evening Delta Team, 
 

Below you will find the advance in the services:  

3777 (C2) Day 30 of 30 

On Schedule: Yes                
Induction Date: 26/JAN/22
Contract Delivery Date:  26/FEB/22
Aircraft Status (Past 24 hours): 

37 Open, 40 closed past 24 hrs. 0 burn rate.

 EMERGENCY EQUIPMENT INSTALL


 AILERON TRIM TEST
 GOGO 2KU ADAPTER PLATE INSTALL

Aircraft Status (Next 24 hours) 

 ELEVATOR TRAVEL TEST


 PASSENGER CABIN FINAL
 WIFI SYSTEM INSTALL
 SPOILER MIXER NO-BACK TEST
 WINGS FINAL
 EMPENNAGE FINAL

ATL Support   

 NONE    

Material Issues  

 01 ITEMS    

Engineering Issues  

 01 ITEMS    
5802 (L) Day 06 of 17 

On Schedule: Yes                
Induction Date: 19/FEB/22
Contract Delivery Date:  08/MAR/22
Aircraft Status (Past 24 hours): 

388 Open, 72 closed past 24 hrs. 39 burn rate.

 EWIS ON PASSENGER CABIN


 LH WING LUBRICATION
 RUDDER LUBRICATION
 RH THRUST REVERSER ACTUATOR EXTERIOR INSTALL

Aircraft Status (Next 24 hours) 

 HEAT EXCHANGER NGS REPLACE


 PASSENGER CABIN BLANKET INSTALL
 ATTENTION TO NRC ISSUED BY BOEING

ATL Support   

 NONE    

Material Issues  

 07 ITEMS    

Engineering Issues  

 03 ITEMS    
0697 (L2) Day 19 of 25

On Schedule: YES             
Induction Date: 06/FEB/22
Contract Delivery Date: 04/MAR/22
Aircraft Status (Past 24 hours):

133 Open, 17 closed past 24 hrs. 19 burn rate.

 RELIEF VALVE CHECK


 RELIEF VALVE CHECK
 LH THRUST REVERSER INSTALLATION
 LH ENGINE CONNECTION
 R4 DOOR SLIDE INSTALLATION

Aircraft Status (Next 24 hours)

 PASSENGER CABIN NRC´S ATTENTION


 LH & RH SPOILERS ADJUSTMENT
 PASSENGER CABIN NRC´S ATTENTION
 LH & RH SPOILERS ADJUSTMENT

ATL Support

 NONE

Material Issues
     
 04 ITEMS

Engineering Issues
   
 04 ITEMS
9514 (C2) Day 01 of 20

On Schedule: YES             
Induction Date: 26/FEB/22
Contract Delivery Date: 16/MAR/22
Aircraft Status (Past 24 hours):

552 Open, 70 closed past 24 hrs. 313 burn rate.

 WASHRACK
 CARGOS COMPARTMENT OPEN UP
 TAILCONE REMOVAL
 WINGS OPEN UP
 SLIDES DEACTIVE AND REMOVAL

Aircraft Status (Next 24 hours)

 EMPENNAGE OPEN UP
 FUNCTIONAL AND OPERATIONAL TEST

ATL Support

 NONE

Material Issues
     
 20 ITEMS

Engineering Issues
   
 00 ITEMS
3855 (C3) Day 11 of 15

On Schedule: Yes                
Induction Date: 14/FEB/22
Contract Delivery Date:  01/MAR/22
Aircraft Status (Past 24 hours):  

94 Open, 47 closed past 24 hrs. 31 burn rate.

 WINGLETS TEST
 FLAP SENSOR HEALT CHECK
 AFT CARGO COMPARTMENT FINAL

Aircraft Status (Next 24 hours)

 AUTOLAND
 WEATHER RADAR ANTENNA REPLACEMENT

ATL Support

 NONE

Material

 10 ITEMS

Engineerin Issues

 01 ITEM
9574 (C) Day 17 of 20

On Schedule: Yes                
Induction Date: 08/FEB/22
Contract Delivery Date:  28/FEB/22
Aircraft Status (Past 24 hours):  

132 Open, 22 closed past 24 hrs. 22 burn rate.

 AIR CONDITIONING PACKAGE TEST


 GALLEY 1 INSTALLATION

Aircraft Status (Next 24 hours)

 RH MLG DOOR ADJUSTMENT


 NRC ROBBERIES ATTENTION

ATL Support

 NONE

Material

 12 ITEMS

Engineerin Issues

 02 ITEM

6819 (H) DAY 23 OF 40 


On Schedule: Yes                
Induction Date: 01/FEB/22
Contract Delivery Date:  14/MAR/22
Aircraft Status (Past 24 hours):  

438 Open, 42 closed past 24 hrs. 27 burn rate.

 DRY BAY CLOSE UP


 L1/R1 SCUFF PLATES INSTALLATION
 PASSENGER CABIN FLOOR PANELS INSTALLATION
 IN PROCESS L1 DOOR SNUBBER INSTALLATION
 PASSENGER CABIN SIDEWALLS INSTALLATION

Aircraft Status (Next 24 hours)

 R1, L4 DOOR SCUFF PLATES INSTALLATION


 LH/RH FUEL TANKS CLOSE UP
 R1 DOOR ADJUSTMENT

ATL Support

 NONE

Material Issues

 17 ITEMS

Engineering Issues

 13 ITEMS