PROJECT Phnom Penh Cambodia Temple PROJECT NO. 5244.009 REV NO.

00

ITP DESCRIPTION Concreting PREPARED BY Kaim Sithaung DATE Click here


to enter a
date.

ITP NO * 002 DISCIPLINE: Civil/Structure REVIEWED BY Justin Landis DATE Click here
Works to enter a
date.

INSPECTION REQUIREMENTS INSPECTION DETAILS

Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A

1. Document Preparation/Permit/Approvals

1.1 Design / Specification Approval Prior to start Submittal Manufacturer R - -


of work Completeness data/spec
sheet

1.2 Risk Assessment / Competencies Approval Prior to start Technical R - -


of work Specification / JSEA/SWMS
Legislation

1.3 Method Statement Approval Prior to start Technical Document R - -


of work Specification Submittal

1.4 ITP Approval Prior to start Submittal Document R R - This Document


of work Completeness Submittal

2. Work Process

2.1 Reinforcement Bar (Material) Tensile Every batch As per Structural Mill Test H W I/R
strength spec Certificate

COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 1 of 4
INSPECTION REQUIREMENTS INSPECTION DETAILS

Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A

2.2 Compressive One Time during As per Concrete H W I/R


Strength trial mix General Note
RCP
Concrete Water Lab Reports
Absorption
Water
Permeability

2.3 Dia. & No. of Each Section As per Structural I/R H -


Structural dwg
Bars dwg

Spacing Each Section ± 25mm Structural dwg I/R H -


Reinforcement Work Lap Length / Each Section Min. 45 dia. Structural dwg I/R H -
Anchorage

Cover Each Section Min. 2 no. Cover Structural I/R H -


blocks per m2 Specification

2.4 Formwork (Material) Surface Finish Each Section Visual Structural I/R S -
Specification

2.5 MEP Fixtures Each Section Visual Approved shop I/R H -


dwg

Dimensions Each Section ± 3mm Structural I/R H -


dwg/
Formwork
Specification

Verticality Each Section ± 3mm Structural I/R H -


dwg/
Specification

COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 2 of 4
INSPECTION REQUIREMENTS INSPECTION DETAILS

Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A

Level Each Section ± 3mm Structural I/R H -


dwg/
Specification

Stability Each Section Rigid Approved shop I/R H -


dwg

2.6 Surface Preparation Before Cleanliness Each Section Free from I/R S -
Concreting waste/foreign Visual
materials

2.7 Mix Proportion Each Truck on As per I/R W - Refer Delivery


Structural
(Concrete Arrival Specification Order
Specification
Grade)

Workability Each Truck on As per Approved Mis Structural I/R W -


(Slump Test) Arrival Design Specification

Concrete Temperature Each Truck on Max. 210 C when Structural I/R W -


Arrival deposited Specification

Compression Each Location Not less than Structural H W I/R Cube Test
Strength (6 specified values Specification Results
Cube Tests, 3
for 7 day & 28
days)

2.8 Concrete Each Truck Delivery less than As per I/R W - Refer Delivery
Duration 2 hours from Approved Tickets
Placing
batching time Method
Statement

COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 3 of 4
INSPECTION REQUIREMENTS INSPECTION DETAILS

Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A

Compaction Each Section Usage of vibrator Structural I/R W -


Specification

Finish Level Each Section Uniform & ± 4mm Structural I/R W -


Specification

Protection Each Section Fully covered with Structural I/R W -


from direct hessian cloth and Specification
sunlight polythene

Curing Each Section Watering for 7 days Structural I/R W -


or use of approved Specification
compound

Inspection Codes: C. CONTRACTOR E. ENGINEER A. THIRD PARTY (TPI)


I: INSPECTION/TEST R: DOCUMENT/REPORT S: SURVEILLANCE H: HOLD POINT (Required Presence notification
required)

W: WITNESS (Notification Required presence not mandatory)

COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009