You are on page 1of 6

EMC Management and Control Plan for Mass Rapid

Transit Railway Project in Malaysia


Syarfa Zahirah Sapuan1a, Ahmed M. Sayegh 2a, Mohd Zarar M. Jenu3a,
a
Research Center for Applied Electromagnetics
Universiti Tun Hussein Onn Malaysia (UTHM), 86400
Parit Raja, Batu Pahat, Johor, Malaysia
1
syarfa@uthm.edu.my
2
ahmed_su2008@yahoo.com
3
zarar@uthm.edu.my

Abstract— Today, railways have numerous communication, system to function satisfactorily in its electromagnetic
navigation, propulsion, power and control systems. These environment, without introducing intolerable electromagnetic
systems are operating in a very limited space resulting in disturbances to anything in that environment [1]. A system is
significant interference issues. Therefore, it is crucial to take into
the account the Electromagnetic Compatibility (EMC) through electromagnetically compatible with its environment if it
the project life time starting in the design stage. This paper satisfies three criteria:
presents briefly the EMC management and control plan of Mass a. It does not cause interference with other systems;
Rapid Transit (MRT) to ensure that the various railway b. It is not susceptible to emissions from other systems;
subsystems can function satisfactorily in their intended c. It does not cause interference with itself.
electromagnetic environment. The EMC approach taken in the
MRT Railway project in Malaysia is outlined in this paper. All
the MRT railway communications systems should not disturb the EMC is concerned with the generation, transmission and
operation of each other or the other nearby systems. These reception of electromagnetic energy. A source produces the
communications systems should not be also susceptible to any emission and a coupling path transfers the emission energy to
intentional/unintentional EMI sources in the MRT railway a receptor. Therefore, there are three approaches to prevent
environment. The EMC management and control plan is helpful interference.
to avoid EMC/EMI issues of MRT such as EMI sources/ victims
a. Suppress the emission at its source;
identification and risk assessment starting from the design to
commissioning. Commonly, all the equipment on the railway b. Make the coupling path as inefficient as possible;
must comply to the relevant EMC railway standards such as c. Make the receptor less susceptible to the emission.
EN50121. Furthermore, cable management is significantly
considered especially for very limited spaces such as tunnels. These three approaches will be implemented in the design
Finally, the necessary mitigation techniques are recommended to and implementation of the communication systems (CS) for
overcome the unexpected EMC challenges which may occur after
Mass Rapid Transit (MRT) railway project in Malaysia.
commissioning.
Therefore, several documentations for rail projects are needed
Keywords— Electromagnetic Compatibility; EMC in Railway; to fulfill the EMC requirement in MRT environment. EMC
Railway; EMC Management; EMC Control Plan. documentation for rail projects as follows:
a. Management and Control plan
I. INTRODUCTION b. Risk Assessment
The population in Klang Valley (KV)- Malaysia is expected c. Procurement Review
to grow to about 10 million by year 2020 based on study d. Design Review and Cable Studies
conducted in 2009 for urban public transport lab. This will e. Test Reports (on-Site test and Laboratory)
drive a critical need for a reliable and efficient integrated f. Final Compliant Documentation
transport system. Therefore, the government of Malaysia has g. Timelines
planned to develop a Mass Rapid Transit (MRT) railway to
meet the demand for efficient transportation system. With The EMC management and control plan is needed in an
numerous mergers in railway industry in the future, Malaysian early stage of the implementation. EMC management is the
railway development by the initiation of the Mass Rapid sets out of the overall scope of EMC activity for a project. It is
Transit Line 2 (MRT2) and Light Rail Transit Line 3; East based on customer requirements, regulatory requirements,
Coast Rail Link and the high-speed rail, a need for a railway and/or technical requirements. In the early stage of the EMC
system operate in satisfactorily is in a very high demand. management plan, it sets out responsibilities, actions,
Basically, EMC is defined as the ability of an equipment or interfaces and documentation required for the project.
Communication system in railway environment are prone to desired between the different systems to ensure every plan is
the EMI. Eugene Rhee [2] propose several studies on the working satisfactorily. Therefore, it is necessary to assign an
EMI/EMC telecommunication intra system between Gimpo EMC coordinator to coordinate the interfacing issue. The
International Airport to Incheon International Airport railway EMC coordinator can be anyone from the railway project team
station. In addition, K.J Satsios [3] reported that there is an and the expertise is not required. The EMC Management team
interference caused to telecommunication cables by nearby comprise of EMC consultant, EMC coordinator and EMC
AC electric traction lines [3]. This issue has been overcome by analysts as shown in Figure 3. The systematic organization are
adopting the FEM calculations method and measurements. able to execute the EMC management and control plan to
Several publications on the EMC in railway issue have been ensure that the EMC requirements are met at all levels of
published in the literature [4-6]. project.
This paper purposes an outline of the management and
control plan to achieve the required level of EMC within the
Commercial Telecom and Information Technology System as
well as with other adjacent equipment or systems in the MRT
Project: Sungai Buloh – Serdang – Putrajaya (SSP)
environment as shown in Figure 1. The next sections describe
the EMC Management activities to be implemented during the
whole life cycle of the project.

