing,CS, Poly dsg 1/2/6/7) 0 11-Dec-21 11-Dec-21* 1


Inst completion - Sludge trt area - Train1
(Sludge thickener 130-1/2, Decan140- TRAIN1 SLUDGE TREATMENT
AREA

STPSMC1210 1/2/7,Lime dosing,CS, Poly dsg 1/2/6/7) 0 25-Dec-21 25-Dec-21* 1


MARAFIQ COMM.1.2.7.1.5 ODOR CONTROL ODOR CONTROL 35 20-Oct-21 30-Nov-21 20-Oct-21 30-Nov-21 (89) Behind Schedule 1
Civil completion - Odor Control area 1(ocu
A/B , AC Filter, Chemical dosing tank and ODOR CONTROL

STPSMC1220 pump) 0 20-Oct-21 20-Oct-21 (130) Behind Schedule 1


Mechanical completion - Odor Control area
1(ocu A/B , AC Filter, Chemical dosing tank ODOR CONTROL

STPSMC1230 and pump) 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1


Piiping Completion - Odor Control area 1(ocu
A/B , AC Filter, Chemical dosing tank and ODOR CONTROL

STPSMC1240 pump) 0 10-Nov-21 10-Nov-21 (109) Behind Schedule 1


Electrical completion - Odor Control
area1(ocu A/B , AC Filter, Chemical dosing ODOR CONTROL

STPSMC1250 tank and pump) 0 20-Nov-21 20-Nov-21 (99) Behind Schedule 1


Instrument completion - Odor Control area
1(ocu A/B , AC Filter, Chemical dosing tank ODOR CONTROL

STPSMC1260 and pump) 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1


MARAFIQ COMM.1.2.7.1.6 TRUCK OFF LOADING TRUCK OFF LOADING 48 5-Oct-21 30-Nov-21 5-Oct-21 30-Nov-21 (89) Behind Schedule 1
Civil completion - Truck Off Loading area
(Guard Area/ Truck bay /Control Room / TRUCK OFF LOADING

STPSMC1270 Flow measurement) 0 5-Oct-21 5-Oct-21 (145) Behind Schedule 1


Mechanical completion - Truck Off Loading
area (Guard Area/ Truck bay /Control TRUCK OFF LOADING

STPSMC1280 Room / Flow measurement) 0 30-Oct-21 30-Oct-21 (120) Behind Schedule 1


Piiping Completion - Truck Off Loading area
(Guard Area/ Truck bay /Control Room / TRUCK OFF LOADING

STPSMC1290 Flow measurement) 0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1


Electrical completion - Truck Off Loading area
(Guard Area/ Truck bay /Control Room / TRUCK OFF LOADING

STPSMC1300 Flow measurement) 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1


Instrument completion - Truck Off Loading
area (Guard Area/ Truck bay /Control TRUCK OFF LOADING

STPSMC1310 Room / Flow measurement) 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1


EXPANSION IN EXISTING SEC
MARAFIQ COMM.1.2.7.1.8 BUILDINGS - SS , COR BUILDING 83 9-Sep-21 15-Dec-21 9-Sep-21 15-Dec-21 (74) Behind Schedule 1
EXPANSION IN EXISTING SEC
MARAFIQ COMM.1.2.7.1.8.7 EXPANSION IN EXISTING SEC BUI BUILDING 0 9-Sep-21 9-Sep-21 9-Sep-21 9-Sep-21 (171) Behind Schedule 1
Electrical Completion Expansion in SEC EXPANSION IN EXISTING SEC
STPPCC14110 Building BUILDING 0 9-Sep-21 9-Sep-21 (171) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.8.5 MCC PANEL ROOM MCC PANEL ROOM 12 15-Sep-21 30-Sep-21 15-Sep-21 30-Sep-21 (150) Behind Schedule 1
STPPCC14000 Civil Completion MCC Panel Room MCC PANEL ROOM 0 15-Sep-21 15-Sep-21 (165) Behind Schedule 1
Electrical Completion MCC Panel Room MCC PANEL ROOM
STPPCC14010 (Cabling, glanding and termination) 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.8.1 SUBSTATION1 ELECTRICAL ROOMS 12 30-Sep-21 14-Oct-21 30-Sep-21 14-Oct-21 (136) Behind Schedule 1
STPPCC13920 Civil Completion SS1 ELECTRICAL ROOMS 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1
Electrical Completion S1 (Cabling, glanding ELECTRICAL ROOMS
STPPCC13930 and termination) 0 14-Oct-21 14-Oct-21 (136) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.8.2 SUBSTATION2 ELECTRICAL ROOMS 27 16-Oct-21 15-Nov-21 16-Oct-21 15-Nov-21 (104) Behind Schedule 1
STPPCC13940 Civil Completion SS2 ELECTRICAL ROOMS 0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1
Electrical Completion SS2 (Cabling, glanding ELECTRICAL ROOMS
STPPCC13950 and termination) 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.8.3 SUBSTATION3 ELECTRICAL ROOMS 26 31-Oct-21 30-Nov-21 31-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC13960 Civil Completion SS3 ELECTRICAL ROOMS 0 31-Oct-21 31-Oct-21 (119) Behind Schedule 1
Electrical Completion SS3 (Cabling, glanding ELECTRICAL ROOMS
STPPCC13970 and termination) 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.8.4 SUBSTATION 4 ELECTRICAL ROOMS 0 30-Sep-21 30-Sep-21 30-Sep-21 30-Sep-21 (150) Behind Schedule 1
STPPCC13980 Civil Completion SS4 ELECTRICAL ROOMS 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1
Electrical Completion SS4 (Cabling, glanding ELECTRICAL ROOMS
STPPCC13990 and termination) 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.8.6 CONTROL OPERATION ROOM ELECTRICAL ROOMS 26 15-Nov-21 15-Dec-21 15-Nov-21 15-Dec-21 (74) Behind Schedule 1
STPPCC14020 Civil Completion Control Operator room ELECTRICAL ROOMS 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
Electrical Completion Control Operator room ELECTRICAL ROOMS
STPPCC14030 (Cabling, glanding and termination) 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
Inst Completion Control Operator room ELECTRICAL ROOMS
STPPCC14820 (Cabling, glanding and termination) 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.9 POTABLE WATER SYSTEM POTABLE WATER SYSTEM 0 15-Nov-21 15-Nov-21 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC14880 Potable water laying POTABLE WATER SYSTEM 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC14890 Potable water laying completion POTABLE WATER SYSTEM 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.10 FIRE WATER SYSTEM FIRE WATER SYSTEM 0 20-Nov-21 20-Nov-21 20-Nov-21 20-Nov-21 (99) Behind Schedule 1
STPPCC14900 Firewater Piping Laying FIRE WATER SYSTEM 0 20-Nov-21 20-Nov-21 (99) Behind Schedule 1
STPPCC14910 Fire water layiing completion FIRE WATER SYSTEM 0 20-Nov-21 20-Nov-21 (99) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.11 SERVICE WATER SYSTEM SERVICE WATER SYSTEM 0 25-Nov-21 25-Nov-21 25-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC14920 Service water piping laying SERVICE WATER SYSTEM 0 25-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC14930 Service water laying completion SERVICE WATER SYSTEM 0 25-Nov-21 25-Nov-21 (94) Behind Schedule 1
MARAFIQ COMM.1.2.7.1.7 FIBER OPTIC SYSTEM FIBER OPTIC SYSTEM 4 30-Nov-21 5-Dec-21 30-Nov-21 5-Dec-21 (84) Behind Schedule 1
STPPCC15400 Fiber Optic cable laying FIBER OPTIC SYSTEM 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
STPPCC15410 Fiber Optic laying completion FIBER OPTIC SYSTEM 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
MARAFIQ COMM.1.2.7.2 TRAIN2 TRAIN2 PRETREATMENT AREA 92 16-Oct-21 30-Jan-22 16-Oct-21 30-Jan-22 (28) Behind Schedule 1
MARAFIQ COMM.1.2.7.2.3 TRAIN2 PRETREATMENT AREA TRAIN2 PRETREATMENT AREA 39 15-Dec-21 30-Jan-22 15-Dec-21 30-Jan-22 (28) Behind Schedule 1
Civil Completion - Pre treatment area - Train 2 (Grit 2A TRAIN2 PRETREATMENT AREA
STPPCC14120 2B, 3A 3B) 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
Piping Completion - Pre treatment area - Train 2 (Grit TRAIN2 PRETREATMENT AREA
STPPCC14130 2A 2B, 3A 3B) 0 20-Dec-21 20-Dec-21 (69) Behind Schedule 1
Mechanical Completion - Pre treatment area - Train 2 TRAIN2 PRETREATMENT AREA
STPPCC14140 (Grit 2A 2B, 3A 3B) 0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Elecrical Completion - Pre treatment area - Train 2 (Grit TRAIN2 PRETREATMENT AREA
STPPCC14150 2A 2B, 3A 3B) 0 30-Jan-22 30-Jan-22 (28) Behind Schedule 1
Instrument Completion - Pre treatment area - Train 2 TRAIN2 PRETREATMENT AREA
STPPCC14160 (Grit 2A 2B, 3A 3B) 0 30-Jan-22 30-Jan-22 (28) Behind Schedule 1
MARAFIQ COMM.1.2.7.2.2 TRAIN2 SECONDARY TREATMENT AREA TRAIN2 SECONDARY TREATMENT AREA 26 16-Oct-21 15-Nov-21 16-Oct-21 15-Nov-21 (104) Behind Schedule 1
Civil completion Train 2 - Secondary Treatment area TRAIN2 SECONDARY TREATMENT AREA
STPPCC12880 (AST2/3,SST 5 to12, RAS2/3, SPS3&4, DC2/3) 0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1
Mechanical Completion Train 2 - Secondary Treatment TRAIN2 SECONDARY TREATMENT AREA
area (AST2/3,SST 5 to12, RAS2/3, SPS3&4, DC2/3)
STPPCC12890 0 25-Oct-21 25-Oct-21 (125) Behind Schedule 1
Piping Ccompletion Train 2 - Secondary Treatment area TRAIN2 SECONDARY TREATMENT AREA
STPPCC12900 (AST2/3,SST 5 to12, RAS2/3, SPS3&4, DC2/3) 0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1
Electrical Completion Train 2 - Secondary Treatment TRAIN2 SECONDARY TREATMENT AREA
STPPCC12910 area (AST2/3,SST 5 to12, RAS2/3, SPS3&4, DC2/3) 0 31-Oct-21 31-Oct-21 (119) Behind Schedule 1
Instrument completion of Train 2 - Secondary
Treatment area (AST2/3,SST 5 to12, RAS2/3, SPS3&4, TRAIN2 SECONDARY TREATMENT AREA

STPPCC12920 DC2/3) 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1


MARAFIQ COMM.1.2.7.2.1 TRAIN2 TERTIARY TREATMENT AREA TRAIN2 TERTIARY TREATMENT AREA 40 15-Nov-21 1-Jan-22 15-Nov-21 1-Jan-22 (57) Behind Schedule 1
Civil completion - Tertiary treatment area Train 2 (RSF 5 TRAIN2 TERTIARY TREATMENT AREA
STPPCC13810 to 18 , CCT Tank 2 to 5) 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
Mechanical completion - Tertiary treatment area Train TRAIN2 TERTIARY TREATMENT AREA
STPPCC13820 2 (RSF 5 to 18 , CCT Tank 2 to 5) 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
Piiping Completion - Tertiary treatment area Train 2 TRAIN2 TERTIARY TREATMENT AREA
STPPCC13830 (RSF 5 to 18 , CCT Tank 2 to 5) 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
Electrical completion - Tertiary treatment area Train 2 TRAIN2 TERTIARY TREATMENT AREA
STPPCC13840 (RSF 5 to 18 , CCT Tank 2 to 5) 0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Instrument completion - Tertiary treatment area Train 2 TRAIN2 TERTIARY TREATMENT AREA
STPPCC13850 (RSF 5 to 18 , CCT Tank 2 to 5) 0 1-Jan-22 1-Jan-22 (57) Behind Schedule 1
MARAFIQ COMM.1.2.7.2.4 TRAIN2 SLUDGETREATMENT AREA TRAIN2 SLUDGETREATMENT AREA 43 6-Nov-21 25-Dec-21 6-Nov-21 25-Dec-21 (64) Behind Schedule 1
Civil compl- Sludge trt area Train2 (Sludge thickener
130-3/4/5/6, Decan140-3,4,5,6Lime dosing,CS,Poly dsg TRAIN2 SLUDGETREATMENT AREA

STPPCC14170 4/5/8/9) 0 6-Nov-21 6-Nov-21 (113) Behind Schedule 1


Piping Compl - Sudge trt area Train 2 (Sludge thickener
130-3/4/5/6, Decan140-3,4,5,6Lime dosing,CS,Poly dsg TRAIN2 SLUDGETREATMENT AREA

STPPCC14180 4/5/8/9) 0 5-Dec-21 5-Dec-21 (84) Behind Schedule 1


Mech Compl - Sludge trt area Train2 (Sludge thickener
130-3/4/5/6, Decan140-3,4,5,6Lime dosing,CS,Poly dsg TRAIN2 SLUDGETREATMENT AREA

STPPCC14190 4/5/8/9) 0 5-Dec-21 5-Dec-21 (84) Behind Schedule 1


Elec Comp - Sludge trt area- Train 2 (Sludge thickener
130-3/4/5/6, Decan140-3,4,5,6Lime dosing,CS,Poly dsg TRAIN2 SLUDGETREATMENT AREA

STPPCC14200 4/5/8/9) 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1


Inst Compl - Sludge trt area Train 2 (Sludge thickener
130-3/4/5/6, Decan140-3,4,5,6Lime dosing,CS,Poly dsg TRAIN2 SLUDGETREATMENT AREA

STPPCC14210 4/5/8/9) 0 25-Dec-21 25-Dec-21 (64) Behind Schedule 1


MARAFIQ COMM.1.2.12 BROWNFIELD BROWNFIELD Train 1 128 15-Sep-21 13-Mar-22 15-Sep-21 13-Mar-22 14 Very Critical 1
MARAFIQ COMM.1.2.12.7 TRAIN1 BROWNFIELD Train 1 LAGOON 91 20-Sep-21 4-Jan-22 20-Sep-21 4-Jan-22 (54) Behind Schedule 1
MARAFIQ COMM.1.2.12.7.1 TRAN1 ANCIALLRY WORKS - LAGOON BROWNFIELD Train 1 LAGOON 12 20-Sep-21 5-Oct-21 20-Sep-21 5-Oct-21 (145) Behind Schedule 1
Civil completion - Ancillary Works (SHL1,2 / SP1,BP1 , BROWNFIELD Train 1 LAGOON
STPSMC1320 DTS3 ) 0 20-Sep-21 20-Sep-21 (160) Behind Schedule 1
Mechanical completion - Ancillary Works (SHL1,2 / BROWNFIELD Train 1 LAGOON
STPSMC1330 SP1,BP1 , DTS3 ) 0 30-Sep-21 30-Sep-21 (150) Behind Schedule 1
Electrical completion - Ancillary Works (SHL1,2 / BROWNFIELD Train 1 LAGOON
STPSMC1350 SP1,BP1 , DTS3) 0 5-Oct-21 5-Oct-21 (145) Behind Schedule 1
MARAFIQ COMM.1.2.12.7.2 TIEINS BROWNFIELD Train 1 LAGOON 43 16-Nov-21 4-Jan-22 16-Nov-21 4-Jan-22 (54) Behind Schedule 1
Interface tie in with the inlet flow splitting chamber - BROWNFIELD Train 1 Tie In
STPPCC14740 pretreatment area channel 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
tie in of the new proposed TSE line (1.2km / 1800 dia) BROWNFIELD Train 1 Tie In
STPPCC14750 with existing TSE tank (only fittings) by pass interface 3 1-Jan-22 3-Jan-22 1-Jan-22 3-Jan-22 (55) Behind Schedule 1
Interface tiein of the new proposed TSE line with the
emergency lagoons - Emergency Lagoons(1600/ 50 mt) BROWNFIELD Train 1 Tie In

STPPCC14760 Main interface 3 1-Jan-22 3-Jan-22 1-Jan-22 3-Jan-22 (55) Behind Schedule 1
Interface tie in from the inlet flow splitting chamber to BROWNFIELD Train 1 Tie In
STPPCC14770 emergency lagoons - Emergency Lagoons( channel) 3 28-Dec-21 30-Dec-21 28-Dec-21 30-Dec-21 (59) Behind Schedule 1
Interface tie in with the existing fire water and potable BROWNFIELD Train 1 Tie In
STPPCC14790 water network - Building and other areas 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
Interface tie in with the existing SWTP control room for BROWNFIELD Train 1 Tie In
STPPCC14800 monitoring purposes - Control room 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
Interface tie in with the existing telecommunication BROWNFIELD Train 1 Tie In
STPPCC14810 network - Buildings 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
Interface Tie in with existing substation for Power BROWNFIELD Train 1 Tie In
STPPCC14840 Supply. 4 16-Nov-21 20-Nov-21 16-Nov-21 20-Nov-21 (99) Behind Schedule 1
MARAFIQ COMM.1.2.12.3 TRAIN2 BROWNFIELD Train 2 128 15-Sep-21 13-Mar-22 15-Sep-21 13-Mar-22 14 Very Critical 1
MARAFIQ COMM.1.2.12.3.2 TRAIN2 ANCIALLRY WORKS - LAGOON BROWNFIELD Train 2 143 15-Sep-21 2-Mar-22 15-Sep-21 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.1.2.12.3.2.1 LOT 2 BROWNFIELD Train 2 LAGOON 130 15-Sep-21 15-Feb-22 15-Sep-21 15-Feb-22 (12) Behind Schedule 1
STPPCC14690 Civil completion - Ancillary Works (SHL3, AL1/2) BROWNFIELD Train 2 LAGOON 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
Mechanical completion - Ancillary Works (SHL3, AL1/2) BROWNFIELD Train 2 LAGOON
STPPCC14700 0 23-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC14720 Electrical completion - Ancillary Works (SHL3, AL1/2) BROWNFIELD Train 2 LAGOON 0 15-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCC14950 Handing over of Lagioon 2 (SHL3, AL1/2) BROWNFIELD Train 2 LAGOON 0 15-Sep-21 15-Sep-21* 1
MARAFIQ COMM.1.2.12.3.2.2 LOT 3 BROWNFIELD Train 2 LAGOON 104 1-Nov-21 2-Mar-22 1-Nov-21 2-Mar-22 3 Very Critical 1
Handing over of Lagoon Lot 3 (AL3/4, SD,HL, BROWNFIELD Train 2 LAGOON
STPPCC14970 SP2,BP2,DTS 4) 0 1-Nov-21 01-Nov-21* 1
Civil Completion - Ancillay works Lot 3 (AL3/4, SD,HL, BROWNFIELD Train 2 LAGOON
STPPCC14980 SP2,BP2, DTS4) 0 31-Jan-22 31-Jan-22 (27) Behind Schedule 1
Mechanical completion - Ancillary Works(AL3/4, SD,HL, BROWNFIELD Train 2 LAGOON
STPPCC14990 SP2,BP2, DTS4) 0 28-Feb-22 28-Feb-22 1 Very Critical 1
Electrical completion - Ancillary Works (AL3/4, SD,HL, BROWNFIELD Train 2 LAGOON
STPPCC15010 SP2,BP2, DTS4) 0 2-Mar-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.1.2.12.3.1 TIE INS BROWNFIELD Train 2 Tie In 15 20-Feb-22 13-Mar-22 20-Feb-22 13-Mar-22 14 Very Critical 1
MARAFIQ COMM.1.2.12.3.1.1 Civil BROWNFIELD Train 2 Tie In 4 20-Feb-22 24-Feb-22 20-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCC14830 Interface tie in with existing roads BROWNFIELD Train 2 Tie In 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCC14940 Road laying completion BROWNFIELD Train 2 Tie In 0 20-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.1.2.12.3.1.2 Piping BROWNFIELD Train 2 Tie In 3 10-Mar-22 13-Mar-22 10-Mar-22 13-Mar-22 14 Very Critical 1
Interface tie in from the emergency lagoons pump
house to the new plant - Emergency Lagoons (500 dia / BROWNFIELD Train 2 Tie In

