Professional Documents
Culture Documents
T1) Payback period is the amount of time it takes you to recover your initial
investment in a project
T2) There is a tendency for different departments or functions to compete for
scarce resources in a zero-sum game when bottom-up budgeting is used to
develop a project budget.
T3) Marketplace conditions influence project initiation.
T28) In a sensitivity analysis, each risk driver is varied at a time, either in small
increments or from optimistic to pessimistic estimates while keeping all other
drivers fixed, to see the effect of variation of the risk driver. The process is
repeated for all risk drivers.
T29) Sudden increases in material costs should be covered in your organization’s
disaster recovery plan.
Multiple-choices questions
MC2) A systems analyst is paid at the rate of $500/hour and will be needed for
40 hours. Her employer uses an overhead multiplier of 60% and does not
factor in personal time. Her total direct labor cost that should be billed at:
A) $20,000.
B) $32,000.
C) $10,250.
D) $40,500.
MC3) Workers paid $150.00 per hour with an overhead charge of 1.45 and a
personal time allowance of 1.15, have what total direct labor cost for an 8-
hour workday?
A) $1513.00
B) $1740.00
C) $2001.00
D) $2368.00
MC5) An activity with a learning rate of 0.9 takes 20 hours for the first iteration.
How long will it take to complete this task for the 10th time?
A) 0.9 hours
B) 10 hours
C) 14 hours
D) 17 hours
MC6) If it takes 50 hours to complete the first unit and the company knows from
experience that the learning rate should be 0.85, how fast can they be
expected to finish the tenth unit?
A) 29 hours
B) 38 hours
C) 50 hours
D) 356 hours
MC7) It took 80 hours of analysis to complete the first phase, but the second
phase was done in 74 hours. If this learning rate continues, then the 8 th
analysis should take a mere:
A) 63 hours and 20 minutes, give or take.
B) 68 hours and 30 minutes, give or take.
C) 57 hours and 15 minutes, give or take.
D) 52 hours and 45 minutes, give or take.
MC10) An early warning signal for the potential of an overdrawn budget is created
when:
A) activity-based costing cannot identify drivers.
B) a bottom-up budget never makes it up the chain of command.
C) contingency funds are applied for.
D) a top-down process moves too quickly down to the functional
managers.
MC11) You work for a road bituminous paving contracting firm. You are asked to
do a job in Jilin, north east China. Which enterprise environmental factor
do you need to pay closest attention to?
A) Availability of resources
B) Weather
C) Infrastructure
D) Company culture
MC12) Your firm has an enterprise architecture which is tightly controlled. All new
development projects must comply with the enterprise architecture. This is
an example of:
A) An enterprise environmental factor
B) A constraint
C) A stakeholder
D) An organizational process asset
MC13) Which estimating technique is best to use if you know the standard usage
rate for a resource (e.g. how many metres of cable per hour an electrical
installer can pull) to estimate the duration of an activity?
A) Analogous estimating
B) Parametric estimating
C) Three-point estimates
D) Reserve analysis
MC15) You are the project manager for a concrete batching plant project. You have
been hired by your organization specifically because of your vast
experience with the technology and with projects of this nature. The project
team is aware of your experience. What type of power do you likely have
on this project?
A) Formal power
B) Coercive power
C) Expert power
D) Referent power
Short questions:
S4) Which planning process group process output is the result of project
deliverable decomposition into manageable components, called work
packages?
What are the basic purposes of the Project Management Plan?
Name some of the subsidiary plans to the Project Management Plan.
S5) What is the method of cost estimating which uses a scalable, mathematical
model?
S6) What is the difference between “above the line” and “below the line” costs?
S7) What is the Argyris’ “Theory of Adult Personality”?
S8) The IRR (Internal Rate of Return) of two different projects are calculated to
be the same. However, one is calculated to have negative NPV (Net Present
Value) while the other one is calculated to have positive NPV. What is the
reason?
S9) The payback periods (calculated by simple payback method) of two different
projects are the same. One is calculated to have a negative NPV while the
other one positive. What is the reason?