Figure 2: Overall EMC Management Plan

Figure 1: Mass Rapid Transit: Sungai Buloh – Serdang – Putrajaya


(SSP)
Electromagnetic Compatibility (EMC) is a significant area Figure 3: EMC organization for communication system in railway
of concern within the railway industry not just due to the environment
complex electromagnetic environment, but also because
failure to comply will have significant safety and cost A. EMC Management Plan
implications. The good strategy for implementing EMC management plan
Overall EMC management is needed for each main system can satisfy effectively the customer requirement. Basically,
as shown in Figure 2. Mainly, there are six (6) systems for these requirements have been mentioned in the tender
EMC Management plan which control by different document in early stage of the railway project design.
contractors. There are EMC management plan for power However, any customer requirement must be supported by the
supply and depot, EMC management plan for communication regulatory standard and environment/technical obligation. The
system, EMC management plan for signaling and EMC main railway standard used in this project is EN 50121-X and
management plan for vehicle train. This paper focuses on other relevant standard based on the different environments.
EMC management plan for communication system (CS). Even It is essential to manage EMC throughout the life cycle of
though each system has been managed by different the project. The EMC management process for this project
contractor/EMC manager, the interfacing and collaboration is shall involve various parties. EMC will be managed from the
design stage through to the installation, commissioning and compatibility in the testing and commissioning stage of the
the liability periods. For a successful implementation of EMC project in conjunction with these other contractors.
management plan, all parties need to cooperate to ensure EMC The mechanisms to ensure that EMC compliances are
compliance for the whole railway environment. The overall achieved shall be initiated at the design stage followed by
EMC management and control strategy for the CS project is during installation and commissioning. It is mandatory for
summarized in Figure 4. suppliers to produce EMC test reports and certifications for
verification.
Section below outlines the EMC control plan at equipment,
intra-system and inter-system levels.
Requirement

EMC Survey
Customer

1) Equipment EMC
As a prerequisite for the design of the subsystems in the CS
Hazard project, information on all EMC tests conducted on individual
Analysis equipment of the subsystems will be collated, inspected and
verified. This is to ensure that the equipment is able to tolerate
EMC Test expected interference as well as not to emit intolerable
Plan interference into the environment.
requirement
Regulatory

EMC
The equipment shall demonstrate compliance with the
Management several requirements. For train borne equipment (TRE), the
EMC Testing
Plan & Report EN 50121 series of EMC standards for emission and immunity
are applicable. Test results from an accredited test laboratory
shall be provided by the suppliers. If any equipment deviates
EMC from the EMC requirements, the justification to deploy the
Compliance
Environmental

equipment shall be submitted in the Test Report submission


requirement

Matric
for consideration prior to installation. The compliance status
of the equipment shall then be recorded in the EMC
Installation & Compliance Matrix (produced during EMC Testing & Report
Assessment phase).