STPPCC14780 50mt) 3 10-Mar-22 13-Mar-22 10-Mar-22 13-Mar-22 14 Very Critical 1


MARAFIQ COMM.1.2.12.3.1.3 Elect and Inst BROWNFIELD Train 2 Tie In 0 1
MARAFIQ COMM.1.3 PRECOMMISSIONIG COMPLETION 133 5-Oct-21 9-Mar-22 5-Oct-21 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.1.3.3 GREENFIELD 129 5-Oct-21 5-Mar-22 5-Oct-21 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.1.3.3.1 TRAIN1 74 5-Oct-21 30-Dec-21 5-Oct-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System 001 Inlet Connection Pre-commissioning Train 1
STPPCC12940 chamber Completion Train 1
0 27-Dec-21 27-Dec-21 (62) Behind Schedule 1
Pre-commissioning
STPPCC12950 Precomm Completion of System 010 Inlet Splitter Box Completion Train 1 Train 1 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
Pre-commissioning
Precomm Completion of System Inlet Flow Measurment Train 1
STPPCC12960 Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Pre-commissioning
STPPCC12970 Precomm Completion of System Inlet Chamber Completion Train 1 Train 1 0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Pre-commissioning
STPPCC12980 Precomm Completion of System Fine Screens Completion Train 1 Train 1 0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System Grit and Grease Pre-commissioning
Train 1
STPPCC12990 Chambers Train1 Completion Train 1
0 29-Dec-21 29-Dec-21 (60) Behind Schedule 1
Precomm Completion of System Distribution Chambers Pre-commissioning
Train 1
STPPCC13000 for (AST) Completion Train 1
0 27-Dec-21 27-Dec-21 (62) Behind Schedule 1
Precomm Completion of System Activated Sludge Tanks Pre-commissioning
Train 1
STPPCC13010 (AST) Completion Train 1
0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
Pre-commissioning
STPPCC13030 Precomm Completion of Blower Building Completion Train 1 Train 1 0 6-Nov-21 6-Nov-21 (113) Behind Schedule 1
Precomm Completion of System Distribution Chambers Pre-commissioning
Train 1
STPPCC13040 for (SST) Train1 Completion Train 1
0 26-Oct-21 26-Oct-21 (124) Behind Schedule 1
Precomm Completion of System Secondary Pre-commissioning
Train 1
STPPCC13060 Sedimentation Tanks (SST) Train 1 Completion Train 1
0 31-Oct-21 31-Oct-21 (119) Behind Schedule 1
Precomm Completion of System Rapid Sand Filters Pre-commissioning
Train 1
STPPCC13080 Train 1 Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System Chlorine Contact Tank Pre-commissioning
Train 1
STPPCC13090 Train1 Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System Reaeration and Pre-commissioning Train 1
STPPCC13100 Chlorine Mixing Tanks Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Pre-commissioning
Precomm Completion of System Chlorine Dosing Station Train 1
STPPCC13110 Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Pre-commissioning
STPPCC13120 Precomm Completion of System TSE Pumping Station Completion Train 1 Train 1 0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Pre-commissioning
Precomm Completion of System TSE VALVE CHAMBER Train 1
STPPCC13130 Completion Train 1
0 16-Dec-21 16-Dec-21 (73) Behind Schedule 1
Precomm Completion of System Excess and Return Pre-commissioning Train 1
STPPCC13140 Sludge Pumping Station Traiin1 Completion Train 1
0 6-Nov-21 6-Nov-21 (113) Behind Schedule 1
Precomm Completion of System Scum Pumping Station Pre-commissioning Train 1
STPPCC13150 Train 1 Completion Train 1
0 6-Nov-21 6-Nov-21 (113) Behind Schedule 1
Precomm Completion of System Sludge Thickening Pre-commissioning
Train 1
STPPCC13160 Train1 Completion Train 1
0 5-Dec-21 5-Dec-21 (84) Behind Schedule 1
Pre-commissioning
Precomm Completion of System Thickened Sludge Tank Train 1
STPPCC13170 Completion Train 1
0 25-Nov-21 25-Nov-21 (94) Behind Schedule 1
Precomm Completion of System Sludge Dewatering Pre-commissioning
Train 1
STPPCC13180 Train1 Completion Train 1
0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
Precomm Completion of System Lime Silo & Sludge Pre-commissioning
Train 1
STPPCC13190 Mixing Unit Completion Train 1
0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
Pre-commissioning
Precomm Completion of System Container Storage Area Train 1
STPPCC13200 Completion Train 1
0 13-Dec-21 13-Dec-21 (76) Behind Schedule 1
Precomm Completion of System Truck Offloading Pre-commissioning
Train 1
STPPCC13220 Station Completion Train 1
0 8-Dec-21 8-Dec-21 (81) Behind Schedule 1
Precomm Completion of System Truck Offloading Pre-commissioning Train 1
STPPCC13230 Station - Guard room Completion Train 1
0 1-Nov-21 1-Nov-21 (118) Behind Schedule 1
Precomm Completion of System Truck Offloading Pre-commissioning Train 1
STPPCC13240 Station - Truck Bay Completion Train 1
0 20-Nov-21 20-Nov-21 (99) Behind Schedule 1
Precomm Completion of System Truck Offloading Pre-commissioning
Train 1
STPPCC13250 Station - Control Room Completion Train 1
0 24-Nov-21 24-Nov-21 (95) Behind Schedule 1
Precomm Completion of System Truck Offloading Pre-commissioning
Train 1
STPPCC13260 Station - Flow Measurement Completion Train 1
0 29-Nov-21 29-Nov-21 (90) Behind Schedule 1
Precomm Completion of System Foul Air Treatment Pre-commissioning
Train 1
STPPCC13270 Unit-1 Completion Train 1
0 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
Precomm Completion of System Foul Air Treatment Pre-commissioning Train 1
STPPCC13280 Unit-2 (Truck Offloading Station) Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System Plant Drain Pumping Pre-commissioning Train 1
STPPCC13290 Station Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System Control Operation Pre-commissioning Train 1
STPPCC13310 Room Completion Train 1
0 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
Precomm Completion of System Sub Station-1 Inlet Pre-commissioning
Train 1
STPPCC13320 chamber Completion Train 1
0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
Precomm Completion of System Sub Station-2 Blower Pre-commissioning
Train 1
STPPCC13330 room Completion Train 1
0 18-Dec-21 18-Dec-21 (71) Behind Schedule 1
Pre-commissioning
Precomm Completion of System Sub Station-4 TSE Area Train 1
STPPCC13340 Completion Train 1
0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
Pre-commissioning
Precomm Completion of System Sub Station-3 SST Area Train 1
STPPCC13350 Completion Train 1
0 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
Precomm Completion of SystemPanel Room for Pre-commissioning
Train 1
STPPCC13360 MCC(SST Area) Completion Train 1
0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1
Pre-commissioning
STPPCC14340 Precomm Completion of Polymer preparation Train 1 Completion Train 1 Train 1 0 30-Nov-21 30-Nov-21 (89) Behind Schedule 1
Pre-commissioning
STPPCC14850 Precomm Completion of Potablw water system Completion Train 1 Train 1 0 25-Dec-21 25-Dec-21 (64) Behind Schedule 1
Pre-commissioning
STPPCC14860 Precomm Completion of Fire watrer system Completion Train 1
Train 1 0 25-Dec-21 25-Dec-21 (64) Behind Schedule 1
Pre-commissioning
STPPCC14870 Precomm completion of Service water System Completion Train 1 Train 1 0 25-Dec-21 25-Dec-21 (64) Behind Schedule 1
Pre-commissioning
STPPCC15420 Precomm completion of Fiber Optic system Completion Train 1 Train 1 0 15-Dec-21 15-Dec-21 (74) Behind Schedule 1
Pre-commissioning
STPPCC15450 Precomm completion in SEC room Completion Train 1 Train 1 0 5-Oct-21 5-Oct-21 (145) Behind Schedule 1
Pre-commissioning
MARAFIQ COMM.1.3.3.2 TRAIN2 Completion Train 2
Train 2 64 20-Dec-21 5-Mar-22 20-Dec-21 5-Mar-22 6 Very Critical 1
Precomm Completion of System Activated Sludge Tanks Pre-commissioning Train 2
STPPCC13020 (AST) Train2 Completion Train 2
0 20-Dec-21 20-Dec-21 (69) Behind Schedule 1
Precomm Completion of System Distribution Chambers Pre-commissioning Train 2
STPPCC13050 for (SST) Train2 Completion Train 2
0 20-Dec-21 20-Dec-21 (69) Behind Schedule 1
Precomm Completion of System Secondary Pre-commissioning
Train 2
STPPCC13070 Sedimentation Tanks (SST) Train 2 Completion Train 2
0 17-Jan-22 17-Jan-22 (41) Behind Schedule 1
Pre-commissioning
STPPCC14220 Precomm Completion of Rapid filters Train 2 Completion Train 2
Train 2 0 5-Mar-22 5-Mar-22 6 Very Critical 1
Pre-commissioning
STPPCC14230 Precomm Completiom of CCT Train 2 Completion Train 2 Train 2 0 14-Feb-22 14-Feb-22 (13) Behind Schedule 1
Precomm Completion of System Excess and Return Pre-commissioning
Train 2
STPPCC14240 Sludge Pumping Station Traiin 2 Completion Train 2
0 20-Dec-21 20-Dec-21 (69) Behind Schedule 1
Precomm Completion of System Scum Pumping Station Pre-commissioning Train 2
STPPCC14250 Train 2 Completion Train 2
0 20-Dec-21 20-Dec-21 (69) Behind Schedule 1
Precomm Completion of System Sludge Thickening Pre-commissioning Train 2
STPPCC14260 Train 2 Completion Train 2
0 31-Jan-22 31-Jan-22 (27) Behind Schedule 1
Precomm Completion of System Sludge Dewatering Pre-commissioning Train 2
STPPCC14270 Train 2 Completion Train 2
0 9-Feb-22 9-Feb-22 (18) Behind Schedule 1
Pre-commissioning
STPPCC14330 Precomm of System Grit chamber Train 2 Completion Train 2
Train 2 0 2-Mar-22 2-Mar-22 3 Very Critical 1
Pre-commissioning
STPPCC14350 Precomm Completion of Polymer preparation Train 2 Completion Train 2 Train 2 0 9-Feb-22 9-Feb-22 (18) Behind Schedule 1
Pre-commissioning
MARAFIQ COMM.1.3.4 BROWNFIELD Completion Train 2 24 9-Feb-22 9-Mar-22 9-Feb-22 9-Mar-22 10 Very Critical 1
Pre-commissioning
MARAFIQ COMM.1.3.4.1 TRAIN1 Completion Train 1 Lagoon 0 9-Feb-22 9-Feb-22 9-Feb-22 9-Feb-22 (18) Behind Schedule 1
Precommissioning completion of Emergency Lagoon Pre-commissioning
Lagoon Lot 1
STPPCC15090 LOT1 Completion Train 1
0 9-Feb-22 9-Feb-22 (18) Behind Schedule 1
Pre-commissioning
MARAFIQ COMM.1.3.4.2 TRAIN2 Completion Train 2 1 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
Precomm Completion of System Emergency Lagoons Pre-commissioning Lagoon Lot 2
STPPCC13300 LOT2 Completion Train 2
0 8-Mar-22 8-Mar-22 9 Very Critical 1
Precommissioning completion of Emergency Lagoon Pre-commissioning Lagoon Lot 3
STPPCC15100 LOT3 Completion Train 2
0 9-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.1.4 COMMISSIONING AND STARTUP COMPLETION 79 23-Dec-21 26-Mar-22 23-Dec-21 26-Mar-22 27 On schedule 1
MARAFIQ COMM.1.4.3 GREEN FIELD Comm Completion GR 79 23-Dec-21 26-Mar-22 23-Dec-21 26-Mar-22 27 On schedule 1
MARAFIQ COMM.1.4.3.1 TRAIN1 Comm Completion GR Train 1 65 23-Dec-21 9-Mar-22 23-Dec-21 9-Mar-22 10 Very Critical 1
Comm Completion of System 001 Inlet Connection Comm Completion GR Train 1 Train 1
STPPCC13370 chamber 0 22-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC13380 Comm Completion of System 010 Inlet Splitter Box Comm Completion GR Train 1 Train 1 0 19-Jan-22 19-Jan-22 (39) Behind Schedule 1
STPPCC13390 Comm Completion of System Inlet Flow Measurment Comm Completion GR Train 1 Train 1 0 22-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC13400 Comm Completion of System Inlet Chamber Comm Completion GR Train 1 Train 1 0 22-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC13410 Comm Completion of System Fine Screens Comm Completion GR Train 1 Train 1 0 22-Jan-22 22-Jan-22 (36) Behind Schedule 1
Comm Completion of System Grit and Grease Chambers Comm Completion GR Train 1 Train 1
STPPCC13420 Train1 0 24-Jan-22 24-Jan-22 (34) Behind Schedule 1
Comm Completion of System Distribution Chambers for Comm Completion GR Train 1 Train 1
STPPCC13430 (AST) 0 26-Jan-22 26-Jan-22 (32) Behind Schedule 1
Comm Completion of System Activated Sludge Tanks Comm Completion GR Train 1 Train 1
STPPCC13440 (AST) 0 29-Jan-22 29-Jan-22 (29) Behind Schedule 1
STPPCC13460 Comm Completion of Blower Building Comm Completion GR Train 1 Train 1 0 31-Jan-22 31-Jan-22 (27) Behind Schedule 1
Comm Completion of System Distribution Chambers for Comm Completion GR Train 1 Train 1
STPPCC13470 (SST) Train1 0 2-Feb-22 2-Feb-22 (25) Behind Schedule 1
Comm Completion of System Secondary Sedimentation Comm Completion GR Train 1 Train 1
STPPCC13490 Tanks (SST) Train1 0 12-Feb-22 12-Feb-22 (15) Behind Schedule 1
Comm Completion of System Rapid Sand Filters Train1 Comm Completion GR Train 1 Train 1
STPPCC13510 0 19-Feb-22 19-Feb-22 (8) Behind Schedule 1
Comm Completion of System Chlorine Contact Tank Comm Completion GR Train 1 Train 1
STPPCC13520 Train1 0 21-Feb-22 21-Feb-22 (6) Behind Schedule 1
Comm Completion of System Reaeration and Chlorine Comm Completion GR Train 1 Train 1
STPPCC13530 Mixing Tanks 0 26-Feb-22 26-Feb-22 (1) Behind Schedule 1
STPPCC13540 Comm Completion of System Chlorine Dosing Station Comm Completion GR Train 1 Train 1 0 7-Mar-22 7-Mar-22 8 Very Critical 1
STPPCC13550 Comm Completion of System TSE Pumping Station Comm Completion GR Train 1 Train 1 0 2-Mar-22 2-Mar-22 3 Very Critical 1
STPPCC13560 Comm Completion of System TSE VALVE CHAMBER Comm Completion GR Train 1 Train 1 0 5-Mar-22 5-Mar-22 6 Very Critical 1
Comm Completion of System Excess and Return Sludge Comm Completion GR Train 1 Train 1
STPPCC13570 Pumping Station Train1 0 7-Feb-22 7-Feb-22 (20) Behind Schedule 1
STPPCC13580 Comm Completion of System Scum Pumping Station Comm Completion GR Train 1 Train 1 0 12-Feb-22 12-Feb-22 (15) Behind Schedule 1
Comm Completion of System Sludge Thickening Train1 Comm Completion GR Train 1 Train 1
STPPCC13590 0 7-Mar-22 7-Mar-22 8 Very Critical 1
STPPCC13600 Comm Completion of System Thickened Sludge Tank Comm Completion GR Train 1 Train 1 0 2-Mar-22 2-Mar-22 3 Very Critical 1
Comm Completion of System Sludge Dewatering Train1 Comm Completion GR Train 1 Train 1
STPPCC13610 0 5-Mar-22 5-Mar-22 6 Very Critical 1
Comm Completion of System Lime Silo & Sludge Mixing Comm Completion GR Train 1 Train 1
STPPCC13620 Unit 0 9-Mar-22 9-Mar-22 10 Very Critical 1
STPPCC13630 Comm Completion of System Container Storage Area Comm Completion GR Train 1 Train 1 0 26-Feb-22 26-Feb-22 (1) Behind Schedule 1
Comm Completion of System Polymer Preperation Comm Completion GR Train 1 Train 1
STPPCC13640 Train1 0 9-Mar-22 9-Mar-22 10 Very Critical 1
STPPCC13650 Comm Completion of System Truck Offloading Station Comm Completion GR Train 1 Train 1 0 26-Jan-22 26-Jan-22 (32) Behind Schedule 1
Comm Completion of System Truck Offloading Station - Comm Completion GR Train 1 Train 1
STPPCC13660 Guard room 0 29-Jan-22 29-Jan-22 (29) Behind Schedule 1
Comm Completion of System Truck Offloading Station - Comm Completion GR Train 1 Train 1
STPPCC13670 Truck Bay 0 22-Jan-22 22-Jan-22 (36) Behind Schedule 1
Comm Completion of System Truck Offloading Station - Comm Completion GR Train 1 Train 1
STPPCC13680 Control Room 0 26-Jan-22 26-Jan-22 (32) Behind Schedule 1
Comm Completion of System Truck Offloading Station - Comm Completion GR Train 1 Train 1
STPPCC13690 Flow Measurement 0 31-Jan-22 31-Jan-22 (27) Behind Schedule 1
Comm Completion of System Foul Air Treatment Unit-1 Comm Completion GR Train 1 Train 1
STPPCC13700 0 7-Mar-22 7-Mar-22 8 Very Critical 1
Comm Completion of System Foul Air Treatment Unit-2 Comm Completion GR Train 1 Train 1
STPPCC13710 (Truck Offloading Station) 0 9-Mar-22 9-Mar-22 10 Very Critical 1
Comm Completion of System Plant Drain Pumping Comm Completion GR Train 1 Train 1
STPPCC13720 Station 0 29-Jan-22 29-Jan-22 (29) Behind Schedule 1
Comm Completion of System Control Operation Room Comm Completion GR Train 1 Train 1
STPPCC13740 0 24-Jan-22 24-Jan-22 (34) Behind Schedule 1
Comm Completion of System Sub Station-1 Inlet Comm Completion GR Train 1 Train 1
STPPCC13750 chamber 0 23-Dec-21 23-Dec-21 (66) Behind Schedule 1
Comm Completion of System Sub Station-2 Blower Comm Completion GR Train 1 Train 1
STPPCC13760 room 0 12-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC13770 Comm Completion of System Sub Station-4 TSE Area Comm Completion GR Train 1 Train 1 0 12-Jan-22 12-Jan-22 (46) Behind Schedule 1
Comm Completion of SystemPanel Room for MCC(SST Comm Completion GR Train 1 Train 1
STPPCC13790 Area) 0 12-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC14370 Comm completion of Polymner preparation Train 1 Comm Completion GR Train 1 Train 1 0 9-Mar-22 9-Mar-22 10 Very Critical 1
STPPCC15130 Commissioning completion of PW system Comm Completion GR Train 1 Train 1 0 18-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC15140 Commissioning completion of FW System Comm Completion GR Train 1 Train 1 0 18-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC15150 Commisisioning completion of Fiber Optic system Comm Completion GR Train 1 Train 1 0 10-Jan-22 10-Jan-22 (48) Behind Schedule 1
MARAFIQ COMM.1.4.3.2 TRAIN2 Comm Completion GR Train 2 Train 2 65 9-Jan-22 26-Mar-22 9-Jan-22 26-Mar-22 27 On schedule 1
Comm Completion of System Activated Sludge Tanks Comm Completion GR Train 2 Train 2
STPPCC13450 (AST) Train2 0 19-Jan-22 19-Jan-22 (39) Behind Schedule 1
Comm Completion of System Distribution Chambers for Comm Completion GR Train 2 Train 2
STPPCC13480 (SST) Train2 0 9-Jan-22 9-Jan-22 (49) Behind Schedule 1
Comm Completion of System Secondary Sedimentation Comm Completion GR Train 2 Train 2
STPPCC13500 Tanks (SST) Train 2 0 10-Mar-22 10-Mar-22 11 Very Critical 1
STPPCC13780 Comm Completion of System Sub Station-3 SST Area Comm Completion GR Train 2 Train 2 0 17-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC14280 Comm Completion of Sludge dewatering Train2 Comm Completion GR Train 2 Train 2 0 6-Mar-22 6-Mar-22 7 Very Critical 1
Comm Completion of System Sludge thickening Train2 Comm Completion GR Train 2 Train 2
STPPCC14290 0 20-Feb-22 20-Feb-22 (7) Behind Schedule 1
Comm Completion of System Excess and Sludge Train2 Comm Completion GR Train 2 Train 2
STPPCC14300 0 9-Jan-22 9-Jan-22 (49) Behind Schedule 1
Comm Completion of System Scum Pumping station Comm Completion GR Train 2 Train 2
STPPCC14310 Train2 0 9-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC14320 Comm Completion of System CCTTrain2 Comm Completion GR Train 2 Train 2 0 6-Mar-22 6-Mar-22 7 Very Critical 1
STPPCC14360 Comm completion of Polymner preparation Train 2 Comm Completion GR Train 2 Train 2 0 9-Mar-22 9-Mar-22 10 Very Critical 1
STPPCC14380 Comm Completion of Rapid filter Train 2 Comm Completion GR Train 2 Train 2 0 26-Mar-22 26-Mar-22 27 On schedule 1
STPPCC14390 Comm completion of Grit and Grease Train 2 Comm Completion GR Train 2 Train 2 0 15-Mar-22 15-Mar-22 16 On schedule 1
MARAFIQ COMM.1.4.4 BROWNFIELD Comm Completion BR Train 1 Comm Completion Brown field 27 20-Feb-22 23-Mar-22 20-Feb-22 23-Mar-22 24 On schedule 1
MARAFIQ COMM.1.4.4.1 TRAIN1 Comm Completion BR Train 1 Comm Completion BR Train 1 0 20-Feb-22 20-Feb-22 20-Feb-22 20-Feb-22 (7) Behind Schedule 1
Comm Completion of System Emergency Lagoons Lot 1 Comm Completion BR Train 1 Lagoons Lot 1
STPPCC13730 0 20-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.1.4.4.2 TRAIN2 Comm Completion BR Train 2 4 19-Mar-22 23-Mar-22 19-Mar-22 23-Mar-22 24 On schedule 1
STPPCC15110 Commissiining completion of Lagoon Lot 2 Comm Completion BR Train 2 Lagoon Lot 2 0 19-Mar-22 19-Mar-22 20 On schedule 1
STPPCC15120 Commissioning completion of Lagoon Lot 3 Comm Completion BR Train 2 Lagoon Lot 3 0 23-Mar-22 23-Mar-22 24 On schedule 1
MARAFIQ COMM.1.5 PERFORMANCE AND RELIABILITY TESTING ( INITIAL ACCEPTA Performance and reliability Train1 & 2 15 10-Apr-22 1-May-22 10-Apr-22 1-May-22 63 On schedule 1
MARAFIQ COMM.1.5.1 TRAIN 1& 2-1 Performance and reliability Train1 & 2 18 10-Apr-22 1-May-22 10-Apr-22 1-May-22 63 On schedule 1
STPPCC15280 PGTR Start - Train1 & 2 Performance and reliability Train1 & 2 0 10-Apr-22 10-Apr-22 1
STPPCC15290 PGTR Completion- Train 1 & 2 Performance and reliability Train1 & 2 0 1-May-22 1-May-22 63 On schedule 1
MARAFIQ COMM.1.5.2 TRAIN2 Performance and reliability Train1 & 2 0 1
MARAFIQ COMM.1.5.3 TRAIN 1& 2 Performance and reliability Train1 & 2 0 1
MARAFIQ COMM.1.6. PLANT COMPLETION Performance and reliability Train1 & 2 0 1-May-22 1-May-22 1-May-22 1-May-22 63 On schedule 1
A1190 Completion of Plant Performance and reliability Train1 & 2 0 1-May-22 1-May-22 63 On schedule 1
MARAFIQ COMM.2 PRECOMMISSIONING- SYSTEM AND SUBSYSTEM Pre-com System and Sub Pre-com System and Sub 155 9-Sep-21 9-Mar-22 9-Sep-21 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.2.24 GREEN FIELD Pre-com System and Sub T-1 151 9-Sep-21 5-Mar-22 9-Sep-21 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.2.24.1 TRAIN1 Pre-com System and Sub T-1 96 9-Sep-21 30-Dec-21 9-Sep-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.20 Expansion in existing SEC building Pre-com System and Sub T-1 22 9-Sep-21 5-Oct-21 9-Sep-21 5-Oct-21 (145) Behind Schedule 1
MARAFIQ COMM.2.24.1.20.1 -MV Existing SEC Switch gear Pre-com System and Sub T-1 MV Existing SEC Switch gear 4 9-Sep-21 13-Sep-21 9-Sep-21 13-Sep-21 (167) Behind Schedule 1
STPPCC11310 System Walkdown Pre-com System and Sub T-1 MV Existing SEC Switch gear 2 9-Sep-21 11-Sep-21 9-Sep-21 11-Sep-21 (169) Behind Schedule 1
STPPCC11380 Punch clearence -A Pre-com System and Sub T-1 MV Existing SEC Switch gear 2 12-Sep-21 13-Sep-21 12-Sep-21 13-Sep-21 (167) Behind Schedule 1
Civil & Structural works in SEC Switchgear
MARAFIQ COMM.2.24.1.20.2 -Civil & Structural works in SEC Switchgear room Pre-com System and Sub T-1 room 8 12-Sep-21 20-Sep-21 12-Sep-21 20-Sep-21 (160) Behind Schedule 1
Civil & Structural works in SEC Switchgear
STPPCC11390 System Walkdown Pre-com System and Sub T-1
room 4 12-Sep-21 15-Sep-21 12-Sep-21 15-Sep-21 (165) Behind Schedule 1
Civil & Structural works in SEC Switchgear
STPPCC11460 Punch clearence -A Pre-com System and Sub T-1 room 4 16-Sep-21 20-Sep-21 16-Sep-21 20-Sep-21 (160) Behind Schedule 1
MARAFIQ COMM.2.24.1.20.3 -SEC switchgear expansion Pre-com System and Sub T-1 SEC switchgear expansion 8 16-Sep-21 26-Sep-21 16-Sep-21 26-Sep-21 (154) Behind Schedule 1
STPPCC11470 System Walkdown Pre-com System and Sub T-1 SEC switchgear expansion 4 16-Sep-21 20-Sep-21 16-Sep-21 20-Sep-21 (160) Behind Schedule 1
STPPCC11540 Punch clearence -A Pre-com System and Sub T-1 SEC switchgear expansion 4 21-Sep-21 26-Sep-21 21-Sep-21 26-Sep-21 (154) Behind Schedule 1
MARAFIQ COMM.2.24.1.20.4 -MV Cable from SEC switchgear to SS 1 Pre-com System and Sub T-1 MV Cable from SEC switchgear to SS 1 12 21-Sep-21 5-Oct-21 21-Sep-21 5-Oct-21 (145) Behind Schedule 1
STPPCC11550 System Walkdown Pre-com System and Sub T-1 MV Cable from SEC switchgear to SS 1 4 21-Sep-21 26-Sep-21 21-Sep-21 26-Sep-21 (154) Behind Schedule 1
STPPCC11580 Continuity and Insulaton test Pre-com System and Sub T-1 MV Cable from SEC switchgear to SS 1 4 27-Sep-21 30-Sep-21 27-Sep-21 30-Sep-21 (150) Behind Schedule 1
STPPCC11620 Punch clearence -A Pre-com System and Sub T-1 MV Cable from SEC switchgear to SS 1 4 2-Oct-21 5-Oct-21 2-Oct-21 5-Oct-21 (145) Behind Schedule 1
MARAFIQ COMM.2.24.1.40. 231-Panel Room for MCC(SST Area) Pre-com System and Sub T-1 Panel Room for MCC(SST Area) 13 2-Oct-21 16-Oct-21 2-Oct-21 16-Oct-21 (134) Behind Schedule 1
System Walkdown - S/ 231- MCC Panel Room SST Area Pre-com System and Sub T-1 Panel Room for MCC(SST Area)
STPPCC12830 2 2-Oct-21 3-Oct-21 2-Oct-21 3-Oct-21 (147) Behind Schedule 1
Continuity and Insulaton test S/ 231- MCC Panel Room Pre-com System and Sub T-1 Panel Room for MCC(SST Area)
STPPCC12850 SST Area 7 4-Oct-21 11-Oct-21 4-Oct-21 11-Oct-21 (139) Behind Schedule 1
Punch clearence -A S/ 231- MCC Panel Room SST Area Pre-com System and Sub T-1 Panel Room for MCC(SST Area)
STPPCC12860 4 12-Oct-21 16-Oct-21 12-Oct-21 16-Oct-21 (134) Behind Schedule 1
STPPCC15390 Energisation of MCC Panel room Pre-com System and Sub T-1 Panel Room for MCC(SST Area) 0 16-Oct-21 16-Oct-21 (134) Behind Schedule 1
MARAFIQ COMM.2.24.1.36. 220-Sub Station-1 Inlet chamber Pre-com System and Sub T-1 Sub Station-1 Inlet chamber 27 16-Oct-21 15-Nov-21 16-Oct-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.2.24.1.36..1 220-1-33 KV MV system Pre-com System and Sub T-1 Sub Station-1 Inlet chamber 27 16-Oct-21 15-Nov-21 16-Oct-21 15-Nov-21 (104) Behind Schedule 1
STPPCC11630 System Walkdown - 220 - 33KV MV System Pre-com System and Sub T-1 Sub Station-1 Inlet chamber 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC11660 Continuity and Insulaton test 220-33KV MV System Pre-com System and Sub T-1 Sub Station-1 Inlet chamber 3 20-Oct-21 23-Oct-21 20-Oct-21 23-Oct-21 (127) Behind Schedule 1
STPPCC11700 Punch issue and clearence -A 220-33KV MV System Pre-com System and Sub T-1 Sub Station-1 Inlet chamber 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC14960 Energisation of S/s 1 Pre-com System and Sub T-1 Sub Station-1 Inlet chamber 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.2.24.1.36..2 220-2-Transformer System Pre-com System and Sub T-1 Transformer System 11 20-Oct-21 1-Nov-21 20-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC11710 System Walkdown - 220 Transformer System Pre-com System and Sub T-1 220 Transformer System 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
Continuity and Insulaton test - 220 Transformer System Pre-com System and Sub T-1 220 Transformer System
STPPCC11740 3 25-Oct-21 27-Oct-21 25-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC11780 Punch clearence -A - 220-2 Transformer System Pre-com System and Sub T-1 220 Transformer System 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
MARAFIQ COMM.2.24.1.36..3 220-3-LV system Pre-com System and Sub T-1 220-03LV system 11 25-Oct-21 6-Nov-21 25-Oct-21 6-Nov-21 (113) Behind Schedule 1
STPPCC11790 System Walkdown 220 LV System Pre-com System and Sub T-1 220-03LV system 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
STPPCC11820 Continuity and Insulaton test 220 LV System Pre-com System and Sub T-1 220-03LV system 3 30-Oct-21 1-Nov-21 30-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC11860 Punch clearence -A 220 LV System Pre-com System and Sub T-1 220-03LV system 4 2-Nov-21 6-Nov-21 2-Nov-21 6-Nov-21 (113) Behind Schedule 1
MARAFIQ COMM.2.24.1.36..4 220-4-EDG 1 System Pre-com System and Sub T-1 220 EDG 1 System 11 30-Oct-21 10-Nov-21 30-Oct-21 10-Nov-21 (109) Behind Schedule 1
STPPCC11870 System Walkdown 220 EDG1 System Pre-com System and Sub T-1 220 EDG 1 System 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC11900 Continuity and Insulaton test 220 EDG1 System Pre-com System and Sub T-1 220 EDG 1 System 3 3-Nov-21 6-Nov-21 3-Nov-21 6-Nov-21 (113) Behind Schedule 1
STPPCC11940 Punch clearence -A 220 EDG1 System Pre-com System and Sub T-1 220 EDG 1 System 4 7-Nov-21 10-Nov-21 7-Nov-21 10-Nov-21 (109) Behind Schedule 1
MARAFIQ COMM.2.24.1.36..5 220-5-UPS & Battery System Pre-com System and Sub T-1 220 UPS & Battery System 11 3-Nov-21 15-Nov-21 3-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC11950 System Walkdown 220 UPS & Battery System Pre-com System and Sub T-1 220 UPS & Battery System 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
Continuity and Insulaton test 220 UPS & Battery Pre-com System and Sub T-1 220 UPS & Battery System
STPPCC11980 System 3 8-Nov-21 10-Nov-21 8-Nov-21 10-Nov-21 (109) Behind Schedule 1
STPPCC12020 Punch clearence -A 220 UPS & Battery System Pre-com System and Sub T-1 220 UPS & Battery System 4 11-Nov-21 15-Nov-21 11-Nov-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.2.24.1.37 221-Sub Station-2 Blower room Pre-com System and Sub T-1 221 Sub Station-2 Blower room 28 16-Nov-21 18-Dec-21 16-Nov-21 18-Dec-21 (71) Behind Schedule 1
MARAFIQ COMM.2.24.1.37.1 221-01-33 KV MV system Pre-com System and Sub T-1 221 Sub Station-2 Blower room 28 16-Nov-21 18-Dec-21 16-Nov-21 18-Dec-21 (71) Behind Schedule 1
STPPCC12030 System Walkdown - S/s 221 - 33KV MV System Pre-com System and Sub T-1 221 Sub Station-2 Blower room 4 16-Nov-21 20-Nov-21 16-Nov-21 20-Nov-21 (99) Behind Schedule 1
Continuity and Insulaton test -S/s 221 - 33KV MV Pre-com System and Sub T-1 221 Sub Station-2 Blower room
STPPCC12060 System 4 21-Nov-21 24-Nov-21 21-Nov-21 24-Nov-21 (95) Behind Schedule 1
STPPCC12100 Punch clearence -A -S/s 221 - 33KV MV System Pre-com System and Sub T-1 221 Sub Station-2 Blower room 4 25-Nov-21 29-Nov-21 25-Nov-21 29-Nov-21 (90) Behind Schedule 1
STPPCC15360 Energisation of S/s2 Pre-com System and Sub T-1 221 Sub Station-2 Blower room 0 18-Dec-21 18-Dec-21 (71) Behind Schedule 1
MARAFIQ COMM.2.24.1.37.2 221-02-Transformer System Pre-com System and Sub T-1 221-02-Transformer System 12 21-Nov-21 4-Dec-21 21-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCC12110 System Walkdown - S/s 221- Transformer system Pre-com System and Sub T-1 221-02-Transformer System 4 21-Nov-21 24-Nov-21 21-Nov-21 24-Nov-21 (95) Behind Schedule 1
Continuity and Insulaton test S/s 221- Transformer Pre-com System and Sub T-1 221-02-Transformer System
STPPCC12140 system 4 25-Nov-21 29-Nov-21 25-Nov-21 29-Nov-21 (90) Behind Schedule 1
STPPCC12180 Punch clearence -A S/s 221- Transformer system Pre-com System and Sub T-1 221-02-Transformer System 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
MARAFIQ COMM.2.24.1.37.3 221-03-LV system Pre-com System and Sub T-1 221-03-LV system 12 25-Nov-21 8-Dec-21 25-Nov-21 8-Dec-21 (81) Behind Schedule 1
STPPCC12190 System Walkdown -S/s 221- LV System Pre-com System and Sub T-1 221-03-LV system 4 25-Nov-21 29-Nov-21 25-Nov-21 29-Nov-21 (90) Behind Schedule 1
STPPCC12220 Continuity and Insulaton test -S/s 221- LV System Pre-com System and Sub T-1 221-03-LV system 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCC12260 Punch clearence -A -S/s 221- LV System Pre-com System and Sub T-1 221-03-LV system 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
MARAFIQ COMM.2.24.1.37.4 221-04-EDG 2 System Pre-com System and Sub T-1 221-04-EDG 2 System 12 30-Nov-21 13-Dec-21 30-Nov-21 13-Dec-21 (76) Behind Schedule 1
STPPCC12270 System Walkdown - S/s 221- EDG2 System Pre-com System and Sub T-1 221-04-EDG 2 System 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCC12300 Continuity and Insulaton test - S/s 221- EDG2 System Pre-com System and Sub T-1 221-04-EDG 2 System 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
STPPCC12340 Punch clearence -A - S/s 221- EDG2 System Pre-com System and Sub T-1 221-04-EDG 2 System 4 9-Dec-21 13-Dec-21 9-Dec-21 13-Dec-21 (76) Behind Schedule 1
MARAFIQ COMM.2.24.1.37.5 221-05-UPS & Battery System Pre-com System and Sub T-1 221-05-UPS & Battery System 12 5-Dec-21 18-Dec-21 5-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCC12350 System Walkdown - S/s 221- UPS & Battery System Pre-com System and Sub T-1 221-05-UPS & Battery System 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
Continuity and Insulaton test S/s 221- UPS & Battery Pre-com System and Sub T-1 221-05-UPS & Battery System
STPPCC12380 System 4 9-Dec-21 13-Dec-21 9-Dec-21 13-Dec-21 (76) Behind Schedule 1
STPPCC12420 Punch clearence -A S/s 221- UPS & Battery System Pre-com System and Sub T-1 221-05-UPS & Battery System 4 14-Dec-21 18-Dec-21 14-Dec-21 18-Dec-21 (71) Behind Schedule 1
MARAFIQ COMM.2.24.1.38. 222-Sub Station-4 TSE Area Pre-com System and Sub T-1 222-Sub Station-4 TSE Area 39 2-Oct-21 15-Nov-21 2-Oct-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.2.24.1.38..1 222-01-4.16 MV system Pre-com System and Sub T-1 222-01-4.16 MV system 39 2-Oct-21 15-Nov-21 2-Oct-21 15-Nov-21 (104) Behind Schedule 1
STPPCC12430 System Walkdown - S/s 222- TSE Area Pre-com System and Sub T-1 222-01-4.16 MV system 4 2-Oct-21 5-Oct-21 2-Oct-21 5-Oct-21 (145) Behind Schedule 1
STPPCC12460 Continuity and Insulaton test - S/s 222- TSE Area Pre-com System and Sub T-1 222-01-4.16 MV system 4 6-Oct-21 10-Oct-21 6-Oct-21 10-Oct-21 (140) Behind Schedule 1
STPPCC12500 Punch clearence -A - S/s 222- TSE Area Pre-com System and Sub T-1 222-01-4.16 MV system 4 11-Oct-21 14-Oct-21 11-Oct-21 14-Oct-21 (136) Behind Schedule 1
STPPCC15370 Energisation of S/s 4 Pre-com System and Sub T-1 222-01-4.16 MV system 0 15-Nov-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.2.24.1.38..2 222-02-Transformer System Pre-com System and Sub T-1 222-02-Transformer System 12 6-Oct-21 19-Oct-21 6-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC12510 System Walkdown - S/s 222- Transformer system Pre-com System and Sub T-1 222-02-Transformer System 4 6-Oct-21 10-Oct-21 6-Oct-21 10-Oct-21 (140) Behind Schedule 1
Continuity and Insulaton test S/s 222- Transformer Pre-com System and Sub T-1 222-02-Transformer System
STPPCC12530 system 4 11-Oct-21 14-Oct-21 11-Oct-21 14-Oct-21 (136) Behind Schedule 1
STPPCC12540 Punch clearence -A- S/s 222- Transformer system Pre-com System and Sub T-1 222-02-Transformer System 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
MARAFIQ COMM.2.24.1.38..3 222-03-LV system Pre-com System and Sub T-1 222-03-LV system 12 11-Oct-21 24-Oct-21 11-Oct-21 24-Oct-21 (126) Behind Schedule 1
STPPCC12550 System Walkdown - S/s 222- LV System Pre-com System and Sub T-1 222-03-LV system 4 11-Oct-21 14-Oct-21 11-Oct-21 14-Oct-21 (136) Behind Schedule 1
STPPCC12570 Continuity and Insulaton test - S/s 222- LV System Pre-com System and Sub T-1 222-03-LV system 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC12580 Punch clearence -A - S/s 222- LV System Pre-com System and Sub T-1 222-03-LV system 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
MARAFIQ COMM.2.24.1.38..4 222-04-EDG 3 System Pre-com System and Sub T-1 222-04-EDG 3 System 12 16-Oct-21 28-Oct-21 16-Oct-21 28-Oct-21 (122) Behind Schedule 1
STPPCC12590 System Walkdown - S/s 222- EDG3 System Pre-com System and Sub T-1 222-04-EDG 3 System 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC12610 Continuity and Insulaton test - S/s 222- EDG3 System Pre-com System and Sub T-1 222-04-EDG 3 System 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
STPPCC12620 Punch clearence -A - S/s 222- EDG3 System Pre-com System and Sub T-1 222-04-EDG 3 System 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
MARAFIQ COMM.2.24.1.38..5 222-05-UPS & Battery System Pre-com System and Sub T-1 222-05-UPS & Battery System 12 20-Oct-21 2-Nov-21 20-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC12630 System Walkdown - S/s 222- UPS & Battery System Pre-com System and Sub T-1 222-05-UPS & Battery System 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
Continuity and Insulaton test - S/s 222- UPS & Battery Pre-com System and Sub T-1 222-05-UPS & Battery System
STPPCC12650 System 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
STPPCC12660 Punch clearence -A - S/s 222- UPS & Battery System Pre-com System and Sub T-1 222-05-UPS & Battery System 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
MARAFIQ COMM.2.24.1.39 230-Sub Station-3 SST Area Pre-com System and Sub T-1 230-Sub Station-3 SST Area 24 1-Dec-21 28-Dec-21 1-Dec-21 28-Dec-21 (61) Behind Schedule 1
MARAFIQ COMM.2.24.1.39.1 230-01-Transformer System Pre-com System and Sub T-1 230-Sub Station-3 SST Area 24 1-Dec-21 28-Dec-21 1-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC12670 System Walkdown S/s 230- Transformer system Pre-com System and Sub T-1 230-Sub Station-3 SST Area 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
Continuity and Insulaton test S/s 230- Transformer Pre-com System and Sub T-1 230-Sub Station-3 SST Area
STPPCC12690 system 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC12700 Punch clearence -A S/s 230- Transformer system Pre-com System and Sub T-1 230-Sub Station-3 SST Area 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC15380 Energisation of S/s 3 Pre-com System and Sub T-1 230-Sub Station-3 SST Area 0 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
MARAFIQ COMM.2.24.1.39.2 230-02-LV system Pre-com System and Sub T-1 230-02-LV system 12 6-Dec-21 19-Dec-21 6-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC12710 System Walkdown - S/s 230- LV System Pre-com System and Sub T-1 230-02-LV system 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC12730 Continuity and Insulaton test - S/s 230- LV System Pre-com System and Sub T-1 230-02-LV system 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC12740 Punch clearence -A - S/s 230- LV System Pre-com System and Sub T-1 230-02-LV system 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
MARAFIQ COMM.2.24.1.39.3 230-03-EDG 3 System Pre-com System and Sub T-1 230-03-EDG 3 System 12 11-Dec-21 23-Dec-21 11-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC12750 System Walkdown- S/s 230 -EDG System Pre-com System and Sub T-1 230-03-EDG 3 System 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC12770 Continuity and Insulaton test - S/s 230 -EDG System Pre-com System and Sub T-1 230-03-EDG 3 System 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC12780 Punch clearence -A - S/s 230 -EDG System Pre-com System and Sub T-1 230-03-EDG 3 System 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
MARAFIQ COMM.2.24.1.39.4 230-04-UPS & Battery System Pre-com System and Sub T-1 230-04-UPS & Battery System 12 15-Dec-21 28-Dec-21 15-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC12790 System Walkdown - S/s 230- UPS & Battery System Pre-com System and Sub T-1 230-04-UPS & Battery System 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
Continuity and Insulaton test - S/s 230- UPS & Battery Pre-com System and Sub T-1 230-04-UPS & Battery System
STPPCC12810 System 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC12820 Punch clearence -A - S/s 230- UPS & Battery System Pre-com System and Sub T-1 230-04-UPS & Battery System 4 25-Dec-21 28-Dec-21 25-Dec-21 28-Dec-21 (61) Behind Schedule 1
MARAFIQ COMM.2.24.1.35 210-Control Operation Room Pre-com System and Sub T-1 210-Control Operation Room 13 16-Dec-21 30-Dec-21 16-Dec-21 30-Dec-21 (59) Behind Schedule 1
210-01-Control Operation Room - Ground
MARAFIQ COMM.2.24.1.35.1 210-01-Control Operation Room - Ground Floor Pre-com System and Sub T-1 Floor 13 16-Dec-21 30-Dec-21 16-Dec-21 30-Dec-21 (59) Behind Schedule 1
210-01-Control Operation Room - Ground
STPPCC11230 System Walkdown Pre-com System and Sub T-1 Floor 2 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 (71) Behind Schedule 1
210-01-Control Operation Room - Ground
STPPCC11260 Continuity and Insulaton test Pre-com System and Sub T-1 Floor 3 19-Dec-21 21-Dec-21 19-Dec-21 21-Dec-21 (68) Behind Schedule 1
210-01-Control Operation Room - Ground
STPPCC11290 Loop testing Pre-com System and Sub T-1 Floor 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
210-01-Control Operation Room - Ground
STPPCC11300 Punch clearence -A Pre-com System and Sub T-1 Floor 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.35.2 210-01-Control Operation Room - First Floor Pre-com System and Sub T-1 210-01-Control Operation Room - First Floor 13 16-Dec-21 30-Dec-21 16-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC14050 System Walkdown Pre-com System and Sub T-1 210-01-Control Operation Room - First Floor 2 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCC14060 Continuity and Insulaton test Pre-com System and Sub T-1 210-01-Control Operation Room - First Floor 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
STPPCC14070 Loop testing Pre-com System and Sub T-1 210-01-Control Operation Room - First Floor 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC14080 Punch clearence -A Pre-com System and Sub T-1 210-01-Control Operation Room - First Floor 3 28-Dec-21 30-Dec-21 28-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.21 Potable Water System Pre-com System and Sub T-1 210-Potable Water System 8 16-Dec-21 25-Dec-21 16-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC15160 System Walk down - Potable Water System Pre-com System and Sub T-1 210-Potable Water System 4 16-Dec-21 20-Dec-21 16-Dec-21 20-Dec-21 (69) Behind Schedule 1
STPPCC15170 Punch Clearence- A Pre-com System and Sub T-1 210-Potable Water System 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
MARAFIQ COMM.2.24.1.22 Fire Water System Pre-com System and Sub T-1 210- Fire Water System 8 16-Dec-21 25-Dec-21 16-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC15190 System Walk down - Fire Water System Pre-com System and Sub T-1 210- Fire Water System 4 16-Dec-21 20-Dec-21 16-Dec-21 20-Dec-21 (69) Behind Schedule 1
STPPCC15200 Punch Clearence- A Pre-com System and Sub T-1 210- Fire Water System 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
MARAFIQ COMM.2.24.1.23 Service Water System Pre-com System and Sub T-1 210-Service Water System 8 16-Dec-21 25-Dec-21 16-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC15210 System Walk down - Service water System Pre-com System and Sub T-1 210-Service Water System 4 16-Dec-21 20-Dec-21 16-Dec-21 20-Dec-21 (69) Behind Schedule 1
STPPCC15220 Punch Clearence- A Pre-com System and Sub T-1 210-Service Water System 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
MARAFIQ COMM.2.24.1.24 Fiber Optic System Pre-com System and Sub T-1 210-Fiber Optic System 8 6-Dec-21 14-Dec-21 6-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC15460 System Walkdown- Fiber Optic System Pre-com System and Sub T-1 210-Fiber Optic System 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC15470 Punch clearence A Pre-com System and Sub T-1 210-Fiber Optic System 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
MARAFIQ COMM.2.24.1.1 S001 Inlet Connenction Chamber Pre-com System and Sub T-1 210-Inlet Connenction Chamber 11 15-Dec-21 27-Dec-21 15-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC0010 System Walkdown Pre-com System and Sub T-1 210-Inlet Connenction Chamber 2 15-Dec-21 16-Dec-21 15-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC1000 Flushing /Cleaning Pre-com System and Sub T-1 210-Inlet Connenction Chamber 1 23-Dec-21 23-Dec-21 23-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC1010 Machinery Cold run test Pre-com System and Sub T-1 210-Inlet Connenction Chamber 1 25-Dec-21 25-Dec-21 25-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC1020 Continuity and Insulaton test Pre-com System and Sub T-1 210-Inlet Connenction Chamber 1 26-Dec-21 26-Dec-21 26-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC1060 Punch clearence -A Pre-com System and Sub T-1 210-Inlet Connenction Chamber 1 27-Dec-21 27-Dec-21 27-Dec-21 27-Dec-21 (62) Behind Schedule 1
MARAFIQ COMM.2.24.1.2 S010 Inlet Splitter Box Pre-com System and Sub T-1 S010 Inlet Splitter Box 13 1-Dec-21 15-Dec-21 1-Dec-21 15-Dec-21 (74) Behind Schedule 1
STPPCC1070 System Walkdown Pre-com System and Sub T-1 S010 Inlet Splitter Box 2 1-Dec-21 2-Dec-21 1-Dec-21 2-Dec-21 (87) Behind Schedule 1
STPPCC1080 Flushing /Cleaning Pre-com System and Sub T-1 S010 Inlet Splitter Box 2 4-Dec-21 5-Dec-21 4-Dec-21 5-Dec-21 (84) Behind Schedule 1
STPPCC1090 Machinery Cold run test Pre-com System and Sub T-1 S010 Inlet Splitter Box 2 6-Dec-21 7-Dec-21 6-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC1100 Continuity and Insulaton test Pre-com System and Sub T-1 S010 Inlet Splitter Box 2 8-Dec-21 9-Dec-21 8-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC1110 Motor rotational check test Pre-com System and Sub T-1 S010 Inlet Splitter Box 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC1140 Punch clearence -A Pre-com System and Sub T-1 S010 Inlet Splitter Box 3 13-Dec-21 15-Dec-21 13-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.2.24.1.3 S020 Inlet Flow Measurement Pre-com System and Sub T-1 S020 Inlet Flow Measurement 26 1-Dec-21 30-Dec-21 1-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC1150 System Walkdown Pre-com System and Sub T-1 S020 Inlet Flow Measurement 2 1-Dec-21 2-Dec-21 1-Dec-21 2-Dec-21 (87) Behind Schedule 1
STPPCC1160 Flushing /Cleaning Pre-com System and Sub T-1 S020 Inlet Flow Measurement 2 4-Dec-21 5-Dec-21 4-Dec-21 5-Dec-21 (84) Behind Schedule 1
STPPCC1170 Machinery Cold run test Pre-com System and Sub T-1 S020 Inlet Flow Measurement 2 6-Dec-21 7-Dec-21 6-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC1180 Continuity and Insulaton test Pre-com System and Sub T-1 S020 Inlet Flow Measurement 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC1190 Motor rotational check test Pre-com System and Sub T-1 S020 Inlet Flow Measurement 2 13-Dec-21 14-Dec-21 13-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC1210 Loop testing Pre-com System and Sub T-1 S020 Inlet Flow Measurement 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC1220 Punch clearence -A Pre-com System and Sub T-1 S020 Inlet Flow Measurement 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.4 S035 Inlet Chamber Pre-com System and Sub T-1 S035 Inlet Chamber 26 1-Dec-21 30-Dec-21 1-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC1230 System Walkdown Pre-com System and Sub T-1 S035 Inlet Chamber 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
STPPCC1240 Flushing /Cleaning Pre-com System and Sub T-1 S035 Inlet Chamber 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC1250 Machinery Cold run test Pre-com System and Sub T-1 S035 Inlet Chamber 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC1260 Continuity and Insulaton test Pre-com System and Sub T-1 S035 Inlet Chamber 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC1280 Motor rotational check test Pre-com System and Sub T-1 S035 Inlet Chamber 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC1290 Loop testing Pre-com System and Sub T-1 S035 Inlet Chamber 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC1300 Punch clearence -A Pre-com System and Sub T-1 S035 Inlet Chamber 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.5 S030 Finescreen Pre-com System and Sub T-1 S030 Finescreen 26 1-Dec-21 30-Dec-21 1-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC1310 System Walkdown Pre-com System and Sub T-1 S030 Finescreen 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
STPPCC1320 Flushing /Cleaning Pre-com System and Sub T-1 S030 Finescreen 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC1330 Machinery Cold run test Pre-com System and Sub T-1 S030 Finescreen 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC1340 Continuity and Insulaton test Pre-com System and Sub T-1 S030 Finescreen 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC1350 Motor rotational check test Pre-com System and Sub T-1 S030 Finescreen 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC1370 Loop testing Pre-com System and Sub T-1 S030 Finescreen 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC1380 Punch clearence -A Pre-com System and Sub T-1 S030 Finescreen 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.6 040 Grit and grease chamber Pre-com System and Sub T-1 040 Grit and grease chamber 25 1-Dec-21 29-Dec-21 1-Dec-21 29-Dec-21 (60) Behind Schedule 1
MARAFIQ COMM.2.24.1.6.1 040-1A-Grit and Grease Chamber-1A Pre-com System and Sub T-1 040 Grit and grease chamber 23 1-Dec-21 27-Dec-21 1-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC1390 System Walkdown Pre-com System and Sub T-1 040 Grit and grease chamber 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
STPPCC1400 Flushing /Cleaning Pre-com System and Sub T-1 040 Grit and grease chamber 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC1410 Machinery Cold run test Pre-com System and Sub T-1 040 Grit and grease chamber 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC1420 Continuity and Insulaton test Pre-com System and Sub T-1 040 Grit and grease chamber 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC1430 Motor rotational check test Pre-com System and Sub T-1 040 Grit and grease chamber 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC1450 Loop testing Pre-com System and Sub T-1 040 Grit and grease chamber 1 25-Dec-21 25-Dec-21 25-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC1460 Punch clearence -A Pre-com System and Sub T-1 040 Grit and grease chamber 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
MARAFIQ COMM.2.24.1.6.2 040-1B-Grit and Grease Chamber-1B Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 25 1-Dec-21 29-Dec-21 1-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC1470 System Walkdown Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
STPPCC1480 Flushing /Cleaning Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC1490 Machinery run test Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC1500 Continuity and Insulaton test Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC1510 Motor rotational check test Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC1530 Loop testing Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 2 25-Dec-21 26-Dec-21 25-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC1540 Punch clearence -A Pre-com System and Sub T-1 040-1B-Grit and Grease Chamber-1B 3 27-Dec-21 29-Dec-21 27-Dec-21 29-Dec-21 (60) Behind Schedule 1
050-Distribution Chambers for Activated
MARAFIQ COMM.2.24.1.7 050-Distribution Chambers for Activated Sludge TanksPre-com System and Sub T-1 Sludge Tanks (AST) 23 1-Dec-21 27-Dec-21 1-Dec-21 27-Dec-21 (62) Behind Schedule 1
050-Distribution Chambers for Activated
STPPCC1870 System Walkdown Pre-com System and Sub T-1 Sludge Tanks (AST) 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
050-Distribution Chambers for Activated
STPPCC1880 Flushing /Cleaning Pre-com System and Sub T-1 Sludge Tanks (AST) 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
050-Distribution Chambers for Activated
STPPCC1890 Machinery Cold run test Pre-com System and Sub T-1
Sludge Tanks (AST) 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
050-Distribution Chambers for Activated
STPPCC1900 Continuity and Insulaton test Pre-com System and Sub T-1 Sludge Tanks (AST) 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
050-Distribution Chambers for Activated
STPPCC1910 Motor rotational check test Pre-com System and Sub T-1 Sludge Tanks (AST) 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
050-Distribution Chambers for Activated
STPPCC1940 Punch clearence -A Pre-com System and Sub T-1 Sludge Tanks (AST) 3 25-Dec-21 27-Dec-21 25-Dec-21 27-Dec-21 (62) Behind Schedule 1
MARAFIQ COMM.2.24.1.8 060-Activated Sludge Tanks (AST) Commissioning 27 16-Oct-21 15-Nov-21 16-Oct-21 15-Nov-21 (104) Behind Schedule 1
MARAFIQ COMM.2.24.1.8.1 060-1-Activated Sludge Tanks-01 Commissioning 060-1-Activated Sludge Tanks-01 27 16-Oct-21 15-Nov-21 16-Oct-21 15-Nov-21 (104) Behind Schedule 1
STPPCC2030 System Walkdown Commissioning 060-1-Activated Sludge Tanks-01 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC2040 Flushing /Cleaning Commissioning 060-1-Activated Sludge Tanks-01 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
STPPCC2050 Machinery Cold run test Commissioning 060-1-Activated Sludge Tanks-01 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
STPPCC2060 Continuity and Insulaton test Commissioning 060-1-Activated Sludge Tanks-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC2070 Motor rotational check test Commissioning 060-1-Activated Sludge Tanks-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC2090 Loop testing Commissioning 060-1-Activated Sludge Tanks-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC2100 Punch clearence -A Commissioning 060-1-Activated Sludge Tanks-01 3 13-Nov-21 15-Nov-21 13-Nov-21 15-Nov-21 (104) Behind Schedule 1
070-Distribution Chambers for Secondary
MARAFIQ COMM.2.24.1.10 070-Distribution Chambers for Secondary Sedimenta Commissioning Sedimentation Tanks (SST) 23 30-Sep-21 26-Oct-21 30-Sep-21 26-Oct-21 (124) Behind Schedule 1
070-Distribution Chambers for Secondary
MARAFIQ COMM.2.24.1.10.1 070-1-Distribution Chambers for Secondary Sedi Commissioning Sedimentation Tanks (SST) 23 30-Sep-21 26-Oct-21 30-Sep-21 26-Oct-21 (124) Behind Schedule 1
070-Distribution Chambers for Secondary
STPPCC2350 System Walkdown Commissioning Sedimentation Tanks (SST) 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
070-Distribution Chambers for Secondary
STPPCC2360 Flushing /Cleaning Commissioning Sedimentation Tanks (SST) 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
070-Distribution Chambers for Secondary
STPPCC2370 Machinery Cold run test Commissioning Sedimentation Tanks (SST) 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
070-Distribution Chambers for Secondary
STPPCC2380 Continuity and Insulaton test Commissioning Sedimentation Tanks (SST) 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
070-Distribution Chambers for Secondary
STPPCC2390 Motor rotational check test Commissioning Sedimentation Tanks (SST) 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
070-Distribution Chambers for Secondary
STPPCC2420 Punch clearence -A Commissioning Sedimentation Tanks (SST) 3 24-Oct-21 26-Oct-21 24-Oct-21 26-Oct-21 (124) Behind Schedule 1
MARAFIQ COMM.2.24.1.9 065-Blower Building Commissioning 065-Blower Building 32 30-Sep-21 6-Nov-21 30-Sep-21 6-Nov-21 (113) Behind Schedule 1
STPPCC2270 System Walkdown Commissioning 065-Blower Building 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
STPPCC2280 Flushing /Cleaning Commissioning 065-Blower Building 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
STPPCC2290 Machinery Cold run test Commissioning 065-Blower Building 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC2300 Continuity and Insulaton test Commissioning 065-Blower Building 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
STPPCC2310 Motor rotational check test Commissioning 065-Blower Building 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
STPPCC2330 Loop testing Commissioning 065-Blower Building 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC2340 Punch clearence -A Commissioning 065-Blower Building 3 3-Nov-21 6-Nov-21 3-Nov-21 6-Nov-21 (113) Behind Schedule 1
MARAFIQ COMM.2.24.1.11 080-Secondary Sedimentation Tanks (SST) Commissioning 080-Secondary Sedimentation Tanks (SST) 27 30-Sep-21 31-Oct-21 30-Sep-21 31-Oct-21 (119) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
MARAFIQ COMM.2.24.1.11.1 080-1-Secondary Sedimentation Tanks (SST)-01 Commissioning 01 27 30-Sep-21 31-Oct-21 30-Sep-21 31-Oct-21 (119) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2590 System Walkdown Commissioning 01 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2600 Flushing /Cleaning Commissioning
01 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2610 Machinery Cold run test Commissioning 01 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2620 Continuity and Insulaton test Commissioning 01 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2630 Motor rotational check test Commissioning 01 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2650 Loop testing Commissioning
01 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
080-1-Secondary Sedimentation Tanks (SST)-
STPPCC2660 Punch clearence -A Commissioning 01 3 28-Oct-21 31-Oct-21 28-Oct-21 31-Oct-21 (119) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
MARAFIQ COMM.2.24.1.11.2 080-2-Secondary Sedimentation Tanks (SST)-02 Commissioning 02 27 30-Sep-21 31-Oct-21 30-Sep-21 31-Oct-21 (119) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2670 System Walkdown Commissioning 02 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2680 Flushing /Cleaning Commissioning
02 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2690 Machinery Cold run test Commissioning 02 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2700 Continuity and Insulaton test Commissioning 02 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2710 Motor rotational check test Commissioning 02 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2730 Loop testing Commissioning
02 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
080-2-Secondary Sedimentation Tanks (SST)-
STPPCC2740 Punch clearence -A Commissioning 02 3 28-Oct-21 31-Oct-21 28-Oct-21 31-Oct-21 (119) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
MARAFIQ COMM.2.24.1.11.3 080-3-Secondary Sedimentation Tanks (SST)-03 Commissioning 03 27 30-Sep-21 31-Oct-21 30-Sep-21 31-Oct-21 (119) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2750 System Walkdown Commissioning 03 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2760 Flushing /Cleaning Commissioning 03 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2770 Machinery Cold run test Commissioning 03 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2780 Continuity and Insulaton test Commissioning 03 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2790 Motor rotational check test Commissioning 03 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2810 Loop testing Commissioning 03 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
080-3-Secondary Sedimentation Tanks (SST)-
STPPCC2820 Punch clearence -A Commissioning 03 3 28-Oct-21 31-Oct-21 28-Oct-21 31-Oct-21 (119) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
MARAFIQ COMM.2.24.1.11.4 080-4-Secondary Sedimentation Tanks (SST)-04 Commissioning 04 27 30-Sep-21 31-Oct-21 30-Sep-21 31-Oct-21 (119) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2830 System Walkdown Commissioning
04 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2840 Flushing /Cleaning Commissioning 04 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2850 Machinery Cold run test Commissioning 04 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2860 Continuity and Insulaton test Commissioning 04 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2870 Motor rotational check test Commissioning
04 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2890 Loop testing Commissioning 04 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
080-4-Secondary Sedimentation Tanks (SST)-
STPPCC2900 Punch clearence -A Commissioning 04 3 28-Oct-21 31-Oct-21 28-Oct-21 31-Oct-21 (119) Behind Schedule 1
120-Excess and Return Sludge Pumping
MARAFIQ COMM.2.24.1.12 120-Excess and Return Sludge Pumping Station Commissioning Station 32 30-Sep-21 6-Nov-21 30-Sep-21 6-Nov-21 (113) Behind Schedule 1
120-Excess and Return Sludge Pumping
MARAFIQ COMM.2.24.1.12.1 120-1-Excess and Return Sludge Pumping Station Commissioning
Station 32 30-Sep-21 6-Nov-21 30-Sep-21 6-Nov-21 (113) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3550 System Walkdown Commissioning Station 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3560 Flushing /Cleaning Commissioning Station 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3570 Machinery Cold run test Commissioning Station 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3580 Continuity and Insulaton test Commissioning
Station 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3590 Motor rotational check test Commissioning Station 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3610 Loop testing Commissioning Station 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
120-Excess and Return Sludge Pumping
STPPCC3620 Punch clearence -A Commissioning Station 3 3-Nov-21 6-Nov-21 3-Nov-21 6-Nov-21 (113) Behind Schedule 1
MARAFIQ COMM.2.24.1.13 125-Scum Pumping Station Commissioning 125-Scum Pumping Station 32 30-Sep-21 6-Nov-21 30-Sep-21 6-Nov-21 (113) Behind Schedule 1
MARAFIQ COMM.2.24.1.13.1 125-1-Scum Pumping Station-01 Commissioning 125-Scum Pumping Station 32 30-Sep-21 6-Nov-21 30-Sep-21 6-Nov-21 (113) Behind Schedule 1
STPPCC3790 System Walkdown Commissioning 125-Scum Pumping Station 4 30-Sep-21 4-Oct-21 30-Sep-21 4-Oct-21 (146) Behind Schedule 1
STPPCC3800 Flushing /Cleaning Commissioning 125-Scum Pumping Station 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
STPPCC3810 Machinery Cold run test Commissioning 125-Scum Pumping Station 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC3820 Continuity and Insulaton test Commissioning 125-Scum Pumping Station 4 20-Oct-21 24-Oct-21 20-Oct-21 24-Oct-21 (126) Behind Schedule 1
STPPCC3830 Motor rotational check test Commissioning 125-Scum Pumping Station 4 25-Oct-21 28-Oct-21 25-Oct-21 28-Oct-21 (122) Behind Schedule 1
STPPCC3850 Loop testing Commissioning 125-Scum Pumping Station 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC3860 Punch clearence -A Commissioning 125-Scum Pumping Station 3 3-Nov-21 6-Nov-21 3-Nov-21 6-Nov-21 (113) Behind Schedule 1
MARAFIQ COMM.2.24.1.13.2 125-2-Scum Pumping Station-02 Commissioning 125-2-Scum Pumping Station-02 27 5-Oct-21 4-Nov-21 5-Oct-21 4-Nov-21 (115) Behind Schedule 1
STPPCC3870 System Walkdown Commissioning 125-2-Scum Pumping Station-02 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
STPPCC3880 Flushing /Cleaning Commissioning 125-2-Scum Pumping Station-02 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
STPPCC3890 Machinery Cold run test Commissioning 125-2-Scum Pumping Station-02 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
STPPCC3900 Continuity and Insulaton test Commissioning 125-2-Scum Pumping Station-02 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
STPPCC3910 Motor rotational check test Commissioning 125-2-Scum Pumping Station-02 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC3930 Loop testing Commissioning 125-2-Scum Pumping Station-02 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC3940 Punch clearence -A Commissioning 125-2-Scum Pumping Station-02 3 2-Nov-21 4-Nov-21 2-Nov-21 4-Nov-21 (115) Behind Schedule 1
MARAFIQ COMM.2.24.1.14 090-Rapid Sand Filters Commissioning 090-Rapid Sand Filters 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.1 090-01-Rapid Sand Filters-01 Commissioning 090-Rapid Sand Filters 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC4110 System Walkdown Commissioning 090-Rapid Sand Filters 1 10-Nov-21 10-Nov-21 10-Nov-21 10-Nov-21 (109) Behind Schedule 1
STPPCC4120 Flushing /Cleaning Commissioning 090-Rapid Sand Filters 1 11-Nov-21 11-Nov-21 11-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC4130 Machinery Cold run test Commissioning 090-Rapid Sand Filters 1 11-Dec-21 11-Dec-21 11-Dec-21 11-Dec-21 (78) Behind Schedule 1
STPPCC4140 Continuity and Insulaton test Commissioning 090-Rapid Sand Filters 1 12-Dec-21 12-Dec-21 12-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC4150 Motor rotational check test Commissioning 090-Rapid Sand Filters 1 13-Dec-21 13-Dec-21 13-Dec-21 13-Dec-21 (76) Behind Schedule 1
STPPCC4170 Loop testing Commissioning 090-Rapid Sand Filters 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC4180 Punch clearence -A Commissioning 090-Rapid Sand Filters 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.2 090-02-Rapid Sand Filters-02 Commissioning 090-02-Rapid Sand Filters-02 43 11-Nov-21 30-Dec-21 11-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC4190 System Walkdown Commissioning 090-02-Rapid Sand Filters-02 2 11-Nov-21 13-Nov-21 11-Nov-21 13-Nov-21 (106) Behind Schedule 1
