1 The amount of Earnest money is about __________% of the estimated value.


2 The smallest unit of PWD organization is under charge of____________.
3 The full form of NIT is___________________.
4 Item rate contract is also known as, unit rate contract. (True/False)
5 Technical Sanction is required before Financial Sanction. (True/False)
6 The time of completion is mentioned in tender form. (True/False)

2. Answer any one from the following: 5×1=5

a) Give the flow chart of PWD Organization.

b) State the duties and responsibilities of Sub-Assistant Engineer.

c) Prepare a list of contract document.