2) Intra-system EMC
Figure 4: EMC Management plan for the System
Intra-system EMC is a basic condition for making sure that
each subsystem of the CS project is not a victim of itself.
Therefore, the system designer must ensure that there is no
B. EMC Control Plan internal source-to- victim combination that can create a
The EMC Control plan shall outline the steps taken to performance degradation or upset. Intra-system EMC
ensure that the CS equipment comply with the requirements of performance for each subsystem shall be monitored
intra-system and intersystem EMC in the railway individually during installation and commissioning at site. An
environment. CS company shall ensure that the emission and EMC checklist shall be produced for each subsystem to
immunity of the equipment during Pre-installation and Post- indicate EMC performance.
installation shall meet the relevant EMC standards in the It is anticipated that the intra-system EMC problems in the
relevant electromagnetic environment. In an event of CS project will not be an issue since these will be taken care
extraordinary interference do occur, mitigation methods such during the subsystem design stage and during procurement
as filtering, bonding and shielding shall be implemented. and installation of equipment for each subsystem.
Basically, the design work could be divided into two rather
distinct parts. The first part is the intra- system EMC 3) Inter-system EMC
consideration. In this part, interaction between the various Inter-system EMC is a basic condition for making sure that
system components shall be evaluated and actions taken to each subsystem of the project is not a victim of external
reduce such interactions. The second part is the inter-system interferences due to other subsystems, other contractor or
EMC consideration, where interactions between the CS external intentional and unintentional sources including
equipment and other equipment operating within the railway lightning. In order to assess inter-system EMC, information
environment must be evaluated and actions taken to reduce regarding the immunity and emission levels of all other
such interactions. equipment that are to be placed in close proximity to the
CS contractor shall interface, liaise, coordinate and equipment will be collated and evaluated, including all
exchange EMC data with all other main contractor and environmental data such as electromagnetic field strengths
captured in the Interface document to ensure EMC integrity in from nearby broadcasting stations.
the design stage, and to appropriately demonstrate The next step would then be the determination of coupling
mechanisms. If the two equipment under consideration are
unlikely to interact (e.g., a great distance away, housed in withstood and the functional degradation permitted for each
separate shielded enclosure, do not share common power immunity test phenomenon and the maximum levels of
supply system, etc.), then no further action would be taken. emissions not to cause interference problems with other
Otherwise, their respective EMC test results would be checked apparatus. It will also be determined by the requirements of
for compatibility. Again, no further action will be taken at this the applicable harmonized standard(s) if these are being used.
point if they are found to be compatible.
Lightning protection aspect shall be considered. CS II. EMC REQUIREMENT FOR COMMUNICATION SYSTEM
contractor should evaluate the lightning protection system,
mitigate and then design accordingly.
The overall requirements for EMC for communication
Should two subsystems be found to be incompatible
System (CS) are described in this section. The EMC
electromagnetically, then negotiation must be carried out
requirements within the boundaries of the relevant EMC
between the CS subsystems or other contractor in order to
determine the best course of action in order to improve on standards will be specified at the design stage. The CS system
EMC. Normally, if the incompatibility arises due to one of the shall operate normally with no degradation in performance
equipment in the subsystem not meeting EMC standards, then and functionality within the emission and immunity
action must be taken to ensure compliance by the said piece of boundaries of the EN50121 and EN61000-6-X standards
equipment. On the other hand, if compatibility arises due to depending on the intended electromagnetic environment of the
exceptional circumstances such as cabling or grounding, then equipment. EN 50121 defines test limits for equipment placed
mutually acceptable remedies should then be taken. within a railway boundary. The railway boundary is defined as
In the process of harmonizing Inter-System EMC, an EMI an area up to 10 m from the center of the nearest running line
Hazard Analysis Report shall be produced. All EMI risks are as shown in Figure 5. The limits in the standard applicable to
identified and classified in a Hazard Log according to the the railway boundary are generally equivalent to limits defined
likelihood of occurrence as well as severity of consequence. in heavy industry environment. Some specific limits are
Subsequently, mitigation measures such as separation, provided for equipment placed within 3 m from the center of
shielding, filtering, bonding and equal potential earthing may the nearest running line. Beyond this 10 m railway zone, light
be required. industrial standards for EMC apply.

4) Control of Suppliers Center of the track


To ensure that the equipment supplied by the manufacturers
or the suppliers meet the EMC requirements, the contractor
3m
will include the safety and EMC specifications and
requirements in the contractual agreement of the supply. These
requirements will act as criteria according to which CS Train
contractor selects the suppliers, which should be able to
provide acceptable evidence of actual performance and can
actually satisfy the engineering needs.
The contractor will check the suppliers’ evidence of EMC
performance and quality control and request them to provide
the EMC test reports and test certificates as a guide to the
intended use of the equipment and the competence of the
suppliers.