S10) How to calculate Return on Investment?
S11) What are the 4 main functions of management?
S12) What are the five most salient characteristics of a project which differentiate
project work from routine process work?
Explain why you choose your five characteristics instead of other features.
Long questions
3) What learning rate is being demonstrated if the first unit takes 15 hours and the
third unit takes 14 hours to complete?
[Ans: 0.9574]
4) Big Mike has to prepare a bid for the swimming pools to be placed in every
backyard in a new housing addition. Each swimming pool represents only a slight
variation on the other, so there is a good opportunity to leverage learning effects
in the bid process. A swimming pool installation can be broken down into four
major steps: excavation, concrete, plumbing, and finish work. Mike has found
the best contractors and asks each of them how long it will take to complete work
on the first pool and what their learning rates are. Amazingly, each contractor is
intimately familiar with learning curve theory and knows what his learning rate is
for this type of work. This information is summarized in the table.
How many manhours will it take to complete the 2nd pool? [83.7]
How many manhours will it take to complete the 25th pool? [55.7]
How many manhours will it take to complete all 25 pools? [1623]
5) What are parametric cost estimates and how are they developed?
6) What is the relationship between WBS, scheduling, and budgeting?
7) How are top-down and bottom-up budgets created? What advantages does
each approach hold over the other?
8) What is a budget contingency and state any three reasons it might be useful?
9) What are three benefits of using contingency funds?
10) Lists ways that changes in the project specification (and thereby the costs and
time scale) can be required, and state why this can result in problems.
11) What methods can be employed to classify costs?
12) What are the logical stages for a bottom up estimate?
13) What are common reasons of project cost overruns?
14) Define contingency thinking. How can it be applied to management?
15) What is the relationship between the environment and an organization in the
Open System View?
16) (a) State some of the benefits of delegation.
(b) Describe the 5 main approaches of delegation.
(c) What are the five key aspects of successful delegation?
(d) In what kinds of environment will delegation and empowerment be most
helpful to an organization?
18) a) Briefly describe the checklist model, simplified scoring model, the Analytical
Hierarchical Process and the Profile Model used for projects selection.
b) What are the relative advantages and disadvantages of these non-financial
projects selection models?
c) How do AHP address the pitfalls of checklist model and simplified scoring
model? What other problems does the AHP produces?
T7) False – even when a project is able to payback, the NPV can still be negative, if
the discount rate is high.
T8) False – even when the NPV is negative, the IRR can be positive. However, in this
case, the IRR is lower than the discount rate.
T9) True
T10) False – when NPV of a project is 0, the IRR is equal to the discount rate.
T11)True. Project must have a start date and an end date. Routine work cannot be
classified as a project.
T12) True, project selection methods are tools and techniques of the Initiation
Process
T13) False. Project selection methods are tools and techniques of the Initiation
Process, but not input to the Initiation Process.
T14) True. Project selection criteria are inputs to the Initiation Process.
T15) False. Public perception, financial return, customer loyalty etc. are outcome
of the projects themselves and cannot be determined by the project selection methods.
T16) False. Cost estimates, duration estimates, baselines for performance
measurement and controls are developed in the Scope Management Process.
T17) True. Scope planning is to progressively elaborate and document the project
scope that produces the product of the project.
T18) True. The lowest level in a WBS should consists of work packages which can
be estimated both in terms of time and cost, which performance can be easily
monitored. There should be only ONE ownership for each work package.
T19) False. Projects must have a start date and an end date
T20) False
T21) False – a project is to produce a unique product
T22) True – risk is highest in the initiating phase while risk impact will be highest
towards the end of executing phase
T23) True – most of the cost is spent is spent in the executing phase (in the Integration
Process of the Executing Process Group), but amount at stake is of course highest in
the closing stage
T24) False – WBS is a top down approach – with the target of chopping the project up
into smaller, manageable work packages which can then be further sub-divided into
deliverables and activities so that cost and time can be assigned to each for planning,
budgeting and for control. Each work package can be seen as a small project of its
own, but it can only have one single ownership – responsibility of which is clearly
defined. In this way the scope of work will be more clearly defined and key tasks will
less likely be omitted.