STPPCC4200 Flushing /Cleaning Commissioning 090-02-Rapid Sand Filters-02 2 14-Nov-21 15-Nov-21 14-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC4210 Machinery Cold run test Commissioning 090-02-Rapid Sand Filters-02 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC4220 Continuity and Insulaton test Commissioning 090-02-Rapid Sand Filters-02 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC4230 Motor rotational check test Commissioning 090-02-Rapid Sand Filters-02 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC4250 Loop testing Commissioning 090-02-Rapid Sand Filters-02 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC4260 Punch clearence -A Commissioning 090-02-Rapid Sand Filters-02 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.3 090-03-Rapid Sand Filters-03 Commissioning 090-03-Rapid Sand Filters-03 41 14-Nov-21 30-Dec-21 14-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC4270 System Walkdown Commissioning 090-03-Rapid Sand Filters-03 2 14-Nov-21 15-Nov-21 14-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC4280 Flushing /Cleaning Commissioning 090-03-Rapid Sand Filters-03 2 16-Nov-21 17-Nov-21 16-Nov-21 17-Nov-21 (102) Behind Schedule 1
STPPCC4290 Machinery Cold run test Commissioning 090-03-Rapid Sand Filters-03 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC4300 Continuity and Insulaton test Commissioning 090-03-Rapid Sand Filters-03 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC4310 Motor rotational check test Commissioning 090-03-Rapid Sand Filters-03 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC4330 Loop testing Commissioning 090-03-Rapid Sand Filters-03 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC4340 Punch clearence -A Commissioning 090-03-Rapid Sand Filters-03 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.4 090-04-Rapid Sand Filters-04 Commissioning 090-04-Rapid Sand Filters-04 15 11-Dec-21 27-Dec-21 11-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC4350 System Walkdown Commissioning 090-04-Rapid Sand Filters-04 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC4360 Flushing /Cleaning Commissioning 090-04-Rapid Sand Filters-04 2 13-Dec-21 14-Dec-21 13-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC4370 Machinery Cold run test Commissioning 090-04-Rapid Sand Filters-04 2 15-Dec-21 16-Dec-21 15-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC4380 Continuity and Insulaton test Commissioning 090-04-Rapid Sand Filters-04 2 18-Dec-21 19-Dec-21 18-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC4390 Motor rotational check test Commissioning 090-04-Rapid Sand Filters-04 2 20-Dec-21 21-Dec-21 20-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC4410 Loop testing Commissioning 090-04-Rapid Sand Filters-04 2 22-Dec-21 23-Dec-21 22-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC4420 Punch clearence -A Commissioning 090-04-Rapid Sand Filters-04 3 25-Dec-21 27-Dec-21 25-Dec-21 27-Dec-21 (62) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.19 090-19-Back wash water Tanks Commissioning 090-19-Back wash water Tanks 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC5550 System Walkdown Commissioning 090-19-Back wash water Tanks 2 10-Nov-21 11-Nov-21 10-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC5560 Flushing /Cleaning Commissioning 090-19-Back wash water Tanks 2 13-Nov-21 14-Nov-21 13-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC5570 Machinery Cold run test Commissioning 090-19-Back wash water Tanks 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC5580 Continuity and Insulaton test Commissioning 090-19-Back wash water Tanks 1 23-Dec-21 23-Dec-21 23-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC5590 Motor rotational check test Commissioning 090-19-Back wash water Tanks 1 25-Dec-21 25-Dec-21 25-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC5610 Loop testing Commissioning 090-19-Back wash water Tanks 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC5620 Punch clearence -A Commissioning 090-19-Back wash water Tanks 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.20 090-20-Backwash water tank filling pumps Commissioning 090-20-Backwash water tank filling pumps 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC5630 System Walkdown Commissioning 090-20-Backwash water tank filling pumps 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC5640 Flushing /Cleaning Commissioning 090-20-Backwash water tank filling pumps 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC5650 Machinery Cold run test Commissioning 090-20-Backwash water tank filling pumps 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC5660 Continuity and Insulaton test Commissioning 090-20-Backwash water tank filling pumps 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC5670 Motor rotational check test Commissioning 090-20-Backwash water tank filling pumps 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC5690 Loop testing Commissioning 090-20-Backwash water tank filling pumps 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC5700 Punch clearence -A Commissioning 090-20-Backwash water tank filling pumps 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.21 090-21-Rapid sand filtration blowers Commissioning 090-21-Rapid sand filtration blowers 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC5710 System Walkdown Commissioning 090-21-Rapid sand filtration blowers 2 10-Nov-21 11-Nov-21 10-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC5720 Flushing /Cleaning Commissioning 090-21-Rapid sand filtration blowers 2 13-Nov-21 14-Nov-21 13-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC5730 Machinery Cold run test Commissioning 090-21-Rapid sand filtration blowers 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC5740 Continuity and Insulaton test Commissioning 090-21-Rapid sand filtration blowers 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC5750 Motor rotational check test Commissioning 090-21-Rapid sand filtration blowers 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC5770 Loop testing Commissioning 090-21-Rapid sand filtration blowers 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC5780 Punch clearence -A Commissioning 090-21-Rapid sand filtration blowers 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
090-22-Air Compressors for Pneumatic
MARAFIQ COMM.2.24.1.14.22 090-22-Air Compressors for Pneumatic actuator Commissioning actuators 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5790 System Walkdown Commissioning actuators 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5800 Flushing /Cleaning Commissioning
actuators 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5810 Machinery Cold run test Commissioning actuators 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5820 Continuity and Insulaton test Commissioning actuators 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5830 Motor rotational check test Commissioning actuators 1 26-Dec-21 26-Dec-21 26-Dec-21 26-Dec-21 (63) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5850 Loop testing Commissioning
actuators 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
090-22-Air Compressors for Pneumatic
STPPCC5860 Punch clearence -A Commissioning actuators 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.14.23 090-23-Backwash waste water pumps Commissioning 090-23-Backwash waste water pumps 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC5870 System Walkdown Commissioning 090-23-Backwash waste water pumps 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC5880 Flushing /Cleaning Commissioning 090-23-Backwash waste water pumps 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC5890 Machinery Cold run test Commissioning 090-23-Backwash waste water pumps 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC5900 Continuity and Insulaton test Commissioning 090-23-Backwash waste water pumps 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC5910 Motor rotational check test Commissioning 090-23-Backwash waste water pumps 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC5930 Loop testing Commissioning 090-23-Backwash waste water pumps 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
STPPCC5940 Punch clearence -A Commissioning 090-23-Backwash waste water pumps 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.15 101-Chlorine Contact Tank Commissioning 101-Chlorine Contact Tank 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.15.1 101-01-Chlorine Contact Tank-01 Commissioning 101-Chlorine Contact Tank 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC5950 System Walkdown Commissioning 101-Chlorine Contact Tank 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC5960 Flushing /Cleaning Commissioning 101-Chlorine Contact Tank 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC5970 Machinery Cold run test Commissioning 101-Chlorine Contact Tank 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC5980 Continuity and Insulaton test Commissioning 101-Chlorine Contact Tank 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC5990 Motor rotational check test Commissioning 101-Chlorine Contact Tank 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC6020 Punch clearence -A Commissioning 101-Chlorine Contact Tank 3 28-Dec-21 30-Dec-21 28-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.17. 103-Chlorine Dosing Station Commissioning 103-Chlorine Dosing Station 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.17..1 103-01-Chorine Drum Storage room Commissioning 103-Chlorine Dosing Station 27 10-Nov-21 11-Dec-21 10-Nov-21 11-Dec-21 (78) Behind Schedule 1
STPPCC6510 System Walkdown Commissioning 103-Chlorine Dosing Station 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC6520 Flushing /Cleaning Commissioning 103-Chlorine Dosing Station 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC6530 Machinery Cold run test Commissioning 103-Chlorine Dosing Station 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC6540 Continuity and Insulaton test Commissioning 103-Chlorine Dosing Station 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC6550 Motor rotational check test Commissioning 103-Chlorine Dosing Station 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC6570 Loop testing Commissioning 103-Chlorine Dosing Station 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC6580 Punch clearence -A Commissioning 103-Chlorine Dosing Station 3 8-Dec-21 11-Dec-21 8-Dec-21 11-Dec-21 (78) Behind Schedule 1
MARAFIQ COMM.2.24.1.17..2 103-02-Evaporator Room Commissioning 103-02-Evaporator Room 27 10-Nov-21 11-Dec-21 10-Nov-21 11-Dec-21 (78) Behind Schedule 1
STPPCC6590 System Walkdown Commissioning 103-02-Evaporator Room 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC6600 Flushing /Cleaning Commissioning 103-02-Evaporator Room 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC6610 Machinery Cold run test Commissioning 103-02-Evaporator Room 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC6620 Continuity and Insulaton test Commissioning 103-02-Evaporator Room 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC6630 Motor rotational check test Commissioning 103-02-Evaporator Room 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC6650 Loop testing Commissioning 103-02-Evaporator Room 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC6660 Punch clearence -A Commissioning 103-02-Evaporator Room 3 8-Dec-21 11-Dec-21 8-Dec-21 11-Dec-21 (78) Behind Schedule 1
MARAFIQ COMM.2.24.1.17..3 103-03-Chlorinator and Injector room Commissioning 103-03-Chlorinator and Injector room 27 10-Nov-21 11-Dec-21 10-Nov-21 11-Dec-21 (78) Behind Schedule 1
STPPCC6670 System Walkdown Commissioning 103-03-Chlorinator and Injector room 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC6680 Flushing /Cleaning Commissioning 103-03-Chlorinator and Injector room 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC6690 Machinery Cold run test Commissioning 103-03-Chlorinator and Injector room 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC6700 Continuity and Insulaton test Commissioning 103-03-Chlorinator and Injector room 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC6710 Motor rotational check test Commissioning 103-03-Chlorinator and Injector room 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC6730 Loop testing Commissioning 103-03-Chlorinator and Injector room 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC6740 Punch clearence -A Commissioning 103-03-Chlorinator and Injector room 3 8-Dec-21 11-Dec-21 8-Dec-21 11-Dec-21 (78) Behind Schedule 1
MARAFIQ COMM.2.24.1.17..4 103-04-Electrical Room with Control Panel Commissioning 103-04-Electrical Room with Control Panel 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC6750 System Walkdown Commissioning 103-04-Electrical Room with Control Panel 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC6760 Flushing /Cleaning Commissioning 103-04-Electrical Room with Control Panel 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC6770 Machinery Cold run test Commissioning 103-04-Electrical Room with Control Panel 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC6780 Continuity and Insulaton test Commissioning 103-04-Electrical Room with Control Panel 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC6790 Motor rotational check test Commissioning 103-04-Electrical Room with Control Panel 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC6810 Loop testing Commissioning 103-04-Electrical Room with Control Panel 3 25-Dec-21 27-Dec-21 25-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC6820 Punch clearence -A Commissioning 103-04-Electrical Room with Control Panel 3 28-Dec-21 30-Dec-21 28-Dec-21 30-Dec-21 (59) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
MARAFIQ COMM.2.24.1.17..5 103-05-Emergency Scrubber, Safety kit storage Commissioning
storage room 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6830 System Walkdown Commissioning storage room 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6840 Flushing /Cleaning Commissioning storage room 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6850 Machinery Cold run test Commissioning storage room 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6860 Continuity and Insulaton test Commissioning
storage room 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6870 Motor rotational check test Commissioning storage room 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6890 Loop testing Commissioning storage room 1 28-Dec-21 28-Dec-21 28-Dec-21 28-Dec-21 (61) Behind Schedule 1
103-05-Emergency Scrubber, Safety kit
STPPCC6900 Punch clearence -A Commissioning storage room 2 29-Dec-21 30-Dec-21 29-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.16. 102-Reaeration and Chlorine Mixing Tanks Commissioning 102-Reaeration and Chlorine Mixing Tanks 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.16..1 102-01-Reaeration and Chlorine Mixing Tanks Commissioning 102-Reaeration and Chlorine Mixing Tanks 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC6350 System Walkdown Commissioning 102-Reaeration and Chlorine Mixing Tanks 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC6360 Flushing /Cleaning Commissioning 102-Reaeration and Chlorine Mixing Tanks 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC6370 Machinery Cold run test Commissioning 102-Reaeration and Chlorine Mixing Tanks 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC6380 Continuity and Insulaton test Commissioning 102-Reaeration and Chlorine Mixing Tanks 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC6390 Motor rotational check test Commissioning 102-Reaeration and Chlorine Mixing Tanks 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC6410 Loop testing Commissioning 102-Reaeration and Chlorine Mixing Tanks 2 28-Dec-21 29-Dec-21 28-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC6420 Punch clearence -A Commissioning 102-Reaeration and Chlorine Mixing Tanks 1 30-Dec-21 30-Dec-21 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.16..2 102-02-Blowers for Reaeration Tanks Commissioning 102-02-Blowers for Reaeration Tanks 40 15-Nov-21 30-Dec-21 15-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC6430 System Walkdown Commissioning 102-02-Blowers for Reaeration Tanks 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC6440 Flushing /Cleaning Commissioning 102-02-Blowers for Reaeration Tanks 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC6450 Machinery Cold run test Commissioning 102-02-Blowers for Reaeration Tanks 2 11-Dec-21 12-Dec-21 11-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC6460 Continuity and Insulaton test Commissioning 102-02-Blowers for Reaeration Tanks 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC6470 Motor rotational check test Commissioning 102-02-Blowers for Reaeration Tanks 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC6490 Loop testing Commissioning 102-02-Blowers for Reaeration Tanks 2 28-Dec-21 29-Dec-21 28-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC6500 Punch clearence -A Commissioning 102-02-Blowers for Reaeration Tanks 1 30-Dec-21 30-Dec-21 30-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.18. 110-TSE Pumping Station Commissioning 110-TSE Pumping Station 44 10-Nov-21 30-Dec-21 10-Nov-21 30-Dec-21 (59) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
MARAFIQ COMM.2.24.1.18..1 110-01-Chlorine Contact Tank Outlet Chamber Commissioning Chamber 27 10-Nov-21 11-Dec-21 10-Nov-21 11-Dec-21 (78) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6910 System Walkdown Commissioning Chamber 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6920 Flushing /Cleaning Commissioning Chamber 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6930 Machinery Cold run test Commissioning Chamber 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6940 Continuity and Insulaton test Commissioning
Chamber 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6950 Motor rotational check test Commissioning Chamber 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6970 Loop testing Commissioning Chamber 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
110-01-Chlorine Contact Tank Outlet
STPPCC6980 Punch clearence -A Commissioning Chamber 3 8-Dec-21 11-Dec-21 8-Dec-21 11-Dec-21 (78) Behind Schedule 1
110-02-TSE Pumping Station with drainage
MARAFIQ COMM.2.24.1.18..2 110-02-TSE Pumping Station with drainage pump Commissioning
pumps 28 15-Nov-21 16-Dec-21 15-Nov-21 16-Dec-21 (73) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC6990 System Walkdown Commissioning pumps 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7000 Flushing /Cleaning Commissioning pumps 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7010 Machinery Cold run test Commissioning pumps 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7020 Continuity and Insulaton test Commissioning
pumps 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7030 Motor rotational check test Commissioning pumps 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7050 Loop testing Commissioning pumps 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7060 Punch clearence -A Commissioning pumps 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
110-02-TSE Pumping Station with drainage
MARAFIQ COMM.2.24.1.18..3 110-03-Booster Pumps for Service Water Commissioning pumps 28 20-Nov-21 21-Dec-21 20-Nov-21 21-Dec-21 (68) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7070 System Walkdown Commissioning pumps 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7080 Flushing /Cleaning Commissioning pumps 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7090 Machinery Cold run test Commissioning pumps 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7100 Continuity and Insulaton test Commissioning pumps 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7110 Motor rotational check test Commissioning pumps 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7130 Loop testing Commissioning pumps 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
Punch clearence -A - Booster Pumps for Service water Commissioning
110-02-TSE Pumping Station with drainage
STPPCC7140 TSE Ps pumps
4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
110-02-TSE Pumping Station with drainage
MARAFIQ COMM.2.24.1.18..4 110-04-Booster Pumps for Chlorination Commissioning pumps 28 24-Nov-21 26-Dec-21 24-Nov-21 26-Dec-21 (63) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7150 System Walkdown Commissioning
pumps 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7160 Flushing /Cleaning Commissioning pumps 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7170 Machinery Cold run test Commissioning pumps 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7180 Continuity and Insulaton test Commissioning pumps 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7190 Motor rotational check test Commissioning pumps 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7210 Loop testing Commissioning pumps 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
110-02-TSE Pumping Station with drainage
STPPCC7220 Punch clearence -A Commissioning pumps 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
MARAFIQ COMM.2.24.1.18..5 110-05-TSE Line (Zone 1 to Zone 5) Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 28 29-Nov-21 30-Dec-21 29-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC7230 System Walkdown Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC7240 Flushing /Cleaning Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC7250 Machinery Cold run test Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC7260 Continuity and Insulaton test Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC7270 Motor rotational check test Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC7290 Loop testing Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC7300 Punch clearence -A Commissioning 110-05-TSE Line (Zone 1 to Zone 5) 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.19. 245-TSE VALVE CHAMBER Commissioning 32 10-Nov-21 16-Dec-21 10-Nov-21 16-Dec-21 (73) Behind Schedule 1
MARAFIQ COMM.2.24.1.19..1 245-01-TSE Bypass upto Interface Commissioning 245-01-TSE Bypass upto Interface 28 10-Nov-21 12-Dec-21 10-Nov-21 12-Dec-21 (77) Behind Schedule 1
STPPCC7310 System Walkdown Commissioning 245-01-TSE Bypass upto Interface 4 10-Nov-21 14-Nov-21 10-Nov-21 14-Nov-21 (105) Behind Schedule 1
STPPCC7320 Flushing /Cleaning Commissioning 245-01-TSE Bypass upto Interface 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC7330 Machinery Cold run test Commissioning 245-01-TSE Bypass upto Interface 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC7340 Continuity and Insulaton test Commissioning 245-01-TSE Bypass upto Interface 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC7350 Motor rotational check test Commissioning 245-01-TSE Bypass upto Interface 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC7370 Loop testing Commissioning 245-01-TSE Bypass upto Interface 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC7380 Punch clearence -A Commissioning 245-01-TSE Bypass upto Interface 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
MARAFIQ COMM.2.24.1.19..2 245-02-TSE main line upto Interface Commissioning 245-01-TSE Bypass upto Interface 28 15-Nov-21 16-Dec-21 15-Nov-21 16-Dec-21 (73) Behind Schedule 1
STPPCC7390 System Walkdown Commissioning 245-01-TSE Bypass upto Interface 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC7400 Flushing /Cleaning Commissioning 245-01-TSE Bypass upto Interface 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC7410 Machinery Cold run test Commissioning 245-01-TSE Bypass upto Interface 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC7420 Continuity and Insulaton test Commissioning 245-01-TSE Bypass upto Interface 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC7430 Motor rotational check test Commissioning 245-01-TSE Bypass upto Interface 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC7450 Loop testing Commissioning 245-01-TSE Bypass upto Interface 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC7460 Punch clearence -A Commissioning 245-01-TSE Bypass upto Interface 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
MARAFIQ COMM.2.24.1.16 130-Sludge Thickening Commissioning 130-Sludge Thickening 32 30-Oct-21 5-Dec-21 30-Oct-21 5-Dec-21 (84) Behind Schedule 1
MARAFIQ COMM.2.24.1.16.1 130-01-Sludge Thickeners - 130-01 Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC7470 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC7480 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC7490 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC7500 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC7510 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC7530 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC7540 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.16.2 130-02-Sludge Thickeners - 130-02 Commissioning 130-01-Sludge Thickeners - 130-01 28 3-Nov-21 5-Dec-21 3-Nov-21 5-Dec-21 (84) Behind Schedule 1
STPPCC7550 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC7560 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC7570 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC7580 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC7590 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC7610 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
STPPCC7620 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 1-Dec-21 5-Dec-21 1-Dec-21 5-Dec-21 (84) Behind Schedule 1
MARAFIQ COMM.2.24.1.21. 135-Thickened Sludge Tank Commissioning 130-01-Sludge Thickeners - 130-01 24 30-Oct-21 25-Nov-21 30-Oct-21 25-Nov-21 (94) Behind Schedule 1
STPPCC7950 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC7960 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC7970 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC7980 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC7990 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8020 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
MARAFIQ COMM.2.24.1.17 140-Sludge Dewatering Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.17.1 140-01-Decanter Feed Pump & Centrifuge Decant Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8030 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8040 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8050 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8060 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8070 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8090 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8100 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.17.2 140-02-Decanter Feed Pump & Centrifuge Decant Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8110 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8120 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8130 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8140 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8150 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8170 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8180 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.18 140-07-Sludge Conveyors Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8510 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8520 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8530 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8540 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8550 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8570 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8580 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.23. 145-Lime Silo & Sludge Mixing Unit Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.23..1 145-01-Lime Silo & Sludge Mixing Unit Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8590 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8600 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8610 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8620 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8630 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8650 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8660 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.23..2 145-02-Air Compressors for Pneumatic actuators Commissioning 130-01-Sludge Thickeners - 130-01 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8670 System Walkdown Commissioning 130-01-Sludge Thickeners - 130-01 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8680 Flushing /Cleaning Commissioning 130-01-Sludge Thickeners - 130-01 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8690 Machinery Cold run test Commissioning 130-01-Sludge Thickeners - 130-01 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8700 Continuity and Insulaton test Commissioning 130-01-Sludge Thickeners - 130-01 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8710 Motor rotational check test Commissioning 130-01-Sludge Thickeners - 130-01 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8730 Loop testing Commissioning 130-01-Sludge Thickeners - 130-01 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8740 Punch clearence -A Commissioning 130-01-Sludge Thickeners - 130-01 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.24. 200-Container Storage Area Commissioning 200-Container Storage Area 12 30-Nov-21 13-Dec-21 30-Nov-21 13-Dec-21 (76) Behind Schedule 1
STPPCC8750 System Walkdown Commissioning 200-Container Storage Area 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCC8760 Floor Coating checking Commissioning 200-Container Storage Area 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
STPPCC8820 Punch clearence -A Commissioning 200-Container Storage Area 4 9-Dec-21 13-Dec-21 9-Dec-21 13-Dec-21 (76) Behind Schedule 1
MARAFIQ COMM.2.24.1.19 150-Polymer Preperation Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.1 150-01-Polymer Preparation for Sludge Thickenin Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8830 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8840 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8850 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8860 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8870 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8890 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8900 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.2 150-02-Polymer Dosing Pumps for Sludge Thicken Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8910 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC8920 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC8930 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC8940 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC8950 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC8970 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC8980 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.3 150-03-Polymer Dosing Pumps for Sludge Thicken Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC8990 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC9000 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC9010 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC9020 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC9030 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC9050 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC9060 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.6 150-PL-02A-Polymer Preparation for Sludge Dewa Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC9230 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC9240 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC9250 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC9260 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC9270 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC9290 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC9300 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.7 150-PL-02B-Polymer Preparation for Sludge Dewa Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC9310 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC9320 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC9330 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC9340 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC9350 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC9370 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC9380 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.8 150-06-Polymer Dosing Pumps for Sludge Dewate Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC9390 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC9400 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC9410 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC9420 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC9430 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC9450 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC9460 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.19.9 150-07-Polymer Dosing Pumps for Sludge Dewate Commissioning 150-Polymer Preperation 28 30-Oct-21 30-Nov-21 30-Oct-21 30-Nov-21 (89) Behind Schedule 1
STPPCC9470 System Walkdown Commissioning 150-Polymer Preperation 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC9480 Flushing /Cleaning Commissioning 150-Polymer Preperation 4 3-Nov-21 7-Nov-21 3-Nov-21 7-Nov-21 (112) Behind Schedule 1
STPPCC9490 Machinery Cold run test Commissioning 150-Polymer Preperation 4 8-Nov-21 11-Nov-21 8-Nov-21 11-Nov-21 (108) Behind Schedule 1
STPPCC9500 Continuity and Insulaton test Commissioning 150-Polymer Preperation 4 13-Nov-21 16-Nov-21 13-Nov-21 16-Nov-21 (103) Behind Schedule 1
STPPCC9510 Motor rotational check test Commissioning 150-Polymer Preperation 4 17-Nov-21 21-Nov-21 17-Nov-21 21-Nov-21 (98) Behind Schedule 1
STPPCC9530 Loop testing Commissioning 150-Polymer Preperation 4 22-Nov-21 25-Nov-21 22-Nov-21 25-Nov-21 (94) Behind Schedule 1
STPPCC9540 Punch clearence -A Commissioning 150-Polymer Preperation 4 27-Nov-21 30-Nov-21 27-Nov-21 30-Nov-21 (89) Behind Schedule 1
MARAFIQ COMM.2.24.1.26. 160-Truck Offloading Station Commissioning 160-Truck Offloading Station 56 5-Oct-21 8-Dec-21 5-Oct-21 8-Dec-21 (81) Behind Schedule 1
MARAFIQ COMM.2.24.1.26..1 160-01-Septage offloading station Coarse Screen Commissioning 160-Truck Offloading Station 56 5-Oct-21 8-Dec-21 5-Oct-21 8-Dec-21 (81) Behind Schedule 1
STPPCC9710 System Walkdown Commissioning 160-Truck Offloading Station 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
STPPCC9720 Flushing /Cleaning Commissioning 160-Truck Offloading Station 4 16-Oct-21 19-Oct-21 16-Oct-21 19-Oct-21 (131) Behind Schedule 1
STPPCC9730 Machinery Cold run test Commissioning 160-Truck Offloading Station 4 30-Oct-21 2-Nov-21 30-Oct-21 2-Nov-21 (117) Behind Schedule 1
STPPCC9740 Continuity and Insulaton test Commissioning 160-Truck Offloading Station 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC9750 Motor rotational check test Commissioning 160-Truck Offloading Station 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC9770 Loop testing Commissioning 160-Truck Offloading Station 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCC9780 Punch clearence -A Commissioning 160-Truck Offloading Station 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
MARAFIQ COMM.2.24.1.26..2 160-02-Truck Offloading pump Station Commissioning 160-Truck Offloading Station 28 10-Oct-21 10-Nov-21 10-Oct-21 10-Nov-21 (109) Behind Schedule 1
STPPCC9790 System Walkdown Commissioning 160-Truck Offloading Station 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
STPPCC9800 Flushing /Cleaning Commissioning 160-Truck Offloading Station 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
STPPCC9810 Machinery Cold run test Commissioning 160-Truck Offloading Station 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
STPPCC9820 Continuity and Insulaton test Commissioning 160-Truck Offloading Station 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC9830 Motor rotational check test Commissioning 160-Truck Offloading Station 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC9850 Loop testing Commissioning 160-Truck Offloading Station 4 2-Nov-21 6-Nov-21 2-Nov-21 6-Nov-21 (113) Behind Schedule 1
STPPCC9860 Punch clearence -A Commissioning 160-Truck Offloading Station 4 7-Nov-21 10-Nov-21 7-Nov-21 10-Nov-21 (109) Behind Schedule 1
MARAFIQ COMM.2.24.1.27. 161-Truck Offloading Station - Guard room Commissioning 160-Truck Offloading Station 16 14-Oct-21 1-Nov-21 14-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC9870 System Walkdown Commissioning 160-Truck Offloading Station 4 14-Oct-21 18-Oct-21 14-Oct-21 18-Oct-21 (132) Behind Schedule 1
STPPCC9900 Continuity and Insulaton test Commissioning 160-Truck Offloading Station 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
STPPCC9930 Loop testing Commissioning 160-Truck Offloading Station 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC9940 Punch clearence -A Commissioning 160-Truck Offloading Station 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
MARAFIQ COMM.2.24.1.28. 162-Truck Offloading Station - Truck Bay Commissioning 160-Truck Offloading Station 28 19-Oct-21 20-Nov-21 19-Oct-21 20-Nov-21 (99) Behind Schedule 1
STPPCC10010 Loop testing Commissioning 160-Truck Offloading Station 4 11-Nov-21 15-Nov-21 11-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC10020 Punch clearence -A Commissioning 160-Truck Offloading Station 4 16-Nov-21 20-Nov-21 16-Nov-21 20-Nov-21 (99) Behind Schedule 1
STPPCC9950 System Walkdown Commissioning 160-Truck Offloading Station 4 19-Oct-21 23-Oct-21 19-Oct-21 23-Oct-21 (127) Behind Schedule 1
STPPCC9960 Flushing /Cleaning Commissioning 160-Truck Offloading Station 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC9970 Machinery Cold run test Commissioning 160-Truck Offloading Station 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC9980 Continuity and Insulaton test Commissioning 160-Truck Offloading Station 4 2-Nov-21 6-Nov-21 2-Nov-21 6-Nov-21 (113) Behind Schedule 1
STPPCC9990 Motor rotational check test Commissioning 160-Truck Offloading Station 4 7-Nov-21 10-Nov-21 7-Nov-21 10-Nov-21 (109) Behind Schedule 1
MARAFIQ COMM.2.24.1.29. 163-Truck Offloading Station - Control Room Commissioning 160-Truck Offloading Station 28 24-Oct-21 24-Nov-21 24-Oct-21 24-Nov-21 (95) Behind Schedule 1
STPPCC10030 System Walkdown Commissioning 160-Truck Offloading Station 4 24-Oct-21 27-Oct-21 24-Oct-21 27-Oct-21 (123) Behind Schedule 1
STPPCC10040 Flushing /Cleaning Commissioning 160-Truck Offloading Station 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC10050 Machinery Cold run test Commissioning 160-Truck Offloading Station 4 2-Nov-21 6-Nov-21 2-Nov-21 6-Nov-21 (113) Behind Schedule 1
STPPCC10060 Continuity and Insulaton test Commissioning 160-Truck Offloading Station 4 7-Nov-21 10-Nov-21 7-Nov-21 10-Nov-21 (109) Behind Schedule 1
STPPCC10070 Motor rotational check test Commissioning 160-Truck Offloading Station 4 11-Nov-21 15-Nov-21 11-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC10090 Loop testing Commissioning 160-Truck Offloading Station 4 16-Nov-21 20-Nov-21 16-Nov-21 20-Nov-21 (99) Behind Schedule 1
STPPCC10100 Punch clearence -A Commissioning 160-Truck Offloading Station 4 21-Nov-21 24-Nov-21 21-Nov-21 24-Nov-21 (95) Behind Schedule 1
MARAFIQ COMM.2.24.1.30. 165-Truck Offloading Station - Flow Measurement Commissioning 160-Truck Offloading Station 28 28-Oct-21 29-Nov-21 28-Oct-21 29-Nov-21 (90) Behind Schedule 1
STPPCC10110 System Walkdown Commissioning 160-Truck Offloading Station 4 28-Oct-21 1-Nov-21 28-Oct-21 1-Nov-21 (118) Behind Schedule 1
STPPCC10120 Flushing /Cleaning Commissioning 160-Truck Offloading Station 4 2-Nov-21 6-Nov-21 2-Nov-21 6-Nov-21 (113) Behind Schedule 1
STPPCC10130 Machinery Cold run test Commissioning 160-Truck Offloading Station 4 7-Nov-21 10-Nov-21 7-Nov-21 10-Nov-21 (109) Behind Schedule 1
STPPCC10140 Continuity and Insulaton test Commissioning 160-Truck Offloading Station 4 11-Nov-21 15-Nov-21 11-Nov-21 15-Nov-21 (104) Behind Schedule 1
STPPCC10150 Motor rotational check test Commissioning 160-Truck Offloading Station 4 16-Nov-21 20-Nov-21 16-Nov-21 20-Nov-21 (99) Behind Schedule 1
STPPCC10170 Loop testing Commissioning 160-Truck Offloading Station 4 21-Nov-21 24-Nov-21 21-Nov-21 24-Nov-21 (95) Behind Schedule 1
STPPCC10180 Punch clearence -A Commissioning 160-Truck Offloading Station 4 25-Nov-21 29-Nov-21 25-Nov-21 29-Nov-21 (90) Behind Schedule 1
MARAFIQ COMM.2.24.1.31. 170-Foul Air Treatment Unit-1 Commissioning 170-Foul Air Treatment Unit-1 25 30-Nov-21 28-Dec-21 30-Nov-21 28-Dec-21 (61) Behind Schedule 1
MARAFIQ COMM.2.24.1.31..1 170-01-Foul Air Treatment Unit-1 Train A Commissioning 170-Foul Air Treatment Unit-1 25 30-Nov-21 28-Dec-21 30-Nov-21 28-Dec-21 (61) Behind Schedule 1
STPPCC10190 System Walkdown Commissioning 170-Foul Air Treatment Unit-1 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCC10200 Flushing /Cleaning Commissioning 170-Foul Air Treatment Unit-1 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
STPPCC10210 Machinery Cold run test Commissioning 170-Foul Air Treatment Unit-1 2 9-Dec-21 11-Dec-21 9-Dec-21 11-Dec-21 (78) Behind Schedule 1
STPPCC10220 Continuity and Insulaton test Commissioning 170-Foul Air Treatment Unit-1 3 12-Dec-21 14-Dec-21 12-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC10230 Motor rotational check test Commissioning 170-Foul Air Treatment Unit-1 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC10250 Loop testing Commissioning 170-Foul Air Treatment Unit-1 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC10260 Punch clearence -A Commissioning 170-Foul Air Treatment Unit-1 4 25-Dec-21 28-Dec-21 25-Dec-21 28-Dec-21 (61) Behind Schedule 1
MARAFIQ COMM.2.24.1.31..2 170-02-Foul Air Treatment Unit-1 Train B Commissioning 170-Foul Air Treatment Unit-1 18 5-Dec-21 25-Dec-21 5-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC10270 System Walkdown Commissioning 170-Foul Air Treatment Unit-1 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
STPPCC10280 Flushing /Cleaning Commissioning 170-Foul Air Treatment Unit-1 2 9-Dec-21 11-Dec-21 9-Dec-21 11-Dec-21 (78) Behind Schedule 1
STPPCC10290 Machinery Cold run test Commissioning 170-Foul Air Treatment Unit-1 2 12-Dec-21 13-Dec-21 12-Dec-21 13-Dec-21 (76) Behind Schedule 1
STPPCC10300 Continuity and Insulaton test Commissioning 170-Foul Air Treatment Unit-1 2 14-Dec-21 15-Dec-21 14-Dec-21 15-Dec-21 (74) Behind Schedule 1
STPPCC10310 Motor rotational check test Commissioning 170-Foul Air Treatment Unit-1 2 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCC10330 Loop testing Commissioning 170-Foul Air Treatment Unit-1 2 19-Dec-21 20-Dec-21 19-Dec-21 20-Dec-21 (69) Behind Schedule 1
STPPCC10340 Punch clearence -A Commissioning 170-Foul Air Treatment Unit-1 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
MARAFIQ COMM.2.24.1.31..3 170-03-Activated Carbon Filter Commissioning 170-Foul Air Treatment Unit-1 16 9-Dec-21 27-Dec-21 9-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC10350 System Walkdown Commissioning 170-Foul Air Treatment Unit-1 2 9-Dec-21 11-Dec-21 9-Dec-21 11-Dec-21 (78) Behind Schedule 1
STPPCC10360 Flushing /Cleaning Commissioning 170-Foul Air Treatment Unit-1 2 12-Dec-21 13-Dec-21 12-Dec-21 13-Dec-21 (76) Behind Schedule 1
STPPCC10370 Machinery Cold run test Commissioning 170-Foul Air Treatment Unit-1 2 14-Dec-21 15-Dec-21 14-Dec-21 15-Dec-21 (74) Behind Schedule 1
STPPCC10380 Continuity and Insulaton test Commissioning 170-Foul Air Treatment Unit-1 2 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCC10390 Motor rotational check test Commissioning 170-Foul Air Treatment Unit-1 2 19-Dec-21 20-Dec-21 19-Dec-21 20-Dec-21 (69) Behind Schedule 1
STPPCC10410 Loop testing Commissioning 170-Foul Air Treatment Unit-1 2 21-Dec-21 22-Dec-21 21-Dec-21 22-Dec-21 (67) Behind Schedule 1
STPPCC10420 Punch clearence -A Commissioning 170-Foul Air Treatment Unit-1 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
MARAFIQ COMM.2.24.1.31..4 170-04-Chemical Tanks and Dosing Pumps Commissioning 170-Foul Air Treatment Unit-1 14 12-Dec-21 27-Dec-21 12-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCC10430 System Walkdown Commissioning 170-Foul Air Treatment Unit-1 2 12-Dec-21 13-Dec-21 12-Dec-21 13-Dec-21 (76) Behind Schedule 1
STPPCC10440 Flushing /Cleaning Commissioning 170-Foul Air Treatment Unit-1 2 14-Dec-21 15-Dec-21 14-Dec-21 15-Dec-21 (74) Behind Schedule 1
STPPCC10450 Machinery Cold run test Commissioning 170-Foul Air Treatment Unit-1 2 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCC10460 Continuity and Insulaton test Commissioning 170-Foul Air Treatment Unit-1 2 19-Dec-21 20-Dec-21 19-Dec-21 20-Dec-21 (69) Behind Schedule 1
STPPCC10470 Motor rotational check test Commissioning 170-Foul Air Treatment Unit-1 2 21-Dec-21 22-Dec-21 21-Dec-21 22-Dec-21 (67) Behind Schedule 1
STPPCC10490 Loop testing Commissioning 170-Foul Air Treatment Unit-1 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC10500 Punch clearence -A Commissioning 170-Foul Air Treatment Unit-1 2 26-Dec-21 27-Dec-21 26-Dec-21 27-Dec-21 (62) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
MARAFIQ COMM.2.24.1.32. 172-Foul Air Treatment Unit-2 (Truck Offloading Sta Commissioning Offloading Station) 27 30-Nov-21 30-Dec-21 30-Nov-21 30-Dec-21 (59) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
MARAFIQ COMM.2.24.1.32..1 172-01-Caustic & Bleach Scrubber Commissioning Offloading Station) 27 30-Nov-21 30-Dec-21 30-Nov-21 30-Dec-21 (59) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10510 System Walkdown Commissioning
Offloading Station) 4 30-Nov-21 4-Dec-21 30-Nov-21 4-Dec-21 (85) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10520 Flushing /Cleaning Commissioning Offloading Station) 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10530 Machinery Cold run test Commissioning Offloading Station) 4 9-Dec-21 13-Dec-21 9-Dec-21 13-Dec-21 (76) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10540 Continuity and Insulaton test Commissioning Offloading Station) 3 14-Dec-21 16-Dec-21 14-Dec-21 16-Dec-21 (73) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10550 Motor rotational check test Commissioning
Offloading Station) 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10570 Loop testing Commissioning Offloading Station) 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10580 Punch clearence -A Commissioning Offloading Station) 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
MARAFIQ COMM.2.24.1.32..2 172-02-Chemical Tanks and Dosing Pumps Commissioning Offloading Station) 23 5-Dec-21 30-Dec-21 5-Dec-21 30-Dec-21 (59) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10590 System Walkdown Commissioning
Offloading Station) 3 5-Dec-21 7-Dec-21 5-Dec-21 7-Dec-21 (82) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10600 Flushing /Cleaning Commissioning Offloading Station) 3 8-Dec-21 11-Dec-21 8-Dec-21 11-Dec-21 (78) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10610 Machinery Cold run test Commissioning Offloading Station) 3 12-Dec-21 14-Dec-21 12-Dec-21 14-Dec-21 (75) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10620 Continuity and Insulaton test Commissioning Offloading Station) 3 15-Dec-21 18-Dec-21 15-Dec-21 18-Dec-21 (71) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10630 Motor rotational check test Commissioning
Offloading Station) 3 19-Dec-21 21-Dec-21 19-Dec-21 21-Dec-21 (68) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10650 Loop testing Commissioning Offloading Station) 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
172-Foul Air Treatment Unit-2 (Truck
STPPCC10660 Punch clearence -A Commissioning Offloading Station) 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.1.33. 180-Plant Drain Pumping Station Commissioning 180-Plant Drain Pumping Station 27 30-Nov-21 30-Dec-21 30-Nov-21 30-Dec-21 (59) Behind Schedule 1
STPPCC10670 System Walkdown Commissioning 180-Plant Drain Pumping Station 2 30-Nov-21 1-Dec-21 30-Nov-21 1-Dec-21 (88) Behind Schedule 1
STPPCC10680 Flushing /Cleaning Commissioning 180-Plant Drain Pumping Station 4 2-Dec-21 6-Dec-21 2-Dec-21 6-Dec-21 (83) Behind Schedule 1
STPPCC10690 Machinery Cold run test Commissioning 180-Plant Drain Pumping Station 4 7-Dec-21 11-Dec-21 7-Dec-21 11-Dec-21 (78) Behind Schedule 1
STPPCC10700 Continuity and Insulaton test Commissioning 180-Plant Drain Pumping Station 4 12-Dec-21 15-Dec-21 12-Dec-21 15-Dec-21 (74) Behind Schedule 1
STPPCC10710 Motor rotational check test Commissioning 180-Plant Drain Pumping Station 2 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCC10730 Loop testing Commissioning 180-Plant Drain Pumping Station 2 25-Dec-21 26-Dec-21 25-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC10740 Punch clearence -A Commissioning Train 2 180-Plant Drain Pumping Station 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
MARAFIQ COMM.2.24.2 TRAIN2 Commissioning Train 2 103 6-Nov-21 5-Mar-22 6-Nov-21 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.2.24.2.8 060-Activated Sludge Tanks (AST) Commissioning Train 2 060-Activated Sludge Tanks (AST) 31 15-Nov-21 20-Dec-21 15-Nov-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.8.2 060-2-Activated Sludge Tanks-02 Commissioning Train 2 060-2-Activated Sludge Tanks-02 27 15-Nov-21 15-Dec-21 15-Nov-21 15-Dec-21 (74) Behind Schedule 1
STPPCC2110 System Walkdown Commissioning Train 2 060-2-Activated Sludge Tanks-02 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC2120 Flushing /Cleaning Commissioning Train 2 060-2-Activated Sludge Tanks-02 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC2130 Machinery Cold run test Commissioning Train 2 060-2-Activated Sludge Tanks-02 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC2140 Continuity and Insulaton test Commissioning Train 2 060-2-Activated Sludge Tanks-02 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC2150 Motor rotational check test Commissioning Train 2 060-2-Activated Sludge Tanks-02 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC2170 Loop testing Commissioning Train 2 060-2-Activated Sludge Tanks-02 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC2180 Punch clearence -A Commissioning Train 2 060-2-Activated Sludge Tanks-02 3 13-Dec-21 15-Dec-21 13-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.2.24.2.8.3 060-3-Activated Sludge Tanks-03 Commissioning Train 2 060-3-Activated Sludge Tanks-03 27 20-Nov-21 20-Dec-21 20-Nov-21 20-Dec-21 (69) Behind Schedule 1
STPPCC2190 System Walkdown Commissioning Train 2 060-3-Activated Sludge Tanks-03 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC2200 Flushing /Cleaning Commissioning Train 2 060-3-Activated Sludge Tanks-03 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC2210 Machinery Cold run test Commissioning Train 2 060-3-Activated Sludge Tanks-03 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC2220 Continuity and Insulaton test Commissioning Train 2 060-3-Activated Sludge Tanks-03 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC2230 Motor rotational check test Commissioning Train 2 060-3-Activated Sludge Tanks-03 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC2250 Loop testing Commissioning Train 2 060-3-Activated Sludge Tanks-03 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC2260 Punch clearence -A Commissioning Train 2 060-3-Activated Sludge Tanks-03 3 18-Dec-21 20-Dec-21 18-Dec-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.6 040 Grit and grease chamber Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 27 31-Jan-22 2-Mar-22 31-Jan-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.2.24.2.6.3 040-2A-Grit and Grease Chamber-2A Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 27 31-Jan-22 2-Mar-22 31-Jan-22 2-Mar-22 3 Very Critical 1
STPPCC1550 System Walkdown Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC1560 Flushing /Cleaning Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC1570 Machinery Cold run test Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCC1580 Continuity and Insulaton test Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCC1590 Motor rotational check test Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCC1610 Loop testing Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCC1620 Punch clearence -A Commissioning Train 2 040-2A-Grit and Grease Chamber-2A 3 28-Feb-22 2-Mar-22 28-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.2.24.2.6.4 040-2B-Grit and Grease Chamber-2B Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 27 31-Jan-22 2-Mar-22 31-Jan-22 2-Mar-22 3 Very Critical 1
STPPCC1630 System Walkdown Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC1640 Flushing /Cleaning Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC1650 Machinery Cold run test Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCC1660 Continuity and Insulaton test Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCC1670 Motor rotational check test Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCC1690 Loop testing Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCC1700 Punch clearence -A Commissioning Train 2 040-2B-Grit and Grease Chamber-2B 3 28-Feb-22 2-Mar-22 28-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.2.24.2.6.5 040-3A-Grit and Grease Chamber-3A Commissioning Train 2 27 31-Jan-22 2-Mar-22 31-Jan-22 2-Mar-22 3 Very Critical 1
STPPCC1710 System Walkdown Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC1720 Flushing /Cleaning Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC1730 Machinery Cold run test Commissioning Train 2 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCC1740 Continuity and Insulaton test Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCC1750 Motor rotational check test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCC1770 Loop testing Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCC1780 Punch clearence -A Commissioning Train 2 3 28-Feb-22 2-Mar-22 28-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.2.24.2.6.6 040-3B-Grit and Grease Chamber-3B Commissioning Train 2 27 31-Jan-22 2-Mar-22 31-Jan-22 2-Mar-22 3 Very Critical 1
STPPCC1790 System Walkdown Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC1800 Flushing /Cleaning Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC1810 Machinery Cold run test Commissioning Train 2 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCC1820 Continuity and Insulaton test Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCC1830 Motor rotational check test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCC1850 Loop testing Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCC1860 Punch clearence -A Commissioning Train 2 3 28-Feb-22 2-Mar-22 28-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.2.24.2.10 070-Distribution Chambers for Secondary Sedimenta Commissioning Train 2 31 15-Nov-21 20-Dec-21 15-Nov-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.10.2 070-2-Distribution Chambers for Secondary Sedi Commissioning Train 2 27 15-Nov-21 15-Dec-21 15-Nov-21 15-Dec-21 (74) Behind Schedule 1
STPPCC2430 System Walkdown Commissioning Train 2 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC2440 Flushing /Cleaning Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC2450 Machinery Cold run test Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC2460 Continuity and Insulaton test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC2470 Motor rotational check test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC2490 Loop testing Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC2500 Punch clearence -A Commissioning Train 2 3 13-Dec-21 15-Dec-21 13-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.2.24.2.10.3 070-3-Distribution Chambers for Secondary Sedi Commissioning Train 2 27 20-Nov-21 20-Dec-21 20-Nov-21 20-Dec-21 (69) Behind Schedule 1
STPPCC2510 System Walkdown Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC2520 Flushing /Cleaning Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC2530 Machinery Cold run test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC2540 Continuity and Insulaton test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC2550 Motor rotational check test Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC2570 Loop testing Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC2580 Punch clearence -A Commissioning Train 2 3 18-Dec-21 20-Dec-21 18-Dec-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.11 080-Secondary Sedimentation Tanks (SST) Commissioning Train 2 55 15-Nov-21 17-Jan-22 15-Nov-21 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.5 080-5-Secondary Sedimentation Tanks (SST)-05 Commissioning Train 2 27 15-Nov-21 15-Dec-21 15-Nov-21 15-Dec-21 (74) Behind Schedule 1
STPPCC2910 System Walkdown Commissioning Train 2 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC2920 Flushing /Cleaning Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC2930 Machinery Cold run test Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC2940 Continuity and Insulaton test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC2950 Motor rotational check test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC2970 Loop testing Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC2980 Punch clearence -A Commissioning Train 2 3 13-Dec-21 15-Dec-21 13-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.6 080-6-Secondary Sedimentation Tanks (SST)-06 Commissioning Train 2 27 20-Nov-21 20-Dec-21 20-Nov-21 20-Dec-21 (69) Behind Schedule 1
STPPCC2990 System Walkdown Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC3000 Flushing /Cleaning Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC3010 Machinery Cold run test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC3020 Continuity and Insulaton test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC3030 Motor rotational check test Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3050 Loop testing Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3060 Punch clearence -A Commissioning Train 2 3 18-Dec-21 20-Dec-21 18-Dec-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.7 080-7-Secondary Sedimentation Tanks (SST)-07 Commissioning Train 2 27 24-Nov-21 25-Dec-21 24-Nov-21 25-Dec-21 (64) Behind Schedule 1
STPPCC3070 System Walkdown Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC3080 Flushing /Cleaning Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC3090 Machinery Cold run test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC3100 Continuity and Insulaton test Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3110 Motor rotational check test Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3130 Loop testing Commissioning Train 2 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC3140 Punch clearence -A Commissioning Train 2 3 22-Dec-21 25-Dec-21 22-Dec-21 25-Dec-21 (64) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.8 080-8-Secondary Sedimentation Tanks (SST)-08 Commissioning Train 2 27 29-Nov-21 29-Dec-21 29-Nov-21 29-Dec-21 (60) Behind Schedule 1
STPPCC3150 System Walkdown Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC3160 Flushing /Cleaning Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC3170 Machinery Cold run test Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3180 Continuity and Insulaton test Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3190 Motor rotational check test Commissioning Train 2 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC3210 Loop testing Commissioning Train 2 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC3220 Punch clearence -A Commissioning Train 2 3 27-Dec-21 29-Dec-21 27-Dec-21 29-Dec-21 (60) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.9 080-9-Secondary Sedimentation Tanks (SST)-09 Commissioning Train 2 27 4-Dec-21 3-Jan-22 4-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC3230 System Walkdown Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC3240 Flushing /Cleaning Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3250 Machinery Cold run test Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3260 Continuity and Insulaton test Commissioning Train 2 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC3270 Motor rotational check test Commissioning Train 2 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC3290 Loop testing Commissioning Train 2 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC3300 Punch clearence -A Commissioning Train 2 3 1-Jan-22 3-Jan-22 1-Jan-22 3-Jan-22 (55) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.10 080-10-Secondary Sedimentation Tanks (SST)-1 Commissioning Train 2 27 8-Dec-21 8-Jan-22 8-Dec-21 8-Jan-22 (50) Behind Schedule 1
STPPCC3310 System Walkdown Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3320 Flushing /Cleaning Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3330 Machinery Cold run test Commissioning Train 2 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC3340 Continuity and Insulaton test Commissioning Train 2 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC3350 Motor rotational check test Commissioning Train 2 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC3370 Loop testing Commissioning Train 2 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
STPPCC3380 Punch clearence -A Commissioning Train 2 3 5-Jan-22 8-Jan-22 5-Jan-22 8-Jan-22 (50) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.11 080-11-Secondary Sedimentation Tanks (SST)-1 Commissioning Train 2 27 13-Dec-21 12-Jan-22 13-Dec-21 12-Jan-22 (46) Behind Schedule 1
STPPCC3390 System Walkdown Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3400 Flushing /Cleaning Commissioning Train 2 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC3410 Machinery Cold run test Commissioning Train 2 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC3420 Continuity and Insulaton test Commissioning Train 2 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC3430 Motor rotational check test Commissioning Train 2 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
STPPCC3450 Loop testing Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC3460 Punch clearence -A Commissioning Train 2 3 10-Jan-22 12-Jan-22 10-Jan-22 12-Jan-22 (46) Behind Schedule 1
