Professional Documents
Culture Documents
Oleh:
Helena Novitasari Lasol*), Yuli Suharnoto*), Dadang Ridwan**), Marasi Deon J**)
ABSTRACT
Sprinkler irrigation network could be a good investment when designed, installed, maintained and managed
well. But manually calculation consumes much time and gives rise to human error. Therefore, this study aims
to evaluate the performance of sprinkler irrigation using secondary data and the data was analyzed by using
simulation of EPANET 2.0 software. This study was conducted on irrigation network in the village of Tenilo,
Gorontalo and the villages of Akar-akar, NTB. The simulation resulted the average pressure at both locations
was excess of the recommended optimum pressure 40 m, but it was not excess the maximum recommended
pressure 65 m. The variation pressure on each location were 2.82 m and 9.35 m. Debit issued by sprinkler
was also nearing discharge plan 9.11 liters/second. The velocity of the flow both locations was not different
much. It was less than maximum allowable speed 3 m/s, it meant that the network was safe from abrasion
and water hammer on a pipe. Based on the results, simulation sprinkler irrigation network installed in the
village of Tenilo and the villages of Akar-akar have met the criteria of hydraulic limitation design of sprinkler
irrigation.
ABSTRAK
Jaringan irigasi curah dapat menjadi investasi yang baik apabila dirancang dengan baik, dipasang,
dipelihara secara tepat. Perhitungan secara manual memakan waktu dan menimbulkan human error.
Oleh karena itu, penelitian ini bertujuan untuk mengevaluasi kinerja (performance) irigasi curah
melalui simulasi hidrolik menggunakan perangkat lunak EPANET 2.0 dengan menggunakan data
sekunder. Penelitian ini dilakukan pada jaringan irigasi curah yang telah terpasang di Desa Tenilo,
Gorontalo dan Desa Akar-akar, NTB. Simulasi menghasilkan tekanan rata-rata pada kedua lokasi
melebihi dari tekanan optimum yang direkomendasikan yaitu 40 m, namun belum melebihi tekanan
maksimum yang direkomendasikan yaitu 65 m. Variasi tekanan pada masing-masing lokasi sebesar
2.82 m dan 9.35 m. Debit yang dihasilkan juga hampir mendekati debit rencana yaitu 9.11 liter/detik.
Kecepatan aliran antara kedua lokasi tidak berbeda jauh. Kecepatan aliran pada kedua lokasi kurang
dari kecepatan maksimum yang diizinkan yaitu 3 m/detik, berarti jaringan ini aman dari abrasi dan
water hammer pada pipa. Berdasarkan hasil simulasi menunjukkan bahwa jaringan irigasi curah yang
telah terpasang di Desa Tenilo dan Desa Akar-Akar telah memenuhi kriteria batasan hidrolik dalam
mendesain sistem jaringan irigasi curah.
Kata Kunci: debit, EPANET 2.0, irigasi curah, kecepatan aliran, tekanan.
Gambar 1 Skema jaringan irigasi curah (Prastowo 2002 dalam Hadi 2010)
2.2 EPANET 2.0 kali diperkenalkan padan tahun 1993 dan versi
yang baru diterbitkan pada tahun 1999
EPANET 2.0 adalah program komputer yang (Sudirman, 2012).
berbasis windows yang merupakan program
simulasi dari perkembangan waktu dari profil Output yang dihasilkan dari program EPANET
hidrolis dan perlakuan kualitas air bersih dalam 2.0 ini antara lain debit yang mengalir dalam
suatu jaringan pipa distribusi (Agustina, 2007). pipa, tekanan air dari masing masing
EPANET dikembangkan oleh Water Supply and titik/node/junction (Agustina, 2007). Hasil
Water Resources Divission USEPA’S National running dari program ini dapat berupa peta
Risk Mangement Research Laboratory dan
pertama
IV. HASIL DAN PEMBAHASAN hektar. Apabila dilihat dari peta kontur, daerah
ini merupakan daerah yang memiliki elevasi
Provinsi Gorontalo merupakan daerah agraris permukaan tanah yang tidak datar atau
dengan keadaan topografi datar, berbukit-bukit berlereng. Berdasarkan hasil analisa sifat dan
sampai dengan bergunung dengan kondisi tipe karakteristik tanah lokasi Arungan Bali desa
iklim A sampai dengan tipe iklim E menurut Akar Akar kecamatan Bayan Lombok Utara,
pembagian tipe iklim Smith & Ferguson, tekstur tanah pada daerah ini mempunyai
sehingga berbagai jenis tanaman pangan dapat kadar fraksi pasir yang tidak terlalu tinggi.
tumbuh dengan baik di daerah ini (Ridwan et al.