5) EMC Test Plan


The EMC Test Plan for the project is a document to 10 m (Railway zone)
describe the list of EMC tests, methods and specifications for
offsite and onsite EMC tests. Offsite tests will be carried out
by the suppliers of the equipment. CS contractor will be >10 m (Lite Industrial Zone)
provided with the EMC Test Reports and certificates of
compliance. In most cases, the offsite EMC Test will be
performed in accredited test laboratory at the manufacturing
stage. Figure 5: Zoning allocation for railway environment
Onsite EMC tests shall be performed by specialists
appointed by the contractor. They will conduct an assessment
before appointing the organization which has the competency The application of level differentiation on EMC
and experience to perform the EMC onsite testing. requirement by zoning as outlined in the previous paragraph is
The content of the EMC Test Plan will be determined by the applicable only if there is no other infrastructure or systems in
specification of the electromagnetic environment to be the vicinity of the railway. The zoning is for guidance in the
determination of applicable EMC standards for the various CS include any requirements to measure such magnetic fields. As
equipment during the conceptual design stage. The zoning such, apparatus which emits excessive magnetic fields should
perimeter is to be adapted accordingly when more information be controlled by implementing various techniques such as
is made available on the presence of strong electromagnetic separation from magnetically sensitive device and usage of
field sources such as at substation and radiating antennas. high permeability material for diverting the stray magnetic
There shall be sufficient protection to prevent EMI of the field.
CS system from affecting the operation of other Systems in The CS equipment are expected not to introduce harmful
the environment and being affected by other systems. radiated and conducted emissions to other equipment or
Equipment supplied by the supplier that is deemed likely to system in the SSP Line environment because individual
equipment shall be tested based on the relevant EMC
produce or be susceptible to electromagnetic disturbance, shall
standards. Declaration of Conformity shall be issued by
be tested and certified to meet the minimum requirements
suppliers for verification purpose. As a minimum, the
specified in the relevant EMC standards and to the satisfaction
maximum emission levels of the equipment shall not exceed
of the customer and shall be supplied with suitable evidence of the levels specified in EN 61000-6-4.
testing in the form of test reports and test certificates. The CS EMC engineer must ensure that the EMI generation for
system shall avoid the use of frequency bands which have telecommunication apparatus in railway environment complies
been occupied by other Systems or will cause Electromagnetic with EN 50121-4 and electrical and electronic apparatus and
Interference (EMI) to and from other systems through proper systems intended for use in railway fixed installations
frequency planning and intermodulation analysis. associated with power supply comply with EN 50121-5. The
Notwithstanding that the individual apparatus of the CS maximum levels of radiated EMI and conducted emission of
system complies with relevant EMC immunity and emission the TRE or within 3 m from the center of the track shall not
levels; they do not of themselves guarantee that the integration exceed the levels specified in the EN-50121-3-2 as shown in
of apparatus will necessarily be satisfactory. As a prerequisite, Figure 5. The details of the emission tests needed as well as
the individual apparatus to be installed in the project must the test levels required.
comply with the relevant EMC standards based on its intended Onsite EMI test shall be performed if interference to other
EM environment. The performance after integration of CS subsystems or within the main systems such as signaling to
apparatus shall be monitored and mitigation measures to be identify the interference source for mitigation measures to be
implemented if interference to other apparatus or susceptibility implemented.
from other apparatus occurs. Intentional emissions from radiating antennas and portable
transceivers which are deployed in the CS system shall not
A. Emission interfere with other equipment in the environment (including
The interference from an equipment or system can be in the cardiac pacemakers) if the other equipment have met the
form of radiated emission, conducted emission, harmonic and relevant radiated immunity standards.
flicker. The sources of radiated and conducted emissions are Moving trains are considered as mobile interference sources
differential mode and common-mode currents existing in the which possibly can affect the performance of sensitive
circuit or cables attached to the equipment. It is desirable to equipment located along the train routes such as in hospitals,
test components, equipment, subsystems and whole system to research facilities and factories. As such all possible victims of