MARAFIQ COMM.2.24.2.11.12 080-12-Secondary Sedimentation Tanks (SST)-1 Commissioning Train 2 27 18-Dec-21 17-Jan-22 18-Dec-21 17-Jan-22 (41) Behind Schedule 1
STPPCC3470 System Walkdown Commissioning Train 2 4 18-Dec-21 21-Dec-21 18-Dec-21 21-Dec-21 (68) Behind Schedule 1
STPPCC3480 Flushing /Cleaning Commissioning Train 2 4 22-Dec-21 26-Dec-21 22-Dec-21 26-Dec-21 (63) Behind Schedule 1
STPPCC3490 Machinery Cold run test Commissioning Train 2 4 27-Dec-21 30-Dec-21 27-Dec-21 30-Dec-21 (59) Behind Schedule 1
STPPCC3500 Continuity and Insulaton test Commissioning Train 2 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
STPPCC3510 Motor rotational check test Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC3530 Loop testing Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC3540 Punch clearence -A Commissioning Train 2 3 15-Jan-22 17-Jan-22 15-Jan-22 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.2.24.2.12. 120-Excess and Return Sludge Pumping Station Commissioning Train 2 31 15-Nov-21 20-Dec-21 15-Nov-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.12..2 120-2-Excess and Return Sludge Pumping Statio Commissioning Train 2 27 15-Nov-21 15-Dec-21 15-Nov-21 15-Dec-21 (74) Behind Schedule 1
STPPCC3630 System Walkdown Commissioning Train 2 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC3640 Flushing /Cleaning Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC3650 Machinery Cold run test Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC3660 Continuity and Insulaton test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC3670 Motor rotational check test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC3690 Loop testing Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3700 Punch clearence -A Commissioning Train 2 3 13-Dec-21 15-Dec-21 13-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.2.24.2.12..3 120-3-Excess and Return Sludge Pumping Statio Commissioning Train 2 27 20-Nov-21 20-Dec-21 20-Nov-21 20-Dec-21 (69) Behind Schedule 1
STPPCC3710 System Walkdown Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC3720 Flushing /Cleaning Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC3730 Machinery Cold run test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC3740 Continuity and Insulaton test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC3750 Motor rotational check test Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC3770 Loop testing Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC3780 Punch clearence -A Commissioning Train 2 3 18-Dec-21 20-Dec-21 18-Dec-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.13. 125-Scum Pumping Station Commissioning Train 2 31 15-Nov-21 20-Dec-21 15-Nov-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.13..3 125-3-Scum Pumping Station-03 Commissioning Train 2 27 15-Nov-21 15-Dec-21 15-Nov-21 15-Dec-21 (74) Behind Schedule 1
STPPCC3950 System Walkdown Commissioning Train 2 4 15-Nov-21 18-Nov-21 15-Nov-21 18-Nov-21 (101) Behind Schedule 1
STPPCC3960 Flushing /Cleaning Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC3970 Machinery Cold run test Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC3980 Continuity and Insulaton test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC3990 Motor rotational check test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC4010 Loop testing Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC4020 Punch clearence -A Commissioning Train 2 3 13-Dec-21 15-Dec-21 13-Dec-21 15-Dec-21 (74) Behind Schedule 1
MARAFIQ COMM.2.24.2.13..4 125-4-Scum Pumping Station-04 Commissioning Train 2 27 20-Nov-21 20-Dec-21 20-Nov-21 20-Dec-21 (69) Behind Schedule 1
STPPCC4030 System Walkdown Commissioning Train 2 4 20-Nov-21 23-Nov-21 20-Nov-21 23-Nov-21 (96) Behind Schedule 1
STPPCC4040 Flushing /Cleaning Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCC4050 Machinery Cold run test Commissioning Train 2 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
STPPCC4060 Continuity and Insulaton test Commissioning Train 2 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCC4070 Motor rotational check test Commissioning Train 2 4 8-Dec-21 12-Dec-21 8-Dec-21 12-Dec-21 (77) Behind Schedule 1
STPPCC4090 Loop testing Commissioning Train 2 4 13-Dec-21 16-Dec-21 13-Dec-21 16-Dec-21 (73) Behind Schedule 1
STPPCC4100 Punch clearence -A Commissioning Train 2 3 18-Dec-21 20-Dec-21 18-Dec-21 20-Dec-21 (69) Behind Schedule 1
MARAFIQ COMM.2.24.2.14. 090-Rapid Sand Filters Commissioning Train 2 55 1-Jan-22 5-Mar-22 1-Jan-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.2.24.2.14..5 090-05-Rapid Sand Filters-05 Commissioning Train 2 25 1-Jan-22 29-Jan-22 1-Jan-22 29-Jan-22 (29) Behind Schedule 1
STPPCC4430 System Walkdown Commissioning Train 2 2 1-Jan-22 2-Jan-22 1-Jan-22 2-Jan-22 (56) Behind Schedule 1
STPPCC4440 Flushing /Cleaning Commissioning Train 2 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCC4450 Machinery Cold run test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCC4460 Continuity and Insulaton test Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCC4470 Motor rotational check test Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCC4490 Loop testing Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCC4500 Punch clearence -A Commissioning Train 2 3 26-Jan-22 29-Jan-22 26-Jan-22 29-Jan-22 (29) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..6 090-06-Rapid Sand Filters-06 Commissioning Train 2 25 3-Jan-22 31-Jan-22 3-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCC4510 System Walkdown Commissioning Train 2 2 3-Jan-22 4-Jan-22 3-Jan-22 4-Jan-22 (54) Behind Schedule 1
STPPCC4520 Flushing /Cleaning Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC4530 Machinery Cold run test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC4540 Continuity and Insulaton test Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC4550 Motor rotational check test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC4570 Loop testing Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC4580 Punch clearence -A Commissioning Train 2 3 29-Jan-22 31-Jan-22 29-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..7 090-07-Rapid Sand Filters-07 Commissioning Train 2 25 5-Jan-22 2-Feb-22 5-Jan-22 2-Feb-22 (25) Behind Schedule 1
STPPCC4590 System Walkdown Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCC4600 Flushing /Cleaning Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCC4610 Machinery Cold run test Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCC4620 Continuity and Insulaton test Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCC4630 Motor rotational check test Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCC4650 Loop testing Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCC4660 Punch clearence -A Commissioning Train 2 3 31-Jan-22 2-Feb-22 31-Jan-22 2-Feb-22 (25) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..8 090-08-Rapid Sand Filters-08 Commissioning Train 2 25 8-Jan-22 5-Feb-22 8-Jan-22 5-Feb-22 (22) Behind Schedule 1
STPPCC4670 System Walkdown Commissioning Train 2 2 8-Jan-22 9-Jan-22 8-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC4680 Flushing /Cleaning Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC4690 Machinery Cold run test Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC4700 Continuity and Insulaton test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC4710 Motor rotational check test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC4730 Loop testing Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC4740 Punch clearence -A Commissioning Train 2 3 2-Feb-22 5-Feb-22 2-Feb-22 5-Feb-22 (22) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..9 090-09-Rapid Sand Filters-09 Commissioning Train 2 25 10-Jan-22 7-Feb-22 10-Jan-22 7-Feb-22 (20) Behind Schedule 1
STPPCC4750 System Walkdown Commissioning Train 2 2 10-Jan-22 11-Jan-22 10-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCC4760 Flushing /Cleaning Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCC4770 Machinery Cold run test Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCC4780 Continuity and Insulaton test Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCC4790 Motor rotational check test Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCC4810 Loop testing Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC4820 Punch clearence -A Commissioning Train 2 3 5-Feb-22 7-Feb-22 5-Feb-22 7-Feb-22 (20) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..10 090-10-Rapid Sand Filters-10 Commissioning Train 2 25 12-Jan-22 9-Feb-22 12-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCC4830 System Walkdown Commissioning Train 2 2 12-Jan-22 13-Jan-22 12-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC4840 Flushing /Cleaning Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC4850 Machinery Cold run test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC4860 Continuity and Insulaton test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC4870 Motor rotational check test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC4890 Loop testing Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC4900 Punch clearence -A Commissioning Train 2 3 7-Feb-22 9-Feb-22 7-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..11 090-11-Rapid Sand Filters-11 Commissioning Train 2 25 15-Jan-22 12-Feb-22 15-Jan-22 12-Feb-22 (15) Behind Schedule 1
STPPCC4910 System Walkdown Commissioning Train 2 2 15-Jan-22 16-Jan-22 15-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCC4920 Flushing /Cleaning Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCC4930 Machinery Cold run test Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCC4940 Continuity and Insulaton test Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCC4950 Motor rotational check test Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC4970 Loop testing Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC4980 Punch clearence -A Commissioning Train 2 3 9-Feb-22 12-Feb-22 9-Feb-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..12 090-12-Rapid Sand Filters-12 Commissioning Train 2 25 17-Jan-22 14-Feb-22 17-Jan-22 14-Feb-22 (13) Behind Schedule 1
STPPCC4990 System Walkdown Commissioning Train 2 2 17-Jan-22 18-Jan-22 17-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC5000 Flushing /Cleaning Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC5010 Machinery Cold run test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC5020 Continuity and Insulaton test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC5030 Motor rotational check test Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC5050 Loop testing Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCC5060 Punch clearence -A Commissioning Train 2 3 12-Feb-22 14-Feb-22 12-Feb-22 14-Feb-22 (13) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..13 090-13-Rapid Sand Filters-13 Commissioning Train 2 25 19-Jan-22 16-Feb-22 19-Jan-22 16-Feb-22 (11) Behind Schedule 1
STPPCC5070 System Walkdown Commissioning Train 2 2 19-Jan-22 20-Jan-22 19-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCC5080 Flushing /Cleaning Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCC5090 Machinery Cold run test Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCC5100 Continuity and Insulaton test Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC5110 Motor rotational check test Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC5130 Loop testing Commissioning Train 2 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCC5140 Punch clearence -A Commissioning Train 2 3 14-Feb-22 16-Feb-22 14-Feb-22 16-Feb-22 (11) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..14 090-14-Rapid Sand Filters-14 Commissioning Train 2 25 22-Jan-22 19-Feb-22 22-Jan-22 19-Feb-22 (8) Behind Schedule 1
STPPCC5150 System Walkdown Commissioning Train 2 2 22-Jan-22 23-Jan-22 22-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC5160 Flushing /Cleaning Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC5170 Machinery Cold run test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC5180 Continuity and Insulaton test Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC5190 Motor rotational check test Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCC5210 Loop testing Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCC5220 Punch clearence -A Commissioning Train 2 3 16-Feb-22 19-Feb-22 16-Feb-22 19-Feb-22 (8) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..15 090-14-Rapid Sand Filters-15 Commissioning Train 2 25 24-Jan-22 21-Feb-22 24-Jan-22 21-Feb-22 (6) Behind Schedule 1
STPPCC5230 System Walkdown Commissioning Train 2 2 24-Jan-22 25-Jan-22 24-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCC5240 Flushing /Cleaning Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCC5250 Machinery Cold run test Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCC5260 Continuity and Insulaton test Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCC5270 Motor rotational check test Commissioning Train 2 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCC5290 Loop testing Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCC5300 Punch clearence -A Commissioning Train 2 3 19-Feb-22 21-Feb-22 19-Feb-22 21-Feb-22 (6) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..16 090-14-Rapid Sand Filters-16 Commissioning Train 2 25 26-Jan-22 23-Feb-22 26-Jan-22 23-Feb-22 (4) Behind Schedule 1
STPPCC5310 System Walkdown Commissioning Train 2 2 26-Jan-22 27-Jan-22 26-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC5320 Flushing /Cleaning Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC5330 Machinery Cold run test Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC5340 Continuity and Insulaton test Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCC5350 Motor rotational check test Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCC5370 Loop testing Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCC5380 Punch clearence -A Commissioning Train 2 3 21-Feb-22 23-Feb-22 21-Feb-22 23-Feb-22 (4) Behind Schedule 1
MARAFIQ COMM.2.24.2.14..17 090-14-Rapid Sand Filters-17 Commissioning Train 2 27 29-Jan-22 28-Feb-22 29-Jan-22 28-Feb-22 1 Very Critical 1
STPPCC5390 System Walkdown Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC5400 Flushing /Cleaning Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC5410 Machinery Cold run test Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCC5420 Continuity and Insulaton test Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCC5430 Motor rotational check test Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCC5450 Loop testing Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCC5460 Punch clearence -A Commissioning Train 2 3 26-Feb-22 28-Feb-22 26-Feb-22 28-Feb-22 1 Very Critical 1
MARAFIQ COMM.2.24.2.14..18 090-14-Rapid Sand Filters-18 Commissioning Train 2 27 2-Feb-22 5-Mar-22 2-Feb-22 5-Mar-22 6 Very Critical 1
STPPCC5470 System Walkdown Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC5480 Flushing /Cleaning Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCC5490 Machinery Cold run test Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCC5500 Continuity and Insulaton test Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCC5510 Motor rotational check test Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCC5530 Loop testing Commissioning Train 2 4 26-Feb-22 1-Mar-22 26-Feb-22 1-Mar-22 2 Very Critical 1
STPPCC5540 Punch clearence -A Commissioning Train 2 3 2-Mar-22 5-Mar-22 2-Mar-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.2.24.2.15. 101-Chlorine Contact Tank Commissioning Train 2 39 1-Jan-22 14-Feb-22 1-Jan-22 14-Feb-22 (13) Behind Schedule 1
MARAFIQ COMM.2.24.2.15..2 101-02-Chlorine Contact Tank-02 Commissioning Train 2 27 1-Jan-22 31-Jan-22 1-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCC6030 System Walkdown Commissioning Train 2 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
STPPCC6040 Flushing /Cleaning Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC6050 Machinery Cold run test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC6060 Continuity and Insulaton test Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC6070 Motor rotational check test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC6090 Loop testing Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC6100 Punch clearence -A Commissioning Train 2 3 29-Jan-22 31-Jan-22 29-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.2.24.2.15..3 101-03-Chlorine Contact Tank-03 Commissioning Train 2 27 5-Jan-22 5-Feb-22 5-Jan-22 5-Feb-22 (22) Behind Schedule 1
STPPCC6110 System Walkdown Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC6120 Flushing /Cleaning Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC6130 Machinery Cold run test Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC6140 Continuity and Insulaton test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC6150 Motor rotational check test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC6170 Loop testing Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC6180 Punch clearence -A Commissioning Train 2 3 2-Feb-22 5-Feb-22 2-Feb-22 5-Feb-22 (22) Behind Schedule 1
MARAFIQ COMM.2.24.2.15..4 101-04-Chlorine Contact Tank-04 Commissioning Train 2 27 10-Jan-22 9-Feb-22 10-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCC6190 System Walkdown Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC6200 Flushing /Cleaning Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC6210 Machinery Cold run test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC6220 Continuity and Insulaton test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC6230 Motor rotational check test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC6250 Loop testing Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC6260 Punch clearence -A Commissioning Train 2 3 7-Feb-22 9-Feb-22 7-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.24.2.15..5 101-05-Chlorine Contact Tank-05 Commissioning Train 2 27 15-Jan-22 14-Feb-22 15-Jan-22 14-Feb-22 (13) Behind Schedule 1
STPPCC6270 System Walkdown Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC6280 Flushing /Cleaning Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCC6290 Machinery Cold run test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCC6300 Continuity and Insulaton test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCC6310 Motor rotational check test Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCC6330 Loop testing Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCC6340 Punch clearence -A Commissioning Train 2 3 12-Feb-22 14-Feb-22 12-Feb-22 14-Feb-22 (13) Behind Schedule 1
MARAFIQ COMM.2.24.2.20. 130-Sludge Thickening Commissioning Train 2 75 6-Nov-21 31-Jan-22 6-Nov-21 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.2.24.2.20..3 130-03-Sludge Thickeners - 130-03 Commissioning Train 2 28 26-Dec-21 26-Jan-22 26-Dec-21 26-Jan-22 (32) Behind Schedule 1
STPPCC7630 System Walkdown Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC7640 Flushing /Cleaning Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC7650 Machinery Cold run test Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC7660 Continuity and Insulaton test Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC7670 Motor rotational check test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC7690 Loop testing Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC7700 Punch clearence -A Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.2.24.2.20..4 130-04-Sludge Thickeners - 130-04 Commissioning Train 2 28 30-Dec-21 31-Jan-22 30-Dec-21 31-Jan-22 (27) Behind Schedule 1
STPPCC7710 System Walkdown Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC7720 Flushing /Cleaning Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC7730 Machinery Cold run test Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC7740 Continuity and Insulaton test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC7750 Motor rotational check test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC7770 Loop testing Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC7780 Punch clearence -A Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.2.24.2.20..5 130-05-Sludge Thickeners - 130-05 Commissioning Train 2 51 6-Nov-21 3-Jan-22 6-Nov-21 3-Jan-22 (55) Behind Schedule 1
STPPCC7790 System Walkdown Commissioning Train 2 4 6-Nov-21 9-Nov-21 6-Nov-21 9-Nov-21 (110) Behind Schedule 1
STPPCC7800 Flushing /Cleaning Commissioning Train 2 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC7810 Machinery Cold run test Commissioning Train 2 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC7820 Continuity and Insulaton test Commissioning Train 2 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC7830 Motor rotational check test Commissioning Train 2 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC7850 Loop testing Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC7860 Punch clearence -A Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
MARAFIQ COMM.2.24.2.20..6 130-06-Sludge Thickeners - 130-06 Commissioning Train 2 51 6-Nov-21 3-Jan-22 6-Nov-21 3-Jan-22 (55) Behind Schedule 1
STPPCC7870 System Walkdown Commissioning Train 2 4 6-Nov-21 9-Nov-21 6-Nov-21 9-Nov-21 (110) Behind Schedule 1
STPPCC7880 Flushing /Cleaning Commissioning Train 2 4 6-Dec-21 9-Dec-21 6-Dec-21 9-Dec-21 (80) Behind Schedule 1
STPPCC7890 Machinery Cold run test Commissioning Train 2 4 11-Dec-21 14-Dec-21 11-Dec-21 14-Dec-21 (75) Behind Schedule 1
STPPCC7900 Continuity and Insulaton test Commissioning Train 2 4 15-Dec-21 19-Dec-21 15-Dec-21 19-Dec-21 (70) Behind Schedule 1
STPPCC7910 Motor rotational check test Commissioning Train 2 4 20-Dec-21 23-Dec-21 20-Dec-21 23-Dec-21 (66) Behind Schedule 1
STPPCC7930 Loop testing Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC7940 Punch clearence -A Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
MARAFIQ COMM.2.24.2.22. 140-Sludge Dewatering Commissioning Train 2 40 26-Dec-21 9-Feb-22 26-Dec-21 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.24.2.22..3 140-03-Decanter Feed Pump & Centrifuge Decan Commissioning Train 2 28 26-Dec-21 26-Jan-22 26-Dec-21 26-Jan-22 (32) Behind Schedule 1
STPPCC8190 System Walkdown Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC8200 Flushing /Cleaning Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC8210 Machinery Cold run test Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC8220 Continuity and Insulaton test Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC8230 Motor rotational check test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC8250 Loop testing Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC8260 Punch clearence -A Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.2.24.2.22..4 140-04-Decanter Feed Pump & Centrifuge Decan Commissioning Train 2 28 30-Dec-21 31-Jan-22 30-Dec-21 31-Jan-22 (27) Behind Schedule 1
STPPCC8270 System Walkdown Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC8280 Flushing /Cleaning Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC8290 Machinery Cold run test Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC8300 Continuity and Insulaton test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC8310 Motor rotational check test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC8330 Loop testing Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC8340 Punch clearence -A Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.2.24.2.22..5 140-05-Decanter Feed Pump & Centrifuge Decan Commissioning Train 2 28 4-Jan-22 5-Feb-22 4-Jan-22 5-Feb-22 (22) Behind Schedule 1
STPPCC8350 System Walkdown Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC8360 Flushing /Cleaning Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC8370 Machinery Cold run test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC8380 Continuity and Insulaton test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC8390 Motor rotational check test Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC8410 Loop testing Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCC8420 Punch clearence -A Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
MARAFIQ COMM.2.24.2.22..6 140-06-Decanter Feed Pump & Centrifuge Decan Commissioning Train 2 28 9-Jan-22 9-Feb-22 9-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCC8430 System Walkdown Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC8440 Flushing /Cleaning Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC8450 Machinery Cold run test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC8460 Continuity and Insulaton test Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC8470 Motor rotational check test Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCC8490 Loop testing Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCC8500 Punch clearence -A Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.24.2.25. 150-Polymer Preperation Commissioning Train 2 40 26-Dec-21 9-Feb-22 26-Dec-21 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.24.2.25..4 150-04-Polymer Dosing Pumps for Sludge Thicken Commissioning Train 2 28 26-Dec-21 26-Jan-22 26-Dec-21 26-Jan-22 (32) Behind Schedule 1
STPPCC9070 System Walkdown Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC9080 Flushing /Cleaning Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC9090 Machinery Cold run test Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC9100 Continuity and Insulaton test Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC9110 Motor rotational check test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC9130 Loop testing Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC9140 Punch clearence -A Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.2.24.2.25..5 150-05-Polymer Dosing Pumps for Sludge Thicken Commissioning Train 2 28 30-Dec-21 31-Jan-22 30-Dec-21 31-Jan-22 (27) Behind Schedule 1
STPPCC9150 System Walkdown Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCC9160 Flushing /Cleaning Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC9170 Machinery Cold run test Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC9180 Continuity and Insulaton test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC9190 Motor rotational check test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC9210 Loop testing Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC9220 Punch clearence -A Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.2.24.2.25..10 150-08-Polymer Dosing Pumps for Sludge Dewa Commissioning Train 2 28 4-Jan-22 5-Feb-22 4-Jan-22 5-Feb-22 (22) Behind Schedule 1
STPPCC9550 System Walkdown Commissioning Train 2 4 4-Jan-22 8-Jan-22 4-Jan-22 8-Jan-22 (50) Behind Schedule 1
STPPCC9560 Flushing /Cleaning Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC9570 Machinery Cold run test Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC9580 Continuity and Insulaton test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC9590 Motor rotational check test Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC9610 Loop testing Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCC9620 Punch clearence -A Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
MARAFIQ COMM.2.24.2.25..11 150-09-Polymer Dosing Pumps for Sludge Dewa Commissioning Train 2 28 9-Jan-22 9-Feb-22 9-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCC9630 System Walkdown Commissioning Train 2 4 9-Jan-22 12-Jan-22 9-Jan-22 12-Jan-22 (46) Behind Schedule 1
STPPCC9640 Flushing /Cleaning Commissioning Train 2 4 13-Jan-22 17-Jan-22 13-Jan-22 17-Jan-22 (41) Behind Schedule 1
STPPCC9650 Machinery Cold run test Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCC9660 Continuity and Insulaton test Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCC9670 Motor rotational check test Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCC9690 Loop testing Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCC9700 Punch clearence -A Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.25 BROWNFIELD Commissioning Train 2 134 5-Oct-21 9-Mar-22 5-Oct-21 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.2.25.1 TRAIN1 Commissioning Train 2 74 5-Oct-21 29-Dec-21 5-Oct-21 29-Dec-21 (60) Behind Schedule 1
MARAFIQ COMM.2.25.1.1 LOT1 Commissioning Train 2 74 5-Oct-21 29-Dec-21 5-Oct-21 29-Dec-21 (60) Behind Schedule 1
MARAFIQ COMM.2.25.1.1.1 190-01-Aerated Lagoon 1, 2, Settlement Pond 1, B Commissioning Train 2 6 23-Dec-21 29-Dec-21 23-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCC10750 System Walkdown 190-1 AL1,2, SP1, BP1 Commissioning Train 2 2 23-Dec-21 25-Dec-21 23-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCC10820 Punch clearence -A 190-1 AL1,2, SP1, BP1 Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
MARAFIQ COMM.2.25.1.1.4 190-04-Distribution Transformer Station 3 (For La Commissioning Train 2 8 5-Oct-21 13-Oct-21 5-Oct-21 13-Oct-21 (137) Behind Schedule 1
STPPCC10990 System Walkdown DTS3 Commissioning Train 2 4 5-Oct-21 9-Oct-21 5-Oct-21 9-Oct-21 (141) Behind Schedule 1
STPPCC11060 Punch clearence -A DTS3 Commissioning Train 2 4 10-Oct-21 13-Oct-21 10-Oct-21 13-Oct-21 (137) Behind Schedule 1
MARAFIQ COMM.2.25.2 TRAIN2 Commissioning Train 2 32 1-Feb-22 9-Mar-22 1-Feb-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.2.25.2.1 LOT2 Commissioning Train 2 32 1-Feb-22 9-Mar-22 1-Feb-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.2.25.2.1.2 190-02-Aerated Lagoon 3, 4, Settlement Pond 2, B Commissioning Train 2 8 1-Feb-22 9-Feb-22 1-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCC10830 System Walkdown 190-2 AL3,4, SP2, BP2 Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCC10900 Punch clearence -A 190-2 AL3,4, SP2, BP2 Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.25.2.1.3 190-03-Sludge Holding Lagoon 1, 2,3, Sludge dige Commissioning Train 2 8 1-Feb-22 9-Feb-22 1-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCC10910 System Walkdown - SHL1,2,3 , SDHL Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCC10980 Punch clearence -A - SHL1,2,3 , SDHL Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.2.25.2.1.5 190-05-Distribution Transformer Station 4 (For La Commissioning Train 2 7 2-Mar-22 9-Mar-22 2-Mar-22 9-Mar-22 10 Very Critical 1
STPPCC11070 System Walkdown DTS4 Commissioning Train 2 4 2-Mar-22 6-Mar-22 2-Mar-22 6-Mar-22 7 Very Critical 1
STPPCC11140 Punch clearence -A DTS4 Commissioning Train 2 3 7-Mar-22 9-Mar-22 7-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.2.25.2.2 LOT3 Commissioning Train 2 8 28-Feb-22 8-Mar-22 28-Feb-22 8-Mar-22 9 Very Critical 1
MARAFIQ COMM.2.25.2.2.6 190-06-Lagoon Drain Pumps with Starter Panels Commissioning Train 2 8 28-Feb-22 8-Mar-22 28-Feb-22 8-Mar-22 9 Very Critical 1
STPPCC11150 System Walkdown Lagoon Pump with Panels Commissioning Train 2 4 28-Feb-22 3-Mar-22 28-Feb-22 3-Mar-22 4 Very Critical 1
STPPCC11220 Punch clearence -A Lagoon Pump with Panels Commissioning Train 2 4 5-Mar-22 8-Mar-22 5-Mar-22 8-Mar-22 9 Very Critical 1
MARAFIQ COMM.3 COMMISSIONING - SYSTEM AND SUBSYSTEM Commissioning Train 2 105 24-Nov-21 26-Mar-22 24-Nov-21 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1 GREENFIELD Commissioning Train 2 105 24-Nov-21 26-Mar-22 24-Nov-21 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.45 TRAIN1 Commissioning Train 2 91 24-Nov-21 9-Mar-22 24-Nov-21 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.41 Expansion in existing SEC Room Commissioning Train 2 9 24-Nov-21 4-Dec-21 24-Nov-21 4-Dec-21 (85) Behind Schedule 1
MARAFIQ COMM.3.1.45.41.1 -MV Existing SEC Switch gear Commissioning Train 2 9 24-Nov-21 4-Dec-21 24-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCM6160 Commissioning MV Exisitng Switch gear Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCM6190 Punch clearence B Commissioning Train 2 5 29-Nov-21 4-Dec-21 29-Nov-21 4-Dec-21 (85) Behind Schedule 1
MARAFIQ COMM.3.1.45.41.2 -Civil & Structural works in SEC Switchgear room Commissioning Train 2 9 24-Nov-21 4-Dec-21 24-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCM6200 Commissioning MV Exisitng Switch gear Room Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCM6230 Punch clearence B Commissioning Train 2 5 29-Nov-21 4-Dec-21 29-Nov-21 4-Dec-21 (85) Behind Schedule 1
MARAFIQ COMM.3.1.45.41.3 -SEC switchgear expansion Commissioning Train 2 9 24-Nov-21 4-Dec-21 24-Nov-21 4-Dec-21 (85) Behind Schedule 1
STPPCM6240 Commissioning MV Exisitng Switch gear Expansion Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCM6270 Punch clearence B Commissioning Train 2 5 29-Nov-21 4-Dec-21 29-Nov-21 4-Dec-21 (85) Behind Schedule 1
MARAFIQ COMM.3.1.45.41.4 -MV Cable from SEC switchgear to SS 1 Commissioning Train 2 9 24-Nov-21 4-Dec-21 24-Nov-21 4-Dec-21 (85) Behind Schedule 1
Through check for commisssioning MV cable from SG Commissioning Train 2
STPPCM6280 to S/s1 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
STPPCM6310 Punch clearence B Commissioning Train 2 5 29-Nov-21 4-Dec-21 29-Nov-21 4-Dec-21 (85) Behind Schedule 1
MARAFIQ COMM.3.1.45.38 220-Sub Station-1 Inlet chamber Commissioning Train 2 26 24-Nov-21 23-Dec-21 24-Nov-21 23-Dec-21 (66) Behind Schedule 1
MARAFIQ COMM.3.1.45.38.1 220-1-33 KV MV system Commissioning Train 2 17 5-Dec-21 23-Dec-21 5-Dec-21 23-Dec-21 (66) Behind Schedule 1
Through check for commisssioning - 220 - 33KV MV Commissioning Train 2
STPPCM6320 System 4 5-Dec-21 8-Dec-21 5-Dec-21 8-Dec-21 (81) Behind Schedule 1
Instrumental / Electrical Fiunctional test - 220 - 33KV Commissioning Train 2
STPPCM6330 MV System 4 9-Dec-21 13-Dec-21 9-Dec-21 13-Dec-21 (76) Behind Schedule 1
Commissioning and service testing of Utilities - 220 - Commissioning Train 2
STPPCM6340 33KV MV System 4 14-Dec-21 18-Dec-21 14-Dec-21 18-Dec-21 (71) Behind Schedule 1
STPPCM6350 Punch clearence B - 220 - 33KV MV System Commissioning Train 2 5 19-Dec-21 23-Dec-21 19-Dec-21 23-Dec-21 (66) Behind Schedule 1
MARAFIQ COMM.3.1.45.38.2 220-2-Transformer System Commissioning Train 2 17 24-Nov-21 13-Dec-21 24-Nov-21 13-Dec-21 (76) Behind Schedule 1
Through check for commisssioning 220 Transformer Commissioning Train 2
STPPCM6360 System 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
Instrumental / Electrical Fiunctional test 220 Commissioning Train 2
STPPCM6370 Transformer System 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
Commissioning and service testing of Utilities 220 Commissioning Train 2
STPPCM6380 Transformer System 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCM6390 Punch clearence B 220 Transformer System Commissioning Train 2 5 8-Dec-21 13-Dec-21 8-Dec-21 13-Dec-21 (76) Behind Schedule 1
MARAFIQ COMM.3.1.45.38.3 220-3-LV system Commissioning Train 2 17 24-Nov-21 13-Dec-21 24-Nov-21 13-Dec-21 (76) Behind Schedule 1
STPPCM6400 Through check for commisssioning 220 LV System Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
Instrumental / Electrical Fiunctional test 220 LV Commissioning Train 2
STPPCM6410 System 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
Commissioning and service testing of Utilities 220 LV Commissioning Train 2
STPPCM6420 System 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCM6430 Punch clearence B 220 LV System Commissioning Train 2 5 8-Dec-21 13-Dec-21 8-Dec-21 13-Dec-21 (76) Behind Schedule 1
MARAFIQ COMM.3.1.45.38.4 220-4-EDG 1 System Commissioning Train 2 17 24-Nov-21 13-Dec-21 24-Nov-21 13-Dec-21 (76) Behind Schedule 1
STPPCM6440 Through check for commisssioning 220 EDG1 System Commissioning Train 2 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
Instrumental / Electrical Fiunctional test 220 EDG1 Commissioning Train 2
STPPCM6450 System 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
Commissioning and service testing of Utilities 220 EDG1 Commissioning Train 2
STPPCM6460 System 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCM6470 Punch clearence B 220 EDG1 System Commissioning Train 2 5 8-Dec-21 13-Dec-21 8-Dec-21 13-Dec-21 (76) Behind Schedule 1
MARAFIQ COMM.3.1.45.38.5 220-5-UPS & Battery System Commissioning Train 2 17 24-Nov-21 13-Dec-21 24-Nov-21 13-Dec-21 (76) Behind Schedule 1
Through check for commisssioning 220 UPS & Battery Commissioning Train 2
STPPCM6480 System 4 24-Nov-21 28-Nov-21 24-Nov-21 28-Nov-21 (91) Behind Schedule 1
Instrumental / Electrical Fiunctional test 220 UPS & Commissioning Train 2
STPPCM6490 Battery System 4 29-Nov-21 2-Dec-21 29-Nov-21 2-Dec-21 (87) Behind Schedule 1
Commissioning and service testing of Utilities 220 UPS Commissioning Train 2
STPPCM6500 & Battery System 4 4-Dec-21 7-Dec-21 4-Dec-21 7-Dec-21 (82) Behind Schedule 1
STPPCM6510 Punch clearence B 220 UPS & Battery System Commissioning Train 2 5 8-Dec-21 13-Dec-21 8-Dec-21 13-Dec-21 (76) Behind Schedule 1
MARAFIQ COMM.3.1.45.36 231-Panel Room for MCC(SST Area) Commissioning Train 2 17 25-Dec-21 12-Jan-22 25-Dec-21 12-Jan-22 (46) Behind Schedule 1
Through check for commisssioning - S/ 231- MCC Panel Commissioning Train 2
STPPCM7080 Room SST Area 4 25-Dec-21 28-Dec-21 25-Dec-21 28-Dec-21 (61) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/ 231- MCC Commissioning Train 2
STPPCM7090 Panel Room SST Area 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Commissioning and service testing of Utilities - S/ 231- Commissioning Train 2
STPPCM7100 MCC Panel Room SST Area 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
Punch clearence B - S/ 231- MCC Panel Room SST Area Commissioning Train 2
STPPCM7110 5 8-Jan-22 12-Jan-22 8-Jan-22 12-Jan-22 (46) Behind Schedule 1
MARAFIQ COMM.3.1.45.37 221-Sub Station-2 Blower room Commissioning Train 2 22 19-Dec-21 12-Jan-22 19-Dec-21 12-Jan-22 (46) Behind Schedule 1
MARAFIQ COMM.3.1.45.37.1 221-01-33 KV MV system Commissioning Train 2 17 25-Dec-21 12-Jan-22 25-Dec-21 12-Jan-22 (46) Behind Schedule 1
Through check for commisssioning - S/s 221 - 33KV Commissioning Train 2
STPPCM6520 MV System 4 25-Dec-21 28-Dec-21 25-Dec-21 28-Dec-21 (61) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 221 - Commissioning Train 2
STPPCM6530 33KV MV System 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 221 Commissioning Train 2
STPPCM6540 - 33KV MV System 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM6550 Punch clearence B - S/s 221 - 33KV MV System Commissioning Train 2 5 8-Jan-22 12-Jan-22 8-Jan-22 12-Jan-22 (46) Behind Schedule 1
MARAFIQ COMM.3.1.45.37.2 221-02-Transformer System Commissioning Train 2 17 19-Dec-21 6-Jan-22 19-Dec-21 6-Jan-22 (52) Behind Schedule 1
Through check for commisssioning S/s 221- Commissioning Train 2
STPPCM6560 Transformer system 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Instrumental / Electrical Fiunctional test S/s 221- Commissioning Train 2
STPPCM6570 Transformer system 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
Commissioning and service testing of Utilities S/s 221- Commissioning Train 2
STPPCM6580 Transformer system 4 28-Dec-21 1-Jan-22 28-Dec-21 1-Jan-22 (57) Behind Schedule 1
STPPCM6590 Punch clearence B Commissioning Train 2 5 2-Jan-22 6-Jan-22 2-Jan-22 6-Jan-22 (52) Behind Schedule 1
MARAFIQ COMM.3.1.45.37.3 221-03-LV system Commissioning Train 2 17 19-Dec-21 6-Jan-22 19-Dec-21 6-Jan-22 (52) Behind Schedule 1
Through check for commisssioning -S/s 221- LV System Commissioning Train 2
STPPCM6600 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Instrumental / Electrical Fiunctional test -S/s 221- LV Commissioning Train 2
STPPCM6610 System 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
Commissioning and service testing of Utilities -S/s 221- Commissioning Train 2
STPPCM6620 LV System 4 28-Dec-21 1-Jan-22 28-Dec-21 1-Jan-22 (57) Behind Schedule 1
STPPCM6630 Punch clearence B -S/s 221- LV System Commissioning Train 2 5 2-Jan-22 6-Jan-22 2-Jan-22 6-Jan-22 (52) Behind Schedule 1
MARAFIQ COMM.3.1.45.37.4 221-04-EDG 2 System Commissioning Train 2 17 19-Dec-21 6-Jan-22 19-Dec-21 6-Jan-22 (52) Behind Schedule 1
Through check for commisssioning - S/s 221- EDG2 Commissioning Train 2
STPPCM6640 System 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 221- Commissioning Train 2
STPPCM6650 EDG2 System 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 221- Commissioning Train 2
STPPCM6660 EDG2 System 4 28-Dec-21 1-Jan-22 28-Dec-21 1-Jan-22 (57) Behind Schedule 1
STPPCM6670 Punch clearence B - S/s 221- EDG2 System Commissioning Train 2 5 2-Jan-22 6-Jan-22 2-Jan-22 6-Jan-22 (52) Behind Schedule 1
MARAFIQ COMM.3.1.45.37.5 221-05-UPS & Battery System Commissioning Train 2 17 19-Dec-21 6-Jan-22 19-Dec-21 6-Jan-22 (52) Behind Schedule 1
Through check for commisssioning - S/s 221- UPS & Commissioning Train 2
STPPCM6680 Battery System 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 221- UPS Commissioning Train 2
STPPCM6690 & Battery System 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 221- Commissioning Train 2
STPPCM6700 UPS & Battery System 4 28-Dec-21 1-Jan-22 28-Dec-21 1-Jan-22 (57) Behind Schedule 1
STPPCM6710 Punch clearence B - S/s 221- UPS & Battery System Commissioning Train 2 5 2-Jan-22 6-Jan-22 2-Jan-22 6-Jan-22 (52) Behind Schedule 1
MARAFIQ COMM.3.1.45.40 222-Sub Station-4 TSE Area Commissioning Train 2 26 14-Dec-21 12-Jan-22 14-Dec-21 12-Jan-22 (46) Behind Schedule 1
MARAFIQ COMM.3.1.45.40.1 222-01-4.16 MV system Commissioning Train 2 17 25-Dec-21 12-Jan-22 25-Dec-21 12-Jan-22 (46) Behind Schedule 1
Through check for commisssioning - S/s 222- TSE Area Commissioning Train 2
STPPCM6720 4 25-Dec-21 28-Dec-21 25-Dec-21 28-Dec-21 (61) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 222- TSE Commissioning Train 2
STPPCM6730 Area 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 222- Commissioning Train 2
STPPCM6740 TSE Area 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM6750 Punch clearence B - S/s 222- TSE Area Commissioning Train 2 5 8-Jan-22 12-Jan-22 8-Jan-22 12-Jan-22 (46) Behind Schedule 1
MARAFIQ COMM.3.1.45.40.2 222-02-Transformer System Commissioning Train 2 17 14-Dec-21 2-Jan-22 14-Dec-21 2-Jan-22 (56) Behind Schedule 1
Through check for commisssioning - S/s 222- Commissioning Train 2
STPPCM6760 Transformer system 4 14-Dec-21 18-Dec-21 14-Dec-21 18-Dec-21 (71) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 222- Commissioning Train 2
STPPCM6770 Transformer system 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 222- Commissioning Train 2
STPPCM6780 Transformer system 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCM6790 Punch clearence B - S/s 222- Transformer system Commissioning Train 2 5 28-Dec-21 2-Jan-22 28-Dec-21 2-Jan-22 (56) Behind Schedule 1
MARAFIQ COMM.3.1.45.40.3 222-03-LV system Commissioning Train 2 17 14-Dec-21 2-Jan-22 14-Dec-21 2-Jan-22 (56) Behind Schedule 1
Through check for commisssioning - S/s 222- LV Commissioning Train 2
STPPCM6800 System 4 14-Dec-21 18-Dec-21 14-Dec-21 18-Dec-21 (71) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 222- LV Commissioning Train 2
STPPCM6810 System 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 222- Commissioning Train 2
STPPCM6820 LV System 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCM6830 Punch clearence B - S/s 222- LV System Commissioning Train 2 5 28-Dec-21 2-Jan-22 28-Dec-21 2-Jan-22 (56) Behind Schedule 1
MARAFIQ COMM.3.1.45.40.4 222-04-EDG 3 System Commissioning Train 2 17 14-Dec-21 2-Jan-22 14-Dec-21 2-Jan-22 (56) Behind Schedule 1
Through check for commisssioning - S/s 222- EDG3 Commissioning Train 2
STPPCM6840 System 4 14-Dec-21 18-Dec-21 14-Dec-21 18-Dec-21 (71) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 222- Commissioning Train 2
STPPCM6850 EDG3 System 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 222- Commissioning Train 2
STPPCM6860 EDG3 System 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCM6870 Punch clearence B - S/s 222- EDG3 System Commissioning Train 2 5 28-Dec-21 2-Jan-22 28-Dec-21 2-Jan-22 (56) Behind Schedule 1
MARAFIQ COMM.3.1.45.40.5 222-05-UPS & Battery System Commissioning Train 2 17 14-Dec-21 2-Jan-22 14-Dec-21 2-Jan-22 (56) Behind Schedule 1
Through check for commisssioning - S/s 222- UPS & Commissioning Train 2
STPPCM6880 Battery System 4 14-Dec-21 18-Dec-21 14-Dec-21 18-Dec-21 (71) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 222- UPS Commissioning Train 2
STPPCM6890 & Battery System 4 19-Dec-21 22-Dec-21 19-Dec-21 22-Dec-21 (67) Behind Schedule 1
Commissioning and service testing of - S/s 222- UPS & Commissioning Train 2
STPPCM6900 Battery System 4 23-Dec-21 27-Dec-21 23-Dec-21 27-Dec-21 (62) Behind Schedule 1
STPPCM6910 Punch clearence B - S/s 222- UPS & Battery System Commissioning Train 2 5 28-Dec-21 2-Jan-22 28-Dec-21 2-Jan-22 (56) Behind Schedule 1
MARAFIQ COMM.3.1.45.39 230-Sub Station-3 SST Area Commissioning Train 2 17 29-Dec-21 17-Jan-22 29-Dec-21 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.3.1.45.39.1 230-01-Transformer System Commissioning Train 2 17 29-Dec-21 17-Jan-22 29-Dec-21 17-Jan-22 (41) Behind Schedule 1
Through check for commisssioning S/s 230- Commissioning Train 2
STPPCM6920 Transformer system 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Instrumental / Electrical Fiunctional test S/s 230- Commissioning Train 2
STPPCM6930 Transformer system 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
Commissioning and service testing of Utilities S/s 230- Commissioning Train 2
STPPCM6940 Transformer system 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM6950 Punch clearence B S/s 230- Transformer system Commissioning Train 2 5 12-Jan-22 17-Jan-22 12-Jan-22 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.3.1.45.39.2 230-02-LV system Commissioning Train 2 17 29-Dec-21 17-Jan-22 29-Dec-21 17-Jan-22 (41) Behind Schedule 1
Through check for commisssioning - S/s 230- LV System Commissioning Train 2
STPPCM6960 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 230- LV Commissioning Train 2
STPPCM6970 System 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 230- Commissioning Train 2
STPPCM6980 LV System 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM6990 Punch clearence B - S/s 230- LV System Commissioning Train 2 5 12-Jan-22 17-Jan-22 12-Jan-22 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.3.1.45.39.3 230-03-EDG 3 System Commissioning Train 2 17 29-Dec-21 17-Jan-22 29-Dec-21 17-Jan-22 (41) Behind Schedule 1
Through check for commisssioning S/s 230 -EDG Commissioning Train 2
STPPCM7000 System 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Instrumental / Electrical Fiunctional test S/s 230 -EDG Commissioning Train 2
STPPCM7010 System 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
Commissioning and service testing of Utilities S/s 230 - Commissioning Train 2
STPPCM7020 EDG System 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM7030 Punch clearence B S/s 230 -EDG System Commissioning Train 2 5 12-Jan-22 17-Jan-22 12-Jan-22 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.3.1.45.39.4 230-04-UPS & Battery System Commissioning Train 2 17 29-Dec-21 17-Jan-22 29-Dec-21 17-Jan-22 (41) Behind Schedule 1
Through check for commisssioning - S/s 230- UPS & Commissioning Train 2
STPPCM7040 Battery System 4 29-Dec-21 2-Jan-22 29-Dec-21 2-Jan-22 (56) Behind Schedule 1
Instrumental / Electrical Fiunctional test - S/s 230- UPS Commissioning Train 2
STPPCM7050 & Battery System 4 3-Jan-22 6-Jan-22 3-Jan-22 6-Jan-22 (52) Behind Schedule 1
Commissioning and service testing of Utilities - S/s 230- Commissioning Train 2
STPPCM7060 UPS & Battery System 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM7070 Punch clearence B - S/s 230- UPS & Battery System Commissioning Train 2 5 12-Jan-22 17-Jan-22 12-Jan-22 17-Jan-22 (41) Behind Schedule 1
MARAFIQ COMM.3.1.45.35 210-Control Operation Room Commissioning Train 2 17 5-Jan-22 24-Jan-22 5-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.35.1 210-01-Control Operation Room - Ground Floor Commissioning Train 2 17 5-Jan-22 24-Jan-22 5-Jan-22 24-Jan-22 (34) Behind Schedule 1
STPPCM6080 Through check for commisssioning Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCM6090 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM6100 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM6110 Punch clearence B Commissioning Train 2 5 19-Jan-22 24-Jan-22 19-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.35.3 210-02-Control Operation Room - First Floor Commissioning Train 2 17 5-Jan-22 24-Jan-22 5-Jan-22 24-Jan-22 (34) Behind Schedule 1
STPPCC14410 Through check for commisssioning Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCC14420 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCC14430 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC14440 Punch clearence B Commissioning Train 2 5 19-Jan-22 24-Jan-22 19-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.42 Potable Water System Commissioning Train 2 14 3-Jan-22 18-Jan-22 3-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC15230 Commissoning of Potable Water System Commissioning Train 2 14 3-Jan-22 18-Jan-22 3-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC15240 Commissionig completion of Potable Water System Commissioning Train 2 0 18-Jan-22 18-Jan-22 (40) Behind Schedule 1
MARAFIQ COMM.3.1.45.43 Fire water System Commissioning Train 2 14 3-Jan-22 18-Jan-22 3-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC15180 Commissioning of Fire Water System Commissioning Train 2 14 3-Jan-22 18-Jan-22 3-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCC15250 Commissioning completion of Fire Water System Commissioning Train 2 0 18-Jan-22 18-Jan-22 (40) Behind Schedule 1
MARAFIQ COMM.3.1.45.44 Service water System Commissioning Train 2 14 26-Dec-21 10-Jan-22 26-Dec-21 10-Jan-22 (48) Behind Schedule 1
STPPCC15260 Commisisoning of Service water System Commissioning Train 2 14 26-Dec-21 10-Jan-22 26-Dec-21 10-Jan-22 (48) Behind Schedule 1
STPPCC15270 Commissioning completion of Service water System Commissioning Train 2 0 10-Jan-22 10-Jan-22 (48) Behind Schedule 1
MARAFIQ COMM.3.1.45.25 Fiber Optic System Commissioning Train 2 18 9-Jan-22 29-Jan-22 9-Jan-22 29-Jan-22 (29) Behind Schedule 1
STPPCC15430 Commissioning of Fiber Optic System Commissioning Train 2 14 9-Jan-22 24-Jan-22 9-Jan-22 24-Jan-22 (34) Behind Schedule 1
STPPCC15440 Commissionig completion of Fiber Optic System Commissioning Train 2 4 25-Jan-22 29-Jan-22 25-Jan-22 29-Jan-22 (29) Behind Schedule 1
MARAFIQ COMM.3.1.45.1 S001 Inlet Connenction Chamber Commissioning Train 2 15 5-Jan-22 22-Jan-22 5-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCM1000 Through check for commisssioning Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM1010 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM1020 Commissioning and service testing of Utilities Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM1030 Punch clearence B Commissioning Train 2 5 17-Jan-22 22-Jan-22 17-Jan-22 22-Jan-22 (36) Behind Schedule 1
MARAFIQ COMM.3.1.45.2 S010 Inlet Splitter Box Commissioning Train 2 13 5-Jan-22 19-Jan-22 5-Jan-22 19-Jan-22 (39) Behind Schedule 1
STPPCM1040 Through check for commisssioning Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM1050 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM1060 Commissioning and service testing of Utilities Commissioning Train 2 2 12-Jan-22 13-Jan-22 12-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM1070 Punch clearence B Commissioning Train 2 5 15-Jan-22 19-Jan-22 15-Jan-22 19-Jan-22 (39) Behind Schedule 1
MARAFIQ COMM.3.1.45.3 S020 Inlet Flow Measurement Commissioning Train 2 15 5-Jan-22 22-Jan-22 5-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCM1080 Through check for commisssioning Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM1090 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM1100 Commissioning and service testing of Utilities Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM1110 Punch clearence B Commissioning Train 2 5 17-Jan-22 22-Jan-22 17-Jan-22 22-Jan-22 (36) Behind Schedule 1
MARAFIQ COMM.3.1.45.4 S035 Inlet Chamber Commissioning Train 2 15 5-Jan-22 22-Jan-22 5-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCM1120 Through check for commisssioning Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM1130 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM1140 Commissioning and service testing of Utilities Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM1150 Punch clearence B Commissioning Train 2 5 17-Jan-22 22-Jan-22 17-Jan-22 22-Jan-22 (36) Behind Schedule 1
MARAFIQ COMM.3.1.45.5 S030 Finescreen Commissioning Train 2 15 5-Jan-22 22-Jan-22 5-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCM1160 Through check for commisssioning Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM1170 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM1180 Commissioning and service testing of Utilities Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM1190 Punch clearence B Commissioning Train 2 5 17-Jan-22 22-Jan-22 17-Jan-22 22-Jan-22 (36) Behind Schedule 1
MARAFIQ COMM.3.1.45.6 040 Grit and grease chamber Commissioning Train 2 15 8-Jan-22 24-Jan-22 8-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.6.1 040-1A-Grit and Grease Chamber-1A Commissioning Train 2 15 8-Jan-22 24-Jan-22 8-Jan-22 24-Jan-22 (34) Behind Schedule 1
STPPCM1200 Through check for commisssioning Commissioning Train 2 2 8-Jan-22 9-Jan-22 8-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCM1210 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM1220 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM1230 Punch clearence B Commissioning Train 2 5 19-Jan-22 24-Jan-22 19-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.6.2 040-1B-Grit and Grease Chamber-1B Commissioning Train 2 15 8-Jan-22 24-Jan-22 8-Jan-22 24-Jan-22 (34) Behind Schedule 1
STPPCM1240 Through check for commisssioning Commissioning Train 2 2 8-Jan-22 9-Jan-22 8-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCM1250 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM1260 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM1270 Punch clearence B Commissioning Train 2 5 19-Jan-22 24-Jan-22 19-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.7 050-Distribution Chambers for Activated Sludge Tanks Commissioning Train 2 15 10-Jan-22 26-Jan-22 10-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCM1440 Through check for commisssioning Commissioning Train 2 2 10-Jan-22 11-Jan-22 10-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM1450 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM1460 Commissioning and service testing of Utilities Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCM1470 Punch clearence B Commissioning Train 2 5 22-Jan-22 26-Jan-22 22-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.3.1.45.34 060-1-Activated Sludge Tanks-01 Commissioning Train 2 15 12-Jan-22 29-Jan-22 12-Jan-22 29-Jan-22 (29) Behind Schedule 1
STPPCM1520 Through check for commisssioning Commissioning Train 2 2 12-Jan-22 13-Jan-22 12-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM1530 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM1540 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM1550 Punch clearence B Commissioning Train 2 5 24-Jan-22 29-Jan-22 24-Jan-22 29-Jan-22 (29) Behind Schedule 1
MARAFIQ COMM.3.1.45.9 065-Blower Building Commissioning Train 2 15 15-Jan-22 31-Jan-22 15-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCM1480 Through check for commisssioning Commissioning Train 2 2 15-Jan-22 16-Jan-22 15-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM1490 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCM1500 Commissioning and service testing of Utilities Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCM1510 Punch clearence B Commissioning Train 2 5 26-Jan-22 31-Jan-22 26-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.3.1.45.8 070-1-Distribution Chambers for Secondary Sedimenta Commissioning Train 2 15 17-Jan-22 2-Feb-22 17-Jan-22 2-Feb-22 (25) Behind Schedule 1
STPPCM1640 Through check for commisssioning Commissioning Train 2 2 17-Jan-22 18-Jan-22 17-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM1650 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM1660 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM1670 Punch clearence B Commissioning Train 2 5 29-Jan-22 2-Feb-22 29-Jan-22 2-Feb-22 (25) Behind Schedule 1
MARAFIQ COMM.3.1.45.11 080-Secondary Sedimentation Tanks (SST) Commissioning Train 2 21 19-Jan-22 12-Feb-22 19-Jan-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.3.1.45.11.1 080-1-Secondary Sedimentation Tanks (SST)-01 Commissioning Train 2 15 19-Jan-22 5-Feb-22 19-Jan-22 5-Feb-22 (22) Behind Schedule 1
STPPCM1760 Through check for commisssioning Commissioning Train 2 2 19-Jan-22 20-Jan-22 19-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCM1770 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCM1780 Commissioning and service testing of Utilities Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCM1790 Punch clearence B Commissioning Train 2 5 31-Jan-22 5-Feb-22 31-Jan-22 5-Feb-22 (22) Behind Schedule 1
MARAFIQ COMM.3.1.45.11.2 080-2-Secondary Sedimentation Tanks (SST)-02 Commissioning Train 2 15 22-Jan-22 7-Feb-22 22-Jan-22 7-Feb-22 (20) Behind Schedule 1
STPPCM1800 Through check for commisssioning Commissioning Train 2 2 22-Jan-22 23-Jan-22 22-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM1810 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM1820 Commissioning and service testing of Utilities Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM1830 Punch clearence B Commissioning Train 2 5 2-Feb-22 7-Feb-22 2-Feb-22 7-Feb-22 (20) Behind Schedule 1
MARAFIQ COMM.3.1.45.11.3 080-3-Secondary Sedimentation Tanks (SST)-03 Commissioning Train 2 15 24-Jan-22 9-Feb-22 24-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCM1840 Through check for commisssioning Commissioning Train 2 2 24-Jan-22 25-Jan-22 24-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCM1850 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCM1860 Commissioning and service testing of Utilities Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCM1870 Punch clearence B Commissioning Train 2 5 5-Feb-22 9-Feb-22 5-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.3.1.45.11.4 080-4-Secondary Sedimentation Tanks (SST)-04 Commissioning Train 2 15 26-Jan-22 12-Feb-22 26-Jan-22 12-Feb-22 (15) Behind Schedule 1
STPPCM1880 Through check for commisssioning Commissioning Train 2 2 26-Jan-22 27-Jan-22 26-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM1890 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM1900 Commissioning and service testing of Utilities Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCM1910 Punch clearence B Commissioning Train 2 5 7-Feb-22 12-Feb-22 7-Feb-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.3.1.45.18 120-Excess and Return Sludge Pumping Station Commissioning Train 2 15 22-Jan-22 7-Feb-22 22-Jan-22 7-Feb-22 (20) Behind Schedule 1
MARAFIQ COMM.3.1.45.18.1 120-1-Excess and Return Sludge Pumping Station Commissioning Train 2 15 22-Jan-22 7-Feb-22 22-Jan-22 7-Feb-22 (20) Behind Schedule 1
STPPCM3920 Through check for commisssioning Commissioning Train 2 2 22-Jan-22 23-Jan-22 22-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM3930 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM3940 Commissioning and service testing of Utilities Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM3950 Punch clearence B Commissioning Train 2 5 2-Feb-22 7-Feb-22 2-Feb-22 7-Feb-22 (20) Behind Schedule 1
MARAFIQ COMM.3.1.45.19 125-Scum Pumping Station Commissioning Train 2 19 22-Jan-22 12-Feb-22 22-Jan-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.3.1.45.19.1 125-1-Scum Pumping Station-01 Commissioning Train 2 15 22-Jan-22 7-Feb-22 22-Jan-22 7-Feb-22 (20) Behind Schedule 1
STPPCM4040 Through check for commisssioning Commissioning Train 2 2 22-Jan-22 23-Jan-22 22-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM4050 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM4060 Commissioning and service testing of Utilities Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM4070 Punch clearence B Commissioning Train 2 5 2-Feb-22 7-Feb-22 2-Feb-22 7-Feb-22 (20) Behind Schedule 1
MARAFIQ COMM.3.1.45.19.2 125-2-Scum Pumping Station-02 Commissioning Train 2 15 26-Jan-22 12-Feb-22 26-Jan-22 12-Feb-22 (15) Behind Schedule 1
STPPCM4080 Through check for commisssioning Commissioning Train 2 2 26-Jan-22 27-Jan-22 26-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM4090 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM4100 Commissioning and service testing of Utilities Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCM4110 Punch clearence B Commissioning Train 2 5 7-Feb-22 12-Feb-22 7-Feb-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.3.1.45.12 090-Rapid Sand Filters Commissioning Train 2 25 22-Jan-22 19-Feb-22 22-Jan-22 19-Feb-22 (8) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.1 090-01-Rapid Sand Filters-01 Commissioning Train 2 15 22-Jan-22 7-Feb-22 22-Jan-22 7-Feb-22 (20) Behind Schedule 1
STPPCM2240 Through check for commisssioning Commissioning Train 2 2 22-Jan-22 23-Jan-22 22-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM2250 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 24-Jan-22 27-Jan-22 24-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM2260 Commissioning and service testing of Utilities Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM2270 Punch clearence B Commissioning Train 2 5 2-Feb-22 7-Feb-22 2-Feb-22 7-Feb-22 (20) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.2 090-02-Rapid Sand Filters-02 Commissioning Train 2 15 24-Jan-22 9-Feb-22 24-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCM2320 Through check for commisssioning Commissioning Train 2 2 24-Jan-22 25-Jan-22 24-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCM2330 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCM2340 Commissioning and service testing of Utilities Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCM2350 Punch clearence B Commissioning Train 2 5 5-Feb-22 9-Feb-22 5-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.3 090-03-Rapid Sand Filters-03 Commissioning Train 2 15 26-Jan-22 12-Feb-22 26-Jan-22 12-Feb-22 (15) Behind Schedule 1