2010). Berdasarkan karekteristik tanah pada masing-
masing lokasi, maka tanaman yang ditanam
Lokasi dipasangnya jaringan irigasi curah pada kedua daerah ini yaitu tanaman jagung.
terletak pada 0° 37’ 33” Lintang Utara dan 122° Tanaman jagung memiliki kebutuhan air
56’ 33” Bujur Timur. Luas lahan jaringan irigasi puncak pada fase pertengahan musim sebesar
curah tersebut yaitu 8 hektar. Apabila dilihat 5.405 mm/hari. Pada Desa Tenilo, karakteristik
dari topografinya, lokasi ini merupakan daerah tanah yang liat dan berpasir menyebabkan
dengan topografi relatif datar. Berdasarkan interval irigasi hanya membutuhkan waktu
data analisis fisik tanah, tekstur tanah di lahan maksimum 2 hari pada fase pertumbuhan awal
tersebut liat berpasir yang memiliki kapasitas dengan waktu pemberian air maksimum 1 jam
menahan air sebesar 133-208 mm/m. (Balai pada fase pertumbuhan pertengahan musim.
Irigasi, 2009). Sedangkan di Desa Akar- akar, tanah berpasir
menyebabkan interval irigasi yang lebih lama
Lokasi kedua pemasangan jaringan irigasi yaitu 5 hari pada semua fase pertumbuhan
curah terletak di Arungan Bali Desa Akar-akar kecuali pada fase pertumbuhan awal dengan
Kecamatan Bayan, Kabupaten Lombok Utara, waktu pemberian air maksimum 4 jam pada
Provinsi Nusa Tenggara Barat (NTB). Lokasi fase pertumbuhan pembungaan. Tabel 3
tersebut terletak pada 8° 13’ 31.89” Lintang menampilkan data dasar yang digunakan untuk
Selatan dan 116° 21’ 25.99” Bujur Timur. Luas perencanaan desain sistem irigasi curah.
lahan jaringan irigasi curah kurang lebih 18
Berdasarkan data debit dari setiap sprinkler liter/detik dan tekanan 40 m. Sehingga,
pada Tabel 3, spesifikasi sprinkler yang paling koefisien emiter dapat diperoleh berdasarkan
sesuai dengan debit tersebut yaitu debit sebesar
persamaan 1 yaitu 1.4 liter/detik/m0.5.
9.11
Tekanan Sprinkler (Bar) Radius Pancaran (m) Diameter Basah (m) Debit (Liter/detik)
3.5 34.2 68.4 8.58
4.0 36.2 72.4 9.11
4.5 37.4 74.8 9.24
5.0 40.4 80.8 9.48
5.5 42.6 85.2 10.00
6.0 44.5 89.0 10.56
6.5 46.2 92.4 11.16
Tabel 6 Karakteristik komponen sistem jaringan irigasi curah di Desa Tenilo, Gorontalo
Koefisien
Komponen Panjang Diameter Koefisien
Jenis Kekasaran Hazen
sistem (m) (mm) minor loss
William
Pipa utama 1 60 127 PVC 150 0.2
Pipa utama 2 10 127 PVC 150 0.6
Pipa utama 3 56 127 PVC 150 0.6
Pipa utama 4 66 127 PVC 150 0.6
Pipa lateral 1 66 101.6 PVC 150 0.6
Pipa lateral 2 30 101.6 PVC 150 0.6
Riser 1.5 76.2 Galvanis 120 0.6 atau 0.8
Katup 76.2 0.2
Untuk skema sistem irigasi curah di Desa Akar- digambarkan sebagai junction pada 27 lateral
Akar dapat ditampilkan melalui software yang digambarkan sebagai link, dan 86 pipa.