T25) True – a poorly defined statement of work does not reflect what the client really
wants and will easily result in scope creep.
T26) False – it is most imperative that honesty is exercised when preparing budget
estimates.
T27) True – while people may dream that budgets can be exact, futuristic and neatly
arranged, these are too good to be true. Budgets should be flexible.
T28) True
T29) False – project specific risk events should be covered in the project’s risk
management plan and risk register.
T30) False. A project must be initiated by someone external to the project. Likewise,
the project charter must be authorized by someone external to the project.
T31) True – the scope statement does include project objective, cost, time and quality
performance requirements.
T32) True – the scope statement provides a basis for development of WBS although
it is not directly affiliated with the work breakdown structure (WBS).
T33) True – the scope statement can sometimes be the basis of a contract between
the buyer and seller
T34) False – scope statement can sometimes be developed by a functional manager
T35) False – project life cycle consists of several project phases, viz conceptualization,
planning, execution (and control), and closing.
T36) False
T37) True – project phases added together becomes a project life cycle.
T38) False
MC1) D taxes
MC2) B $32,000
MC3) C $2001.00
MC4) B construction equipment rental
MC6) A 29 hours
MC7) A) learning rate = 74/80=0.925, time for the 8th iteration is
MC8) (A) The project plan is supported by WBS, budget and schedule.
MC9) B Top-down budgeting
MC10) C – when contingency money is applied for, it gives a warning signal for the
potential of an overdrawn budget.
MC11) B weather – in areas with dire bitter cold climate, weather is always an EEF.
MC13) B) – Parametric estimating uses know historical data, such as production rates,
to estimate. Answer A is incorrect because analogous estimating uses comparison
with other, similar project work.
Answer C is incorrect because the three-point estimate use best, worst, and most likely
estimates to calculate duration:
a + 4m + c
D=
6
where D is the estimated activity duration, a is the most pessimistic estimate, c is the
most optimistic estimate, and m is the most likely duration.
Answer D is incorrect because it refers to the process of including contingency
reserves into estimates, not actually calculating estimate.
MC15) C – Expert power – it is good to have expert power. Unluckily one person
cannot be expert in all aspects of a project operation. Therefore, it is often necessary
for a project manager to exercise other types of power, e.g. personal power.
S2) Future value, interest rate (or discount rate), number of time periods
S4) The Work Breakdown Structure (WBS) is the result of decomposing work into
smaller, more manageable components until the work and deliverables are defined to
the work package level.
The Project Management Plan is the result (output) of the develop project
management plan process that documents the actions necessary to DEFINE,
PREPARE, INTEGRATE, and COORDINATE all subsidiary plans (according to
PMBOK)
The subsidiary project management plans could include:
- Project scope management plan
- Requirements management plan
- Cost management plan
- Quality management plan
- Process improvement plan
- Human resource plan
- Communication management plan
- Risk management plan
- Procurement management plan
S8) One possible reason is that the discount rate (made up of inflation rate, interest
rate, cost of capital etc.) is higher than the calculated IRR – in this case, the NPV of
that project will be negative. This can happen when we are comparing two different
investments in two different countries where the inflation rate can be different.
Furthermore, cost of capital (e.g. bank loan interest rate) can also be different from
project to project – riskier project typically requires higher interest rates from banks. A
very high interest rate will also result in a negative NPV, if the company is able to afford
the interest rate at all.
S9) Again, one possible reason is because of different discount rate due to different
cost of capital, for example.
S12)
Salient characteristics which differentiate projects from routine process work include:
a) there are always the triple constraint of TIME/COST/SCOPE, and
RESOURCES constraints,
b) project is a TEMPORARY, TRANSIENT endeavour having defined life span
with a start date and an end date,
c) undertaken for a business case to achieve an established OBJECTIVE, for a
UNIQUE product, frequently involving CHANGES,
d) NON-ROUTINE work, which always includes an element of UNCERTAINTY
and risk,
e) it operates in a temporary structure in which authority of the project
manager is FUZZY.