STPPCM2360 Through check for commisssioning Commissioning Train 2 2 26-Jan-22 27-Jan-22 26-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM2370 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM2380 Commissioning and service testing of Utilities Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCM2390 Punch clearence B Commissioning Train 2 5 7-Feb-22 12-Feb-22 7-Feb-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.4 090-04-Rapid Sand Filters-04 Commissioning Train 2 15 29-Jan-22 14-Feb-22 29-Jan-22 14-Feb-22 (13) Behind Schedule 1
STPPCM2400 Through check for commisssioning Commissioning Train 2 2 29-Jan-22 30-Jan-22 29-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCM2410 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCM2420 Commissioning and service testing of Utilities Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCM2430 Punch clearence B Commissioning Train 2 5 9-Feb-22 14-Feb-22 9-Feb-22 14-Feb-22 (13) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.10 090-19-Back wash water Tanks Commissioning Train 2 15 24-Jan-22 9-Feb-22 24-Jan-22 9-Feb-22 (18) Behind Schedule 1
STPPCM3000 Through check for commisssioning Commissioning Train 2 2 24-Jan-22 25-Jan-22 24-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCM3010 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Jan-22 30-Jan-22 26-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCM3020 Commissioning and service testing of Utilities Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCM3030 Punch clearence B Commissioning Train 2 5 5-Feb-22 9-Feb-22 5-Feb-22 9-Feb-22 (18) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.45 090-20-Backwash water tank filling pumps Commissioning Train 2 15 26-Jan-22 12-Feb-22 26-Jan-22 12-Feb-22 (15) Behind Schedule 1
STPPCM3040 Through check for commisssioning Commissioning Train 2 2 26-Jan-22 27-Jan-22 26-Jan-22 27-Jan-22 (31) Behind Schedule 1
STPPCM3050 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 29-Jan-22 1-Feb-22 29-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM3060 Commissioning and service testing of Utilities Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCM3070 Punch clearence B Commissioning Train 2 5 7-Feb-22 12-Feb-22 7-Feb-22 12-Feb-22 (15) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.46 090-21-Rapid sand filtration blowers Commissioning Train 2 15 29-Jan-22 14-Feb-22 29-Jan-22 14-Feb-22 (13) Behind Schedule 1
STPPCM3080 Through check for commisssioning Commissioning Train 2 2 29-Jan-22 30-Jan-22 29-Jan-22 30-Jan-22 (28) Behind Schedule 1
STPPCM3090 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 31-Jan-22 3-Feb-22 31-Jan-22 3-Feb-22 (24) Behind Schedule 1
STPPCM3100 Commissioning and service testing of Utilities Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCM3110 Punch clearence B Commissioning Train 2 5 9-Feb-22 14-Feb-22 9-Feb-22 14-Feb-22 (13) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.47 090-22-Air Compressors for Pneumatic actuator Commissioning Train 2 15 31-Jan-22 16-Feb-22 31-Jan-22 16-Feb-22 (11) Behind Schedule 1
STPPCM3120 Through check for commisssioning Commissioning Train 2 2 31-Jan-22 1-Feb-22 31-Jan-22 1-Feb-22 (26) Behind Schedule 1
STPPCM3130 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 2-Feb-22 6-Feb-22 2-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCM3140 Commissioning and service testing of Utilities Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCM3150 Punch clearence B Commissioning Train 2 5 12-Feb-22 16-Feb-22 12-Feb-22 16-Feb-22 (11) Behind Schedule 1
MARAFIQ COMM.3.1.45.12.48 090-23-Backwash waste water pumps Commissioning Train 2 15 2-Feb-22 19-Feb-22 2-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM2280 Through check for commisssioning Commissioning Train 2 2 2-Feb-22 3-Feb-22 2-Feb-22 3-Feb-22 (24) Behind Schedule 1
STPPCM2290 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 5-Feb-22 8-Feb-22 5-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCM2300 Commissioning and service testing of Utilities Commissioning Train 2 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCM2310 Punch clearence B Commissioning Train 2 5 14-Feb-22 19-Feb-22 14-Feb-22 19-Feb-22 (8) Behind Schedule 1
MARAFIQ COMM.3.1.45.13 101-Chlorine Contact Tank Commissioning Train 2 15 5-Feb-22 21-Feb-22 5-Feb-22 21-Feb-22 (6) Behind Schedule 1
MARAFIQ COMM.3.1.45.13.1 101-01-Chlorine Contact Tank-01 Commissioning Train 2 15 5-Feb-22 21-Feb-22 5-Feb-22 21-Feb-22 (6) Behind Schedule 1
STPPCM3160 Through check for commisssioning Commissioning Train 2 2 5-Feb-22 6-Feb-22 5-Feb-22 6-Feb-22 (21) Behind Schedule 1
STPPCM3170 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 7-Feb-22 10-Feb-22 7-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCM3180 Commissioning and service testing of Utilities Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3190 Punch clearence B Commissioning Train 2 5 16-Feb-22 21-Feb-22 16-Feb-22 21-Feb-22 (6) Behind Schedule 1
MARAFIQ COMM.3.1.45.14 102-Reaeration and Chlorine Mixing Tanks Commissioning Train 2 17 7-Feb-22 26-Feb-22 7-Feb-22 26-Feb-22 (1) Behind Schedule 1
MARAFIQ COMM.3.1.45.14.1 102-01-Reaeration and Chlorine Mixing Tanks Commissioning Train 2 15 7-Feb-22 23-Feb-22 7-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM3360 Through check for commisssioning Commissioning Train 2 2 7-Feb-22 8-Feb-22 7-Feb-22 8-Feb-22 (19) Behind Schedule 1
STPPCM3370 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 9-Feb-22 13-Feb-22 9-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCM3380 Commissioning and service testing of Utilities Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3390 Punch clearence B Commissioning Train 2 5 19-Feb-22 23-Feb-22 19-Feb-22 23-Feb-22 (4) Behind Schedule 1
MARAFIQ COMM.3.1.45.14.2 102-02-Blowers for Reaeration Tanks Commissioning Train 2 15 9-Feb-22 26-Feb-22 9-Feb-22 26-Feb-22 (1) Behind Schedule 1
STPPCM3400 Through check for commisssioning Commissioning Train 2 2 9-Feb-22 10-Feb-22 9-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCM3410 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3420 Commissioning and service testing of Utilities Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3430 Punch clearence B Commissioning Train 2 5 21-Feb-22 26-Feb-22 21-Feb-22 26-Feb-22 (1) Behind Schedule 1
MARAFIQ COMM.3.1.45.15 103-Chlorine Dosing Station Commissioning Train 2 23 9-Feb-22 7-Mar-22 9-Feb-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.15.1 103-01-Chorine Drum Storage room Commissioning Train 2 15 9-Feb-22 26-Feb-22 9-Feb-22 26-Feb-22 (1) Behind Schedule 1
STPPCM3440 Through check for commisssioning Commissioning Train 2 2 9-Feb-22 10-Feb-22 9-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCM3450 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3460 Commissioning and service testing of Utilities Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3470 Punch clearence B Commissioning Train 2 5 21-Feb-22 26-Feb-22 21-Feb-22 26-Feb-22 (1) Behind Schedule 1
MARAFIQ COMM.3.1.45.15.2 103-02-Evaporator Room Commissioning Train 2 15 12-Feb-22 28-Feb-22 12-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3480 Through check for commisssioning Commissioning Train 2 2 12-Feb-22 13-Feb-22 12-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCM3490 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3500 Commissioning and service testing of Utilities Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM3510 Punch clearence B Commissioning Train 2 5 23-Feb-22 28-Feb-22 23-Feb-22 28-Feb-22 1 Very Critical 1
MARAFIQ COMM.3.1.45.15.3 103-03-Chlorinator and Injector room Commissioning Train 2 15 14-Feb-22 2-Mar-22 14-Feb-22 2-Mar-22 3 Very Critical 1
STPPCM3520 Through check for commisssioning Commissioning Train 2 2 14-Feb-22 15-Feb-22 14-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3530 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3540 Commissioning and service testing of Utilities Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM3550 Punch clearence B Commissioning Train 2 5 26-Feb-22 2-Mar-22 26-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.3.1.45.15.4 103-04-Electrical Room with Control Panel Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
STPPCM3560 Through check for commisssioning Commissioning Train 2 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3570 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM3580 Commissioning and service testing of Utilities Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM3590 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.15.5 103-05-Emergency Scrubber, Safety kit storage r Commissioning Train 2 15 19-Feb-22 7-Mar-22 19-Feb-22 7-Mar-22 8 Very Critical 1
STPPCM3600 Through check for commisssioning Commissioning Train 2 2 19-Feb-22 20-Feb-22 19-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3610 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM3620 Commissioning and service testing of Utilities Commissioning Train 2 4 26-Feb-22 1-Mar-22 26-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM3630 Punch clearence B Commissioning Train 2 5 2-Mar-22 7-Mar-22 2-Mar-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.16 110-TSE Pumping Station Commissioning Train 2 19 9-Feb-22 2-Mar-22 9-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.3.1.45.16.1 110-01-Chlorine Contact Tank Outlet Chamber Commissioning Train 2 15 9-Feb-22 26-Feb-22 9-Feb-22 26-Feb-22 (1) Behind Schedule 1
STPPCM3640 Through check for commisssioning Commissioning Train 2 2 9-Feb-22 10-Feb-22 9-Feb-22 10-Feb-22 (17) Behind Schedule 1
STPPCM3650 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 12-Feb-22 15-Feb-22 12-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3660 Commissioning and service testing of Utilities Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3670 Punch clearence B Commissioning Train 2 5 21-Feb-22 26-Feb-22 21-Feb-22 26-Feb-22 (1) Behind Schedule 1
MARAFIQ COMM.3.1.45.16.2 110-02-TSE Pumping Station with drainage pump Commissioning Train 2 15 12-Feb-22 28-Feb-22 12-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3680 Through check for commisssioning Commissioning Train 2 2 12-Feb-22 13-Feb-22 12-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCM3690 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3700 Commissioning and service testing of Utilities Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM3710 Punch clearence B Commissioning Train 2 5 23-Feb-22 28-Feb-22 23-Feb-22 28-Feb-22 1 Very Critical 1
MARAFIQ COMM.3.1.45.16.3 110-03-Booster Pumps for Service Water Commissioning Train 2 15 14-Feb-22 2-Mar-22 14-Feb-22 2-Mar-22 3 Very Critical 1
STPPCM3720 Through check for commisssioning Commissioning Train 2 2 14-Feb-22 15-Feb-22 14-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3730 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3740 Commissioning and service testing of Utilities Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM3750 Punch clearence B Commissioning Train 2 5 26-Feb-22 2-Mar-22 26-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.3.1.45.16.4 110-04-Booster Pumps for Chlorination Commissioning Train 2 15 12-Feb-22 28-Feb-22 12-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3760 Through check for commisssioning Commissioning Train 2 2 12-Feb-22 13-Feb-22 12-Feb-22 13-Feb-22 (14) Behind Schedule 1
STPPCM3770 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 14-Feb-22 17-Feb-22 14-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3780 Commissioning and service testing of Utilities Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM3790 Punch clearence B Commissioning Train 2 5 23-Feb-22 28-Feb-22 23-Feb-22 28-Feb-22 1 Very Critical 1
MARAFIQ COMM.3.1.45.16.5 110-05-TSE Line (Zone 1 to Zone 5) Commissioning Train 2 15 14-Feb-22 2-Mar-22 14-Feb-22 2-Mar-22 3 Very Critical 1
STPPCM3800 Through check for commisssioning TSE Line 1 to 5 Commissioning Train 2 2 14-Feb-22 15-Feb-22 14-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM3810 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM3820 Commissioning and service testing of Utilities Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM3830 Punch clearence B Commissioning Train 2 5 26-Feb-22 2-Mar-22 26-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.3.1.45.17 245-TSE VALVE CHAMBER Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.17.1 245-01-TSE Bypass upto Interface Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
STPPCM3840 Through check for commisssioning byepass interface Commissioning Train 2 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3850 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM3860 Commissioning and service testing of Utilities Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM3870 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.17.2 245-02-TSE main line upto Interface Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
Through check for commisssioning main line interface Commissioning Train 2
STPPCM3880 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM3890 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM3900 Commissioning and service testing of Utilities Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM3910 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.20 130-Sludge Thickening Commissioning Train 2 19 14-Feb-22 7-Mar-22 14-Feb-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.20.20 135-Thickened Sludge Tank Commissioning Train 2 15 14-Feb-22 2-Mar-22 14-Feb-22 2-Mar-22 3 Very Critical 1
STPPCM4440 Through check for commisssioning Commissioning Train 2 2 14-Feb-22 15-Feb-22 14-Feb-22 15-Feb-22 (12) Behind Schedule 1
STPPCM4450 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 16-Feb-22 20-Feb-22 16-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4460 Commissioning and service testing of Utilities Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM4470 Punch clearence B Commissioning Train 2 5 26-Feb-22 2-Mar-22 26-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.3.1.45.20.1 130-01-Sludge Thickeners - 130-01 Commissioning Train 2 13 16-Feb-22 2-Mar-22 16-Feb-22 2-Mar-22 3 Very Critical 1
STPPCM4200 Through check for commisssioning Commissioning Train 2 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM4210 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM4220 Commissioning and service testing of Utilities Commissioning Train 2 2 23-Feb-22 24-Feb-22 23-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM4230 Punch clearence B Commissioning Train 2 5 26-Feb-22 2-Mar-22 26-Feb-22 2-Mar-22 3 Very Critical 1
MARAFIQ COMM.3.1.45.20.2 130-02-Sludge Thickeners - 130-02 Commissioning Train 2 15 19-Feb-22 7-Mar-22 19-Feb-22 7-Mar-22 8 Very Critical 1
STPPCM4240 Through check for commisssioning Commissioning Train 2 2 19-Feb-22 20-Feb-22 19-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4250 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM4260 Commissioning and service testing of Utilities Commissioning Train 2 4 26-Feb-22 1-Mar-22 26-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4270 Punch clearence B Commissioning Train 2 5 2-Mar-22 7-Mar-22 2-Mar-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.21 140-Sludge Dewatering Commissioning Train 2 16 16-Feb-22 6-Mar-22 16-Feb-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.45.21.1 140-01-Decanter Feed Pump & Centrifuge Decant Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
STPPCM4480 Through check for commisssioning Commissioning Train 2 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM4490 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM4500 Commissioning and service testing of Utilities Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM4510 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.21.2 140-02-Decanter Feed Pump & Centrifuge Decant Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
STPPCM4520 Through check for commisssioning Commissioning Train 2 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM4530 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM4540 Commissioning and service testing of Utilities Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM4550 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.21.7 140-07-Sludge Conveyors Commissioning Train 2 15 17-Feb-22 6-Mar-22 17-Feb-22 6-Mar-22 7 Very Critical 1
STPPCM4720 Through check for commisssioning Commissioning Train 2 2 17-Feb-22 19-Feb-22 17-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM4730 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM4740 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM4750 Punch clearence B Commissioning Train 2 5 1-Mar-22 6-Mar-22 1-Mar-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.45.23 145-Lime Silo & Sludge Mixing Unit Commissioning Train 2 15 21-Feb-22 9-Mar-22 21-Feb-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.23.1 145-01-Lime Silo & Sludge Mixing Unit Commissioning Train 2 15 21-Feb-22 9-Mar-22 21-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM4760 Through check for commisssioning Commissioning Train 2 2 21-Feb-22 22-Feb-22 21-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM4770 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM4780 Commissioning and service testing of Utilities Commissioning Train 2 4 28-Feb-22 3-Mar-22 28-Feb-22 3-Mar-22 4 Very Critical 1
STPPCM4790 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.23.2 145-02-Air Compressors for Pneumatic actuators Commissioning Train 2 11 23-Feb-22 7-Mar-22 23-Feb-22 7-Mar-22 8 Very Critical 1
STPPCM4800 Through check for commisssioning Commissioning Train 2 2 23-Feb-22 24-Feb-22 23-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM4810 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM4820 Commissioning and service testing of Utilities Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4830 Punch clearence B Commissioning Train 2 5 2-Mar-22 7-Mar-22 2-Mar-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.22 150-Polymer Preperation Commissioning Train 2 12 24-Feb-22 9-Mar-22 24-Feb-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.22.1 150-01-Polymer Preparation for Sludge Thickenin Commissioning Train 2 11 24-Feb-22 8-Mar-22 24-Feb-22 8-Mar-22 9 Very Critical 1
STPPCM4880 Through check for commisssioning Commissioning Train 2 2 24-Feb-22 26-Feb-22 24-Feb-22 26-Feb-22 (1) Behind Schedule 1
STPPCM4890 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 27-Feb-22 28-Feb-22 27-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM4900 Commissioning and service testing of Utilities Commissioning Train 2 2 1-Mar-22 2-Mar-22 1-Mar-22 2-Mar-22 3 Very Critical 1
STPPCM4910 Punch clearence B Commissioning Train 2 5 3-Mar-22 8-Mar-22 3-Mar-22 8-Mar-22 9 Very Critical 1
MARAFIQ COMM.3.1.45.22.2 150-02-Polymer Dosing Pumps for Sludge Thicken Commissioning Train 2 11 26-Feb-22 9-Mar-22 26-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM4920 Through check for commisssioning Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM4930 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4940 Commissioning and service testing of Utilities Commissioning Train 2 2 2-Mar-22 3-Mar-22 2-Mar-22 3-Mar-22 4 Very Critical 1
STPPCM4950 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.22.3 150-03-Polymer Dosing Pumps for Sludge Thicken Commissioning Train 2 11 26-Feb-22 9-Mar-22 26-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM4960 Through check for commisssioning Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM4970 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4980 Commissioning and service testing of Utilities Commissioning Train 2 2 2-Mar-22 3-Mar-22 2-Mar-22 3-Mar-22 4 Very Critical 1
STPPCM4990 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.22.6 150-PL-02A-Polymer Preparation for Sludge Dewa Commissioning Train 2 11 26-Feb-22 9-Mar-22 26-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM5080 Through check for commisssioning Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5090 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5100 Commissioning and service testing of Utilities Commissioning Train 2 2 2-Mar-22 3-Mar-22 2-Mar-22 3-Mar-22 4 Very Critical 1
STPPCM5110 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.22.7 150-PL-02B-Polymer Preparation for Sludge Dewa Commissioning Train 2 11 26-Feb-22 9-Mar-22 26-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM5120 Through check for commisssioning Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5130 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5140 Commissioning and service testing of Utilities Commissioning Train 2 2 2-Mar-22 3-Mar-22 2-Mar-22 3-Mar-22 4 Very Critical 1
STPPCM5150 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.22.8 150-06-Polymer Dosing Pumps for Sludge Dewate Commissioning Train 2 11 26-Feb-22 9-Mar-22 26-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM5160 Through check for commisssioning Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5170 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5180 Commissioning and service testing of Utilities Commissioning Train 2 2 2-Mar-22 3-Mar-22 2-Mar-22 3-Mar-22 4 Very Critical 1
STPPCM5190 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.22.9 150-07-Polymer Dosing Pumps for Sludge Dewate Commissioning Train 2 11 26-Feb-22 9-Mar-22 26-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM5200 Through check for commisssioning Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5210 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5220 Commissioning and service testing of Utilities Commissioning Train 2 2 2-Mar-22 3-Mar-22 2-Mar-22 3-Mar-22 4 Very Critical 1
STPPCM5230 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.26 160-Truck Offloading Station Commissioning Train 2 17 8-Jan-22 26-Jan-22 8-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.3.1.45.26.1 160-01-Septage offloading station Coarse Screens Commissioning Train 2 15 8-Jan-22 24-Jan-22 8-Jan-22 24-Jan-22 (34) Behind Schedule 1
STPPCM5320 Through check for commisssioning Commissioning Train 2 2 8-Jan-22 9-Jan-22 8-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCM5330 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM5340 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM5350 Punch clearence B Commissioning Train 2 5 19-Jan-22 24-Jan-22 19-Jan-22 24-Jan-22 (34) Behind Schedule 1
MARAFIQ COMM.3.1.45.26.2 160-02-Truck Offloading pump Station Commissioning Train 2 15 10-Jan-22 26-Jan-22 10-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCM5360 Through check for commisssioning Commissioning Train 2 2 10-Jan-22 11-Jan-22 10-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM5370 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM5380 Commissioning and service testing of Utilities Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCM5390 Punch clearence B Commissioning Train 2 5 22-Jan-22 26-Jan-22 22-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.3.1.45.27 161-Truck Offloading Station - Guard room Commissioning Train 2 15 12-Jan-22 29-Jan-22 12-Jan-22 29-Jan-22 (29) Behind Schedule 1
STPPCM5400 Through check for commisssioning Commissioning Train 2 2 12-Jan-22 13-Jan-22 12-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM5410 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM5420 Commissioning and service testing of Utilities Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM5430 Punch clearence B Commissioning Train 2 5 24-Jan-22 29-Jan-22 24-Jan-22 29-Jan-22 (29) Behind Schedule 1
MARAFIQ COMM.3.1.45.28 162-Truck Offloading Station - Truck Bay Commissioning Train 2 15 5-Jan-22 22-Jan-22 5-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCM5440 Through check for commisssioning Commissioning Train 2 2 5-Jan-22 6-Jan-22 5-Jan-22 6-Jan-22 (52) Behind Schedule 1
STPPCM5450 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM5460 Commissioning and service testing of Utilities Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM5470 Punch clearence B Commissioning Train 2 5 17-Jan-22 22-Jan-22 17-Jan-22 22-Jan-22 (36) Behind Schedule 1
MARAFIQ COMM.3.1.45.29 163-Truck Offloading Station - Control Room Commissioning Train 2 17 8-Jan-22 26-Jan-22 8-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCM5480 Through check for commisssioning Commissioning Train 2 4 8-Jan-22 11-Jan-22 8-Jan-22 11-Jan-22 (47) Behind Schedule 1
STPPCM5490 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM5500 Commissioning and service testing of Utilities Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCM5510 Punch clearence B Commissioning Train 2 5 22-Jan-22 26-Jan-22 22-Jan-22 26-Jan-22 (32) Behind Schedule 1
MARAFIQ COMM.3.1.45.30 165-Truck Offloading Station - Flow Measurement Commissioning Train 2 17 12-Jan-22 31-Jan-22 12-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCM5520 Through check for commisssioning Commissioning Train 2 4 12-Jan-22 16-Jan-22 12-Jan-22 16-Jan-22 (42) Behind Schedule 1
STPPCM5530 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 17-Jan-22 20-Jan-22 17-Jan-22 20-Jan-22 (38) Behind Schedule 1
STPPCM5540 Commissioning and service testing of Utilities Commissioning Train 2 4 22-Jan-22 25-Jan-22 22-Jan-22 25-Jan-22 (33) Behind Schedule 1
STPPCM5550 Punch clearence B Commissioning Train 2 5 26-Jan-22 31-Jan-22 26-Jan-22 31-Jan-22 (27) Behind Schedule 1
MARAFIQ COMM.3.1.45.24 200-Container Storage Area Commissioning Train 2 7 19-Feb-22 26-Feb-22 19-Feb-22 26-Feb-22 (1) Behind Schedule 1
STPPCM4840 Through check for commisssioning Commissioning Train 2 2 19-Feb-22 20-Feb-22 19-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4870 Punch clearence B Commissioning Train 2 5 21-Feb-22 26-Feb-22 21-Feb-22 26-Feb-22 (1) Behind Schedule 1
MARAFIQ COMM.3.1.45.31 170-Foul Air Treatment Unit-1 Commissioning Train 2 17 16-Feb-22 7-Mar-22 16-Feb-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.31.1 170-01-Foul Air Treatment Unit-1 Train A Commissioning Train 2 15 16-Feb-22 5-Mar-22 16-Feb-22 5-Mar-22 6 Very Critical 1
STPPCM5560 Through check for commisssioning Commissioning Train 2 2 16-Feb-22 17-Feb-22 16-Feb-22 17-Feb-22 (10) Behind Schedule 1
STPPCM5570 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 19-Feb-22 22-Feb-22 19-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM5580 Commissioning and service testing of Utilities Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5590 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.31.2 170-02-Foul Air Treatment Unit-1 Train B Commissioning Train 2 15 19-Feb-22 7-Mar-22 19-Feb-22 7-Mar-22 8 Very Critical 1
STPPCM5600 Through check for commisssioning Commissioning Train 2 2 19-Feb-22 20-Feb-22 19-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM5610 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM5620 Commissioning and service testing of Utilities Commissioning Train 2 4 26-Feb-22 1-Mar-22 26-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5630 Punch clearence B Commissioning Train 2 5 2-Mar-22 7-Mar-22 2-Mar-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.31.3 170-03-Activated Carbon Filter Commissioning Train 2 11 21-Feb-22 5-Mar-22 21-Feb-22 5-Mar-22 6 Very Critical 1
STPPCM5640 Through check for commisssioning Commissioning Train 2 2 21-Feb-22 22-Feb-22 21-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM5650 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 23-Feb-22 24-Feb-22 23-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM5660 Commissioning and service testing of Utilities Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5670 Punch clearence B Commissioning Train 2 5 28-Feb-22 5-Mar-22 28-Feb-22 5-Mar-22 6 Very Critical 1
MARAFIQ COMM.3.1.45.31.4 170-04-Chemical Tanks and Dosing Pumps Commissioning Train 2 11 23-Feb-22 7-Mar-22 23-Feb-22 7-Mar-22 8 Very Critical 1
STPPCM5680 Through check for commisssioning Commissioning Train 2 2 23-Feb-22 24-Feb-22 23-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM5690 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 26-Feb-22 27-Feb-22 26-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5700 Commissioning and service testing of Utilities Commissioning Train 2 2 28-Feb-22 1-Mar-22 28-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5710 Punch clearence B Commissioning Train 2 5 2-Mar-22 7-Mar-22 2-Mar-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.32 172-Foul Air Treatment Unit-2 (Truck Offloading Stat Commissioning Train 2 17 19-Feb-22 9-Mar-22 19-Feb-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.32.1 172-01-Caustic & Bleach Scrubber Commissioning Train 2 15 19-Feb-22 7-Mar-22 19-Feb-22 7-Mar-22 8 Very Critical 1
STPPCM5720 Through check for commisssioning Commissioning Train 2 2 19-Feb-22 20-Feb-22 19-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM5730 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 21-Feb-22 24-Feb-22 21-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM5740 Commissioning and service testing of Utilities Commissioning Train 2 4 26-Feb-22 1-Mar-22 26-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5750 Punch clearence B Commissioning Train 2 5 2-Mar-22 7-Mar-22 2-Mar-22 7-Mar-22 8 Very Critical 1
MARAFIQ COMM.3.1.45.32.2 172-02-Chemical Tanks and Dosing Pumps Commissioning Train 2 15 21-Feb-22 9-Mar-22 21-Feb-22 9-Mar-22 10 Very Critical 1
STPPCM5760 Through check for commisssioning Commissioning Train 2 2 21-Feb-22 22-Feb-22 21-Feb-22 22-Feb-22 (5) Behind Schedule 1
STPPCM5770 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 23-Feb-22 27-Feb-22 23-Feb-22 27-Feb-22 (0) Behind Schedule 1
STPPCM5780 Commissioning and service testing of Utilities Commissioning Train 2 4 28-Feb-22 3-Mar-22 28-Feb-22 3-Mar-22 4 Very Critical 1
STPPCM5790 Punch clearence B Commissioning Train 2 5 5-Mar-22 9-Mar-22 5-Mar-22 9-Mar-22 10 Very Critical 1
MARAFIQ COMM.3.1.45.33 180-Plant Drain Pumping Station Commissioning Train 2 17 10-Jan-22 29-Jan-22 10-Jan-22 29-Jan-22 (29) Behind Schedule 1
STPPCM5800 Through check for commisssioning Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM5810 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Jan-22 18-Jan-22 15-Jan-22 18-Jan-22 (40) Behind Schedule 1
STPPCM5820 Commissioning and service testing of Utilities Commissioning Train 2 4 19-Jan-22 23-Jan-22 19-Jan-22 23-Jan-22 (35) Behind Schedule 1
STPPCM5830 Punch clearence B Commissioning Train 2 5 24-Jan-22 29-Jan-22 24-Jan-22 29-Jan-22 (29) Behind Schedule 1
MARAFIQ COMM.3.1.46 TRAIN2 Commissioning Train 2 82 21-Dec-21 26-Mar-22 21-Dec-21 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.6 040 Grit and grease chamber Commissioning Train 2 11 3-Mar-22 15-Mar-22 3-Mar-22 15-Mar-22 16 On schedule 1
MARAFIQ COMM.3.1.46.6.3 040-2A-Grit and Grease Chamber-2A Commissioning Train 2 11 3-Mar-22 15-Mar-22 3-Mar-22 15-Mar-22 16 On schedule 1
STPPCM1280 Through check for commisssioning Commissioning Train 2 2 3-Mar-22 5-Mar-22 3-Mar-22 5-Mar-22 6 Very Critical 1
STPPCM1290 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM1300 Commissioning and service testing of Utilities Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM1310 Punch clearence B Commissioning Train 2 5 10-Mar-22 15-Mar-22 10-Mar-22 15-Mar-22 16 On schedule 1
MARAFIQ COMM.3.1.46.6.4 040-2B-Grit and Grease Chamber-2B Commissioning Train 2 11 3-Mar-22 15-Mar-22 3-Mar-22 15-Mar-22 16 On schedule 1
STPPCM1320 Through check for commisssioning Commissioning Train 2 2 3-Mar-22 5-Mar-22 3-Mar-22 5-Mar-22 6 Very Critical 1
STPPCM1330 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM1340 Commissioning and service testing of Utilities Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM1350 Punch clearence B Commissioning Train 2 5 10-Mar-22 15-Mar-22 10-Mar-22 15-Mar-22 16 On schedule 1
MARAFIQ COMM.3.1.46.6.5 040-3A-Grit and Grease Chamber-3A Commissioning Train 2 11 3-Mar-22 15-Mar-22 3-Mar-22 15-Mar-22 16 On schedule 1
STPPCM1360 Through check for commisssioning Commissioning Train 2 2 3-Mar-22 5-Mar-22 3-Mar-22 5-Mar-22 6 Very Critical 1
STPPCM1370 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM1380 Commissioning and service testing of Utilities Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM1390 Punch clearence B Commissioning Train 2 5 10-Mar-22 15-Mar-22 10-Mar-22 15-Mar-22 16 On schedule 1
MARAFIQ COMM.3.1.46.6.6 040-3B-Grit and Grease Chamber-3B Commissioning Train 2 11 3-Mar-22 15-Mar-22 3-Mar-22 15-Mar-22 16 On schedule 1
STPPCM1400 Through check for commisssioning Commissioning Train 2 2 3-Mar-22 5-Mar-22 3-Mar-22 5-Mar-22 6 Very Critical 1
STPPCM1410 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM1420 Commissioning and service testing of Utilities Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM1430 Punch clearence B Commissioning Train 2 5 10-Mar-22 15-Mar-22 10-Mar-22 15-Mar-22 16 On schedule 1
MARAFIQ COMM.3.1.46.8 060-Activated Sludge Tanks (AST) Commissioning Train 2 26 21-Dec-21 19-Jan-22 21-Dec-21 19-Jan-22 (39) Behind Schedule 1
MARAFIQ COMM.3.1.46.8.2 060-2-Activated Sludge Tanks-02 Commissioning Train 2 17 1-Jan-22 19-Jan-22 1-Jan-22 19-Jan-22 (39) Behind Schedule 1
STPPCM1560 Through check for commisssioning Commissioning Train 2 4 1-Jan-22 4-Jan-22 1-Jan-22 4-Jan-22 (54) Behind Schedule 1
STPPCM1570 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 5-Jan-22 9-Jan-22 5-Jan-22 9-Jan-22 (49) Behind Schedule 1
STPPCM1580 Commissioning and service testing of Utilities Commissioning Train 2 4 10-Jan-22 13-Jan-22 10-Jan-22 13-Jan-22 (45) Behind Schedule 1
STPPCM1590 Punch clearence B Commissioning Train 2 5 15-Jan-22 19-Jan-22 15-Jan-22 19-Jan-22 (39) Behind Schedule 1
MARAFIQ COMM.3.1.46.8.3 060-3-Activated Sludge Tanks-03 Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM1600 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM1610 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM1620 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM1630 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.10 070-Distribution Chambers for Secondary Sedimenta Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.10.2 070-2-Distribution Chambers for Secondary Sedi Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM1680 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM1690 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM1700 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM1710 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.10.3 070-3-Distribution Chambers for Secondary Sedi Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM1720 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM1730 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM1740 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM1750 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.11 080-Secondary Sedimentation Tanks (SST) Commissioning Train 2 45 18-Jan-22 10-Mar-22 18-Jan-22 10-Mar-22 11 Very Critical 1
MARAFIQ COMM.3.1.46.11.5 080-5-Secondary Sedimentation Tanks (SST)-05 Commissioning Train 2 17 18-Jan-22 6-Feb-22 18-Jan-22 6-Feb-22 (21) Behind Schedule 1
STPPCM1920 Through check for commisssioning Commissioning Train 2 4 18-Jan-22 22-Jan-22 18-Jan-22 22-Jan-22 (36) Behind Schedule 1
STPPCM1930 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCM1940 Commissioning and service testing of Utilities Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCM1950 Punch clearence B Commissioning Train 2 5 1-Feb-22 6-Feb-22 1-Feb-22 6-Feb-22 (21) Behind Schedule 1
MARAFIQ COMM.3.1.46.11.6 080-6-Secondary Sedimentation Tanks (SST)-06 Commissioning Train 2 17 23-Jan-22 10-Feb-22 23-Jan-22 10-Feb-22 (17) Behind Schedule 1
STPPCM1960 Through check for commisssioning Commissioning Train 2 4 23-Jan-22 26-Jan-22 23-Jan-22 26-Jan-22 (32) Behind Schedule 1
STPPCM1970 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCM1980 Commissioning and service testing of Utilities Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM1990 Punch clearence B Commissioning Train 2 5 6-Feb-22 10-Feb-22 6-Feb-22 10-Feb-22 (17) Behind Schedule 1
MARAFIQ COMM.3.1.46.11.7 080-7-Secondary Sedimentation Tanks (SST)-07 Commissioning Train 2 17 27-Jan-22 15-Feb-22 27-Jan-22 15-Feb-22 (12) Behind Schedule 1
STPPCM2000 Through check for commisssioning Commissioning Train 2 4 27-Jan-22 31-Jan-22 27-Jan-22 31-Jan-22 (27) Behind Schedule 1
STPPCM2010 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM2020 Commissioning and service testing of Utilities Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM2030 Punch clearence B Commissioning Train 2 5 10-Feb-22 15-Feb-22 10-Feb-22 15-Feb-22 (12) Behind Schedule 1
MARAFIQ COMM.3.1.46.11.8 080-8-Secondary Sedimentation Tanks (SST)-08 Commissioning Train 2 17 1-Feb-22 20-Feb-22 1-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM2040 Through check for commisssioning Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM2050 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM2060 Commissioning and service testing of Utilities Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM2070 Punch clearence B Commissioning Train 2 5 15-Feb-22 20-Feb-22 15-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.1.46.11.9 080-9-Secondary Sedimentation Tanks (SST)-09 Commissioning Train 2 17 6-Feb-22 24-Feb-22 6-Feb-22 24-Feb-22 (3) Behind Schedule 1
STPPCM2080 Through check for commisssioning Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM2090 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM2100 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM2110 Punch clearence B Commissioning Train 2 5 20-Feb-22 24-Feb-22 20-Feb-22 24-Feb-22 (3) Behind Schedule 1
MARAFIQ COMM.3.1.46.11.10 080-10-Secondary Sedimentation Tanks (SST)-1 Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM2120 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM2130 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM2140 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM2150 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.11.11 080-11-Secondary Sedimentation Tanks (SST)-1 Commissioning Train 2 17 15-Feb-22 6-Mar-22 15-Feb-22 6-Mar-22 7 Very Critical 1
STPPCM2160 Through check for commisssioning Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM2170 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM2180 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM2190 Punch clearence B Commissioning Train 2 5 1-Mar-22 6-Mar-22 1-Mar-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.46.11.12 080-12-Secondary Sedimentation Tanks (SST)-1 Commissioning Train 2 17 20-Feb-22 10-Mar-22 20-Feb-22 10-Mar-22 11 Very Critical 1
STPPCM2200 Through check for commisssioning Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM2210 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM2220 Commissioning and service testing of Utilities Commissioning Train 2 4 1-Mar-22 5-Mar-22 1-Mar-22 5-Mar-22 6 Very Critical 1
STPPCM2230 Punch clearence B Commissioning Train 2 5 6-Mar-22 10-Mar-22 6-Mar-22 10-Mar-22 11 Very Critical 1
MARAFIQ COMM.3.1.46.17 120-Excess and Return Sludge Pumping Station Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.17.2 120-2-Excess and Return Sludge Pumping Station Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM3960 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM3970 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM3980 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM3990 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.17.3 120-3-Excess and Return Sludge Pumping Station Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM4000 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM4010 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM4020 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM4030 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.18 125-Scum Pumping Station Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.18.3 125-3-Scum Pumping Station-03 Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM4120 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM4130 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM4140 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM4150 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.18.4 125-4-Scum Pumping Station-04 Commissioning Train 2 17 21-Dec-21 9-Jan-22 21-Dec-21 9-Jan-22 (49) Behind Schedule 1
STPPCM4160 Through check for commisssioning Commissioning Train 2 4 21-Dec-21 25-Dec-21 21-Dec-21 25-Dec-21 (64) Behind Schedule 1
STPPCM4170 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 26-Dec-21 29-Dec-21 26-Dec-21 29-Dec-21 (60) Behind Schedule 1
STPPCM4180 Commissioning and service testing of Utilities Commissioning Train 2 4 30-Dec-21 3-Jan-22 30-Dec-21 3-Jan-22 (55) Behind Schedule 1
STPPCM4190 Punch clearence B Commissioning Train 2 5 4-Jan-22 9-Jan-22 4-Jan-22 9-Jan-22 (49) Behind Schedule 1
MARAFIQ COMM.3.1.46.24 101-Chlorine Contact Tank Commissioning Train 2 17 15-Feb-22 6-Mar-22 15-Feb-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.46.24.2 101-02-Chlorine Contact Tank-02 Commissioning Train 2 17 15-Feb-22 6-Mar-22 15-Feb-22 6-Mar-22 7 Very Critical 1
STPPCM3200 Through check for commisssioning Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM3210 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM3220 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3230 Punch clearence B Commissioning Train 2 5 1-Mar-22 6-Mar-22 1-Mar-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.46.24.3 101-03-Chlorine Contact Tank-03 Commissioning Train 2 17 15-Feb-22 6-Mar-22 15-Feb-22 6-Mar-22 7 Very Critical 1
STPPCM3240 Through check for commisssioning Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM3250 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM3260 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3270 Punch clearence B Commissioning Train 2 5 1-Mar-22 6-Mar-22 1-Mar-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.46.24.4 101-04-Chlorine Contact Tank-04 Commissioning Train 2 17 15-Feb-22 6-Mar-22 15-Feb-22 6-Mar-22 7 Very Critical 1
STPPCM3280 Through check for commisssioning Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM3290 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM3300 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3310 Punch clearence B Commissioning Train 2 5 1-Mar-22 6-Mar-22 1-Mar-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.46.24.5 101-05-Chlorine Contact Tank-05 Commissioning Train 2 17 15-Feb-22 6-Mar-22 15-Feb-22 6-Mar-22 7 Very Critical 1
STPPCM3320 Through check for commisssioning Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM3330 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM3340 Commissioning and service testing of Utilities Commissioning Train 2 4 24-Feb-22 28-Feb-22 24-Feb-22 28-Feb-22 1 Very Critical 1
STPPCM3350 Punch clearence B Commissioning Train 2 5 1-Mar-22 6-Mar-22 1-Mar-22 6-Mar-22 7 Very Critical 1
MARAFIQ COMM.3.1.46.13 090-Rapid Sand Filters Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.5 090-05-Rapid Sand Filters-05 Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
STPPCM2480 Through check for commisssioning Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM2490 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2500 Commissioning and service testing of Utilities Commissioning Train 2 2 10-Mar-22 12-Mar-22 10-Mar-22 12-Mar-22 13 Very Critical 1
STPPCM2510 Punch clearence B Commissioning Train 2 12 13-Mar-22 26-Mar-22 13-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.6 090-06-Rapid Sand Filters-06 Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
STPPCM2440 Through check for commisssioning Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM2450 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2460 Commissioning and service testing of Utilities Commissioning Train 2 2 10-Mar-22 12-Mar-22 10-Mar-22 12-Mar-22 13 Very Critical 1
STPPCM2470 Punch clearence B Commissioning Train 2 12 13-Mar-22 26-Mar-22 13-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.7 090-07-Rapid Sand Filters-07 Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
STPPCM2520 Through check for commisssioning Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM2530 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2540 Commissioning and service testing of Utilities Commissioning Train 2 2 10-Mar-22 12-Mar-22 10-Mar-22 12-Mar-22 13 Very Critical 1
STPPCM2550 Punch clearence B Commissioning Train 2 12 13-Mar-22 26-Mar-22 13-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.8 090-08-Rapid Sand Filters-08 Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
STPPCM2560 Through check for commisssioning Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM2570 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2580 Commissioning and service testing of Utilities Commissioning Train 2 2 10-Mar-22 12-Mar-22 10-Mar-22 12-Mar-22 13 Very Critical 1
STPPCM2590 Punch clearence B Commissioning Train 2 12 13-Mar-22 26-Mar-22 13-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.9 090-09-Rapid Sand Filters-09 Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
STPPCM2600 Through check for commisssioning Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM2610 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2620 Commissioning and service testing of Utilities Commissioning Train 2 2 10-Mar-22 12-Mar-22 10-Mar-22 12-Mar-22 13 Very Critical 1
STPPCM2630 Punch clearence B Commissioning Train 2 12 13-Mar-22 26-Mar-22 13-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.10 090-10-Rapid Sand Filters-10 Commissioning Train 2 18 6-Mar-22 26-Mar-22 6-Mar-22 26-Mar-22 27 On schedule 1
STPPCM2640 Through check for commisssioning Commissioning Train 2 2 6-Mar-22 7-Mar-22 6-Mar-22 7-Mar-22 8 Very Critical 1
STPPCM2650 Instrumental / Electrical Fiunctional test Commissioning Train 2 2 8-Mar-22 9-Mar-22 8-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2660 Commissioning and service testing of Utilities Commissioning Train 2 2 10-Mar-22 12-Mar-22 10-Mar-22 12-Mar-22 13 Very Critical 1
STPPCM2670 Punch clearence B Commissioning Train 2 12 13-Mar-22 26-Mar-22 13-Mar-22 26-Mar-22 27 On schedule 1
MARAFIQ COMM.3.1.46.13.11 090-11-Rapid Sand Filters-11 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2680 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2690 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2700 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2710 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.12 090-12-Rapid Sand Filters-12 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2720 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2730 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2740 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2750 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.13 090-13-Rapid Sand Filters-13 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2760 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2770 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2780 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2790 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.14 090-14-Rapid Sand Filters-14 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2800 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2810 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2820 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2830 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.15 090-14-Rapid Sand Filters-15 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2840 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2850 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2860 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2870 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.16 090-14-Rapid Sand Filters-16 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2880 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2890 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2900 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2910 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.17 090-14-Rapid Sand Filters-17 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2920 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2930 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2940 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2950 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.13.18 090-14-Rapid Sand Filters-18 Commissioning Train 2 17 6-Mar-22 24-Mar-22 6-Mar-22 24-Mar-22 25 On schedule 1
STPPCM2960 Through check for commisssioning Commissioning Train 2 4 6-Mar-22 9-Mar-22 6-Mar-22 9-Mar-22 10 Very Critical 1
STPPCM2970 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM2980 Commissioning and service testing of Utilities Commissioning Train 2 4 15-Mar-22 19-Mar-22 15-Mar-22 19-Mar-22 20 On schedule 1
STPPCM2990 Punch clearence B Commissioning Train 2 5 20-Mar-22 24-Mar-22 20-Mar-22 24-Mar-22 25 On schedule 1
MARAFIQ COMM.3.1.46.19 130-Sludge Thickening Commissioning Train 2 17 1-Feb-22 20-Feb-22 1-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.1.46.19.3 130-03-Sludge Thickeners - 130-03 Commissioning Train 2 17 1-Feb-22 20-Feb-22 1-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4280 Through check for commisssioning Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM4290 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM4300 Commissioning and service testing of Utilities Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4310 Punch clearence B Commissioning Train 2 5 15-Feb-22 20-Feb-22 15-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.1.46.19.4 130-04-Sludge Thickeners - 130-04 Commissioning Train 2 17 1-Feb-22 20-Feb-22 1-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4320 Through check for commisssioning Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM4330 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM4340 Commissioning and service testing of Utilities Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4350 Punch clearence B Commissioning Train 2 5 15-Feb-22 20-Feb-22 15-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.1.46.19.5 130-05-Sludge Thickeners - 130-05 Commissioning Train 2 17 1-Feb-22 20-Feb-22 1-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4360 Through check for commisssioning Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM4370 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM4380 Commissioning and service testing of Utilities Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4390 Punch clearence B Commissioning Train 2 5 15-Feb-22 20-Feb-22 15-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.1.46.19.6 130-06-Sludge Thickeners - 130-06 Commissioning Train 2 17 1-Feb-22 20-Feb-22 1-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM4400 Through check for commisssioning Commissioning Train 2 4 1-Feb-22 5-Feb-22 1-Feb-22 5-Feb-22 (22) Behind Schedule 1
STPPCM4410 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 6-Feb-22 9-Feb-22 6-Feb-22 9-Feb-22 (18) Behind Schedule 1
STPPCM4420 Commissioning and service testing of Utilities Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4430 Punch clearence B Commissioning Train 2 5 15-Feb-22 20-Feb-22 15-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.1.46.21 140-Sludge Dewatering Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.21.3 140-03-Decanter Feed Pump & Centrifuge Decant Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4560 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4570 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM4580 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM4590 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.21.4 140-04-Decanter Feed Pump & Centrifuge Decant Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4600 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4610 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM4620 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM4630 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.21.5 140-05-Decanter Feed Pump & Centrifuge Decant Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4640 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4650 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM4660 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM4670 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.21.6 140-06-Decanter Feed Pump & Centrifuge Decant Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM4680 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM4690 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM4700 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM4710 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.25 150-Polymer Preperation Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.25.4 150-04-Polymer Dosing Pumps for Sludge Thicken Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5000 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM5010 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM5020 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM5030 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.25.5 150-05-Polymer Dosing Pumps for Sludge Thicken Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5040 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM5050 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM5060 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM5070 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.25.10 150-08-Polymer Dosing Pumps for Sludge Dewat Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5240 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM5250 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM5260 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM5270 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.1.46.25.11 150-09-Polymer Dosing Pumps for Sludge Dewat Commissioning Train 2 17 10-Feb-22 1-Mar-22 10-Feb-22 1-Mar-22 2 Very Critical 1
STPPCM5280 Through check for commisssioning Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM5290 Instrumental / Electrical Fiunctional test Commissioning Train 2 4 15-Feb-22 19-Feb-22 15-Feb-22 19-Feb-22 (8) Behind Schedule 1
STPPCM5300 Commissioning and service testing of Utilities Commissioning Train 2 4 20-Feb-22 23-Feb-22 20-Feb-22 23-Feb-22 (4) Behind Schedule 1
STPPCM5310 Punch clearence B Commissioning Train 2 5 24-Feb-22 1-Mar-22 24-Feb-22 1-Mar-22 2 Very Critical 1
MARAFIQ COMM.3.2 BROWNFIELD Commissioning Train 2 36 10-Feb-22 23-Mar-22 10-Feb-22 23-Mar-22 24 On schedule 1
MARAFIQ COMM.3.2.1 TRAIN1 Commissioning Train 2 9 10-Feb-22 20-Feb-22 10-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.2.1.1 LOT1 Commissioning Train 2 9 10-Feb-22 20-Feb-22 10-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.2.1.1.1 190-01-Aerated Lagoon 1, 2, Settlement Pond 1, Ba Commissioning Train 2 7 10-Feb-22 17-Feb-22 10-Feb-22 17-Feb-22 (10) Behind Schedule 1
Through check for commisssioning 190-1 AL1,2, SP1, Commissioning Train 2
STPPCM5840 BP1 2 10-Feb-22 12-Feb-22 10-Feb-22 12-Feb-22 (15) Behind Schedule 1
STPPCM5870 Punch clearence B 190-1 AL1,2, SP1, BP1 Commissioning Train 2 5 13-Feb-22 17-Feb-22 13-Feb-22 17-Feb-22 (10) Behind Schedule 1
MARAFIQ COMM.3.2.1.1.4 190-04-Distribution Transformer Station 3 (For Lago Commissioning Train 2 9 10-Feb-22 20-Feb-22 10-Feb-22 20-Feb-22 (7) Behind Schedule 1
STPPCM5960 Through check for commisssioning DTS3 Commissioning Train 2 4 10-Feb-22 14-Feb-22 10-Feb-22 14-Feb-22 (13) Behind Schedule 1
STPPCM5990 Punch clearence B DTS3 Commissioning Train 2 5 15-Feb-22 20-Feb-22 15-Feb-22 20-Feb-22 (7) Behind Schedule 1
MARAFIQ COMM.3.2.2 TRAIN2 Commissioning Train 2 13 9-Mar-22 23-Mar-22 9-Mar-22 23-Mar-22 24 On schedule 1
MARAFIQ COMM.3.2.2.1 LOT2 Commissioning Train 2 10 9-Mar-22 20-Mar-22 9-Mar-22 20-Mar-22 21 On schedule 1
MARAFIQ COMM.3.2.2.1.2 190-02-Aerated Lagoon 3, 4, Settlement Pond 2, Ba Commissioning Train 2 9 9-Mar-22 19-Mar-22 9-Mar-22 19-Mar-22 20 On schedule 1
Through check for commisssioning 190-2 AL3,4, SP2, Commissioning Train 2
STPPCM5880 BP2 4 9-Mar-22 13-Mar-22 9-Mar-22 13-Mar-22 14 Very Critical 1
STPPCM5910 Punch clearence B 190-2 AL3,4, SP2, BP2 Commissioning Train 2 5 14-Mar-22 19-Mar-22 14-Mar-22 19-Mar-22 20 On schedule 1
MARAFIQ COMM.3.2.2.1.3 190-03-Sludge Holding Lagoon 1, 2,3, Sludge diges Commissioning Train 2 9 9-Mar-22 19-Mar-22 9-Mar-22 19-Mar-22 20 On schedule 1
STPPCM5920 Through check for commisssioning - SHL1,2,3 , SDHL Commissioning Train 2 4 9-Mar-22 13-Mar-22 9-Mar-22 13-Mar-22 14 Very Critical 1
STPPCM5950 Punch clearence B - SHL1,2,3 , SDHL Commissioning Train 2 5 14-Mar-22 19-Mar-22 14-Mar-22 19-Mar-22 20 On schedule 1
MARAFIQ COMM.3.2.2.1.5 190-05-Distribution Transformer Station 4 (For Lago Commissioning Train 2 9 10-Mar-22 20-Mar-22 10-Mar-22 20-Mar-22 21 On schedule 1
STPPCM6000 Through check for commisssioning DTS4 Commissioning Train 2 4 10-Mar-22 14-Mar-22 10-Mar-22 14-Mar-22 15 Critical 1
STPPCM6030 Punch clearence B DTS4 Commissioning Train 2 5 15-Mar-22 20-Mar-22 15-Mar-22 20-Mar-22 21 On schedule 1
MARAFIQ COMM.3.2.2.34 LOT3 Commissioning Train 2 9 14-Mar-22 23-Mar-22 14-Mar-22 23-Mar-22 24 On schedule 1
MARAFIQ COMM.3.2.2.34.6 190-06-Lagoon Drain Pumps with Starter Panels Commissioning Train 2 9 14-Mar-22 23-Mar-22 14-Mar-22 23-Mar-22 24 On schedule 1
Through check for commisssioning Lagoon drain pump Commissioning Train 2
STPPCM6040 with panel 4 14-Mar-22 17-Mar-22 14-Mar-22 17-Mar-22 18 On schedule 1
STPPCM6070 Punch clearence B Lagoon drain pump with panel Commissioning Train 2 5 19-Mar-22 23-Mar-22 19-Mar-22 23-Mar-22 24 On schedule 1
MARAFIQ COMM.4 PERFORMANCE AND RELIABILITY TESTING ( INITIAL ACCEPTANCE Commissioning Train 2 40 5-Mar-22 1-May-22 5-Mar-22 1-May-22 63 On schedule 1
MARAFIQ COMM.4.13 TRAIN1&2 Commissioning Train 2 50 5-Mar-22 1-May-22 5-Mar-22 1-May-22 63 On schedule 1
MARAFIQ COMM.4.13.1 PRETREATMENT Commissioning Train 2 11 16-Mar-22 28-Mar-22 16-Mar-22 28-Mar-22 29 On schedule 1
STPPCF1000 Performance testing Pretreatment Train1&2 Commissioning Train 2 7 16-Mar-22 23-Mar-22 16-Mar-22 23-Mar-22 24 On schedule 1
STPPCF1030 Punch list Close out - C Commissioning Train 2 4 24-Mar-22 28-Mar-22 24-Mar-22 28-Mar-22 29 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1040 final 0 28-Mar-22 28-Mar-22 29 On schedule 1
MARAFIQ COMM.4.13.2 SECONDARY TREATMENT Commissioning Train 2 34 12-Mar-22 19-Apr-22 12-Mar-22 19-Apr-22 51 On schedule 1
STPPCF1050 Performance testing Secondary Treatment Train1&2 Commissioning Train 2 14 12-Mar-22 27-Mar-22 12-Mar-22 27-Mar-22 28 On schedule 1
STPPCF1080 Punch list Close out - C Commissioning Train 2 14 28-Mar-22 19-Apr-22 28-Mar-22 19-Apr-22 51 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1090 final 0 19-Apr-22 19-Apr-22 51 On schedule 1
MARAFIQ COMM.4.13.3 TERTIARY TREATMENT Commissioning Train 2 29 27-Mar-22 30-Apr-22 27-Mar-22 30-Apr-22 62 On schedule 1
STPPCF1100 Performance testing Tertiary treatment Train1&2 Commissioning Train 2 10 27-Mar-22 10-Apr-22 27-Mar-22 10-Apr-22 42 On schedule 1
STPPCF1130 Punch list Close out - C Commissioning Train 2 10 10-Apr-22 30-Apr-22 10-Apr-22 30-Apr-22 62 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1140 final 0 30-Apr-22 30-Apr-22 62 On schedule 1
MARAFIQ COMM.4.13.4 SLUDGE DEWATERING Commissioning Train 2 45 10-Mar-22 1-May-22 10-Mar-22 1-May-22 63 On schedule 1
STPPCF1150 Performance testing Sludfge Dewatering Train1&2 Commissioning Train 2 21 10-Mar-22 4-Apr-22 10-Mar-22 4-Apr-22 36 On schedule 1
STPPCF1180 Punch list Close out - C Commissioning Train 2 14 4-Apr-22 1-May-22 4-Apr-22 1-May-22 63 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1190 final 0 1-May-22 1-May-22 63 On schedule 1
MARAFIQ COMM.4.13.5 ODOUR CONTROL Commissioning Train 2 45 10-Mar-22 1-May-22 10-Mar-22 1-May-22 63 On schedule 1
STPPCF1200 Performance testing Odour Control Train1&2 Commissioning Train 2 21 10-Mar-22 4-Apr-22 10-Mar-22 4-Apr-22 36 On schedule 1
STPPCF1230 Punch list Close out - C Commissioning Train 2 14 4-Apr-22 1-May-22 4-Apr-22 1-May-22 63 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1240 final 0 1-May-22 1-May-22 63 On schedule 1
MARAFIQ COMM.4.13.6 TRUCK OFFLOADING Commissioning Train 2 45 10-Mar-22 1-May-22 10-Mar-22 1-May-22 63 On schedule 1
STPPCF1250 Performance testing Truck Off loding Train1&2 Commissioning Train 2 21 10-Mar-22 4-Apr-22 10-Mar-22 4-Apr-22 36 On schedule 1
STPPCF1280 Punch list Close out - C Commissioning Train 2 14 4-Apr-22 1-May-22 4-Apr-22 1-May-22 63 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1290 final 0 1-May-22 1-May-22 63 On schedule 1
MARAFIQ COMM.4.13.7 ANCILLARY WORKS - LAGOON Commissioning Train 2 48 5-Mar-22 30-Apr-22 5-Mar-22 30-Apr-22 62 On schedule 1
MARAFIQ COMM.4.13.7.1 LOT1 Commissioning Train 2 30 5-Mar-22 7-Apr-22 5-Mar-22 7-Apr-22 39 On schedule 1
STPPCF1300 Performance testing - Lot 1 Commissioning Train 2 14 5-Mar-22 20-Mar-22 5-Mar-22 20-Mar-22 21 On schedule 1
STPPCF1330 Punch list Close out - C Commissioning Train 2 14 21-Mar-22 7-Apr-22 21-Mar-22 7-Apr-22 39 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCF1340 final 0 7-Apr-22 7-Apr-22 39 On schedule 1
MARAFIQ COMM.4.13.7.8 LOT2 Commissioning Train 2 28 21-Mar-22 21-Apr-22 21-Mar-22 21-Apr-22 53 On schedule 1
STPPCC15030 Performace testing - Lot 2 Commissioning Train 2 14 21-Mar-22 7-Apr-22 21-Mar-22 7-Apr-22 39 On schedule 1
STPPCC15050 Punch list Close out - C Commissioning Train 2 7 9-Apr-22 21-Apr-22 9-Apr-22 21-Apr-22 53 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCC15060 final 0 21-Apr-22 21-Apr-22 53 On schedule 1
MARAFIQ COMM.4.13.7.2 LOT3 Commissioning Train 2 31 24-Mar-22 30-Apr-22 24-Mar-22 30-Apr-22 62 On schedule 1
STPPCC15040 Performance testing - Lot 3 Commissioning Train 2 15 24-Mar-22 16-Apr-22 24-Mar-22 16-Apr-22 48 On schedule 1
STPPCC15070 Punch list Close out - C Commissioning Train 2 7 16-Apr-22 30-Apr-22 16-Apr-22 30-Apr-22 62 On schedule 1
Completion of Performance testing and Obtaining IA - Commissioning Train 2
STPPCC15080 final 0 30-Apr-22 30-Apr-22 62 On schedule 1
MARAFIQ COMM.4.14 TRAIN2 0 1
MARAFIQ COMM.4.14.8 PRETREATMENT TRAIN2 0 1
MARAFIQ COMM.4.14.9 SECONDARY TREATMENT TRAIN2 0 1
MARAFIQ COMM.4.14.10 TERTIARY TREATMENT TRAIN2 0 1
MARAFIQ COMM.4.14.11 SLUDGE DEWATERING TRAIN2 0 1
MARAFIQ COMM.4.14.12 ANCILLARY WORKS - LAGOON TRAIN2 0 1
MARAFIQ COMM.8 COMPLETION OF PLANT 0 1-May-22 1-May-22 1-May-22 1-May-22 63 On schedule 1
STPPCC12870 Completion and Handpover of Plant 0 1-May-22 1-May-22 63 On schedule 1
SWTP -9 TRAIN 1 SCHEDULE
Commisioning Start Pre-Commissioning
14-Nov-21 24-Aug-21
date Start Date