see whether they emit beyond allowable emission limits. EMI along the train routes due to the CS equipment installed
Conducted emission should be tested to not exceeding 30 on board the train shall be identified and mitigated.
MHz for noise currents propagating through conductive B. Immunity
medium such as ac/dc power lines, input-output lines and
earth lines. Radiated emission to be measured at frequencies Immunity is defined as the ability of a device, equipment or
above 30 MHz in special test-sites such as Open Area Test system to perform without degradation in the presence of
Sites and Anechoic Chamber. Implementation of best electromagnetic interference. Systems installed in a railway
practices in circuit design, grounding, bonding, filtering and environment are very much required to possess sufficient level
shielding should results in emission within the acceptable of immunity against the various interference sources. These
limits. sources of interference can be:
Harmonic and flicker emission limits are to control the
harmonic currents and voltage changes due to equipment a. High voltage line to substations;
connected to public power supply system. b. Traction system;
When one item of equipment is in close proximity to c. Wayside radios;
another, low frequency magnetic fields can cause interference. d. Portable radios and phones;
This is especially a problem for CRT image ‘wobble’, but also e. Telecommunication equipment;
for baseband circuits such as instrumentation, video and audio, f. Auxiliary apparatus with high power ratings;
whose circuits and cables can couple with the magnetic fields g. Auxiliary power converters.
and suffer significant amounts of crosstalk in some situations.
There are no harmonized EMC emissions standards which Any sensitive electronic equipment shall be capable of
operating in an environment with substantial amounts of
radiated interference present. The equipment may be subjected necessary to take a number of precautions to ensure that its
to radiated energy from handheld transceivers and other EMC performance requirements can be met. Trying to fix the
communications systems. EMC performance once the equipment has been designed and
CS equipment which are installed on-board train shall built will be more difficult and costly. Therefore, the main
comply with the immunity requirements as specified in EN concern in EMC Management Plan and Control Plan is all the
50121-3-2. EN 50121-4 standard applies for the immunity of main issue of EMC need to be take into consideration in early
CS equipment which are installed in the railway environment of the design stage. This paper can be a guideline to an EMC
(excluding on-board train). engineer on how the EMC Management and Control Plan have
The equipment shall possess sufficient immunity against been conducted.
conducted and radiated interferences. The tests to be the
conducted are as follows: IV. ACKNOWLEDGMENT
The authors would like to acknowledge Universiti Tun
a. RF Radiated Interference; Hussein Onn Malaysia (UTHM) for their funding of this
b. RF Conducted Interference; research under Research Acculturation Grant Scheme (RAGS)
c. Induced Interference; research grant, R069.
d. Electrostatic Discharge;
e. Electrical Fast transients/Bursts;
f. Voltage Surge; REFERENCES
g. Magnetic Field;
h. Voltage Dips and Voltage Interruptions. [1] C.R.Paul, “Introduction to Electromagnetic Compatibility,” 2nd ed., ,
Hoboken, NJ, USA, John Wiley & Sons, Inc., December 2006.
This is by no means an exhaustive list but it gives an [2] E. Rhee, C. Kim, (2014). Electromagnetic Compatibility Analysis for
indication of the main immunity tests for the CS equipment. the Railway Telecommunication Intra-subsystem. International Journal
of Software Engineering and its Applications. Vol.8. No.5. pp. 115-126.
The immunity of equipment against the aforementioned [3] K.J Satsios, D. P. Labridis, P.S Dpkopoulos. (April 1999). Inductive
conditions shall be tested according to the test frequencies and Interference caused to Telecommunication Cables by Nearby AC
severities. However, exclusion shall be made to the test Electric Traction Lines Measurements and FEM Calculations. IEEE
requirements if the frequencies and levels of the interference Trans. On Power Delivery, vol. 14, no.2, pp. 588 – 592.
[4] M.W.C. Chu, B.T. Loi & Ron Yong, 2010 WUTC on Electromagnetic
sources are known. Compatibility Management on New Projects, Oct 2010
[5] M.W.C. Chu & B.T. Loi, APEMC 2012, Electromagnetic Compatibility
III. CONCLUSIONS Design Management Challenges on Downtown Line (DTL) Project
[6] Z Yujie. (2016). Electromagnetic Compatibility (EMC) Management
The EMC Management and Control Plan shall describe the Challenges on Tuas West Extension (TWE) Project. 7th Asia Pacific
philosophy and procedure to be taken, including mitigation International Symposium on Electromagnetic Compatibility, pp. 326-
measures, if necessary, during the various stages to ensure that 328.
the EMC of the CS equipment with its environment, including
that of the other suppliers. When designing the equipment, it is

You might also like