EPANET
Elevasi permukaan tanah pada sprinkler
2.0 seperti pada Gambar 3 dan karakteristik terendah yaitu 41 m dan elevasi permukaan
komponen sistem pada Tabel 7. Gambar 3
tanah pada sprinkler tertinggi yaitu 60 m, serta
menunjukan konfigurasi jaringan irigasi curah lokasi umur berada pada elevasi permukaan
yang digunakan untuk simulasi. Pada jaringan tanah 51 m.
tersebut terdapat 34 posisi sprinkler pipa yang
Gambar 3 Layout sistem irigasi curah di Desa Akar-akar, Nusa Tenggara Timur
Koefisien
Kekasaran Koefisien
Komponen sistem Panjang (m) Diameter (mm) Jenis
Hazen minor loss
William
Pipa utama 66 127 PVC 150 0.6
55 127 PVC 150 0.6
33 127 PVC 150 0.6
Pipa lateral 66 101.6 PVC 150 0.6
58 101.6 PVC 150 0.6
36 101.6 PVC 150 0.6
33 101.6 PVC 150 0.6
30 101.6 PVC 150 0.6
28 101.6 PVC 150 0.6
24 101.6 PVC 150 0.6
8 101.6 PVC 150 0.6
Riser 1.5 76.2 Galvanis 120 0.6
Katup 76.2 0.2
Sumber: Balai Irigasi Bekasi 2009
4.1 Tekanan dan Debit boleh melebihi 8 m (20% dari tekanan optimum
Tekanan mempunyai kaitan erat dengan debit sprinkler). Perbandingan hasil simulasi terhadap
aliran. Aliran yang mempunyai tekanan cukup hasil observasi untuk tekanan dan debit di Desa
akan mampu mengalirkan air dengan baik. Akan Tenilo dan Akar-Akar disajikan pada Tabel 8.
tetapi, apabila tekanan dalam pipa tidak Tabel 8 menunjukan bahwa tekanan rata-rata
mencukupi dapat menyebabkan air tidak dapat pada kedua lokasi melebihi dari tekanan
mengalir. Faktor tekanan harus diperhatikan optimum yang direkomendasikan yaitu 40 m.
karena apabila tekanan yang ada pada sistem Nilai tersebut belum melebihi nilai tekanan izin
melebihi batas maka akan terjadi kerusakan maksimum yang direkomendasikan yaitu 65 m,
pipa akibat teknis seperti pipa pecah sehingga berarti air yang dipompa dapat dikeluarkan oleh
mengakibatkan kebocoran (Akbar, 2013). sprinkler untuk memenuhi kebutuhan debit yang
Performansi suatu sprinkler akan baik jika direncanakan sebesar 9.11 liter/detik. Tekanan
mengikuti tekanan operasi yang disarankan oleh yang terlalu besar ini, menyebabkan semburan
pabrik pembuatnya. Jika tekanan operasi lebih air pecah terlalu banyak menimbulkan kabut
kecil atau lebih besar dari yang yang mudah menguap serta hilang ke udara, dan
direkomendasikan maka akan terjadi sebagian besar air akan jatuh dekat sprinkler.
penyimpangan kinerja (Balai Irigasi 2009). Hal tersebut akan mempengarui jarak pancaran
Untuk sprinkler tipe gun sprinkler BIR V.1 dan keseragaman sebaran air. Oleh karena itu,
tekanan operasi optimum yang untuk mendapatkan nilai tekanan yang
direkomendasikan yaitu 4 bar atau 40 m sesuai mendekati tekanan optimum dapat dilakukan
dengan spesifikasi sprinkler yang dipilih. Untuk dengan pengaturan kran pada riser.
variasi tekanan 20% (FAO, 2001) antara titik
terendah dan titik tertinggi yang diizinkan tidak
Simulasi Observasi
Parameter Desa Tenilo Desa Akar-Akar Desa
Desa Tenilo
Terendah Tertinggi Terendah Tertinggi Akar-Akar
Elevasi permukaan
5.5 6.8 41 60
tanah (m)
Tekanan rata-rata (m) 52.51 55.33 53.55 44.20 ≥ 45 35 - 60
Variasi Tekanan (m) 2.82 9.35
Debit rata-rata 8.58 – 10.56 8.58 –
10.15 10.42 10.25 9.31
(liter/detik) 10.56
Simulasi Perhitungan
Parameter Desa Tenilo Desa Akar-Akar Desa Desa
Terendah Tertinggi Terendah Tertinggi Tenilo Akar-Akar
Elevasi permukaan tanah (m) 5.5 6.8 41 60
Kecepatan aliran rata-rata 1.88 -
2.23 2.28 2.04 2.25 1.88 -2.32
(m/detik) 2.32