Commisioning Pre-Commissioning
As of: 27-Feb-22 8-Mar-22 13-Dec-21
Completion date Completion Date

Free
Activity Description Location Structure Discipline No. Start Finish Total Float
Float
STPCP Precomm of Chlorination and Air treatment PRECOMMISSIONING TERTIARY TREATMENT TERTIARY TREATMENT 1 4-Sep-21 (176) 19-Sep-21 (161)
STPCPM Energise / Commissioning - Electrical PRECOMMISSIONING BUILDINGS Substation 1 25-Aug-21 (186) 4-Sep-21 (176)
10160 Substation Building S/s 220
STPCPM Energise / Commissioning - Transformer PRECOMMISSIONING BUILDINGS Substation 1 24-Aug-21 (187) 3-Sep-21 (177)
10200 station S/s 222
STPCPM Energise / Commissioning - Transformer PRECOMMISSIONING BUILDINGS Substation 1 4-Sep-21 (176) 14-Sep-21 (166)
10210 station S/s 221
Status
Delayed

Delayed

Delayed

Delayed
PERMIT STATUS
SN Description Discipline Date Raise
1 Permit for Civil Foundation Lagoon Civil 06-Sep-21
2 Road cutting for fire Brown area Piping 06-Sep-21
3 Road cutting for Potable Water Brown area Piping 06-Sep-21
4 Permit for DTS_4 Lagoon Electrical Works Electrical 07-Sep-21
5 Existing Pump Station to Splitter Box Works General 08-Sep-21
6 Permit from ISD in By-pass Line Civil 18-Sep-21
Risk Assessment and MS of the Potable Water Line
7 Piping 18-Sep-21
Brown
8 FOC Permit Instrumentation 27-Sep-21
9 Surface Aerator Assembly - Lagoon Area  Mechanical 29-Sep-21
10 Inlet Splitter Box Civil 11-Oct-21
11 Electrical Panel Civil Foundation for DTS 4 Civil 21-Nov-21
12 Mechanical Foundation Civil 21-Nov-21
13 RA for Thrust block Zone 5 Tie in. Civil 21-Nov-21
14 Bypass line fence relocation permit Civil 05-Dec-21
Truck offloading conrete slab (Relocation of FENCE,
15 Civil 06-Dec-21
Permits and etc.)
16 Regarding the proposal fence for raising chamber  Civil 19-Dec-21
PERMIT STATUS
Orginal Forecast
Re-Schedule Status Level
Completion Date
Closed
Open
Open
Closed
Open
Open
Closed
18-Oct-21 Closed
Closed
Open
Open
Closed
Open
Open
Open
Open
Remarks
Already started

With Mario
Material and Submittal Statu
SN Description Discipline Type Date Raise
11 Water Heater E and I Material 06-Sep-21
12 Water Tanks Civil Material 06-Sep-21

18 Countertop Civil Material 06-Sep-21

19 Caged Ladders Civil Material 07-Sep-21


21 Exhaust Pipe for CDS Mechanical Material 07-Sep-21
22 W.C Civil Material 13-Sep-21
23 Perinial Spray Civil Material 13-Sep-21
24 Wash Basin Civil Material 13-Sep-21
25 Faucets and Mixers Civil Material 13-Sep-21
31 Ajyal pipes for brown field Piping Material 13-Sep-21
32 Potable pipes for Pump Station to Splitter Box Piping Material 13-Sep-21
33 Flap Valves Material not on site Mechanical Material 19-Sep-21
48 Granite delivery Civil Material 12-Oct-21
50 SPS Manhole covers Civil Material 20-Nov-21
51 Tiel Grout material Civil Material 20-Nov-21
52 Storm Manhole Cover Civil Material 20-Nov-21
53 Basin Covers Civil Material 20-Nov-21
54 Skirting Civil Material 20-Nov-21
55 Threshold Civil Material 20-Nov-21
56 Tile Grout Civil Material 20-Nov-21
57 Cage ladders (Process) Civil Material 20-Nov-21
Remaining Covers in auction
al and Submittal Status
Expected date Status Level Remarks
30-Sep-21 Open
30-Sep-21 Open
MAR Already submitted to client with polyester
Open material. But client requirement is acrylic. So we will
submit MAR for acrylic counter top ASAP.
30-Sep-21 Open
12-Sep-21 Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
16-Dec-21
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


ROADS AND STORM DRAINAGE ROADS AND STORM DRAINAGE 65 8-Sep-21 8-Nov-21 (111) #N/A
1 Road Network ROADS AND STORM DRAINAGE 122 15-Jul-21 15-Nov-21 (104) #N/A
1 Storm Dranaige ROADS AND STORM DRAINAGE 147 5-May-21 30-Sep-21 (150) #N/A
INLET CHAMBER AND INLET SPLITTER BOX -001/010 INLET CHAMBER AND INLET SPLITTER BOX -001/010 100 29-Jun-21 26-Sep-21 (154) #N/A
1 BEAM AND SLAB at El+11.60 INLET CHAMBER AND INLET SPLITTER BOX -001/010 27 29-Jun-21 20-Jul-21 (222) #N/A
1 OUTER WAL upto El+14.50 INLET CHAMBER AND INLET SPLITTER BOX -001/010 20 18-Jul-21 5-Aug-21 (206) #N/A
1 BAFFLE WALL & INNER WALL INLET CHAMBER AND INLET SPLITTER BOX -001/010 20 26-Jul-21 14-Aug-21 (197) #N/A
1 BEAM AND SLAB at El+14.50 INLET CHAMBER AND INLET SPLITTER BOX -001/010 21 17-Aug-21 6-Sep-21 (174) #N/A
1 STAIRS INLET CHAMBER AND INLET SPLITTER BOX -001/010 33 9-Aug-21 8-Sep-21 (172) #N/A
1 Stairs at El. +8.20 INLET CHAMBER AND INLET SPLITTER BOX -001/010 11 9-Aug-21 19-Aug-21 (192) #N/A
1 Stairs at El. +10.30 INLET CHAMBER AND INLET SPLITTER BOX -001/010 11 16-Aug-21 26-Aug-21 (185) #N/A
1 Stairs at El. +12.40 INLET CHAMBER AND INLET SPLITTER BOX -001/010 11 22-Aug-21 1-Sep-21 (179) #N/A
1 Stairs at El. +14.50 INLET CHAMBER AND INLET SPLITTER BOX -001/010 11 30-Aug-21 8-Sep-21 (172) #N/A
1 TESTING & FINISHING WORKS INLET CHAMBER AND INLET SPLITTER BOX -001/010 45 10-Aug-21 21-Sep-21 (159) #N/A
1 STEEL STRUCTURES INLET CHAMBER AND INLET SPLITTER BOX -001/010 5 16-Sep-21 21-Sep-21 (159) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR INLET CHAMBER AND INLET SPLITTER BOX -001/010 15 12-Sep-21 26-Sep-21 (154) #N/A
INLET FLOW MEASUREMENT 020 INLET FLOW MEASUREMENT 020 113 19-Jun-21 30-Sep-21 (150) #N/A
1 WALL INLET FLOW MEASUREMENT 020 30 19-Jun-21 15-Jul-21 (227) #N/A
1 Top Slab INLET FLOW MEASUREMENT 020 21 11-Aug-21 30-Aug-21 (181) #N/A
1 Cable Pull Pit INLET FLOW MEASUREMENT 020 34 29-Aug-21 29-Sep-21 (151) #N/A
1 SLAB INLET FLOW MEASUREMENT 020 21 29-Aug-21 16-Sep-21 (164) #N/A
1 WALL INLET FLOW MEASUREMENT 020 16 14-Sep-21 29-Sep-21 (151) #N/A
1 TESTING & FINISHING WORKS INLET FLOW MEASUREMENT 020 61 19-Jul-21 14-Sep-21 (166) #N/A
1 STEEL STRUCTURES INLET FLOW MEASUREMENT 020 10 29-Aug-21 7-Sep-21 (173) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR INLET FLOW MEASUREMENT 020 15 18-Sep-21 30-Sep-21 (150) #N/A
FINE SCREEN & INLET CHAMBER -030/035 FINE SCREEN & INLET CHAMBER -030/035 141 3-Jul-21 10-Nov-21 (109) #N/A
INLET CHAMBER FINE SCREEN & INLET CHAMBER -030/035 23 24-Jul-21 12-Aug-21 (199) #N/A
1 SLAB at +13.0m FINE SCREEN & INLET CHAMBER -030/035 23 24-Jul-21 12-Aug-21 (199) #N/A
FINE SREEN FINE SCREEN & INLET CHAMBER -030/035 103 3-Jul-21 5-Oct-21 (145) #N/A
1 COLUMN upto El. +10.90m FINE SCREEN & INLET CHAMBER -030/035 8 3-Jul-21 8-Jul-21 (234) #N/A
1 BEAM AND SLAB AT EL. +10.90m FINE SCREEN & INLET CHAMBER -030/035 16 5-Jul-21 20-Jul-21 (222) #N/A
1 COLUMN upto El. +13.00m FINE SCREEN & INLET CHAMBER -030/035 16 17-Jul-21 31-Jul-21 (211) #N/A
1 BEAM AND SLAB AT EL. +13.00m FINE SCREEN & INLET CHAMBER -030/035 16 27-Jul-21 10-Aug-21 (201) #N/A
1 COLUMN upto El. +17.70m FINE SCREEN & INLET CHAMBER -030/035 16 7-Aug-21 22-Aug-21 (189) #N/A
1 BEAM AND SLAB AT EL. +17.70m FINE SCREEN & INLET CHAMBER -030/035 15 18-Aug-21 31-Aug-21 (180) #N/A
1 COLUMN upto El. +22.30m FINE SCREEN & INLET CHAMBER -030/035 15 28-Aug-21 9-Sep-21 (171) #N/A
1 BEAM AND SLAB AT EL. +22.30m FINE SCREEN & INLET CHAMBER -030/035 16 6-Sep-21 21-Sep-21 (159) #N/A
1 PARAPET & TOP SLAB WATER PROOFING FINE SCREEN & INLET CHAMBER -030/035 20 18-Sep-21 5-Oct-21 (145) #N/A
1 STAIR (West Side) FINE SCREEN & INLET CHAMBER -030/035 38 7-Aug-21 11-Sep-21 (169) #N/A
1 Stair to el.+9.15m FINE SCREEN & INLET CHAMBER -030/035 14 7-Aug-21 19-Aug-21 (192) #N/A
1 Stair to el. +11.075m FINE SCREEN & INLET CHAMBER -030/035 14 21-Aug-21 2-Sep-21 (178) #N/A
1 Stair to el. +13.00m FINE SCREEN & INLET CHAMBER -030/035 15 29-Aug-21 11-Sep-21 (169) #N/A
1 TESTING & FINISHING WORKS FINE SCREEN & INLET CHAMBER -030/035 42 7-Aug-21 15-Sep-21 (165) #N/A
1 ARCHITECTURAL WORKS FINE SCREEN & INLET CHAMBER -030/035 53 18-Sep-21 6-Nov-21 (113) #N/A
1 STEEL STRUCTURES FINE SCREEN & INLET CHAMBER -030/035 8 27-Oct-21 3-Nov-21 (116) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR FINE SCREEN & INLET CHAMBER -030/035 15 27-Oct-21 10-Nov-21 (109) #N/A
GRIT AND GREASE CHAMBERS- 040 GRIT AND GREASE CHAMBERS- 040 150 3-Jul-21 18-Nov-21 (101) #N/A
1 COLUMN 2nd Level (South) GRIT AND GREASE CHAMBERS- 040 22 3-Jul-21 22-Jul-21 (220) #N/A
1 COLUMN 2nd Level (North) GRIT AND GREASE CHAMBERS- 040 22 13-Jul-21 3-Aug-21 (208) #N/A
1 SLAB +10.80m GRIT AND GREASE CHAMBERS- 040 20 12-Jul-21 31-Jul-21 (211) #N/A
1 WALL (+10.80m to +13.00m) Middle GRIT AND GREASE CHAMBERS- 040 21 27-Jul-21 15-Aug-21 (196) #N/A
1 WALL (+10.80m to +13.00m) South GRIT AND GREASE CHAMBERS- 040 21 7-Aug-21 26-Aug-21 (185) #N/A
1 WALL (+10.80m to +13.00m) North GRIT AND GREASE CHAMBERS- 040 21 18-Aug-21 6-Sep-21 (174) #N/A
1 CHANNEL SLAB +EL12.00m GRIT AND GREASE CHAMBERS- 040 20 11-Aug-21 30-Aug-21 (181) #N/A
1 CHANNEL WALL GRIT AND GREASE CHAMBERS- 040 20 4-Sep-21 22-Sep-21 (158) #N/A
1 TOP SLAB (El+13.00m) GRIT AND GREASE CHAMBERS- 040 24 26-Sep-21 18-Oct-21 (132) #N/A
1 TESTING & FINISHING WORKS GRIT AND GREASE CHAMBERS- 040 103 10-Aug-21 14-Nov-21 (105) #N/A
1 MIDDLE GRIT AND GREASE CHAMBERS- 040 95 10-Aug-21 7-Nov-21 (112) #N/A
1 SOUTH GRIT AND GREASE CHAMBERS- 040 92 17-Aug-21 11-Nov-21 (108) #N/A
1 NORTH GRIT AND GREASE CHAMBERS- 040 87 24-Aug-21 14-Nov-21 (105) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR GRIT AND GREASE CHAMBERS- 040 15 4-Nov-21 18-Nov-21 (101) #N/A
DISTRIBUTION CHAMBER FOR AST -050 DISTRIBUTION CHAMBER FOR AST -050 134 3-Jul-21 3-Nov-21 (116) #N/A
1 SLAB +10.00m DISTRIBUTION CHAMBER FOR AST -050 19 3-Jul-21 20-Jul-21 (222) #N/A
1 Channel Slab +10.50m (10units) DISTRIBUTION CHAMBER FOR AST -050 20 17-Jul-21 3-Aug-21 (208) #N/A
1 Channel Wall DISTRIBUTION CHAMBER FOR AST -050 20 5-Aug-21 23-Aug-21 (188) #N/A
1 Slab at El.+11.50m DISTRIBUTION CHAMBER FOR AST -050 17 21-Aug-21 5-Sep-21 (175) #N/A
1 COLUMN up to +13.0m DISTRIBUTION CHAMBER FOR AST -050 21 19-Aug-21 7-Sep-21 (173) #N/A
1 TOP SLAB +13.0m DISTRIBUTION CHAMBER FOR AST -050 20 7-Sep-21 26-Sep-21 (154) #N/A
1 STEEL STRUCTURES DISTRIBUTION CHAMBER FOR AST -050 5 20-Sep-21 25-Sep-21 (155) #N/A
1 TESTING & FINISHING WORKS DISTRIBUTION CHAMBER FOR AST -050 43 20-Sep-21 30-Oct-21 (120) #N/A
1 STAIR FOR AST DC & GRIT AND GREASE DISTRIBUTION CHAMBER FOR AST -050 39 26-Sep-21 31-Oct-21 (119) #N/A
1 STAIRS (GRID 1/ M~P) DISTRIBUTION CHAMBER FOR AST -050 27 26-Sep-21 20-Oct-21 (130) #N/A
1 Stairs at El. +9.13 DISTRIBUTION CHAMBER FOR AST -050 11 26-Sep-21 5-Oct-21 (145) #N/A
1 Stairs at El. +11.25 DISTRIBUTION CHAMBER FOR AST -050 11 3-Oct-21 12-Oct-21 (138) #N/A
1 Stairs at El. +13.00 DISTRIBUTION CHAMBER FOR AST -050 11 10-Oct-21 20-Oct-21 (130) #N/A

Page 43 of 76
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


1 STAIRS (GRID 12/ A~D) DISTRIBUTION CHAMBER FOR AST -050 36 28-Sep-21 31-Oct-21 (119) #N/A
1 Stairs at El. +8.80 DISTRIBUTION CHAMBER FOR AST -050 11 28-Sep-21 9-Oct-21 (141) #N/A
1 Stairs at El. +10.725 DISTRIBUTION CHAMBER FOR AST -050 12 6-Oct-21 17-Oct-21 (133) #N/A
1 Stairs at El. +12.30 DISTRIBUTION CHAMBER FOR AST -050 11 13-Oct-21 24-Oct-21 (126) #N/A
1 Stairs at El. +13.00 DISTRIBUTION CHAMBER FOR AST -050 11 21-Oct-21 31-Oct-21 (119) #N/A
1 STAIRS (GRID 12/J~L) DISTRIBUTION CHAMBER FOR AST -050 29 4-Oct-21 31-Oct-21 (119) #N/A
1 Stairs at El. +9.325 DISTRIBUTION CHAMBER FOR AST -050 12 4-Oct-21 14-Oct-21 (136) #N/A
1 Stairs at El. +11.25 DISTRIBUTION CHAMBER FOR AST -050 12 12-Oct-21 23-Oct-21 (127) #N/A
1 Stairs at El. +13.00 DISTRIBUTION CHAMBER FOR AST -050 12 20-Oct-21 31-Oct-21 (119) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR DISTRIBUTION CHAMBER FOR AST -050 15 21-Oct-21 3-Nov-21 (116) #N/A
Biological Tanks - 050 / 060 AST Biological Tanks - 050 / 060 AST 185 25-Apr-21 7-Sep-21 (173) #N/A
AREA 1 Biological Tanks - 050 / 060 AST 40 13-Jul-21 18-Aug-21 (193) #N/A
1 TESTING & FINISHING WORKS Biological Tanks - 050 / 060 AST 25 13-Jul-21 4-Aug-21 (207) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Biological Tanks - 050 / 060 AST 15 5-Aug-21 18-Aug-21 (193) #N/A
AREA 2 Biological Tanks - 050 / 060 AST 170 25-Apr-21 24-Aug-21 (187) #N/A
1 STAIRS AND OUSTSIDE STRUCTURE Biological Tanks - 050 / 060 AST 27 3-Jul-21 27-Jul-21 (215) #N/A
1 STAIRS 4 Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 STAIRS 5 Biological Tanks - 050 / 060 AST 13 3-Jul-21 13-Jul-21 (229) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 10 4-Jul-21 13-Jul-21 (229) #N/A
1 STAIRS 6 Biological Tanks - 050 / 060 AST 27 3-Jul-21 27-Jul-21 (215) #N/A
1 COLUMN Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 BEAM Biological Tanks - 050 / 060 AST 12 4-Jul-21 15-Jul-21 (227) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 12 10-Jul-21 21-Jul-21 (221) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 12 15-Jul-21 27-Jul-21 (215) #N/A
1 STEEL STRUCTURES Biological Tanks - 050 / 060 AST 25 3-Jul-21 25-Jul-21 (217) #N/A
1 TESTING & FINISHING WORKS Biological Tanks - 050 / 060 AST 165 25-Apr-21 19-Aug-21 (192) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Biological Tanks - 050 / 060 AST 15 10-Aug-21 24-Aug-21 (187) #N/A
AREA 3 Biological Tanks - 050 / 060 AST 78 27-Jun-21 7-Sep-21 (173) #N/A
1 STAIRS AND OUSTSIDE STRUCTURE Biological Tanks - 050 / 060 AST 58 27-Jun-21 19-Aug-21 (192) #N/A
1 STAIRS 2 Biological Tanks - 050 / 060 AST 15 27-Jun-21 11-Jul-21 (231) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 7 27-Jun-21 3-Jul-21 (239) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 8 3-Jul-21 11-Jul-21 (231) #N/A
1 STAIRS 3 Biological Tanks - 050 / 060 AST 15 3-Jul-21 15-Jul-21 (227) #N/A
1 BEAM Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 12 4-Jul-21 15-Jul-21 (227) #N/A
1 STAIRS 4 Biological Tanks - 050 / 060 AST 15 3-Jul-21 15-Jul-21 (227) #N/A
1 BEAM Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 12 4-Jul-21 15-Jul-21 (227) #N/A
1 STAIRS 5 Biological Tanks - 050 / 060 AST 47 3-Jul-21 15-Aug-21 (196) #N/A
1 COLUMN Biological Tanks - 050 / 060 AST 8 3-Jul-21 10-Jul-21 (232) #N/A
1 BEAM Biological Tanks - 050 / 060 AST 12 22-Jul-21 3-Aug-21 (208) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 12 28-Jul-21 9-Aug-21 (202) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 12 3-Aug-21 15-Aug-21 (196) #N/A
1 STAIRS 6 Biological Tanks - 050 / 060 AST 52 3-Jul-21 19-Aug-21 (192) #N/A
1 COLUMN Biological Tanks - 050 / 060 AST 13 3-Jul-21 14-Jul-21 (228) #N/A
1 BEAM Biological Tanks - 050 / 060 AST 12 27-Jul-21 8-Aug-21 (203) #N/A
1 TREAD AND RISER Biological Tanks - 050 / 060 AST 12 2-Aug-21 14-Aug-21 (197) #N/A
1 LANDING Biological Tanks - 050 / 060 AST 12 8-Aug-21 19-Aug-21 (192) #N/A
1 STEEL STRUCTURES Biological Tanks - 050 / 060 AST 20 26-Jul-21 14-Aug-21 (197) #N/A
1 TESTING & FINISHING WORKS Biological Tanks - 050 / 060 AST 67 3-Jul-21 2-Sep-21 (178) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Biological Tanks - 050 / 060 AST 15 24-Aug-21 7-Sep-21 (173) #N/A
DISTRIBUTION FOR SECONDARY SEDIMENTATION TANKS DCDISTRIBUTION FOR SECONDARY SEDIMENTATION TAN 57 19-Jun-21 10-Aug-21 (201) #N/A
1 STAIRS DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 16 3-Jul-21 17-Jul-21 (225) #N/A
1 COLUMN DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 8 3-Jul-21 10-Jul-21 (232) #N/A
1 TREAD AND RISER DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 12 5-Jul-21 17-Jul-21 (225) #N/A
1 TESTING & FINISHING WORKS DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 57 19-Jun-21 10-Aug-21 (201) #N/A
TANK 2 TANK 2 7 3-Jul-21 8-Jul-21 (234) #N/A
1 TESTING & FINISHING WORKS TANK 2 7 3-Jul-21 8-Jul-21 (234) #N/A
TANK 3 TANK 3 7 3-Jul-21 8-Jul-21 (234) #N/A
1 TESTING & FINISHING WORKS TANK 3 7 3-Jul-21 8-Jul-21 (234) #N/A
TANK 4 TANK 4 17 23-Jun-21 8-Jul-21 (234) #N/A
1 TESTING & FINISHING WORKS TANK 4 17 23-Jun-21 8-Jul-21 (234) #N/A
STAIRS (SST 1 & 2) TANK 4 8 3-Jul-21 10-Jul-21 (232) #N/A
1 TREAD AND RISER (2nd Leve) TANK 4 8 3-Jul-21 10-Jul-21 (232) #N/A
STAIRS (SST 2 & 4) TANK 4 7 27-Jun-21 5-Jul-21 (237) #N/A
1 TREAD AND RISER (2nd Level) TANK 4 7 27-Jun-21 5-Jul-21 (237) #N/A
1 STEEL STRUCTURES TANK 4 30 3-Jul-21 29-Jul-21 (213) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR TANK 4 15 1-Aug-21 15-Aug-21 (196) #N/A
DISTRIBUTION FOR SECONDARY SEDIMENTATION TANKS DCDISTRIBUTION FOR SECONDARY SEDIMENTATION TAN 93 16-Jun-21 1-Sep-21 (179) #N/A
1 RINGWALL (OUTER & CHAMBER) DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 37 16-Jun-21 12-Jul-21 (230) #N/A
1 RINGWALL (INNER & CONNECTION WALL) DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 23 7-Jul-21 28-Jul-21 (214) #N/A

Page 44 of 76
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


1 PLATFORM DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 25 29-Jul-21 22-Aug-21 (189) #N/A
1 STAIRS DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 34 22-Jul-21 22-Aug-21 (189) #N/A
1 FOOTING DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 19 22-Jul-21 9-Aug-21 (202) #N/A
1 COLUMN DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 12 4-Aug-21 16-Aug-21 (195) #N/A
1 TREAD AND RISER DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 12 11-Aug-21 22-Aug-21 (189) #N/A
1 TESTING & FINISHING WORKS DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 43 24-Jul-21 1-Sep-21 (179) #N/A
TANK 5 TANK 5 111 3-Jul-21 13-Oct-21 (137) #N/A
1 MAIN STRUCTURE TANK 5 60 3-Jul-21 28-Aug-21 (183) #N/A
1 CENTRAL SLAB (6100mm Diameter) TANK 5 8 3-Jul-21 10-Jul-21 (232) #N/A
1 CENTRAL RING WALL 2nd Lift (Inside) TANK 5 23 10-Jul-21 31-Jul-21 (211) #N/A
1 CENTRAL RING WALL 2nd Lift (outside) along with top slab TANK 5 23 7-Aug-21 28-Aug-21 (183) #N/A
1 TESTING & FINISHING WORKS TANK 5 40 6-Sep-21 13-Oct-21 (137) #N/A
TANK 6 93 3-Jul-21 27-Sep-21 (153) #N/A
1 MAIN STRUCTURE TANK 6 63 3-Jul-21 30-Aug-21 (181) #N/A
1 CENTRAL SLAB (6100mm Diameter) TANK 6 11 3-Jul-21 12-Jul-21 (230) #N/A
1 CENTRAL RING WALL 2nd Lift (Inside) TANK 6 23 6-Jul-21 27-Jul-21 (215) #N/A
1 CENTRAL RING WALL 2nd Lift (outside) along with top slab TANK 6 23 9-Aug-21 30-Aug-21 (181) #N/A
1 TESTING & FINISHING WORKS TANK 6 33 28-Aug-21 27-Sep-21 (153) #N/A
TANK 7 TANK 7 63 29-Jun-21 26-Aug-21 (185) #N/A
1 MAIN STRUCTURE TANK 7 26 29-Jun-21 24-Jul-21 (218) #N/A
1 CENTRAL RING WALL 2nd Lift (Inside) TANK 7 7 29-Jun-21 6-Jul-21 (236) #N/A
1 CENTRAL RING WALL 2nd Lift (outside) along with top slab TANK 7 23 3-Jul-21 24-Jul-21 (218) #N/A
1 TESTING & FINISHING WORKS TANK 7 40 21-Jul-21 26-Aug-21 (185) #N/A
TANK 8 TANK 8 119 3-Jul-21 20-Oct-21 (130) #N/A
1 MAIN STRUCTURE TANK 8 92 3-Jul-21 26-Sep-21 (154) #N/A
1 CENTRAL WALL (1st Lift) TANK 8 30 3-Jul-21 29-Jul-21 (213) #N/A
1 CENTRAL SLAB (6100mm Diameter) TANK 8 22 31-Jul-21 19-Aug-21 (192) #N/A
1 CENTRAL RING WALL 2nd Lift (Inside) TANK 8 23 19-Aug-21 9-Sep-21 (171) #N/A
1 CENTRAL RING WALL 2nd Lift (outside) along with top slab TANK 8 23 5-Sep-21 26-Sep-21 (154) #N/A
1 TESTING & FINISHING WORKS TANK 8 32 21-Sep-21 20-Oct-21 (130) #N/A
STAIRS (SST 5 & 7) STAIRS (SST 5 & 7) 34 28-Aug-21 27-Sep-21 (153) #N/A
1 FOOTING STAIRS (SST 5 & 7) 19 28-Aug-21 14-Sep-21 (166) #N/A
1 COLUMN STAIRS (SST 5 & 7) 12 9-Sep-21 21-Sep-21 (159) #N/A
1 TREAD AND RISER STAIRS (SST 5 & 7) 12 16-Sep-21 27-Sep-21 (153) #N/A
STAIRS (SST 6 & 8) STAIRS (SST 6 & 8) 34 28-Aug-21 20-Oct-21 (130) #N/A
1 FOOTING STAIRS (SST 6 & 8) 19 28-Aug-21 14-Sep-21 (166) #N/A
1 COLUMN STAIRS (SST 6 & 8) 12 9-Sep-21 21-Sep-21 (159) #N/A
1 TREAD AND RISER STAIRS (SST 6 & 8) 12 16-Sep-21 27-Sep-21 (153) #N/A
1 STEEL STRUCTURES STAIRS (SST 6 & 8) 15 22-Sep-21 6-Oct-21 (144) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR STAIRS (SST 6 & 8) 15 6-Oct-21 20-Oct-21 (130) #N/A
DISTRIBUTION FOR SECONDARY SEDIMENTATION TANKS DCDISTRIBUTION FOR SECONDARY SEDIMENTATION TAN 80 19-Jun-21 31-Aug-21 (180) #N/A
1 RINGWALL (INNER & CONNECTION WALL) DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 30 19-Jun-21 15-Jul-21 (227) #N/A
1 PLATFORM DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 25 16-Jul-21 9-Aug-21 (202) #N/A
1 STAIRS DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 34 17-Jul-21 16-Aug-21 (195) #N/A
1 FOOTING DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 19 17-Jul-21 3-Aug-21 (208) #N/A
1 COLUMN DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 12 29-Jul-21 10-Aug-21 (201) #N/A
1 TREAD AND RISER DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 12 5-Aug-21 16-Aug-21 (195) #N/A
1 TESTING & FINISHING WORKS DISTRIBUTION FOR SECONDARY SEDIMENTATION TANK 49 17-Jul-21 31-Aug-21 (180) #N/A
TANK 9 TANK 9 31 27-Jun-21 25-Jul-21 (217) #N/A
1 TESTING & FINISHING WORKS TANK 9 31 27-Jun-21 25-Jul-21 (217) #N/A
TANK 10 TANK 10 34 4-Jul-21 4-Aug-21 (207) #N/A
1 MAIN STRUCTURE TANK 10 7 4-Jul-21 10-Jul-21 #N/A
1 CENTRAL RING WALL 2nd Lift (outside) along with top slab TANK 10 7 4-Jul-21 10-Jul-21 #N/A
1 TESTING & FINISHING WORKS TANK 10 32 6-Jul-21 4-Aug-21 (207) #N/A
TANK 11 TANK 11 14 3-Jul-21 15-Jul-21 (227) #N/A
1 TESTING & FINISHING WORKS TANK 11 14 3-Jul-21 15-Jul-21 (227) #N/A
TANK 12 TANK 12 38 3-Jul-21 7-Aug-21 (204) #N/A
1 TESTING & FINISHING WORKS TANK 12 38 3-Jul-21 7-Aug-21 (204) #N/A
STAIRS (SST 9 & 11) STAIRS (SST 9 & 11) 29 23-Jun-21 20-Jul-21 (222) #N/A
1 FOOTING STAIRS (SST 9 & 11) 7 23-Jun-21 7-Jul-21 (235) #N/A
1 COLUMN STAIRS (SST 9 & 11) 12 3-Jul-21 13-Jul-21 (229) #N/A
1 TREAD AND RISER STAIRS (SST 9 & 11) 12 8-Jul-21 20-Jul-21 (222) #N/A
STAIRS (SST 10 & 12) STAIRS (SST 10 & 12) 34 4-Aug-21 5-Sep-21 (175) #N/A
1 FOOTING STAIRS (SST 10 & 12) 19 4-Aug-21 22-Aug-21 (189) #N/A
1 COLUMN STAIRS (SST 10 & 12) 12 18-Aug-21 29-Aug-21 (182) #N/A
1 TREAD AND RISER STAIRS (SST 10 & 12) 12 24-Aug-21 5-Sep-21 (175) #N/A
1 STEEL STRUCTURES STAIRS (SST 10 & 12) 15 15-Jul-21 29-Jul-21 (213) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR STAIRS (SST 10 & 12) 15 22-Aug-21 5-Sep-21 (175) #N/A
(RAS/SAS) Recirculated / Surplus activated Sludge Pumping (RAS/SAS) Recirculated / Surplus activated Sludge Pu 85 3-Jul-21 19-Sep-21 (161) #N/A
1 EXTENDED SLAB WITH BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 20 3-Jul-21 21-Jul-21 (221) #N/A
1 STAIR at EL+7.20 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 21-Jul-21 1-Aug-21 (210) #N/A
1 EL+8.58 to 10.50 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 21-Jul-21 1-Aug-21 (210) #N/A
1 COLUMN (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 21-Jul-21 3-Aug-21 (208) #N/A
1 BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 24 31-Jul-21 22-Aug-21 (189) #N/A
1 STAIR at EL+10.50 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 20 22-Aug-21 8-Sep-21 (172) #N/A

Page 45 of 76
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


1 EL+10.50 to 12.62 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 22-Aug-21 2-Sep-21 (178) #N/A
1 EL+12.62 to 14.20 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 29-Aug-21 8-Sep-21 (172) #N/A
1 MANHOLES (RAS/SAS) Recirculated / Surplus activated Sludge Pum 6 22-Aug-21 28-Aug-21 (183) #N/A
1 STEEL STRUCTURES (RAS/SAS) Recirculated / Surplus activated Sludge Pum 10 28-Aug-21 6-Sep-21 (174) #N/A
1 TESTING & FINISHING WORKS (RAS/SAS) Recirculated / Surplus activated Sludge Pum 80 3-Jul-21 14-Sep-21 (166) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR (RAS/SAS) Recirculated / Surplus activated Sludge Pum 15 6-Sep-21 19-Sep-21 (161) #N/A
(RAS/SAS) Recirculated / Surplus activated Sludge Pumping (RAS/SAS) Recirculated / Surplus activated Sludge Pu 118 3-Jul-21 20-Oct-21 (130) #N/A
1 TOP SLAB WITH BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 24 3-Jul-21 24-Jul-21 (218) #N/A
1 2ND LEVEL (RAS/SAS) Recirculated / Surplus activated Sludge Pum 80 25-Jul-21 6-Oct-21 (144) #N/A
1 SLAB (RAS/SAS) Recirculated / Surplus activated Sludge Pum 27 25-Jul-21 18-Aug-21 (193) #N/A
1 WALL (RAS/SAS) Recirculated / Surplus activated Sludge Pum 18 14-Aug-21 30-Aug-21 (181) #N/A
1 TOP SLAB (RAS/SAS) Recirculated / Surplus activated Sludge Pum 18 8-Sep-21 25-Sep-21 (155) #N/A
1 STAIR (RAS/SAS) Recirculated / Surplus activated Sludge Pum 18 20-Sep-21 6-Oct-21 (144) #N/A
1 EXTENDED WALL (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 26-Aug-21 8-Sep-21 (172) #N/A
1 EXTENDED SLAB WITH BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 5-Sep-21 18-Sep-21 (162) #N/A
1 STAIR at EL+7.20 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 20 25-Sep-21 13-Oct-21 (137) #N/A
1 EL+7.20 to 8.58 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 25-Sep-21 6-Oct-21 (144) #N/A
1 EL+8.58 to 10.50 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 2-Oct-21 13-Oct-21 (137) #N/A
1 COLUMN (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 14-Sep-21 27-Sep-21 (153) #N/A
1 BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 23-Sep-21 6-Oct-21 (144) #N/A
1 STAIR at EL+10.50 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 20 28-Sep-21 17-Oct-21 (133) #N/A
1 EL+10.50 to 12.62 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 28-Sep-21 10-Oct-21 (140) #N/A
1 EL+12.62 to 14.20 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 5-Oct-21 17-Oct-21 (133) #N/A
1 MANHOLES (RAS/SAS) Recirculated / Surplus activated Sludge Pum 2 4-Oct-21 6-Oct-21 (144) #N/A
1 STEEL STRUCTURES (RAS/SAS) Recirculated / Surplus activated Sludge Pum 10 6-Oct-21 16-Oct-21 (134) #N/A
1 TESTING & FINISHING WORKS (RAS/SAS) Recirculated / Surplus activated Sludge Pum 87 25-Jul-21 13-Oct-21 (137) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR (RAS/SAS) Recirculated / Surplus activated Sludge Pum 15 6-Oct-21 20-Oct-21 (130) #N/A
(RAS/SAS) Recirculated / Surplus activated Sludge Pumping (RAS/SAS) Recirculated / Surplus activated Sludge Pu 102 23-Jun-21 26-Sep-21 (154) #N/A
1 2ND LEVEL (RAS/SAS) Recirculated / Surplus activated Sludge Pum 62 23-Jun-21 19-Aug-21 (192) #N/A
1 SLAB (RAS/SAS) Recirculated / Surplus activated Sludge Pum 7 23-Jun-21 7-Jul-21 (235) #N/A
1 WALL (RAS/SAS) Recirculated / Surplus activated Sludge Pum 22 24-Jun-21 15-Jul-21 (227) #N/A
1 TOP SLAB (RAS/SAS) Recirculated / Surplus activated Sludge Pum 16 24-Jul-21 8-Aug-21 (203) #N/A
1 STAIR (RAS/SAS) Recirculated / Surplus activated Sludge Pum 18 3-Aug-21 19-Aug-21 (192) #N/A
1 EXTENDED WALL (RAS/SAS) Recirculated / Surplus activated Sludge Pum 16 3-Jul-21 17-Jul-21 (225) #N/A
1 EXTENDED SLAB WITH BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 13-Jul-21 26-Jul-21 (216) #N/A
1 STAIR at EL+7.20 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 20 8-Aug-21 25-Aug-21 (186) #N/A
1 EL+7.20 to 8.58 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 8-Aug-21 18-Aug-21 (193) #N/A
1 EL+8.58 to 10.50 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 15-Aug-21 25-Aug-21 (186) #N/A
1 COLUMN (RAS/SAS) Recirculated / Surplus activated Sludge Pum 14 22-Jul-21 4-Aug-21 (207) #N/A
1 BEAM (RAS/SAS) Recirculated / Surplus activated Sludge Pum 24 1-Aug-21 23-Aug-21 (188) #N/A
1 STAIR at EL+10.50 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 20 23-Aug-21 11-Sep-21 (169) #N/A
1 EL+10.50 to 12.62 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 23-Aug-21 4-Sep-21 (176) #N/A
1 EL+12.62 to 14.20 (RAS/SAS) Recirculated / Surplus activated Sludge Pum 12 30-Aug-21 11-Sep-21 (169) #N/A
1 MANHOLES (RAS/SAS) Recirculated / Surplus activated Sludge Pum 6 23-Aug-21 29-Aug-21 (182) #N/A
1 STEEL STRUCTURES (RAS/SAS) Recirculated / Surplus activated Sludge Pum 10 29-Aug-21 7-Sep-21 (173) #N/A
1 TESTING & FINISHING WORKS (RAS/SAS) Recirculated / Surplus activated Sludge Pum 87 3-Jul-21 21-Sep-21 (159) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR (RAS/SAS) Recirculated / Surplus activated Sludge Pum 15 12-Sep-21 26-Sep-21 (154) #N/A
Blower building - 065 Blower building - 065 100 24-Jun-21 25-Sep-21 (155) #N/A
1 ROOF BEAM/SLAB (EL. +21.90m) Blower building - 065 11 24-Jun-21 7-Jul-21 (235) #N/A
1 GRADE SLAB (BLOWER ROOM) Blower building - 065 25 3-Jul-21 25-Jul-21 (217) #N/A
1 HOLLOW CORE SLAB INSTALLATION Blower building - 065 23 11-Jul-21 1-Aug-21 (210) #N/A
1 PARAPET & TOP SLAB WATER PROOFING Blower building - 065 18 3-Jul-21 19-Jul-21 (223) #N/A
1 ARCHITECTURAL WORKS Blower building - 065 86 3-Jul-21 20-Sep-21 (160) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Blower building - 065 15 11-Sep-21 25-Sep-21 (155) #N/A
Plant drain Pumping station 180 Plant drain Pumping station 180 73 3-Jul-21 8-Sep-21 (172) #N/A
1 DRAIN WALL & TOP SLAB Plant drain Pumping station 180 1 3-Jul-21 3-Jul-21 (239) #N/A
1 TOP SLAB Plant drain Pumping station 180 27 1-Aug-21 25-Aug-21 (186) #N/A
1 MANHOLES/PRECAST COVER Plant drain Pumping station 180 5 25-Aug-21 30-Aug-21 (181) #N/A
1 STEEL STRUCTURES Plant drain Pumping station 180 5 25-Aug-21 31-Aug-21 (180) #N/A
1 TESTING & FINISHING WORKS (PUMP STATION) Plant drain Pumping station 180 10 25-Aug-21 4-Sep-21 (176) #N/A
1 TESTING & FINISHING WORKS (DRAIN) Plant drain Pumping station 180 47 17-Jul-21 29-Aug-21 (182) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Plant drain Pumping station 180 15 25-Aug-21 8-Sep-21 (172) #N/A
Sand Filter - 090 / Filtered Water Tank 100 Sand Filter - 090 / Filtered Water Tank 100 159 17-Jun-21 13-Nov-21 (106) #N/A
PART 1A (GRID F/G-L), (1-3) Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 (23) TOTAL 6.30 NOZZEL LEVEL SLAB GRID F/G-L/3 (PART 2) Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
PART 2 (GRID F/G, B/C), (3-8) Sand Filter - 090 / Filtered Water Tank 100 53 13-Jul-21 31-Aug-21 (180) #N/A
1 (29) SLAB AT 12.80 LEVEL (GRID 3 TO 6) Sand Filter - 090 / Filtered Water Tank 100 20 13-Jul-21 1-Aug-21 (210) #N/A
1 (30a) WALLS FROM 12.80 LEVEL TO 16.05 LEVEL (GRID 3) Sand Filter - 090 / Filtered Water Tank 100 15 27-Jul-21 9-Aug-21 (202) #N/A
1 (30b) WALLS FROM 12.80 LEVEL TO 16.05 LEVEL (GRID 4) Sand Filter - 090 / Filtered Water Tank 100 15 28-Jul-21 11-Aug-21 (200) #N/A
1 (30c) WALLS FROM 12.80 LEVEL TO 16.05 LEVEL (GRID 5) Sand Filter - 090 / Filtered Water Tank 100 15 31-Jul-21 12-Aug-21 (199) #N/A
1 (30d) WALLS FROM 12.80 LEVEL TO 16.05 LEVEL (GRID 6) Sand Filter - 090 / Filtered Water Tank 100 15 2-Aug-21 15-Aug-21 (196) #N/A
1 (31) SLAB AT 16.50 LEVEL (GRID 3 TO 6) Sand Filter - 090 / Filtered Water Tank 100 20 10-Aug-21 29-Aug-21 (182) #N/A
1 (32) TOTAL 6.30 NOZZEL LEVEL SLAB GRID F/G-B/C/3-1 Sand Filter - 090 / Filtered Water Tank 100 20 14-Aug-21 31-Aug-21 (180) #N/A
PART 2A (GRID F/G-B/C), (1-3) Sand Filter - 090 / Filtered Water Tank 100 75 27-Jun-21 5-Sep-21 (175) #N/A
1 (8) 8.1 LEVEL SLAB Sand Filter - 090 / Filtered Water Tank 100 10 3-Jul-21 11-Jul-21 (231) #N/A

