ITP NO * 002 DISCIPLINE: Civil/Structure REVIEWED BY Justin Landis DATE Click here
Works to enter a
date.
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
1. Document Preparation/Permit/Approvals
2. Work Process
2.1 Reinforcement Bar (Material) Tensile Every batch As per Structural Mill Test H W I/R
strength spec Certificate
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 1 of 4
INSPECTION REQUIREMENTS INSPECTION DETAILS
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
2.4 Formwork (Material) Surface Finish Each Section Visual Structural I/R S -
Specification
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 2 of 4
INSPECTION REQUIREMENTS INSPECTION DETAILS
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
2.6 Surface Preparation Before Cleanliness Each Section Free from I/R S -
Concreting waste/foreign Visual
materials
Compression Each Location Not less than Structural H W I/R Cube Test
Strength (6 specified values Specification Results
Cube Tests, 3
for 7 day & 28
days)
2.8 Concrete Each Truck Delivery less than As per I/R W - Refer Delivery
Duration 2 hours from Approved Tickets
Placing
batching time Method
Statement
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 3 of 4
INSPECTION REQUIREMENTS INSPECTION DETAILS
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 4 of 4