Professional Documents
Culture Documents
Faculty of Engineering
Cost Estimation
and Budgeting
MEBS6003
K.F. Chan (Mr.) 2
Best
guess Final known cost
MEBS6003
K.F. Chan (Mr.) 6
Cost Estimation
and Budgeting – Road Map
◼ Plan Cost Management – from Project Management
Plan and Project Charter to Cost Management Plan
◼ Estimate Costs – from the above + Human Resource
Management Plan, Scope baseline, Project Schedule,
Risk Register to Activity Cost Estimates and Basis of
Estimates
◼ Determine Budget – from the above to Cost
Baselines and Project Funding Requirements
◼ Control Cost
MEBS6003
K.F. Chan (Mr.) 7
▪ Travel
MEBS6003
K.F. Chan (Mr.) 8
MEBS6003
K.F. Chan (Mr.) 9
MEBS6003
K.F. Chan (Mr.) 10
10
Cost Classifications
MEBS6003
K.F. Chan (Mr.) 11
11
Cost Estimation
12
Which approach?
◼ Knowledge of the firm’s industry
◼ Ability to mange cost variables
◼ History of successful projects the firm
possesses
◼ Number of similar projects undertaken
◼ Knowledge and resourcefulness of
project managers
◼ Company’s budgeting requirements
MEBS6003
K.F. Chan (Mr.) 13
13
14
MEBS6003
15
15
MEBS6003
K.F. Chan (Mr.) 16
16
MEBS6003
K.F. Chan (Mr.) 17
17
Estimation accuracy
◼ Order of Magnitude estimate -25 to
+75%
◼ Preliminary estimate -15 to +50%
◼ Budget estimate -10 to +25%
◼ Definitive estimate -5 to +10%
MEBS6003
K.F. Chan (Mr.) 18
18
Top-down estimating
Considers
the The project
whole
project
first.
• Intuitive
Greater • Probably ball-park
detail • Useful when there is:
might - little time available
not be - little information
possible
19
Top-down estimating
☺ Brings in budgetary discipline and
control.
Difficulty in translating long range
budgets into short range budgets.
Competition among departments for
budget
Analogous estimate is an example of
top down estimating
MEBS6003
K.F. Chan (Mr.) 20
20
Bottom-up estimating
21
Bottom-up estimating
☺ Clear flow of information and the use of
detailed data such as cost, schedule,
resources information.
Reduces top management’s control of
the budgetary process to one of
oversight.
Fine tuning can be time consuming.
MEBS6003
K.F. Chan (Mr.) 22
22
Parametric estimation
MEBS6003
K.F. Chan (Mr.) 23
23
Prime cost
24
Prime cost
25
Prime cost
Overhead
Contingency (grey area)
Escalation
P C sums (if any)
Selling price
K.F. Chan (Mr.)
26
Prime cost
Overhead
27
Prime cost
Overhead
28
Prime cost
Overhead
Contingency (grey area)
A contingency allowance is often added in an
attempt to offset all or some of the inevitable
errors in design and building during the project.
29
Prime cost
Overhead
Contingency (grey area)
Escalation
AAn
Now escalation
P allowance
to consider
contingency C sums
two
sum may
often be added
(ifadded
any)
isbelow-the-line to
tocosts:
offset
offset future rises in labour and
the costs of possible design and buildmaterial
costs caused
mistakes duringbythe
cost inflation. life of the
forthcoming
Mark-up for profit
project. This
This is not is usuallywhen
necessary a lowthe
percentage of
annual cost
the above-the-line
inflation rate is verycosts, set
low or asprojects
for high as of
competitive Selling price
project pricing will allow.
short duration.
K.F. Chan (Mr.)
30
31
Example of a PC sum.
Prime cost
A fixed price has been quoted for a flat roof
repair.
Overhead
But a PC sum has been added saying that an
additional cost of £60 per square
Contingency (grey metre
area)will be
charged if the underlying decking is found to be
rotted and needingEscalation
replacement.
32
Prime cost
Overhead
Contingency (grey area)
Escalation
P C sums (if any)
The last three items:
• Contingency
• Escalation
• PC sums
K.F. Chan (Mr.) are known as below-the-line costs.