Page 46 of 76
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


1 (9) WALL GRID 7 FROM 5.10 LEVEL TO 6.50 LEVEL (F/G-B/C) Sand Filter - 090 / Filtered Water Tank 100 10 3-Jul-21 11-Jul-21 (231) #N/A
1 GRID F STRUCTURE Sand Filter - 090 / Filtered Water Tank 100 7 29-Jun-21 5-Jul-21 (237) #N/A
1 (12) WALLS UPTO BOTTOM 9.45 LEVEL SLAB Sand Filter - 090 / Filtered Water Tank 100 7 29-Jun-21 5-Jul-21 (237) #N/A
1 GRID E STRUCTURE Sand Filter - 090 / Filtered Water Tank 100 7 29-Jun-21 8-Jul-21 (234) #N/A
1 (15) WALLS UPTO BOTTOM 9.45 LEVEL SLAB Sand Filter - 090 / Filtered Water Tank 100 7 29-Jun-21 8-Jul-21 (234) #N/A
1 GRID D STRUCTURE Sand Filter - 090 / Filtered Water Tank 100 7 3-Jul-21 8-Jul-21 (234) #N/A
1 (18) WALLS UPTO BOTTOM 9.45 LEVEL SLAB Sand Filter - 090 / Filtered Water Tank 100 7 3-Jul-21 8-Jul-21 (234) #N/A
1 GRID C STRUCTURE Sand Filter - 090 / Filtered Water Tank 100 13 3-Jul-21 13-Jul-21 (229) #N/A
1 (21) WALLS UPTO BOTTOM 9.45 LEVEL SLAB Sand Filter - 090 / Filtered Water Tank 100 13 3-Jul-21 13-Jul-21 (229) #N/A
1 (33) 9.45 LEVEL SLAB GRID F Sand Filter - 090 / Filtered Water Tank 100 20 3-Jul-21 20-Jul-21 (222) #N/A
1 (33) 9.45 LEVEL SLAB GRID E Sand Filter - 090 / Filtered Water Tank 100 20 18-Jul-21 4-Aug-21 (207) #N/A
1 (33) 9.45 LEVEL SLAB GRID D Sand Filter - 090 / Filtered Water Tank 100 20 2-Aug-21 19-Aug-21 (192) #N/A
1 (33) 9.45 LEVEL SLAB GRID C Sand Filter - 090 / Filtered Water Tank 100 20 17-Aug-21 5-Sep-21 (175) #N/A
1 (22a) WALLS UPTO BOTTOM 7.95 LEVEL WITH SPANNEL (F/G-B/ Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 (22b) WALLS UPTO BOTTOM 7.95 LEVEL WITH SPANNEL (F/G-B/ Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 (22c) WALLS UPTO BOTTOM 7.95 LEVEL WITH SPANNEL (F/G-B/ Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 (22d) WALLS UPTO BOTTOM 7.95 LEVEL WITH SPANNEL (F/G-B/ Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 SPANNEL (F/G-B/C, 2-3) (PART 3) Sand Filter - 090 / Filtered Water Tank 100 7 27-Jun-21 5-Jul-21 (237) #N/A
1 SPANNEL (F/G-B/C, 2-3) (PART 4) Sand Filter - 090 / Filtered Water Tank 100 7 30-Jun-21 8-Jul-21 (234) #N/A
1 (23) TOTAL 6.30 NOZZEL LEVEL SLAB GRID F/G-B/C/3-1 Sand Filter - 090 / Filtered Water Tank 100 20 17-Aug-21 4-Sep-21 (176) #N/A
PART 3 (A-B/C,3-8) Sand Filter - 090 / Filtered Water Tank 100 68 3-Jul-21 2-Sep-21 (178) #N/A
1 (23) TOTAL NOZZEL SLAB AT 6.30 LEVEL Sand Filter - 090 / Filtered Water Tank 100 15 21-Aug-21 2-Sep-21 (178) #N/A
1 (26) SLAB AT 12.80 LEVEL Sand Filter - 090 / Filtered Water Tank 100 7 3-Jul-21 8-Jul-21 (234) #N/A
1 (27) WALL FROM 12.80 LEVEL TO 16.05 Sand Filter - 090 / Filtered Water Tank 100 15 4-Jul-21 18-Jul-21 (224) #N/A
1 (28) SLAB AT 16.05 LEVEL Sand Filter - 090 / Filtered Water Tank 100 15 13-Jul-21 26-Jul-21 (216) #N/A
PART 3A (A-B/C,1-3) Sand Filter - 090 / Filtered Water Tank 100 83 20-Jun-21 5-Sep-21 (175) #N/A
1 (6A) COLUMN UNDER NOZZEL SLAB Sand Filter - 090 / Filtered Water Tank 100 7 27-Jun-21 3-Jul-21 (239) #N/A
1 (10A) SLAB AT 8.1 LEVEL Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 (11A) WALL FROM 7.1 TO 9.45 LEVEL Sand Filter - 090 / Filtered Water Tank 100 9 3-Jul-21 10-Jul-21 (232) #N/A
1 (12A) WALL FROM 8.1 TO 9.45 LEVEL Sand Filter - 090 / Filtered Water Tank 100 15 24-Jul-21 5-Aug-21 (206) #N/A
1 GRID B STRUCTURE Sand Filter - 090 / Filtered Water Tank 100 23 3-Jul-21 24-Jul-21 (218) #N/A
1 (16A) SLOPE SLAB AT 6.50 LEVEL (6.50 TO 7.20) LEVEL Sand Filter - 090 / Filtered Water Tank 100 16 3-Jul-21 17-Jul-21 (225) #N/A
1 (17A) WALLS UPTO BOTTOM 9.45 LEVEL SLAB Sand Filter - 090 / Filtered Water Tank 100 13 12-Jul-21 24-Jul-21 (218) #N/A
1 9.45 LEVEL SLAB GRID B Sand Filter - 090 / Filtered Water Tank 100 15 20-Jul-21 2-Aug-21 (209) #N/A
1 SPANNEL (A-B/C,1-8) Sand Filter - 090 / Filtered Water Tank 100 7 20-Jun-21 5-Jul-21 (237) #N/A
1 (19A) WALL FROM 5.10 TO 9.45 LEVEL Sand Filter - 090 / Filtered Water Tank 100 15 3-Jul-21 15-Jul-21 (227) #N/A
1 (20) WALL UPTO 6.50 LEVEL Sand Filter - 090 / Filtered Water Tank 100 15 12-Jul-21 25-Jul-21 (217) #N/A
1 (23) TOTAL NOZZEL SLAB AT 6.30 LEVEL Sand Filter - 090 / Filtered Water Tank 100 15 23-Aug-21 5-Sep-21 (175) #N/A
1 STAIRCASE (AFTER BACKFILLING OF LEVEL 7.20m) Sand Filter - 090 / Filtered Water Tank 100 29 20-Jul-21 15-Aug-21 (196) #N/A
1 STAIRCASE (inner) Sand Filter - 090 / Filtered Water Tank 100 14 20-Jul-21 1-Aug-21 (210) #N/A
1 STAIRCASE (North) Sand Filter - 090 / Filtered Water Tank 100 14 25-Jul-21 5-Aug-21 (206) #N/A
1 STAIRCASE (South) Sand Filter - 090 / Filtered Water Tank 100 14 29-Jul-21 10-Aug-21 (201) #N/A
1 STAIRCASE (East) Sand Filter - 090 / Filtered Water Tank 100 14 3-Aug-21 15-Aug-21 (196) #N/A
1 ARCHITECTURAL WORKS Sand Filter - 090 / Filtered Water Tank 100 86 17-Jun-21 5-Sep-21 (175) #N/A
LEAK TEST AND FINISHING Sand Filter - 090 / Filtered Water Tank 100 138 3-Jul-21 8-Nov-21 (111) #N/A
1 FINISHING AND TESTING GRID (F'~L)/ 1~2 Sand Filter - 090 / Filtered Water Tank 100 20 3-Jul-21 20-Jul-21 (222) #N/A
1 FINISHING AND TESTING GRID (F'~L)/ 7~8 Sand Filter - 090 / Filtered Water Tank 100 44 3-Jul-21 12-Aug-21 (199) #N/A
1 FINISHING AND TESTING GRID (5~4) Sand Filter - 090 / Filtered Water Tank 100 34 17-Jul-21 17-Aug-21 (194) #N/A
1 FINISHING AND TESTING GRID (F'~A)/ 1~2 Sand Filter - 090 / Filtered Water Tank 100 44 28-Jul-21 7-Sep-21 (173) #N/A
1 FINISHING AND TESTING GRID (F'~A)/ 7~8 & VALVE CHAMBESand Filter - 090 / Filtered Water Tank 100 44 9-Aug-21 19-Sep-21 (161) #N/A
1 FINISHING AND TESTING FILTER AREA GRID (F'~L)/ (6~7) Sand Filter - 090 / Filtered Water Tank 100 32 22-Aug-21 20-Sep-21 (160) #N/A
1 FINISHING AND TESTING FILTER AREA GRID (F'~L)/ (2~3) Sand Filter - 090 / Filtered Water Tank 100 32 2-Sep-21 3-Oct-21 (147) #N/A
1 FINISHING AND TESTING FILTER AREA GRID (F'~A)/ (6~7) Sand Filter - 090 / Filtered Water Tank 100 32 12-Sep-21 12-Oct-21 (138) #N/A
1 FINISHING AND TESTING FILTER AREA GRID (F'~A)/ (2~3) Sand Filter - 090 / Filtered Water Tank 100 32 21-Sep-21 21-Oct-21 (129) #N/A
1 FINISHING AND TESTING BACKWASH WATER TANK GALLERY ARE Sand Filter - 090 / Filtered Water Tank 100 41 30-Sep-21 8-Nov-21 (111) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Sand Filter - 090 / Filtered Water Tank 100 15 30-Oct-21 13-Nov-21 (106) #N/A
Chlorine Contact Tanks Reaeration and Chlorine Mixing tan Chlorine Contact Tanks Reaeration and Chlorine Mixi 48 15-Jul-21 2-Sep-21 (178) #N/A
1 ROOF WATER PROOFING AND CURB WALL Chlorine Contact Tanks Reaeration and Chlorine Mixin 36 15-Jul-21 19-Aug-21 (192) #N/A
1 STEEL STRUCTURES Chlorine Contact Tanks Reaeration and Chlorine Mixin 15 17-Jul-21 29-Jul-21 (213) #N/A
1 TESTING & FINISHING WORKS OUTLET (DRID B~D) Chlorine Contact Tanks Reaeration and Chlorine Mixin 36 19-Jun-21 21-Jul-21 (221) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Chlorine Contact Tanks Reaeration and Chlorine Mixin 15 19-Aug-21 2-Sep-21 (178) #N/A
TSE Storage and Pumping station 110 TSE Storage and Pumping station 110 173 2-Jun-21 10-Nov-21 (109) #N/A
1 CORBEL TSE Storage and Pumping station 110 45 2-Jun-21 13-Jul-21 (229) #N/A
1 Column Upto El+13.65 TSE Storage and Pumping station 110 24 13-Jul-21 5-Aug-21 (206) #N/A
1 TOP BEAM TSE Storage and Pumping station 110 24 2-Aug-21 24-Aug-21 (187) #N/A
1 TOP SLAB (HOLLOW CORE) PRECAST TSE Storage and Pumping station 110 5 17-Aug-21 22-Aug-21 (189) #N/A
1 TOP SLAB (HOLLOW CORE) INSTALLATION (GRID A~B) El. +13TSE Storage and Pumping station 110 19 24-Aug-21 11-Sep-21 (169) #N/A
1 PARAPET TSE Storage and Pumping station 110 39 11-Sep-21 17-Oct-21 (133) #N/A
1 ARCHITECTURAL WORKS TSE Storage and Pumping station 110 86 17-Aug-21 6-Nov-21 (113) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR TSE Storage and Pumping station 110 15 27-Oct-21 10-Nov-21 (109) #N/A
1 TSE VALVE CHAMBER-245 TSE Storage and Pumping station 110 130 30-Jun-21 21-Oct-21 (129) #N/A
1 RAFT TSE Storage and Pumping station 110 22 30-Jun-21 12-Jul-21 (230) #N/A
1 WALL TSE Storage and Pumping station 110 18 7-Jul-21 25-Jul-21 (217) #N/A
1 PIPE SUPPORT TSE Storage and Pumping station 110 18 17-Jul-21 3-Aug-21 (208) #N/A
1 TOP SLAB +7.40m TSE Storage and Pumping station 110 17 20-Jul-21 4-Aug-21 (207) #N/A

Page 47 of 76
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


1 WALL 2nd Lift TSE Storage and Pumping station 110 17 1-Aug-21 17-Aug-21 (194) #N/A
1 TOP SLAB +12.40m TSE Storage and Pumping station 110 18 14-Aug-21 30-Aug-21 (181) #N/A
1 STEEL STRUCTURES TSE Storage and Pumping station 110 5 28-Aug-21 1-Sep-21 (179) #N/A
1 TESTING & FINISHING WORKS TSE Storage and Pumping station 110 48 1-Sep-21 17-Oct-21 (133) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR TSE Storage and Pumping station 110 15 7-Oct-21 21-Oct-21 (129) #N/A
Chlorine Dosing Station- 103 Chlorine Dosing Station- 103 69 16-Jun-21 14-Aug-21 (197) #N/A
1 ARCHITECTURAL WORKS Chlorine Dosing Station- 103 32 19-Jun-21 18-Jul-21 (224) #N/A
1 NEUTRALIZATION SCRUBBER Chlorine Dosing Station- 103 15 16-Jun-21 8-Jul-21 (234) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Chlorine Dosing Station- 103 15 31-Jul-21 14-Aug-21 (197) #N/A
SLUDGE DEWATERING BUILDING-140 SLUDGE DEWATERING BUILDING-140 150 3-Jul-21 18-Nov-21 (101) #N/A
1 STAIR (South Side) SLUDGE DEWATERING BUILDING-140 31 12-Jul-21 9-Aug-21 (202) #N/A
1 Stair to el. +12.60m SLUDGE DEWATERING BUILDING-140 18 12-Jul-21 28-Jul-21 (214) #N/A
1 Stair to el. +15.40m SLUDGE DEWATERING BUILDING-140 18 24-Jul-21 9-Aug-21 (202) #N/A
1 STAIR (North Side) SLUDGE DEWATERING BUILDING-140 41 10-Aug-21 16-Sep-21 (164) #N/A
1 Stair to el.+8.50m SLUDGE DEWATERING BUILDING-140 18 10-Aug-21 26-Aug-21 (185) #N/A
1 Stair to el.+10.50m SLUDGE DEWATERING BUILDING-140 18 21-Aug-21 6-Sep-21 (174) #N/A
1 Stair to el.+12.60m SLUDGE DEWATERING BUILDING-140 18 31-Aug-21 16-Sep-21 (164) #N/A
1 Stair Middle (inner) SLUDGE DEWATERING BUILDING-140 18 18-Sep-21 4-Oct-21 (146) #N/A
1 Stair to el. +15.40m SLUDGE DEWATERING BUILDING-140 18 18-Sep-21 4-Oct-21 (146) #N/A
1 COLUMN ( LINTEL BEAM 3 TOLINTEL BEAM 4) SLUDGE DEWATERING BUILDING-140 16 3-Jul-21 17-Jul-21 (225) #N/A
1 LINTEL BEAM El+ 18.50m SLUDGE DEWATERING BUILDING-140 20 13-Jul-21 1-Aug-21 (210) #N/A
1 COLUMN ( LINTEL BEAM 4 TO LINTEL BEAM 5) SLUDGE DEWATERING BUILDING-140 20 27-Jul-21 15-Aug-21 (196) #N/A
1 LINTEL BEAM El+ 20.65m SLUDGE DEWATERING BUILDING-140 20 11-Aug-21 30-Aug-21 (181) #N/A
1 ROOF SLAB (HOLLOW CORE) SLUDGE DEWATERING BUILDING-140 17 25-Aug-21 9-Sep-21 (171) #N/A
1 PARAPET & TOP SLAB WATER PROOFING SLUDGE DEWATERING BUILDING-140 14 6-Sep-21 19-Sep-21 (161) #N/A
1 STAIR (Outer) SLUDGE DEWATERING BUILDING-140 43 12-Sep-21 23-Oct-21 (127) #N/A
1 Stair to el.+8.80m SLUDGE DEWATERING BUILDING-140 18 12-Sep-21 28-Sep-21 (152) #N/A
1 Stair to el.+10.70m SLUDGE DEWATERING BUILDING-140 18 23-Sep-21 10-Oct-21 (140) #N/A
1 Stair to el.+12.60m SLUDGE DEWATERING BUILDING-140 18 6-Oct-21 23-Oct-21 (127) #N/A
THICKENING TANK & SUMP PIT SLUDGE DEWATERING BUILDING-140 29 3-Jul-21 28-Jul-21 (214) #N/A
1 TOP SLAB SLUDGE DEWATERING BUILDING-140 29 3-Jul-21 28-Jul-21 (214) #N/A
1 ARCHITECTURAL WORKS SLUDGE DEWATERING BUILDING-140 81 25-Aug-21 9-Nov-21 (110) #N/A
1 STEEL STRUCTURES SLUDGE DEWATERING BUILDING-140 5 10-Nov-21 14-Nov-21 (105) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR SLUDGE DEWATERING BUILDING-140 15 6-Nov-21 18-Nov-21 (101) #N/A
FOUL AIR TREATMENT INLET-170 FOUL AIR TREATMENT INLET-170 64 3-Jul-21 31-Aug-21 (180) #N/A
1 STRUCTURAL STEEL FOUL AIR TREATMENT INLET-170 23 11-Jul-21 31-Jul-21 (211) #N/A
1 WALL ( P1)- After Tank Installation FOUL AIR TREATMENT INLET-170 14 3-Jul-21 15-Jul-21 (227) #N/A
1 TESTING & FINISHING WORKS FOUL AIR TREATMENT INLET-170 28 1-Aug-21 26-Aug-21 (185) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR FOUL AIR TREATMENT INLET-170 15 17-Aug-21 31-Aug-21 (180) #N/A
1 TRUCK OFF LOADING BAY FOUL AIR TREATMENT INLET-170 100 28-Jun-21 29-Sep-21 (151) #N/A
TRUCK OFFLOADING STATION- Truck Bay & Flow MeasuremeTRUCK OFFLOADING STATION- Truck Bay & Flow Meas 100 28-Jun-21 29-Sep-21 (151) #N/A
1 RAFT EL. +4.5m (Flow measurement system) TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 28 3-Jul-21 28-Jul-21 (214) #N/A
1 WALL EL. +4.5m (Flow measurement system) TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 26 4-Aug-21 28-Aug-21 (183) #N/A
1 TOP SLAB P-2 TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 23 28-Jun-21 19-Jul-21 (223) #N/A
1 TOP SLAB (SUMP PIT) TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 25 26-Aug-21 19-Sep-21 (161) #N/A
1 MANHOLE COVERS TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 8 16-Sep-21 25-Sep-21 (155) #N/A
1 TESTING & FINISHING WORKS TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 73 7-Jul-21 13-Sep-21 (167) #N/A
1 SUMP PIT UPTO EL. +4.5m TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 18 7-Jul-21 24-Jul-21 (218) #N/A
1 CHANNEL & SUMP PIT TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 42 5-Aug-21 13-Sep-21 (167) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR TRUCK OFFLOADING STATION- Truck Bay & Flow Meas 15 15-Sep-21 29-Sep-21 (151) #N/A
Truck Offloading shed (FOUL AIR TREATMENT) -172 Truck Offloading shed (FOUL AIR TREATMENT) -172 53 3-Jul-21 19-Aug-21 (192) #N/A
1 STRUCTURAL STEEL Truck Offloading shed (FOUL AIR TREATMENT) -172 15 10-Jul-21 22-Jul-21 (220) #N/A
1 WALL - After Tank Installation Truck Offloading shed (FOUL AIR TREATMENT) -172 28 3-Jul-21 28-Jul-21 (214) #N/A
1 TESTING & FINISHING WORKS Truck Offloading shed (FOUL AIR TREATMENT) -172 19 29-Jul-21 15-Aug-21 (196) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Truck Offloading shed (FOUL AIR TREATMENT) -172 15 7-Aug-21 19-Aug-21 (192) #N/A
Truck Offloading Operator room - 163 Truck Offloading Operator room - 163 51 3-Jul-21 18-Aug-21 (193) #N/A
1 PARAPET & TOP SLAB WATER PROOFING Truck Offloading Operator room - 163 10 3-Jul-21 11-Jul-21 (231) #N/A
1 ARCHITECTURAL WORKS Truck Offloading Operator room - 163 46 3-Jul-21 14-Aug-21 (197) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Truck Offloading Operator room - 163 15 4-Aug-21 18-Aug-21 (193) #N/A
Truck Offloading Guard House -161 Truck Offloading Guard House -161 39 3-Jul-21 7-Aug-21 (204) #N/A
1 STAIR Truck Offloading Guard House -161 30 3-Jul-21 29-Jul-21 (213) #N/A
1 ARCHITECTURAL WORKS Truck Offloading Guard House -161 34 3-Jul-21 2-Aug-21 (209) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Truck Offloading Guard House -161 15 24-Jul-21 7-Aug-21 (204) #N/A
1 BUILDINGS Truck Offloading Guard House -161 193 25-May-21 27-Oct-21 (123) #N/A
SUBSTATION 1 -Inlet chamber 220 SUBSTATION 1 -Inlet chamber 220 64 19-Jun-21 16-Aug-21 (195) #N/A
1 ARCHITECTURAL WORKS SUBSTATION 1 -Inlet chamber 220 59 19-Jun-21 11-Aug-21 (200) #N/A
1 DIESEL GENERATOR SHED SUBSTATION 1 -Inlet chamber 220 42 3-Jul-21 10-Aug-21 (201) #N/A
1 CIVIL WORKS SUBSTATION 1 -Inlet chamber 220 16 3-Jul-21 17-Jul-21 (225) #N/A
1 GRADE SLAB SUBSTATION 1 -Inlet chamber 220 13 17-Jul-21 29-Jul-21 (213) #N/A
1 PEDESTAL SUBSTATION 1 -Inlet chamber 220 13 25-Jul-21 5-Aug-21 (206) #N/A
1 STEEL STRUCTURE SUBSTATION 1 -Inlet chamber 220 5 5-Aug-21 10-Aug-21 (201) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR SUBSTATION 1 -Inlet chamber 220 15 2-Aug-21 16-Aug-21 (195) #N/A
SUBSTATION 2- Blower Room 221 SUBSTATION 2- Blower Room 221 81 16-Jun-21 30-Aug-21 (181) #N/A
1 PARAPET & TOP SLAB WATER PROOFING SUBSTATION 2- Blower Room 221 10 16-Jun-21 6-Jul-21 (236) #N/A
1 ARCHITECTURAL WORKS SUBSTATION 2- Blower Room 221 60 21-Jun-21 12-Aug-21 (199) #N/A

Page 48 of 76
2/27/2022 7:49
Completion Dates
No. STRUCTURE NAME Duration Start Finish Float Status

CONSTRUCTION 265 25-Apr-21 18-Nov-21 (101) Delayed


1 DIESEL GENERATOR SHED SUBSTATION 2- Blower Room 221 58 3-Jul-21 25-Aug-21 (186) #N/A
1 CIVIL WORKS SUBSTATION 2- Blower Room 221 16 3-Jul-21 17-Jul-21 (225) #N/A
1 GRADE SLAB SUBSTATION 2- Blower Room 221 29 17-Jul-21 12-Aug-21 (199) #N/A
1 PEDESTAL SUBSTATION 2- Blower Room 221 13 8-Aug-21 21-Aug-21 (190) #N/A
1 STEEL STRUCTURE SUBSTATION 2- Blower Room 221 5 21-Aug-21 25-Aug-21 (186) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR SUBSTATION 2- Blower Room 221 15 16-Aug-21 30-Aug-21 (181) #N/A
SUBSTATION 3 - SST Area 230 SUBSTATION 3 - SST Area 230 126 3-Jul-21 27-Oct-21 (123) #N/A
1 COLUMN SUBSTATION 3 - SST Area 230 18 3-Jul-21 19-Jul-21 (223) #N/A
1 ROOF SLAB/BEAM SUBSTATION 3 - SST Area 230 19 15-Jul-21 2-Aug-21 (209) #N/A
1 LINTEL BEAM SUBSTATION 3 - SST Area 230 14 2-Sep-21 15-Sep-21 (165) #N/A
1 PARAPET & TOP SLAB WATER PROOFING SUBSTATION 3 - SST Area 230 32 28-Jul-21 26-Aug-21 (185) #N/A
1 GRADE SLAB SUBSTATION 3 - SST Area 230 20 29-Jul-21 17-Aug-21 (194) #N/A
1 ARCHITECTURAL WORKS SUBSTATION 3 - SST Area 230 80 28-Jul-21 10-Oct-21 (140) #N/A
1 DIESEL GENERATOR SHED SUBSTATION 3 - SST Area 230 54 2-Sep-21 23-Oct-21 (127) #N/A
1 CIVIL WORKS SUBSTATION 3 - SST Area 230 16 2-Sep-21 16-Sep-21 (164) #N/A
1 GRADE SLAB SUBSTATION 3 - SST Area 230 25 16-Sep-21 10-Oct-21 (140) #N/A
1 PEDESTAL SUBSTATION 3 - SST Area 230 13 6-Oct-21 18-Oct-21 (132) #N/A
1 STEEL STRUCTURE SUBSTATION 3 - SST Area 230 5 18-Oct-21 23-Oct-21 (127) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR SUBSTATION 3 - SST Area 230 15 13-Oct-21 27-Oct-21 (123) #N/A
SUBSTATION 4 - TSE Area 222 SUBSTATION 4 - TSE Area 222 39 3-Jul-21 8-Aug-21 (203) #N/A
1 ARCHITECTURAL WORKS SUBSTATION 4 - TSE Area 222 24 3-Jul-21 25-Jul-21 (217) #N/A
1 DIESEL GENERATOR SHED SUBSTATION 4 - TSE Area 222 13 3-Jul-21 14-Jul-21 (228) #N/A
1 STEEL STRUCTURE SUBSTATION 4 - TSE Area 222 13 3-Jul-21 14-Jul-21 (228) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR SUBSTATION 4 - TSE Area 222 15 25-Jul-21 8-Aug-21 (203) #N/A
Panel Room - for MCC - ( SST Area ) 231 Panel Room - for MCC - ( SST Area ) 231 52 3-Jul-21 19-Aug-21 (192) #N/A
1 LINTEL BEAM Panel Room - for MCC - ( SST Area ) 231 17 26-Jul-21 10-Aug-21 (201) #N/A
1 PARAPET & TOP SLAB WATER PROOFING Panel Room - for MCC - ( SST Area ) 231 15 3-Jul-21 15-Jul-21 (227) #N/A
1 GRADE SLAB Panel Room - for MCC - ( SST Area ) 231 15 3-Jul-21 15-Jul-21 (227) #N/A
1 ARCHITECTURAL WORKS Panel Room - for MCC - ( SST Area ) 231 47 3-Jul-21 15-Aug-21 (196) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Panel Room - for MCC - ( SST Area ) 231 15 5-Aug-21 19-Aug-21 (192) #N/A
Control Operation Room 210 Control Operation Room 210 124 25-May-21 23-Aug-21 (188) #N/A
1 ARCHITECTURAL WORKS Control Operation Room 210 119 25-May-21 18-Aug-21 (193) #N/A
1 PUNCH LIST AND HANDING OVER TO CONTRACTOR Control Operation Room 210 15 9-Aug-21 23-Aug-21 (188) #N/A

Page 49 of 76
CONTRACTOR'S ISSUES STATUS
Orginal Forecast
SN Description Discipline Date Raise
Completion Date
105 Underground cable laying slow progress Electrical 29-Nov-21
108 APR for Electrical works for Lagoon Electrical 05-Dec-21
109 Epoxy floor coating for SEC Room Electrical 05-Dec-21
110 Street lighting installation poor progress Electrical 05-Dec-21
SSUES STATUS
Date Closed Status Remarks
Closed
Closed
Open No manpower allocated
Closed No manpower allocated
SWTP-9 OPEN FRONTS
Orginal Forecast
SN Description Discipline Date Raise
Completion Date
Excavation Up To Tie In And Pipe Laying Zone
5 Civil 19-Aug-21
4
17 Eye wash station Civil 19-Aug-21
18 Exhaust Vents Mechanical 19-Aug-21
19 Emergency Shower CDS Mechanical 19-Aug-21
20 Cage ladders Civil 19-Aug-21
21 Fire fighting lines 19-Aug-21
22 OCU-1 Slow progress Mechanical 19-Aug-21
26 Tile works COR Civil 21-Aug-21
27 Ceiling COR Civil 21-Aug-21
29 Guard House Tile Works Civil 21-Aug-21
30 TOL Control Room Tiles Civil 21-Aug-21
31 TOL Control Room Electrical Works E&I 21-Aug-21
35 Pipe Support at Blower Room Mechanical 22-Aug-21
36 Potable Water Tie-in Excavation Piping 23-Aug-21 29-Aug-21
39 Blower Building Mechanical 29-Aug-21
41 Silo Installation Mechanical 29-Aug-21
44 Site Development plan (Hardscape and Civil 31-Aug-21
Landscape) COR Area
Precast Pipe Support for Splitter to OCU
51 Civil 08-Sep-21
Suction Line
52 Existing Pump Station to Splitter Box Works Piping 08-Sep-21
53 RSF Lighting and power E&I 08-Sep-21
56 Raised floor system Mockup Civil 08-Sep-21
63 Scum Manhole installation Zone 1 Civil 18-Sep-21
70 Pneumatic Testing for Ast-1 Diffusers Mechanical 19-Sep-21
71 Sample Penstock Mechanical 19-Sep-21
80 OCU-1 Slow progress Mechanical 25-Sep-21
85 Penstock Functionality Mechanical 26-Sep-21
Sludge Dewatering Mechanical Equipment
87 Mechanical 26-Sep-21
installation
90 Underground pipe for OCU Mechanical 27-Sep-21
Pre-cast hollow core slabs for sludge building
93 Civil 27-Sep-21
building
95 Fire hydrant mock-up Mechanical 27-Sep-21
96 Aeration Pipe installation at AST-2 South Side Mechanical 29-Sep-21
101 TSE Pipeline above ground start date Piping 02-Oct-21
104 TOL Control room to Guard House E&I 03-Oct-21
109 Grit and Grease blower pipe fabrication Civil 03-Oct-21
115 SS4 to RSF LV E&I 07-Oct-21
116 SS4 to CCT LV E&I 07-Oct-21
120 AST-3 Will be finish This month Mechanical 11-Oct-21
121 HDPE liner installation for Aeration 2 Civil 11-Oct-21
122 Sanitary drain from control building to PDPS Piping 11-Oct-21
136 Dewatering building SS piping works Mechanical 17-Oct-21
Distribution chamber for Activated tanks
141 20-Nov-21
Distribution Chamber epoxy coating
PDPS Mechanical, Electrical and Coating
142 20-Nov-21
resumption
143 Ceiling finish for Blower building 20-Nov-21
Grit and Grease RCC to be completed by 5th
144 20-Nov-21
December
145 Skylar Arabia General Contracting Est 20-Nov-21

146 Sludge Dewatering North and East Side to be 20-Nov-21


expedited to open electrical and plumbing

147 Zone 2 completion 20-Nov-21 24-Dec-21


148 Blower Electrical 13-Dec-21
149 SS3 Elecatrical 13-Dec-21
150 TSE Electrical 13-Dec-21
151 SDB Electrical 13-Dec-21
Data, Telephone, CCTV &Fire Alarm For
152 Substation -1 Inlet Chamber  13-Dec-21

Data, Telephone, CCTV &Fire Alarm For


153 Substation -2  13-Dec-21

Data, Telephone, CCTV &Fire Alarm For


154 13-Dec-21
Substation -3 
Data, Telephone, CCTV &Fire Alarm For
155 Substation 4 (TSE Area)  13-Dec-21

Data, Telephone, CCTV &Fire Alarm For


156 Control Operation Room  13-Dec-21

Data, Telephone, CCTV &Fire Alarm For Panel


157 room for MCC (SST area)  13-Dec-21
158 TOL Bay Pavement 13-Dec-21
PEN FRONTS
Date Closed Status Remarks

Open Access problem


Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open

Open
Open
Open
Open
Open
Open Next Week
Open Next week
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open
Open To be verified
Open
Open
Open

Open
Open
Open
Open

Open

Open
Open
Open
Open
Open
Open

Open

Open

Open

Open

Open
Open
SWTP-9 PROJECT ACTION ISSUE TRACKER
As of: 27-Feb-22
SN Description No. Type Discipline Latest Date Action date Date Closed Status Remarks (Marafiq) Wabag Response
Raised
1 SST Zone 1 Backfilling 1 Action Civil 27-Jul-21 29-Jul-21 31-Jul-21 Closed
2 Distribution Box not on site 1 Action E&I 27-Jul-21 21-Aug-21 3-Oct-21 Closed 3rd week of august will be arrived
3 Schedule not Distributed 1 Action All 27-Jul-21 28-Jul-21 Closed Distributed
4 No manpower allocated at Splitter Box 1 Action Civil 27-Jul-21 28-Jul-21 31-Jul-21 Closed Staging Started as forecast TBV.
5 Slow progress on DC-1 Readiness for Water Filling 1 Action Civil 26-Jul-21 31-Jul-21 31-Jul-21 Closed Today it will be done
6 Light Fixtures Installation SS4 1 Action E&I 26-Jul-21 1-Aug-21 31-Jul-21 Closed On-going scaffolding
7 Transformer Installation 1 Action E&I 26-Jul-21 27-Jul-21 28-Jul-21 Closed Completed
8 ES Tanks No manpower allocated for coating 1 Action Civil 27-Jul-21 Not Possible Closed confined space
Allow the contractor to backfill but not
9 ES-8 Leak Test 1 Action Civil 27-Jul-21 4-Aug-21 Closed started. With tank issue
10 Pickling and Passivation 1 Action Mechanical 27-Jul-21 29-Jul-21 31-Jul-21 Closed Contractor to submit the MOM
11 RSF Partial Tank Leak Test 1 Action Civil 27-Jul-21 4-Aug-21 31-Jul-21 Closed Leak Test Readiness work on-going
12 GFC drawing are attached in RFI. 1 Action E&I 27-Jul-21 Completed 28-Jul-21 Closed For Monitoring
13 Bridge for 12 1 Action Mechanical 29-Jul-21 31-Jul-21 31-Jul-21 Closed Central Bearing installed
14 SST-9 Bearing to be installed today 1 Action Mechanical 29-Jul-21 29-Jul-21 1-Aug-21 Closed
15 List Instruments for every Structure 1 Action E&I 27-Jul-21 28-Jul-21 31-Jul-21 Closed Received
Contractor promise to provide this
16 Lamination Kit 1 Issue Piping 31-Jul-21 7-Aug-21 Closed week. Partial only came
17 SST 9,11,12 Bridges 1 Action Mechanical Closed Start Partial at SST12
18 SST Zone 1 External Coating Resumption 1 Action Civil 27-Jul-21 31-Jul-21 31-Jul-21 Closed
19 RSF Backwash Water Filling 1 Action Civil 25-Jul-21 31-Jul-21 31-Jul-21 Closed
20 DC-1 Water filling 1 Action Civil 31-Jul-21 31-Jul-21 31-Jul-21 Closed
21 Roof Water proofing at COR 1 Action Civil 31-Jul-21 31-Jul-21 31-Jul-21 Closed
22 Screed at RSF Re-Aaeration tank connection 1 Action Civil 31-Jul-21 31-Jul-21 31-Jul-21 Closed
23 TOL COR Painting 1 Issue Civil 31-Jul-21 31-Jul-21 31-Jul-21 Closed To start today
24 RSF Blower Room Crane 1 Action Mechanical 31-Jul-21 31-Jul-21 31-Jul-21 Closed Installation start today
25 Suction Pipe from OCU to Grit and Grease 1 Action PDPS 31-Jul-21 31-Jul-21 31-Jul-21 Closed Partial installation to start today
26 Inlet Chamber slab Grid A to B @ el. +10.90 1 Issue Civil 17-Jul-21 31-Jul-21 31-Jul-21 Closed Delayed Expedite add manpower
27 Inlet Chamber slab Grid S to U @ el. +10.90 1 Issue Civil 17-Jul-21 6-Aug-21 Closed Delayed Expedite add manpower
28 Grit and Grease wall and top slab 1 Action Civil 31-Jul-21 31-Jul-21 31-Jul-21 Closed Expedite add manpower
29 TSE Valve Chamber Zone-4 1 Action Civil 31-Jul-21 31-Jul-21 31-Jul-21 Closed Target date
30 Removal of scaffolding RSF Blower 1 Action RSF 31-Jul-21 31-Jul-21 31-Jul-21 Closed No need to remove
31 Washout Chamber TSE Discharge header 1 Action Civil 31-Jul-21 31-Jul-21 4-Aug-21 Closed Excavation completed
32 HVAC Foundation for all Substation 1 Issue Civil 31-Jul-21 14-Aug-21 Closed This
33 Blower Building Grade Slab 1 Action Civil 31-Jul-21 1-Aug-21 Closed
34 (DN 500) MH 26 to MH 27 1 Action Piping 31-Jul-21 31-Jul-21 3-Aug-21 Closed Pouring Today
35 (DN 700) MH 19 to MH 20 1 Action Piping 31-Jul-21 31-Jul-21 3-Aug-21 Closed Pouring Today
36 Catch Basin 1 Issue Civil/Piping 31-Jul-21 5-Aug-21 Closed Work started Plan need to submit
37 Operation and Maintenance Manual 1 Issue Mechanical 1-Aug-21 Closed Ongoing
38 Bridge for 12 1 Action Mechanical 1-Aug-21 4-Aug-21 4-Aug-21 Closed Central Bearing installed
39 SST 9 Central Bearing 1 Action Mechanical Closed
40 Manpower 1 Issue All 1-Aug-21 2-Aug-21 Closed Main Issue
41 OCU-1 Pipe InstallationOCU-1 Pipe Shifting 1 Issue Mechanical 1-Aug-21 3-Aug-21 4-Aug-21 Closed Start installation
42 SS2 Electrical Accessories 1 Action E&I 1-Aug-21 4-Aug-21 10-Aug-21 Closed Work starts
43 Nesma & SAS Meeting 1 Issue E&I 1-Aug-21 5-Aug-21 10-Aug-21 Closed Today
44 Quantity for cable 1 Issue E&I 1-Aug-21 9-Aug-21 10-Aug-21 Closed
45 Key Personnel List and Contact Details 1 Action 1-Aug-21 2-Aug-21 10-Aug-21 Closed
46 Roll up doors not yet installed 1 Action Civil 3-Aug-21 10-Aug-21 31-Aug-21 Closed Stagging works started
47 Walk Through (Remaining Activities) 1 Action All 3-Aug-21 22-Aug-21 Closed Balance work need to submit
48 Duct bank installation 1 Issue Civil 3-Aug-21 5-Aug-21 Closed Starts today
49 Pickling and passivation shop visit 1 Action Mechanical 3-Aug-21 8-Aug-21 Closed Anytime
50 Fire fighting works 1 Action Mechanical 3-Aug-21 14-Aug-21 Closed NOVAC
51 Lagoon schedule 1 Action E&I 3-Aug-21 3-Aug-21 3-Aug-21 Closed
52 DC-1 Leak test 1 Action Civil 3-Aug-21 3-Aug-21 Closed QA/QC
53 Relay setting to discuss with SEC 1 Action E&I 4-Aug-21 10-Aug-21 15-Aug-21 Closed Today submission
54 Testing of Electrical Equipment to scheduled as soo 1 Action E&I 4-Aug-21 5-Aug-21 15-Aug-21 Closed Not possible this time
55 Ductbank at the AST1 to MCC Room must be started 1 Action E&I 4-Aug-21 16-Aug-21 1-Sep-21 Closed Change in plan
56 Ductbank at the AST3 to SS-03 Room must be starte 1 Action E&I 10-Aug-21 10-Aug-21 1-Sep-21 Closed
57 Aeration Pipe support must be started AST-1 and 2 1 Action Mechanical 4-Aug-21 12-Aug-21 1-Sep-21 Closed Takannah will start today
58 RSF Filter Cells Area Partial Leak Test 1 Action Civil 4-Aug-21 15-Aug-21 1-Sep-21 Closed On-going / Delayed
59 Water Heater MAR 1 Issue Civil 4-Aug-21 1-Sep-21 Closed Rejected
60 Cholirination Scrubber duct piping 1 Action Mechanical 4-Aug-21 18-Aug-21 1-Sep-21 Closed On-going / Delayed
61 Kerb stone details 1 Action Civil 4-Aug-21 4-Aug-21 1-Sep-21 Closed Rejected
62 Lifting plan fro duct banks weight to be verified 1 Action Hse 4-Aug-21 1-Sep-21 Closed
63 Installation for earth pit works Buildings 1 Issue Civil/Elec 4-Aug-21 5-Aug-21 1-Sep-21 Closed
64 IFC Drawings Issue 1 Issue E&I 4-Aug-21 5-Aug-21 1-Sep-21 Closed
65 CCT Upstand Slow progress screed must be started 1 Issue Civil 5-Aug-21 19-Aug-21 28-Aug-21 Closed
66 Water Heater to submit new Material 1 Action Civil 5-Aug-21 28-Aug-21 Closed
67 Electrical Lighting poles 1 Action E&I 5-Aug-21 7-Aug-21 28-Aug-21 Closed
68 RSF Blower Room Electrical Works 1 Action E&I 5-Aug-21 28-Aug-21 Closed Not possible this time
69 SST-7 Water Filling Readiness 1 Issue Civil 5-Aug-21 7-Aug-21 28-Aug-21 Closed
70 Structure Assessment 1 Action General 5-Aug-21 9-Aug-21 Closed Schedule
71 Zone 4 Pipe 1 Action Piping 5-Aug-21 Postponed After Thrust Blcok
72 Zone-5 Tie End 1 Action Piping 5-Aug-21 31-Aug-21 Postponed Target End of August
73 SST-9 Bridge 1 Action Mechanical 5-Aug-21 5-Aug-21 Closed
74 Instrumentation Progress 1 Action E&I 5-Aug-21 8-Aug-21 Closed
75 Lagoon NTP from Masa to Start Electrical Works 1 Action E&I 5-Aug-21 9-Aug-21 Closed Follow up
76 Scum Pump StationProgress 1 Action Mechanical 5-Aug-21 8-Aug-21 Closed
77 Pump Drain Pump Station Progress Coating 1 Action Civil 5-Aug-21 10-Sep-21 Closed
78 FOC Route proposal 1 Action E&I 5-Aug-21 12-Aug-21 28-Aug-21 Closed Proposal must be submitted
79 Catch basin slow progress 3/62 CB this week 1 Action Civil/Piping 7-Aug-21 12-Aug-21 28-Aug-21 Closed Started at AST-3area
80 SST-11 Bridge 1 Action Mechanical 8-Aug-21 12-Aug-21 28-Aug-21 Closed Bridge Shifted Shifted
81 Gallery Plug installation North east side 4 filters 1 Action Piping 8-Aug-21 12-Aug-21 28-Aug-21 Closed Needs to verify
82 DC-1 Refilling 1 Action Civil 8-Aug-21 28-Aug-21 Closed
83 Steel covers for all opening (TOL, SPS, ES) 1 Action Civil 8-Aug-21 28-Aug-21 Closed
84 Panel Drawing Instrumentation 1 Action E&I 8-Aug-21 28-Aug-21 Closed
85 Spacing for power and communication cable standar 1 Action E&I 8-Aug-21 28-Aug-21 Closed
86 Cable Tray work 1 Action Civil 8-Aug-21 12-Aug-21 20-Aug-21 Closed Visited site no manpower allocated
87 Cable Glanding & Termination Work 1 Action E&I 8-Aug-21 16-Aug-21 20-Aug-21 Closed 1 more week
88 Light Fixtures Installation(Buiding Outside) and Mater 1 Action E&I 8-Aug-21 20-Aug-21 Closed Material Arrived on site
89 Cable tray and accessories 1 Action E&I 9-Aug-21 10-Aug-21 20-Aug-21 Closed
90 Pull pit installaton 1 Action E&I 9-Aug-21 20-Aug-21 Closed Ongoing
91 Pole Foundation Works 1 Action E&I 9-Aug-21 20-Aug-21 Closed Ongoing
92 Push Button Control Station installation 1 Action E&I 9-Aug-21 Pending Next week
93 Fire Water Activity RSF and CCT Area 1 Action Mechanical 9-Aug-21 20-Aug-21 Closed Excavation start
94 LV Delivery 1 Action 9-Aug-21 10-Aug-21 20-Aug-21 Closed Complete delivery
95 Handrail 1 Action Civil 9-Aug-21 15-Aug-21 Posponed No manpower allocated
96 Mechanical Equipment List and Status 1 Action Mechanical 9-Aug-21 10-Aug-21 20-Aug-21 Closed Pending
97 Crane Installation for RSF 1 9-Aug-21 15-Aug-21 20-Aug-21 Closed 15-10-17 Aug
98 SEC Shutdown Activities Start date 1 Action E&I 11-Aug-21 15-Aug-21 20-Aug-21 Closed Confirmed
99 Chlorination Ducting 1 Action Mechanical 11-Aug-21 12-Aug-21 20-Aug-21 Closed
100 Checklist for Shutdown 1 Action 12-Aug-21 12-Aug-21 20-Aug-21 Closed
101 CCT Screed 1 Action Civil 18-Aug-21 20-Aug-21 Closed No manpower Allocated
102 Sika 1 Issue QA/QC 18-Aug-21 23-Aug-21 25-Aug-21 Closed Mock-up
103 SS4 HVAC Foundation Painting 1 Action Civil 18-Aug-21 20-Aug-21 25-Aug-21 Closed No manpower allocated
104 Manhole near CDS 1 Action Civil 18-Aug-21 25-Aug-21 Closed No manpower allocated
105 Lagoon Schedule 1 Action E&I 18-Aug-21 17-Aug-21 25-Aug-21 Closed
106 Slow progress for Washout chamber neAR sst-5 1 Action Piping 18-Aug-21 18-Aug-21 25-Aug-21 Closed No manpower allocated
107 SST-10 Bridge 1 Action Mechanical 18-Aug-21 18-Aug-21 25-Aug-21 Closed
108 SS4 HVAC Installation Package Unit 1 Action Mechanical 18-Aug-21 22-Aug-21 25-Aug-21 Closed
109 Progress Map Action Genral 18-Aug-21 18-Aug-21 25-Aug-21 Closed
110 Pipe Support Submittal- Post anchoring-Splitter Box 1 Action Mechanical 18-Aug-21 25-Aug-21 25-Aug-21 Closed Drawing Update
111 Test Manifold needs to be on site 2 Nos.-Standby 1 Action Piping 18-Aug-21 25-Aug-21 25-Aug-21 Closed No manpower allocated
112 Tile works 1 Action Civil 19-Aug-21 25-Aug-21 10-Sep-21 Closed Drawing Update
113 Ceiling 1 Action Civil 19-Aug-21 25-Aug-21 10-Sep-21 Closed Drawing Update
114 Roof Water Proofing SS-1 and SS-2 1 Action Civil 19-Aug-21 25-Aug-21 5-Sep-21 Closed No manpower allocated
115 Lighting Fixtures SS-1 and SS-2 1 Action E&I 19-Aug-21 25-Aug-21 5-Sep-21 Closed
116 Street Lighting Foundation RSF 1 Action E&I 19-Aug-21 25-Aug-21 5-Sep-21 Closed Verify
117 CDS Roll up doors 1 Action Civil 19-Aug-21 25-Aug-21 5-Sep-21 Closed No manpower allocated
118 Slow Progress for masonry works at blower building 1 Action Civil 19-Aug-21 25-Aug-21 5-Sep-21 Closed
119 FAT Schedule 1 Action E&I 19-Aug-21 25-Aug-21 5-Sep-21 Closed Next Week
120 Walk Through (Remaining Activities) Meeting 3:00P 1 Action General 24-Aug-21 25-Aug-21 5-Sep-21 Closed List
121 Tile Pattern Lay-out 1 Action Civil 24-Aug-21 25-Aug-21 8-Sep-21 Closed Drawing Update
122 Raised floor system 1 Action Civil 24-Aug-21 25-Aug-21 8-Sep-21 Closed Drawing Update
123 Reflected Ceiling Drawing 1 Action Civil 24-Aug-21 25-Aug-21 8-Sep-21 Closed Drawing Update
124 Granite 1 Action Civil 25-Aug-21 21-Sep-21 8-Sep-21 Closed Communicate for material and Drawing To submit Mar and drawings
125 On-site FAT Readiness 1 Action E&I 26-Aug-21 25-Aug-21 8-Sep-21 Closed
126 Haunch in the SSt Wall 1 Action Civil 27-Aug-21 25-Aug-21 8-Sep-21 Closed Communicate Engineering/CM
127 SST-5 Water Filling 1 Action Civil 28-Aug-21 25-Aug-21 8-Sep-21 Closed
Type of paint surface aerator platform and
128 application procedure. 1 Action Mechanical 25-Aug-21 1-Sep-21 8-Sep-21 Closed
129 Meeting with Electrical and Civil Team for Lagoon 1 Action Civil 26-Aug-21 1-Sep-21 8-Sep-21 Closed
130 Lagoon Panel Foundation drawing 1 Action Civil 26-Aug-21 1-Sep-21 8-Sep-21 Closed
131 Penstock Wall thickening 1 Action Civil 26-Aug-21 2-Sep-21 8-Sep-21 Closed
132 FOC Route Site Visit 1 Action E&I 30-Aug-21 4-Sep-21 8-Sep-21 Closed Possible 3 locations
133 Perforated Aluminum Screen roof 1 Action Civl 31-Aug-21 4-Sep-21 4-Sep-21 Closed
134 Wash out chamber pipe testing 1 Action Piping 31-Aug-21 4-Sep-21 4-Sep-21 Closed
135 Walkthrough meeting 3:00PM 1 Action General 31-Aug-21 4-Sep-21 Cancelled
136 Backfilling at Inlet Flow Measurement 1 Action Civil 1-Sep-21 4-Sep-21 4-Sep-21 Closed
137 Duct Bank 11 and 12 1 Action Civil 1-Sep-21 4-Sep-21 4-Sep-21 Closed 12 Started
138 HVAC Foundation Substation 1 1 Action Civil 1-Sep-21 4-Sep-21 4-Sep-21 Closed
139 Fire fighting works NOVAC drawings 1 Action Civil 1-Sep-21 4-Sep-21 10-Sep-21 Closed
140 FOC Submittal Inside Plant 1 Action E&I 1-Sep-21 21-Sep-21 21-Sep-21 Closed Masa permit to meet today
141 PQR for road works 1 Action Civil 1-Sep-21 4-Sep-21 15-Sep-21 Closed
142 Silo Method Statement 1 Action 1-Sep-21 4-Sep-21 15-Sep-21 Closed
143 GRE Inspetion Third report 250 mm missing 1 Action Piping 1-Sep-21 4-Sep-21 15-Sep-21 Closed
144 SAS pipe Issue Backfilling 1 Action Piping 2-Sep-21 15-Sep-21 Closed
145 Conclude Expansion joint Mock-up (sikadur) 1 Action Civil 2-Sep-21 15-Sep-21 Closed Needs to close
146 Penstock Leak Root Cause Report 1 Action Mechanical 2-Sep-21 15-Sep-21 15-Sep-21 Closed Needs 1 sample area
147 Piping for CDS 1 Action 2-Sep-21 4-Sep-21 15-Sep-21 Closed
148 Coating for RSF 1 Action Civil 2-Sep-21 5-Oct-21 15-Sep-21 Closed Mock-up
149 Stair footing rebar needs to be cut and rectified 1 Action Civil 4-Sep-21 20-Sep-21 Closed To be verified
150 RAS 1 columnRFI must be sepatae from the beam. 1 Action Civil 4-Sep-21 20-Sep-21 Closed Under reiew
151 MOM 48 hours after the meeting. 1 Action General 4-Sep-21 20-Sep-21 Closed Not receive
152 Recovery Schedule 1 Action General 4-Sep-21 5-Sep-21 20-Sep-21 Closed
153 Scaffolding removal for SS3 1 Action Civil 4-Sep-21 5-Sep-21 20-Sep-21 Closed
154 HVAC Package Unit Installation SS 1 1 Action Mechanical 4-Sep-21 13-Oct-21 16-Sep-21 Closed
155 Remaining Works 1 Action General 4-Sep-21 Closed No action done
156 Lamination for Golden Joints 1 Action Piping 4-Sep-21 8-Sep-21 20-Sep-21 Closed
157 Excavation Start date Zone 4 and 5 Piping 1 Action Piping 4-Sep-21 12-Sep-21 Closed Zone 5 Started
158 To power up the SS4 Generator to CDS Panels 1 Action E&I 6-Sep-21 12-Sep-21 12-Sep-21 Closed Inspection must be done first/Checklist
159 Panel installation at TOL Control Building 1 Action E&I 6-Sep-21 12-Sep-21 Closed Communicated
160 Floor and trech epoxy painting Sludge Dewatering 1 Action Civil 6-Sep-21 8-Sep-21 12-Sep-21 Closed
161 Permits to be Submitted List 1 Action General 6-Sep-21 12-Sep-21 Closed Communicated
162 Novac meeting 1 Action Mechanical 6-Sep-21 8-Sep-21 12-Sep-21 Closed Communicated
163 Permit for Civil Foundation at Lagoon (Work permit) 1 Action Civil 6-Sep-21 12-Sep-21 Closed Communicated
164 Water Proofing Aluminum termination 1 Action Civil 6-Sep-21 29-Sep-21 12-Sep-21 Closed For COR/Mock-up MAR Submitted
165 Washout Chamber resumption of works at TSE 1 Action Civil 6-Sep-21 8-Sep-21 5-Oct-21 Closed Communicated
166 Completion of SS-1 and SS-2 Concrete Pads 1 Action Civil 6-Sep-21 29-Sep-21 5-Oct-21 Closed
167 Cable Status Log 1 Action E&I 6-Sep-21 8-Sep-21 12-Sep-21 Closed Communicated
168 RAS-1 MS, RA, Scaffolding certificate 1 Action Civil 7-Sep-21 8-Sep-21 12-Sep-21 Closed Communicated
169 Novac to start 1 Action Mechanical 8-Sep-21 9-Oct-21 12-Sep-21 Closed
170 Sludge Dewatering Epoxy Floor painting 1 Action Civil 8-Sep-21 12-Sep-21 Closed Communicated
171 TOL Conduiting 1 Action E&I 8-Sep-21 12-Sep-21 Closed Communicated
172 RSF Lighting and power Works Blower 1 Action E&I 8-Sep-21 29-Sep-21 12-Sep-21 Closed Next week/Lack of manpower
173 CDS Piping Chlorinator piping UPVC 1 Action Civil 9-Sep-21 30-Sep-21 12-Sep-21 Closed
174 Separation cable in CDS 1 Action Civil 9-Sep-21 25-Sep-21 Closed Communicated
175 Survey for all underground Cable after laying 1 Action Civil 9-Sep-21 25-Sep-21 Closed
176 Panel Preservation is must for PLC 1 Action Civil 9-Sep-21 25-Sep-21 Closed Communicated
Expedite, this will delay installation of
177 Manholes for between SS-1 and Grit and Grease 1 Action Civil 9-Sep-21 25-Sep-21 Closed
Generator
178 Fire fighting pipe delaying the CCT Screed 1 Action Piping 11-Sep-21 25-Sep-21 Closed To allocate area for the pump
179 Date of finish at Zone 5 NSH 1 Action Piping 11-Sep-21 30-Oct-21 Closed
Support for Aeration pipe cannot drill due to steel
180 bars 1 Action Piping 11-Sep-21 25-Sep-21 Closed

