Emergency Prepredness & Response Plan
Emergency Prepredness & Response Plan
COMMUNICATION
ASSEMBLY POINT RESCUE TEAM FIRE FIGHERS FIRST AIDERS SEARCH TEAM
TEAM
COORDINATOR
3) Declare the emergency by available sources (whistle, siren or by Assembly point co-coordinator Team
4) Ensure all staff and workmen have assembled at assembly point. Team
9) Inform senior / top management of the company. Communication Team Security Team
10) Control all the movements of the vehicles as well as visitors and EHS officer
employees.
11) Maintain the record of the actions taken
Fire Emergency 2) Declare emergency by blowing siren/whistle/shouting and alert all Fire Fighting Team Security Team
employees/ and residents.
3) Instruct the firefighting team to rush to the fire spot with firefighting Communication Team
equipment.
4) Contact nearest fire brigade for immediate help. Communication Team Assembly Point
5) Ensure all employees have gathered at assembly point. coordinator
4. 6) Instruct first aid trained persons for providing immediate first aid and send Team
the affected person to hospitals with escorts. First aid and rescue team
9) Investigate the cause and initiate the corrective action to prevent Communication Team EHS Committee
5. Natural disaster 1) In case of flooding, immediate action is to evacuate people at site. Rescue Team
2) Provide help and supply of food, water and electricity to the affected people.
to hospital.
Communication Team Rescue
7) Call the ambulance.
Team
8) Accompany the affected person to the hospital.
9) Provide the necessary help for adequate medical treatment. First aiders, Rescue Team
10) Inform senior officers of the company. Communication Team EHS
11) Investigate the cause and initiate the corrective action. officer
Maintain the record of the action taken. EHS officer
8 Collapse of crane while 1) Restrict the entries in the affected area. EHS Team EHS Team
lifting or lowering the load 2) Barricade the entire area. Assembly point co-coordinator Team
3) Declare the emergency by available sources (whistle, siren or by Rescue Team
shouting). Assembly point co-coordinator Team
4) Ensure the operator and signalman is safe. Communication Team
5) Ensure all staff and workmen have assembled at assembly point. Communication Team
6) Instruct the evacuation/rescue team to carry out the evacuation.
7) If required, call for external agency such as ambulance or fire brigade for First aid Team Rescue Team
removing debris and evacuate the affected people. Communication Team
8) Provide first aid. Communication Team EHS officer
9) Send the casualty to hospital with responsible person.
11) Control all the movements of the vehicles as well as visitors and
employees.
12) Maintain the record of the actions taken
EHS officer
11 Chocking of breathing of the 1) Make people aware about severity of the disease. EHS officer
person due to cement dust 2) Take preventive actions by providing prevention equipment or items for
EHS officer
near batching plant Personal protection
3) Provide first aid; ensure isolation, admitting to the affected person to the First aid and Rescue Team
Reviewed By Approved By