33
Prime cost
Overhead
Contingency (grey area)
Escalation
P C sums (if any)
Selling price
K.F. Chan (Mr.)
34
35
Responsibility of higher
management – not dept
managers
(accountability without
corresponding power)
Overhead
Contingency Hold these budgets in
reserve and draw down
Escalation later, if needed
36
Prime costs £
Direct labour cost 100 000
Labour burden 20 000
Direct materials cost 150 000
Materials burden 20 000
Direct expenses 10 000
Estimated prime cost 300 000
Overheads at 66.67% 200 000
Estimated cost of sales 500 000
Below-the-line items
Escalation allowance 2% 10 000
Contingency 5% 25 000
Adjusted cost of sales 535 000
40% mark-up for profit 214 000
Proposed selling price 749 000
Provisional items
37
• The optimist
estimates usually too low
• The pessimist
estimates usually too high
People as estimators
• The waverer
totally unreliable - no set pattern
• The genius
always right but a very rare animal
MEBS6003
K.F. Chan (Mr.) 38
38
Direct labour by
standard grades
39
40
Add below
the line items
Estimates are
now budgets
Review / agree
the estimates
Make initial
estimates
Logical
List all the
cost items stages for
Define and
code the WBS a bottom-up
Define cost estimate
the project
MEBS6003
K.F. Chan (Mr.) 41
41
Time-phased budget
◼ The time-phased budget allocates costs
across both project activities and the
anticipated time in which the budget is
to be expended.
MEBS6003
K.F. Chan (Mr.) 42
42
Learning curve
◼ The learning curve originated in the time of
Frederick Taylor (1856-1915), often called
the father of industrial engineering and time
study in industrial applications, and Henry
Ford (1863-1947), the father of the
assembly line. Taylor noticed that when
workers were given a piece of work to do,
the time that it took them to do the work
decreased each time they repeated the piece
of work.
43
Learning Curves
Each doubling of output results in a
reduction in time to perform the last
iteration.
Tx = T1 X b
where
Tx = time requiredfor the x unit of output
T1 = time requiredfor the first unit of output
X = the number of units to be produced (iterations)
log(learning % ) log LR
b = learning curve slope = =
log 2 log 2
MEBS6003
LR = learning curve % 44
44
45
Learning curve
◼ Henry Ford made great use of this information in developing
the assembly line. If very short work operations are used, the
amount of time that it takes to double the number of times to
do the work becomes short as well. What this means is that if
we were to design work so that the time interval to do the
work is very short, people would come down the learning
curve very quickly and reach the flat part of the curve. At
this point they could be considered to be fully productive on
their work assignment.
◼ What Ford wanted was a way to incorporate new people into
his factory with a minimum of training and experience. By
making the work tasks very short, people would become
proficient at them very quickly. It was important for him to
be able to bring in a new person with very little experience or
training to learn the job and do the job proficiently as quickly
as possible so that he did not rely on the labour force
K.F. Chan (Mr.)
46
47
48
49
Control Cost
MEBS6003
K.F. Chan (Mr.) 50
50
51
HONESTY
◼ PADDING - Exaggerates activity
duration and costs – padding allows
plenty of time and contingency for the
work to be completed
◼ As the Parkinson’s Law states, “Work expands so
as to fill the time available for its completion”, the
trouble with padding is that the task will magically
expand to require the exaggerated activity duration
and cost available.
MEBS6003
K.F. Chan (Mr.) 52
52
Remarks on Budget
Contingencies
The allocation of extra funds to
cover uncertainties and improve
the chance of finishing on time.
Contingency reserve to cater
for known unknowns
Management reserve to cope
with unknown unknowns
MEBS6003
53
53
MEBS6003
K.F. Chan (Mr.) 54
54
MEBS6003
K.F. Chan (Mr.) 55
55
Appropriateness of applying
contingency funds in cost
estimation
◼ Recognizes that the future
is unknown
◼ Provision in the plan for
cost increase
◼ Application of contingency
fund gives an early
warning of potential
overdrawn budget
MEBS6003
K.F. Chan (Mr.) 56
56