To expedite Blower building Plastering ang painting


181 works west side area 1 Action Civil 11-Sep-21 25-Sep-21 Closed
182 TOL Control Room Backfilling 1 Action Civil 12-Sep-21 15-Sep-21 Closed Affecting Electrical works
183 Sludge Dewatering Proposed Opening 1 Action Civil 12-Sep-21 15-Sep-21 Closed
184 Fire Fighting line at Ast will start 1 Action Civil 13-Sep-21 15-Sep-21 Closed
185 Quantity Plan for E&I 1 Action E&I 14-Sep-21 15-Sep-21 Closed
186 Lagoon Foundation 1 Action Civil 14-Sep-21 25-Sep-21 Closed
187 HDPE Pipe Certification SDR 9 Certificatification 1 Action Piping 14-Sep-21 25-Sep-21 Closed MIR should submitted
188 Tie end List and Lay-out plan 1 Action Civil 16-Sep-21 18-Sep-21 Closed
189 Plumbing Presentation for all lines 1 Action Piping 11-Sep-21 12-Sep-21 Closed
35 Manpower to be added for Epoxy coating
190 surface preparation 1 Action Civil 18-Sep-21 28-Sep-21 Closed 17 added
191 Fine Screen Slab pouring 1 Action Civil 18-Sep-21 5-Oct-21 Closed
192 SS3 grade Slab 1 Action Civil 18-Sep-21 28-Sep-21 Closed
193 Golden lamination 1 Action Piping 18-Sep-21 28-Sep-21 Closed
194 GRE Pipes MS 1 Action Piping 18-Sep-21 28-Sep-21 Closed
195 SST Status to be submitted 1 Action Mechanical 19-Sep-21 21-Sep-21 28-Sep-21 Closed
External Piping connection SST to Scump pump
196 1 Action Mechanical 19-Sep-21 10-Oct-21 Postponed
(HDPE)
197 No significant progress at AST-2 1 Action E&I 19-Sep-21 28-Sep-21 Closed Lack of Manpower
Crane removal at splitter box holding MV cable
198 1 Action E&I 19-Sep-21 22-Sep-21 28-Sep-21 Closed
works

199 Panel Preservation in SS4 lots of dust reoccurence 1 Action E&I 19-Sep-21 28-Sep-21 Closed For NCR if not taken action this week
200 Cable laying at Zone 3 1 Action E&I 19-Sep-21 28-Sep-21 Closed
All structures to be 6 meters away from the fence
201 as MASA requirement 1 Action HSE 20-Sep-21 Moved
202 All Tie End connections Schedule 1 Action Civil 20-Sep-21 20-Sep-21 28-Sep-21 Closed
203 MV Cable SEC to 1 2 3 and 4 1 Action E&I 20-Sep-21 27-Sep-21 28-Sep-21 Closed
204 Fire Alarm detectors 1 Action E&I 20-Sep-21 28-Sep-21 Closed
205 Sludge Tank Concrete Cover 1 Action Civil 25-Sep-21 13-Nov-21 Closed Next week
206 Pre-commissioning test pack 1 Action QA/QC 20-Sep-21 22-Sep-21 28-Sep-21 Closed
207 Substation 3 to start grade slab 1 Action Civil 21-Sep-21 25-Sep-21 28-Sep-21 Closed
208 CDS Channel unattended for a long time 1 Action Civil 21-Sep-21 25-Sep-21 5-Sep-21 Closed To be verified
Coarse Screen at truck TOL Area surface
209 1 Action 21-Sep-21 1-Oct-21 Closed To be verified
preparation Civil
210 AST-3 Handrail Completion 1 Action Civil 21-Sep-21 5-Oct-21 1-Oct-21 Closed
Zone 4 Leak test Readiness for TSE Valve chamber
211 1 Action 21-Sep-21 28-Oct-21 Postponed To complete this week tie filling
and overflow Civil
212 Duct bank concrete at SS-1 1 Action Civil 22-Sep-21 1-Oct-21 Closed
213 Scum line connecting SPS HDPE 1 Action Civil 22-Sep-21 1-Oct-21 Postponed
214 List /Index for all that needs test packs 1 Action QA/QC 22-Sep-21 1-Oct-21 Closed
215 Schedule for SS1 -S4 and Cds (Remaining Works) 1 Action General 25-Sep-21 1-Oct-21 Closed Today
216 Manpower head count for NSH 1 Action HSE 25-Sep-21 26-Sep-21 1-Oct-21 Closed Saturday
217 Sikadur application to start covering 1 Action Civil 4-Oct-21 22-Nov-21 Closed Contractor to proceed
218 Steel fixers to expedite grit and Grease Tank 1 Action Civil 25-Sep-21 1-Oct-21 Closed
219 Ballast delivery for Ast-3 26 pcs 1 Action Civil 25-Sep-21 14-Oct-21 19-Oct-21 Closed Complete delivery
220 Re-bar for DC-2 Walkway 1 Action Civil 25-Sep-21 10-Oct-21 19-Oct-21 Closed
221 RAS-1 Formworks 1 Action Civil 25-Sep-21 5-Oct-21 Closed
222 Fusrock will come for the ES-8 issue 1 Action Civil 25-Sep-21 28-Sep-21 Closed
223 Schedule for Zone 5 tie-in connection 1 Action Piping 25-Sep-21 26-Sep-21 28-Sep-21 Closed
224 Safety officer to be mobilized 1 Action Piping 25-Sep-21 5-Oct-21 Closed
225 Scaffolding installation west Ast-2 1 Action Mechanical 26-Sep-21 5-Oct-21 Closed This week will start
226 AST-1 pipe suppport 1 Action Mechanical 26-Sep-21 9-Oct-21 5-Oct-21 Closed To start
227 SST-7 bridge will be started 1 Action Mechanical 26-Sep-21 16-Oct-21 Closed Lifting plan to be submitted today To be verified
228 Dedicated team to work on the OCU-2 1 Action Mechanical 26-Sep-21 5-Oct-21 Closed
229 OCU piping to start 1 Action Mechanical 26-Sep-21 27-Sep-21 5-Oct-21 Closed
230 Completion of Scrubber connection 1 Action Mechanical 26-Sep-21 Closed Completion Sheeting must be installed
231 Submersible Pump Installation at RAS-1 1 Action Mechanical 26-Sep-21 27-Sep-21 5-Oct-21 Closed
232 Flap valve installation AST-1 and AST-2 1 Action Mechanical 26-Sep-21 27-Sep-21 5-Oct-21 Closed Material not on site/Bolts
233 Scum hopper Completion 1 Action Mechanical 26-Sep-21 27-Sep-21 5-Oct-21 Closed
234 Mechanical open Fronts 1 Action Mechanical 26-Sep-21 6-Oct-21 Closed Closed
235 Transmitter Installation 1 Action E&I 26-Sep-21 6-Oct-21 Closed
236 AST to MCC Cable installation 1 Action E&I 26-Sep-21 9-Oct-21 6-Oct-21 Closed
237 SS4 PLC Panel 1 Action E&I 26-Sep-21 6-Oct-21 Closed Urgent/Preservation
238 Instrumentation Cables from SS4 to Instruments 1 Action E&I 26-Sep-21 6-Oct-21 Closed
239 FOC tube connection to pull pits will be completed 1 Action E&I 26-Sep-21 27-Sep-21 6-Oct-21 Closed
240 Punch points close out for Lagoon Electrical Works 1 Action E&I 27-Sep-21 1-Dec-21 Closed
241 MLR Pump installation at AST-2 1 Action Mechanical 27-Sep-21 7-Oct-21 6-Oct-21 Closed Today
242 RAS Pumps will be shifted today 1 Action Mechanical 27-Sep-21 Closed
243 Gates installation next week for RAS 2 1 Action Mechanical 27-Sep-21 11-Oct-21 11-Oct-21 Closed
244 Gates installation next week for RAS 3 on-going 1 Action Mechanical 27-Sep-21 4-Oct-21 4-Oct-21 Closed
245 Rising Pipe for RAS-1 (Coring) 1 Action Mechanical 27-Sep-21 11-Oct-21 11-Oct-21 Closed Next week Core cutting
246 TOL gates will be started tomorrow 1 Action Mechanical 27-Sep-21 30-Dec-99 Postponed Shifted inside
247 Tethering Post installation lagoon 1 Action Civil 6-Oct-21 18-Nov-21 8-Dec-21 Closed Delivered on site
248 DC-3 to start penstock installation next week 1 Action Mechanical 27-Sep-21 17-Oct-21 Closed Ongoing Scaffolding started
249 MCC room panel support will be started tomorrow 1 Action E&I 27-Sep-21 3-Oct-21 3-Oct-21 Closed Not released by Civil

Sludge dewatering Electrical works wil be installed


250 1 Action E&I 27-Sep-21 4-Oct-21 Closed
next week
251 Zone 4 Tse Tank Water leak test 1 Action Civil 27-Sep-21 8-Oct-21 Closed
252 TSE Building and Sludge Column and beam pouring 1 Action Civil 27-Sep-21 9-Oct-21 10-Oct-21 Closed Today
253 Fire piping pipe fabrication area visit 1 Action Mechanical 27-Sep-21 Closed Sunday 10-3-2021
254 Checklist for the Lagoon works scope 1 Action Electrical 27-Sep-21 Closed
FLOOR TILE LAYOUT FOR CONTROL OPERATION
255 BUILDING. Doc.no. 3895 1 Action Civil 27-Sep-21 Closed

Site Sketch for Toilet Wall Tile Layout for Control


256 1 Action Civil 27-Sep-21 Closed
Operation Building. Doc No. 3896
257 Excavation for MV cable near fine screen 1 Action E&I 29-Sep-21 Closed
258 Excavation for storm pipe near fine screen 29-Sep-21 Postponed
259 Additional 22 manpower for TAKANAH 1 Action Mechanical 29-Sep-21 30-Sep-21 Closed 18 Added
260 Checkered Plate stability st sub-station 2 1 Action 29-Sep-21 Closed
261 Manhole installation near PDPS 1 Action 29-Sep-21 Closed
262 Surface Aerator Assembly - Lagoon Area  1 Action Mechanical 29-Sep-21 Closed
263 By-pass Channel Completion date 1 Action Civil 29-Sep-21 12-Oct-21 Closed
Sludge Dewatering Grade beam breaking to
264 accommodate the Panel 1 Action E&I 29-Sep-21 Closed
265 Leak test for Lagoon to close 1 Action Civil 29-Sep-21 Closed
266 Opening in the Splitter at Lvl. 14.5 Slab issue 1 Action Civil 29-Sep-21 Closed
267 TOL Area parking and Drain pipe issue dwg 1 Action Civil 29-Sep-21 Closed
268 Repair of ES-8 (MS) 1 Action Civil 6-Oct-21 Closed To be resolved at earliest
269 SS-4 Cable RD Crossing to be protected 1 Action 29-Sep-21 Closed
LIFTING SS DIFFUSER GRID Proposed Galvanized
270 1 Action Mechanical 2-Oct-21 10-Oct-21 Closed Change into nylon rope
steel wire rope slings and D-Shackles
271 DC-2 Internal Wall after 2 days 1 Action Civil 2-Oct-21 Closed
25 manpower more to be mobilize for surface
272 1 Action Civil 2-Oct-21 Closed
preparation
273 Gate Pass for pump station Brown area materials 1 Action Piping 2-Oct-21 Closed
274 MV Cable Excavation Splitter box to PDPS 1 Action E&I 2-Oct-21 Closed
275 MCC Panels will be shifted tomorrow 1 Action E&I 3-Oct-21 Closed
276 Completion of Electrical works to be verified SS4 1 Action E&I 3-Oct-21 18-Nov-21 Closed PLC Panel termination balance transformer termination balance
277 Glanding completion for Substation 4 1 Action E&I 3-Oct-21 27-Oct-21 Closed PLC Panel termination need to be done
278 DB willl be delivered on 19/43 1 Action E&I 3-Oct-21 Closed Verify
279 Control cable at SS4 completion date 1 Action E&I 3-Oct-21 Closed This week will be completed
280 SST-1 Zone Walkdown 1 Action E&I 3-Oct-21 17-Oct-21 Closed October 10, 2021 meeting
CDS Field termination JB, Solenoid Valves, analizer,
281 Panels and etc 1 Action E&I 3-Oct-21 14-Oct-21 Closed Verify
282 Exhaust fan Installation at CDS 1 Action Mechanical 3-Oct-21 Postponed
283 12 manpower additional for NIC 1 Action E&I 3-Oct-21 Closed
284 MV Panels Completion SS-2 1 Action E&I 3-Oct-21 Closed
285 Cable tray drop 1 Action E&I 3-Oct-21 Closed
286 SS-1 Lighting fixtures will be completed this week 1 Action E&I 3-Oct-21 24-Oct-21 Closed Completion Tranformer area balance
Sludge Dewatering Panel installation partial
287 completion 1 Action E&I 3-Oct-21 Closed
288 Lagoon works Earthing 1 Action E&I 3-Oct-21 6-Oct-21 Closed Today
289 Fire Alarm panels will start this week 1 Action E&I 3-Oct-21 10-Oct-21 Closed
290 100% Plant Model Navisworks 1 Action Engineering 4-Oct-21 Closed
291 RAS-1 Handrail 1 Action Civil 7-Oct-21 22-Nov-21 Closed
292 Pipe pedestals at Pipe gallery 1 Action Mechanical 4-Oct-21 14-Oct-21 Closed
293 Re-routing of lighting wires at 1f COR 1 Action E&I 5-Oct-21 Closed
294 MAR and MS for aluminum walkway joint cover 1 Action Civil 5-Oct-21 Closed
Sludge Dewatering GF remaining room handover to
295 1 Action Civil 5-Oct-21 Closed
Electrical and Mechanical
296 Regarding the TSE Zone-04/05 fence work 1 Action Civil 5-Oct-21 Closed Raised by MR
297 RSF Backwash water filling. 1 Action Civil 5-Oct-21 Closed
Handrail installation for stair is not
298 acceptable/needs Plastic joint not bend 1 Action Civil 6-Oct-21 Closed

Finishing Activities Mock-up (Wall and Floor, Tiles,


299 1 Action Civil 7-Oct-21 13-Nov-21 Closed Ceiling Completed
Ceiling, Raised floor system)
Sludge Dewatering Grade beam breaking to
300 accommodate the Panel MS 1 Action Civil 6-Oct-21 Closed
301 DG Foundation works to start at SS3 1 Action Civil 11-Oct-21 25-Nov-21 Closed Crane accessibility
302 TSE Above ground piping near SS-4 1 Action Piping 7-Oct-21 Closed
303 Weekly & Monthly Report 1 Action 6-Oct-21 Closed Raised by MA
304 RAS-1 Coating 1 Action Civil 6-Oct-21 Closed
305 Zone 5 drain chamber completion date 1 Action Civil 16-Oct-21 11-Nov-21 Closed
306 DG installation at SS-2 1 Action Mechanical 7-Oct-21 19-Oct-21 23-Oct-21 Closed
307 SS-3 Masonry works 1 Action Civil 7-Oct-21 Closed
Start date of breaking the rcc for panel access
308 1 Action Civil 7-Oct-21 27-Oct-21 Closed Marking by today (21-Oct-21)
Sludge Dewatering)
Sludge Dewatering Mechanical works and Steel
309 platforms 1 Action Mechanical 7-Oct-21 Closed

To start external surface preparation


310 SST Zone 3 backfill 1 Action Civil 18-Oct-21 4-Nov-21 Closed
and Epoxy Coating.
311 ES-8 Proposal 1 Action Civil 9-Oct-21 16-Oct-21 repeated
312 Hollow contractor to come for TSE 1 Action Civil 9-Oct-21 Closed
313 Ceiling mock up this week 1 Action Civil 9-Oct-21 14-Oct-21 Closed
314 Raise floor system Mock-up 1 Action Civil 9-Oct-21 14-Oct-21 repeated Next week
315 TSE overflow readiness will be this week 1 Action Civil 9-Oct-21 4-Nov-21 Closed
316 Overflow By-pass Channel this week pouring 1 Action Civil 9-Oct-21 Closed
317 Lagoon Aeration tank 2 surface preparation 1 Action Civil 19-Oct-21 Closed APR Issue

SEWER pipe from guard, control OCU-2 and tanker


318 bay drain to TOS and concrete road details. 1 Action Civil 9-Oct-21 Closed

319 Sludge dewatering Beam 1 Action Civil 9-Oct-21 12-Oct-21 Closed


320 Surface Aerator Assembly  1 Action Mechanical 10-Oct-21 Closed
ALUMINIUM FLASHING ON TERMINATION OF
321 WATER PROOFING MEMBRANE FOR ALL BUILDINGS 1 Action Civil 10-Oct-21 Closed
& WATER RETAINING STRUCTURES
322 20 Takanah manpower to be supplied next week 1 Action Mechanical 10-Oct-21 Closed
323 1 Crane will be added by TAKANAH 1 Action Mechanical 10-Oct-21 26-Oct-21 Closed
324 Ast-2 All Cable tray 1 Action E&I 10-Oct-21 22-Nov-21 Closed
Lagoon Electrical works to be checked/ Walk
325 through 1 Action E&I 10-Oct-21 28-Oct-21 Closed Internal Walkthrough

Cables for the Penstocks to perform health check to


326 be connected to the new panels. Connect only 1 Action E&I 10-Oct-21 17-Oct-21 Closed

Panels and Cables to be handovered to MARAFIQ


327 1 Action E&I 10-Oct-21 INFO
for Inventory

328 Re-Aeration tank LV cable will be started this week 1 Action E&I 10-Oct-21 17-Oct-21 Closed

329 Hollowcore installation for TSE PS 1 Action Civil 20-Oct-21 25-Nov-21 Closed Mechanical activities need to complete

METHOD STATEMENT FOR INLET SPLITTER BOX


330 AND BYPASS CHANNEL (Lagoons) TIE-IN 1 Action 11-Oct-21 11-Nov-21 Closed MS Submitted
CONNECTION
331 Surface Aerators Bracket Issue 1 Action Mechanical 11-Oct-21 Closed Material received
332 Hollowcore installation for Sludge Dewatering 1 Action Civil 20-Oct-21 10-Dec-21 Closed Mechanical activities need to complete
333 Pumps Log sheet to be shared to MARAFIQ 1 Action Mechanical 11-Oct-21 Closed
334 MV Cable Hypotential Test Kits 1 Action E&I 11-Oct-21 INFO
335 Sample of new counter top/ Wash basin 1 Action Civil 27-Oct-21 Open
Overhead crane must be installed prior to hollow
336 1 Action Mechanical 12-Oct-21 INFO
core
337 Electrical Progress Log Sheet 1 Action Electrical 12-Oct-21 Closed Today
338 Sample Penstock at DC-1 1 Action Mechanical 12-Oct-21 17-Oct-21 Pending Will be done with power supply
339 Interface permit log sheet 1 Action Civil 13-Oct-21 Closed
Ms For Installation Of Ceramic Tiles For Building
340 (Control Operation Building, Tos Guard Room & Tos 1 Action Submittal 14-Oct-21 Closed
Control Room.)
341 Risk Register Update 1 Action Submittal 14-Oct-21 Closed
342 Splitter box to SS-1 MV Cable 1 Action Submittal 14-Oct-21 Closed
343 DC-2 walkway completion date 1 Action Civil 16-Oct-21 2-Nov-21 Closed
344 TSE Beam form and scaffolding removal 1 Action Civil 16-Oct-21 Closed
345 Overflow chamber Leak test in Zone-04 1 Action Civil 28-Oct-21 4-Nov-21 Closed
346 SS3 Mansonry works completion date 1 Action Civil 16-Oct-21 7-Nov-21 Closed
347 Leak test of Byepass channel to lagoon 1 Action Civil 10-Nov-21 Closed
348 Scum Manhole SST-1 1 Action Civil 16-Oct-21 Closed
349 Manhole in between Grit and Grease and SS-1 1 Action Civil 16-Oct-21 Closed
350 Manhole in between MCC Room and AST-1 1 Action Civil 16-Oct-21 4-Nov-21 Closed Ongoing
351 Lagoon Fire Hydrant Source 1 Action Mechanical 17-Oct-21 repeated Raised by MA with Email
352 Pipe supports in by-pass channel to lagoon 1 Action Civil 10-Nov-21 14-Dec-21 Closed
353 Pneumatic Test for AST-1 Head Branch 1 Action Mechanical 20-Sep-21 14-Dec-21 Closed Before safety walkdown both the test neecd to complete
ES-7 next week to resume the penstock installation
354 1 Action Mechanical 27-Sep-21 5-Dec-21 Closed Walll Thickening Done
and thickening
355 Sheeting for OCU-2 1 Action Mechanical 9-Oct-21 28-Oct-21 Completed Bolts received
356 Substation 2 fire fighting completion this week 1 Action Mechanical 17-Oct-21 repeated
357 AST-1 Cable termination 1 Action E&I 17-Oct-21 18-Nov-21 Closed Completion
AST-3 Completion for Cable 3, JB, LPPS and
358 Instruments 1 Action E&I 17-Oct-21 18-Nov-21 Closed

To cut the Sludge dewatering to make Access for Sketch need to be subitted and Planned
359 MCC panel. 1 Action E&I 17-Oct-21 repeated next week
360 Nesma Material log sheet status 1 Action E&I 18-Oct-21 Closed
Lagoon Fire Hydrant Source/planning accordingly Raised by MA with Email to Lalit, Amir
361 1 Action Mechanical 10-Oct-21 Closed
for lagoon testing to Visit the location
362 Lagoon Lot 1 to be completed 1 Action General 18-Oct-21 10-Nov-21 repeated
363 Plates for surface Aerators 1 Action Mechanical 18-Oct-21 repeated
Zone 5 Tie-in Connection Readiness (Schedule and
364 Material Checklist) 1 Action Piping 18-Oct-21 Closed
365 Fire water line to start at brown area 1 Action Mechanical 11-Oct-21 Closed
366 TOL near Control room Ductbank 1 Action Civil 19-Oct-21 2-Nov-21 Closed
367 Fire fighting System Readiness (SS Buildings) 1 Action Mechanical 17-Oct-21 4-Nov-21 Closed SS-04 Started
368 Schedule of works for HCIS (Nesma) 1 Action E&I 20-Oct-21 Closed
369 Loop Folders sample 1 Action E&I 20-Oct-21 2-Nov-21 Closed
Comprehensive plan for commissioning utilities
370 required such as Power, water (all types)…etc for 1 Action General 20-Oct-21 Closed Raised MA
testing and commissioning.
371 Panel Preservation at MCC room 1 Action E&I 20-Oct-21 Closed
372 OCU-2 completion 1 Action Mechanical 17-Oct-21 4-Nov-21 20-Dec-21 Open
373 25 Manpower to be supplied by Takanah 1 Action Mechanical 17-Oct-21 18-Oct-21 Closed Total 46 Persons
374 Screed for Blower building 1 Action Civil 20-Oct-21 Closed Inspection by today
375 CCT floor Epoxy coating 1 Action Civil 20-Oct-21 Closed
376 RSF Backwash tank dewatering 1 Action Civil 20-Oct-21 Closed
377 Inlet splitter box leak test 1 Action Civil 20-Oct-21 Postponed
378 Chequered plate in DC issue 1 Action Civil 27-Oct-21 Closed
379 Service water pump line to CDS this week 1 Action Mechanical 17-Oct-21 Closed Backfilling completion waited

380 Proposed Sanitary pipe to be connected to storm 1 Action Piping 29-Sep-21 Closed Rejected

381 Catch Pits slow progress 1 Issue Piping 16-Oct-21 Closed


382 Lagoon DTS-04 Works 1 Electrical
383 Decanter Installation in SDB
384 Silo Installation preparation
385 Chequered plate in SS Modification 1 Action Electrical 9-Nov-21 Postponed After all the works it will be rectified
386 Pump station at brown area 1 Action Piping 19-Oct-21 19-Dec-21 Open Gate pass in process
HDPE Piping and scum piping connection (All SST
387 Area) 1 Action Piping 28-Oct-21 22-Nov-21 Closed
388 Lagoon Byepass channel and piping works 1 Action Piping 9-Nov-21 Repeated
389 SS-01,02&04 Earthing works 1 Action Electrical 10-Nov-21 22-Nov-21 Closed
390 Electrical Technician mobilization 1 Action Electrical 10-Nov-21 Closed
391 Electrical testing contractor mobilization at site 1 Action Electrical 10-Nov-21 7-Dec-21 Closed
Existing Pump station to splitter box pipeline and
392 1 Action Piping 9-Nov-21 20-Dec-21 Open APR Issue
supports
393 TOS Potable water and service water line 1 Action Piping 9-Nov-21 postponed Open
394 Saudi cranes visit for TSE PS 1 Action Mechanical 18-Nov-21 Closed
395 SS-01,02&04 Lightning works 1 Action Electrical 18-Nov-21 Closed
396 Fire hydrant valve protection 1 Action Mechanical 18-Nov-21 4-Dec-21 Closed Material to be submitted
397 TSE Tank Epoxy Coating 1 Action Civil 20-Nov-21 Closed
398 Chlorination Pipe from TSE to CDS 1 Action Piping 20-Nov-21 Repeated
399 RSF North Side remaining filter tank leak test 1 Action Civil 20-Nov-21 Closed
400 DC-2 leak test 1 Action Civil 20-Nov-21 13-Dec-21 Open Not Possible
Surface preparartion for HDPE liner installation for
401 Aeration 2 1 Action Civil 20-Nov-21 Repeated
402 TSE building Crane installation completion 1 Action Mechanical 20-Nov-21 Repeated
403 DC3 penstock installation 1 Action Mechanical 20-Nov-21 Closed
404 Pipe Gallery SS and GRP piping 1 Action Mechanical 20-Nov-21 Closed
405 Scum manhole complete installation 1 Action Mechanical 20-Nov-21 repeated
406 CDS Completion 1 Action General 20-Nov-21 4-Dec-21 Closed
407 SS1 E and I Completion 1 Action General 20-Nov-21 Closed
408 SS2 E and I Completion 1 Action General 20-Nov-21 Closed
409 SS4 E and I Completion 1 Action General 20-Nov-21 Closed
410 Walk down Schedule 1 Action General 20-Nov-21 Closed
411 DC-2 Penstock to be installed 1 Action Mechanical 20-Nov-21 24-Nov-21 Closed
412 Raised floor system 1 Action Civil 20-Nov-21 7-Dec-21 Closed With comment
413 Door Installation Status and Master Key Log 1 Action Civil 20-Nov-21 14-Dec-21 Open After installation of all doors
414 Steel supports for Blower building 1 Action Mechanical 20-Nov-21 28-Nov-21 Closed
415 Steel Platform for dewatering building 1 Action Mechanical 20-Nov-21 4-Dec-21 Closed
416 By pass pipe support to be started tomorrow 1 Action Civil 20-Nov-21 21-Nov-21 Repeated
417 RSF North side water filling 1 Action Civil 20-Nov-21 25-Nov-21 Repeated
418 Hollow core slab 2 days for TSE Building 1 Action Civil 20-Nov-21 22-Nov-21 Repeated
419 Water Supply Testing for buildings 1 Action Piping 20-Nov-21 Closed
420 Manhole Storm water Cover shape issue 1 Action Piping 20-Nov-21 Engineering Open
421 Water filling for DC-3 1 Action Civil 20-Nov-21 21-Nov-21 Closed
422 Scum Pump Station 1 Completion date 1 Action Civil 21-Nov-21 Closed
423 SST-8 Dewatering 1 Action Civil 21-Nov-21 Closed
424 SST-8 Bridge 1 Action Civil 21-Nov-21 1-Dec-21 Closed
425 Crew for closing punch list 1 Action General 21-Nov-21 Open Poor progress
426 SS piping for Sludge Dewatering 1 Action Mechanical 21-Nov-21 Postponed
427 Manlift MS for pickling and passivation MS 1 Action Mechanical 21-Nov-21 Closed Not practical
Cable routing for CDS to be provided clearance for
428 1 Action Electrical 21-Nov-21 Closed
piping team
429 Balance material for FAT partial 1 Action Electrical 21-Nov-21 21-Dec-21 Open
430 LOTO for Electrical Energization Flow Chart 1 Action General 21-Nov-21 18-Dec-21 Open
Floor and trench Painting for SS3 holding the
431 Electrical works 1 Action Civil 21-Nov-21 Repeated

Termination issue on incomer cable SEC room and Meet MASA Today shutdown next
432 1 Action Electrical 21-Nov-21 Closed
needs to discuss all so the hipot week
Lagoon Power cable to existing penstock is damage
433 need to be glanded. (Cable damage) 1 Action Electrical 21-Nov-21 1-Dec-21 Closed
434 COR Panel orientation will be finalized 1 Action Electrical 21-Nov-21 25-Nov-21 Closed
435 FOC Cable pulling Brown area 1 Action E&I 21-Nov-21 Closed
436 High Voltage team terminator (Incomer cables) 1 Action Electrical 21-Nov-21 Repeated
Method Statement for Inlet Splitter box Tie-In
437 connection with existing chamber closure of 1 Action Mechanical 21-Nov-21 Closed
comments
438 Failure to submit daily report 1 Action General 21-Nov-21 Closed Discussed with MASA
439 Encasing of HDPE pipes 1 Action Piping 21-Nov-21 Engineering Open Mani to respond
440 Old cable removal from Lagoon 1 Action Electrical 21-Nov-21 1-Dec-21 Closed On-progress
Zone 5 Thrust block at Tie in (RA must be
441 submitted) 1 Action Civil 23-Nov-21 1-Dec-21 2-Dec-21 Open Submitted MA
442 Manhole benching and leak test 1 Action Piping 24-Nov-21 Open
443 SS-3 Floor epoxy paint 1 Action Civil 24-Nov-21 Closed
444 Grader issue for roads 1 Action Civil 25-Nov-21 Closed
445 Silo Installation preparation 1 Action Mechanical 25-Nov-21 20-Dec-21 Open
446 Backfilling washout chamber Zone 5 1 Action Civil 25-Nov-21 closed
447 Leak repair for Overflow chamber repair Zone 4 1 Action Civil 25-Nov-21 1-Dec-21 Closed
448 AST-1 Northt side excavation closure 1 Action Civil 25-Nov-21 Not possible Open
449 Cage ladder Installation 1 Action Civil 27-Nov-21 16-Dec-21 Open
450 SST-8 release to Mechanical 1 Action Civil 27-Nov-21 Closed
451 Dewatering of Overflow chamber 1 Action Civil 27-Nov-21 Closed
452 Guard House completion 1 Action Civil 27-Nov-21 Open
453 RAS-1 and RAS-3 Coating 1 Action Civil 27-Nov-21 Open
454 RAS-1 Railing 1 Action Civil 27-Nov-21 Repeated
455 Pipe Support for By pass 1 Action Civil 27-Nov-21 Repeated
456 OCU-1 block Work 1 Action Civil 27-Nov-21 11-Dec-21 Closed
457 RSF Technical Gallery Coating 1 Action Civil 27-Nov-21 Closed
458 Clamps for TSE zone 1 1 Action Piping 27-Nov-21 16-Dec-21 Open
459 Zone 5 backfilling 1 Action Piping 27-Nov-21 Closed
December 10 all manholes and catchpits must be
460 1 Action Piping 27-Nov-21 Open
done
461 OCU-1 support 1 Action Mechanical 28-Nov-21 Closed
462 SST Progress Tracking Sheet 1 Action Mechanical 28-Nov-21 Closed
463 AST-3 poor Progress Ballast 1 Action Mechanical 28-Nov-21 Closed
464 AST Main header pipe blower 1 Action Mechanical 28-Nov-21 6-Dec-21 Closed
465 SST-8 Bridge Shifting 1 Action Mechanical 28-Nov-21 1-Dec-21 Closed
466 Calibration PSV for pressure testing 1 Action Mechanical 28-Nov-21 1-Dec-21 Closed
467 Lifting to be done on diffuser this week 1 Action Mechanical 28-Nov-21 12-Dec-21 Open
468 OCU-1 Civil Works 1 Action Mechanical 28-Nov-21 Repeated
469 Piping Material for Takanah 1 Action Mechanical 28-Nov-21 Closed
470 Ballast for AST-3 North side 1 Action Mechanical 28-Nov-21 Repeated
471 LOTO for Mechanical 1 Action Mechanical 28-Nov-21 Repeated
472 DB installation for MCC 1 Action Electrical 28-Nov-21 1-Dec-21 Closed
473 Rating of DG in MCC issue 1 Action Electrical 28-Nov-21 Closed
474 SDB Panel installation MCC panel 1 Action Electrical 28-Nov-21 1-Dec-21 Closed
475 RSF to SS4 LV cable pulling halt due to loose soil 1 Action Electrical 28-Nov-21 Closed
476 Cover for all openings 1 Action General 28-Nov-21 Closed
477 Cable route from SS-2 and Blower Building 1 Action Electrical 28-Nov-21 Closed
478 One side termination HV incomer 1 Action Electrical 28-Nov-21 30-Nov-21 Closed
479 Testing Procedure 1 Action Electrical 28-Nov-21 Closed
Fabrication and installation of Air piping from the
480 1 Action Mechanical 29-Nov-21 Repeated
blowers to the AST’s
Firewater network piping- Both areas (Green field
481 and Brown field) 1 Action Mechanical 29-Nov-21 Closed
482 Storm water network- Manholes and catchpits 1 Action Mechanical 29-Nov-21 Repeated
Casting of supports for Foul air system and Lagoon
483 bypass lines. 1 Action Mechanical 29-Nov-21 Closed

Platforms and supports for Blower building and


484 1 Action Mechanical 29-Nov-21 Repeated
Sludge De watering building
Tethering posts for lagoons needs to be casted and
485 placed on site 1 Action Mechanical 29-Nov-21 Repeated

Rapid Sand Filter – Piping (SS and GRP) has to


486 1 Action Mechanical 29-Nov-21 Repeated
speeded up  
Platforms and supports for Blower building and
487 Sludge De watering building 1 Action Mechanical 29-Nov-21 Repeated

Tethering posts for lagoons needs to be casted and


488 placed on site 1 Action Mechanical 29-Nov-21 Repeated

Rapid Sand Filter – Piping (SS and GRP) has to


489 1 Action Mechanical 29-Nov-21 Repeated
speeded up  
490 Lagoon pump station to start tomorrow 1 Action Mechanical 29-Nov-21 Repeated
Pin holes found in metallic below with NCR needs
491 repair procedure 1 Action Mechanical 29-Nov-21 Closed
492 Aerator Issue on the assembly 1 Action Mechanical 29-Nov-21 Closed
493 Equipment installation Log 1 Action Mechanical 29-Nov-21 Closed
E&I progress log sheet including street lighting and
494 1 Action Electrical 29-Nov-21 2-Dec-21 Closed
area lighting
495 Lagoon foundation DTS-4 1 Action Electrical 30-Nov-21 Closed
496 RAS Mechanical works in the Valve chamber 1 Action Mechanical 30-Nov-21 Open
497 Lighting poles and loop cables 1 Action Electrical 1-Dec-21 Closed
498 TOL Temination to be expedited 1 Action Electrical 1-Dec-21 Closed
499 Manpower allocation 1 Action Electrical 1-Dec-21 Closed
500 SS-1 hipot readiness 1 Action Electrical 1-Dec-21 Closed
501 Water tank insulation Action Civil 1-Dec-21 Closed
502 Lagoon Proposal for Panel foundation Action Civil 1-Dec-21 15-Dec-21 Open
503 Lagoon Emergency push button Action Electrical 1-Dec-21 Open
504 Grader not on site holding the road works Action Civil 1-Dec-21 Open
505 Expedite WP and Backfilling for bypass channel Action Civil 4-Dec-21 Closed
Expedite WP and Backfilling for TSE Overflow
506 Action Civil 4-Dec-21 Closed
Chamber
507 Grit and grease leak test Action Civil 4-Dec-21 Open
508 Fine screen slab completion Action Civil 4-Dec-21 7-Dec-21 Closed
509 ES-8 WATER FILLING Action Civil 4-Dec-21 Open
510 Pump station start date Action Civil 4-Dec-21 Repeated
Lagoon foundation issue raised to Wabag
511 Action Civil 4-Dec-21 Repeated
Engineering
512 OCU-1 Masonry Works Action Civil 4-Dec-21 Repeated
513 Manhole benching and Testing Action Civil 4-Dec-21 Repeated
514 Telescopic valves for SST 5,6 and 7 1 Action Mechanical 5-Dec-21 20-Dec-27 Closed
515 Zone 3 SST 9,10,12 scum hoppers 1 Action Mechanical 5-Dec-21 15-Dec-21 Closed
516 SST-8 Bridge Completion 1 Action Mechanical 5-Dec-21 7-Dec-21 Closed
517 SSt-8 Mechanical Works Completion 1 Action Mechanical 5-Dec-21 24-Dec-21 Open
518 SS for Main Blower Pipe 1 Action Mechanical 5-Dec-21 6-Dec-21 Repeated
519 Leak test of DC-2 1 Action Mechanical 5-Dec-21 8-Dec-21 Repeated
520 PDPS Piping 1 Action Mechanical 5-Dec-21 Closed
521 ES-7 Penstock 1 Action Mechanical 5-Dec-21 Closed
522 Es 1-7 will be released for fire water line 1 Action Mechanical 5-Dec-21 21-21-21 Closed
523 Stainless Steel Repair procedure (critical Issue) 1 Action Mechanical 5-Dec-21 Closed Need to solve this critical issue
524 Street Lighting Foundation RSF 1 Action Mechanical 5-Dec-21 Repeated
525 Testing Witness RFI Schedule to Submit 1 Action Electrical 5-Dec-21 5-Dec-21 Closed
Test Procedure and formats to be shared to testing
526 crew 1 Action Electrical 5-Dec-21 Closed
527 RAS 2 and 3 Scaffolding affecting electrical Works 1 Action Civil 5-Dec-21 Open
528 SS3 Civil clearance for electrical panel rooms 1 Action Civil 5-Dec-21 18-Dec-21 Open
529 Transformer installation at SS3 1 Action Electrical 5-Dec-21 20-Dec-21 Open
530 Wall mounted panel installation Blower Building 1 Action Electrical 5-Dec-21 Closed
531 RSF Handrail 1 Action Electrical 5-Dec-21 Closed
532 APR for Electrical lagoon works 1 Action Electrical 5-Dec-21 Closed
533 Panel blocking the door in COR building 1 Action Electrical 5-Dec-21 Closed
534 Street Lighting installation permit issue 1 Action Electrical 5-Dec-21 Closed Critical Issue/Permit
535 Cover follow up by Abdulaziz 1 Action Civil 6-Dec-21 Closed
Reminder to Electrical team tomake the site ready
536 prior to testing 1 Action Electrical 6-Dec-21 Closed
537 Brown area fire fighting line to complete this week 1 Action Piping 6-Dec-21 On-going Closed
538 Options for COR workstations (Phani) 1 Action E&I 6-Dec-21 Open
Stop log in for Splitter box as per requested ny
539 MASA 1 Action Civil 6-Dec-21 Closed
540 TSE chamber zone 4 backfilling 1 Action Civil 6-Dec-21 Closed
541 OCU-2 Completion 1 Action Mechanical 6-Dec-21 15-Dec-21 Repeated
542 RAS pumps will be shifted this week 1 Action Mechanical 6-Dec-21 Repeated
543 Scada Room completion 1 Action E&I 6-Dec-21 On-going Open
Incomer cable to COR needs conduits to be
544 installed 1 Action E&I 6-Dec-21 Open
545 RAS handrail 1 and 3 1 Action Civil 6-Dec-21 Open
Truck offloading conrete slab (FENCE, Permits and
546 etc.) 1 Action Civil 6-Dec-21 Closed
547 Fire Fighting line east side to start this week 1 Action Piping 6-Dec-21 Repeated
Mooring rope and MASA requirements to access
548 the Lagoons 1 Action Mechanical 6-Dec-21 Closed

DT-MFQ-5369-NCR # PMC-024-Bellow spools seem


549 welds Crack 1 Action Mechanical 6-Dec-21 Open
550 Lagoon HDPE Liner Works resumption 1 Action Civil 7-Dec-21 Closed
551 Exposed conduits under ceiling at COR building 1 Action E&I 7-Dec-21 Closed
552 Quantity and open Fronts Weekly meeting 1 Action General 7-Dec-21 Open
553 3D Model lay-out (Navisworks) 1 Action Engineering 8-Dec-21 Open
554 Shutdown for fire water line 1 Action Civil 8-Dec-21 Closed
555 Fine Screen Columns 1 Action Civil 8-Dec-21 12-Dec-21 Closed
556 Fine Screen hollow core 1 Action Civil 8-Dec-21 Open After Beam casting for dimension
557 TSE Plastering 1 Action Civil 11-Dec-21 Open
558 TSE Roof waterproofing 1 Action Civil 11-Dec-21 Closed
559 CCT cover slab water proofing completion 1 Action Civil 11-Dec-21 Closed
560 SS3 Electrical Works 1 Action Electrical 11-Dec-21 Repeated
561 Completion of OCU-1 Masonry works 1 Action Civil 11-Dec-21 Closed
562 Completion of OCU-1 Roof Sheeting 1 Action Civil 11-Dec-21 Open
563 TOL Control Room Toilet and Kitchen works 1 Action Civil 11-Dec-21 Open
564 Raised floor with comment 1 Action Civil 11-Dec-21 repeated
565 Threshold for Epoxy flooring 1 Action Civil 11-Dec-21 Open
566 Screed proposal for site mixing 1 Action Civil 11-Dec-21 19-Dec-21 Open
Sealant linewhite color paint applicable for all
567 building 1 Action Civil 11-Dec-21 Open
568 Ramps and Landings 1 Action Civil 11-Dec-21 Open
569 SDB SS pipe 1 Action Mechanical 12-Dec-21 18-Dec-21 Open
570 Critical Lifting plan for Pickling and passivation 1 Action Mechanical 12-Dec-21 Closed
571 Penstock instalation at Grit and Grease 1 Action Mechanical 12-Dec-21 Closed
572 RAS-1 Monorail 1 Action Mechanical 12-Dec-21 Closed
573 Fire water line excavation toward green field 1 Action Mechanical 13-Dec-21 Closed
574 Lagoon proposal for the lagoon to use scaffolding 1 Action Mechanical 13-Dec-21 14-Dec-21 Closed
575 Submersible pump at RAS 3 1 Action Mechanical 13-Dec-21 19-Dec-21 Open
Progress for SS pipes must be submitted with spool
576 number for tracking 1 Action Mechanical 13-Dec-21 16-Dec-21 Open

Battery system must be ready before


577 commissioning 1 Action Electrical 14-Dec-21 Open
HCIS Load requirement for UPS (Security System,
578 Size of UPS does it includes the future plant) 1 Action E&I 15-Dec-21 Open
579 Door locks must be in placed all substations 1 Action Civil 15-Dec-21 Open
580 Hipot MV Swith gear 1 Action Electrical 15-Dec-21 16-Dec-21 Closed
581 Fire water line near SS4 and Ocu-1 testing 1 Action Piping 15-Dec-21 18-Dec-21 Open
Debris from the SST-2 North side needs jack
582 hammer 1 Action Civil 15-Dec-21 20-Dec-21 Open

Temporary Energization of Panel Room 231


583 1 Action Electrical 15-Dec-21 Open
Concerns by Paul
584 Blower room south side painting 1 Action Civil 15-Dec-21 Open
585 Blower room ceiling painting 1 Action Civil 15-Dec-21 Open
586 Blower room SS pipe support at lower roof 1 Action Mechanical 15-Dec-21 Open
587 Remaining balance for Ballast installation at Ast-3 1 Action Mechanical 15-Dec-21 Open

Inside building for Blower room electrical room


588 painting for trenches 1 Action Civil 15-Dec-21 Open
589 Perimeter Street lighting and CCTV 1 Action Electrical 19-Dec-21 Open
590 Regarding the proposal fence for raising chamber  1 Action Civil 19-Dec-21 Open
591 RFI'S Signatures for testing MASA 1 Issue Piping 19-Dec-21 Open
592 Blower room trench epoxy paint 1 Action Civil 20-Dec-21 20-Dec-21 Open
593
No.Activity
1 By pass line to lagoon Civil
2 RSF remaining slab Civil
3 RSF Channel to re-aeration tank (Blower Line) Civil
4 RCC stairs RSF Civil
5 TSE Plaster Civil
6 Scrubber Potable Waterline Waterline Piping
7 All potable waterline Piping
8 Substation 2 to COR LV Cable Electrical
9 TSE tank Epoxy Coating Civil
10 Battery Room Completion Electrical
11 Ladder completion Civil
12 Blower Room Steel platform completion Mechanical
13 OCU-2 completion
15 Lifting to be done on diffuser this week
16 RAS Mechanical works in the Valve chamber
17 SSt-8 Mechanical Works Completion
18 DT-MFQ-5369-NCR # PMC-024-Bellow spools seem welds Crack
19 SDB SS pipe
Submersible pump at RAS 3
Progress for SS pipes must be submitted with spool number for tracking
Blower room SS pipe support at lower roof
Remaining balance for Ballast installation at Ast-3
Expedite
NO. DESCRIPTION

1 Delay  in  Handing  over  and construction  of  Lagoon  Lot  2 and  Lot  3 
contributing  to overall back log of 2 % rolling up  near  to  1%  in  overall Project. 
2 Sourcing  of  Manpower  for construction is delayed due to nonavailabi of 
skilled Manpower in Market. 

Delay  in  handing  over  of structures  to 


3 other disciplines. The main buildings under  RCC  works  are 
Head Works/Aerated  Grit Chambers  and Substation‐3. Balance  all  buildings 
are under MEI installation. 
Shifting  of  Manpower  after completion  of  one 
4 structure to other structure due to less availability  of  work  force 
is delaying the completion.  
5 Non availability of Knowledge full  APR  to  pass  through  the testing 
methods, causing and impacting  work  delay  in Brown field works. 
No. Statement

There is no existing sanitary system on Stage 6 site. New


facilities shall have a sewage system made of pipes which
1 will be collected to the drain pumping station for the
delivery to Stage 6 inlet for treatment in the new plant.
(Design Basis). 

2 Contaminated bermed and run off storm waters.

Storm Drainage: storm drainage shall be collected and


3
sent to inlet works.
1.09 ENVIRONMENTAL REQUIREMENTS B. Allow only
4 rainwater run-off in the storm drain system.

1 B. Allow only rainwater run-off in the storm drain system.

Discharges into storm water sewers or channels must not


2 contain any human waste, sullage water or other
substances that may cause a nuisance or injury to health.

Saudi Arabia has a long dry season, small discharges, such


as a drain from a single tap, may increase the risk of
infestation because protozoans or other parasites may
breed.
Source

Design Basis Report for Civil Services

Environmental

Scope of Work

SECTION 15160

SECTION 15160 STORM DRAINAGE PIPING1.09


ENVIRONMENTAL REQUIREMENTS
Jacobs Reply

This is an instruction that in this is a new facility contractor must install


a new sanitary line going to PDPS.

This are stocked and run-off storm water to be possibly contaminated but
not from a sanitary line.

This does not support regarding sanitary line to be in one pipe with storm.

This is the concluding statement as per RC Specification it does not


mention any exemption.

This is the concluding statement as per RC Specification it does not


mention any exemption.
SWTP-9 MEETING SCHEDULE
No. Discipline Saturday Sunday Monday Tuesday Wednesday Thursday
Construction WPM Stan-up Meeting
1 Civil 14:00 10:00 8:00 8:00 8:00
2 Mechanical 14:00 10:00 8:00 8:00 8:00
3 E and I 14:30 10:00 8:00 8:00 8:00
4 Piping 14:30 10:00 8:00 8:00 8:00

You might also like