RIYADH REFINERY
Page 1 of 4
DIESEL HYDRO-TREATER PROJECT
RIYADH REFINERY
TABLE OF CONTENTS
1. SCOPE
2. REFERENCE
3. SAFETY
4. WORK PROCEDURE
Page 2 of 4
DIESEL HYDRO-TREATER PROJECT
RIYADH REFINERY
1- SCOPE
2- REFERENCE
2.1 SAES-P-104
2.2 SAES-Q-001
2.3 09-SAMSS-097
3- SAFETY
3.1 Ensure compliance with Saudi Aramco Construction Manual and any other
applicable safety requirements during work execution.
3.2 Obtain proper work permit for the activity and implement the
recommendations.
4- WORK PROCEDURE
4.1 Expose the aggregate by chipping out the top of the duct bank
concrete.
4.2 Clean the surface with wire brush and remove any foreign material or
dust.
Page 3 of 4
DIESEL HYDRO-TREATER PROJECT
RIYADH REFINERY
4.3 Apply bonding agent prior to application of plaster material mixed with
red dye.
4.4 Apply 20mm plaster (Ratio 1:3 of cement:sand) mix with red dye on top
of concrete.
4.6 Inspect the work with TPSA and backfill the area after approval.