Please note that the following points alone are not absolutely correct answers:
- emergency,
- delivering benefits,
- mission focused,
- common goals,
- integrating,
- social construction
Certain routine work may also involve these elements to some extent.
Furthermore, points like multi-disciplined work, multi-disciplinary, ALONE, are
incorrect as well because they may also be applicable to routine process work.
(not necessarily similar projects). Parametric estimation takes older work and uses a
multiplier to account for the impact of inflation, labor and materials increases, and other
reasonable costs. Cost drivers, or unit rates, come from older work – older work can
be your company’s own work or can be from other published sources.
6) The central goal of a budget is the need to support, rather than conflict with the
project's and organization's goals. The project budget is a plan that identifies the
allocated resources, the project's goals, and the schedule that allows an organization
to achieve those goals. The project budget must be coordinated with the project
activities defined in the work breakdown structure, as the WBS sets the stage for
creating the project schedule and the budget assigns the necessary resources to
support the schedule.
7) Top-down budgeting requires direct input from the organization's top management;
in essence, this approach seeks to first ascertain the opinions and experiences of top
management regarding estimated project costs. Bottom-up budgeting begins
inductively from the work breakdown structure to apply direct costs to project activities
that are then aggregated, first at the work package level, then at the deliverable level,
at which point all task budgets are combined, and then higher up the chain to create
an overall project budget. Top-down budgeting has the benefit of experienced senior
personnel getting directly involved in project estimation, but can create friction
between departments, functions, and managers at lower levels in the organization as
they scramble for the largest share of the budget that they can grab. Bottom-up
budgeting emphasizes the need to create detailed plans and facilitates coordination
between project managers and functional department heads. Unfortunately, bottom-
up budgeting reduces top management's control of the budget process to one of
oversight and may result in a disconnect between their strategic plans and the
direction the project is taking.
9) Use of contingency funds is at first glance not a cause for celebration; however,
there are three benefits derived from the use of these funds.
1) The first benefit is that their use recognizes that the future contains unknowns and
the problems that arise are likely to have a direct effect of the project budget. The
project has a cushion of contingency to combat the time and money variance.
2) The second benefit is that the company has already made provision for extra
expense and as these funds are used, it opens management's eyes to the
possibility of a significant budget increase on the horizon.
3) Finally, application to the contingency funds givens an early warning signal of
potential overdrawn budget so management can take a close look at the project
and begin formulating additional plans in case the negative trend continues.
17)
Chiefly relative merits of the simple payback period financial model are:
☺ Simple
☺ Easy to understand
☺ Can be discounted to take into account of interest rate, inflation (discounted
payback)
Limited window for comparison
Conflicting conclusion if comparing total life cycle profits against payback period
The payback period model tends to favour projects of quicker return but not
necessarily those with longer term benefits.
Chiefly relative merits of the net present value financial model are:
☺ Take into account the time value of cash flow
☺ Enable direct comparison of projects on the same basis – on today
☺ Allow for inflation and deflation
Mathematically more complicated
Discount rate can be uncertain especially for the distant future
Major relative merits of the internal rate of return financial model are list below:
Take into account of the time value of cash flow
No need to pre-determine a discount rate
Enable direct comparison between projects
Bench marked against corporate-wide capital cost
Mathematically even more involving than NPV
Benchmark can be misleading because of the differences in project nature
18) b)
Advantages of the checklist model:
a. Easy to tie critical strategic goals for the company to various project alternatives
b. An easy to comprehend and use method
Limitations of the checklist model:
i. Intuitive and not accurate
ii. Wrong to treat evaluations on scale of real numbers. For example, difference
between 3 and 2 is not the same as the difference between 2 and 1. Also how
much difference is there between 3 and 2?
iii. Dependence on the relevance of the selected criteria and the accuracy of the
weightings