Professional Documents
Culture Documents
Click
Here
www.leanTakt.com
https://amzn.to/3
Takt Startup Guide & Process Tracker:
Click
Here
ttps://amzn.to/3oHedox
promised in the interview.
in the local market for this type of building.
one-line diagrams.
n by phase.
sidere leveling work steps to another work package in another Takt time
ard checks need to be done for those steps, work packages, or Takt wagons
ning buffer Takt wagon to trigger the planning and preparation of the work soon enough to ensure the success of that work
n the book and perform the parametric calulations in the schedule health section of the book
W board showing visually how crews should install the scope of work
sequence, trade flow, process times within Takt wagons and the overall plan
ms per the book Elevating Construction Superintendents in the logistics section
most current Takt zone outlines after the optimization that was done to identify the right batch sizes
nd schedule risk amounts and mitigate the risk weekly in team meetings
Click
Here
https://www.elevateconstructionist.com/upcoming-events
Takt Integrity Checklist:
ll make, when combined, over 100 years of experience in the review of your plan before submitting a GMP.
Project Name
Col
SEPTEMBER OCTOBER NOVEMBER
7 14 21 28 5 12 19 26 2 9 16 23 30
Milestone Summary
Notice to Proceed
Substantial Completion
ASSUMPTIONS
Critical Procurement
Description Lead Time (wks) Date Needed
Risks
Opportunities
GUIDELINES
Identify the throughput of the system
Identify bottlenecks
Check the stagger of areas
Include appropriate buffers
Avoid Christmas & Thanksgiving weeks
Coordinate everything
GOALS
Find the rhythm of the project
RULES
If a contractor is not complete, they work Saturday
Nothing hits the floor
Just in time deliveries and manpower
No going faster or slower
STURBANCE PERMIT
MAKE SAFE UTILITIES
MOBILIZATION
EXCAVATION
SHORING
PIERS
FOOTINGS
STEM/RETAINING WA
STEM/RETAINING
UG MEP
UG MEP
BIM
BIM LEGEND
Model Coordination
Prepare Shop Drawings + Lay
Shop Drawing Approval
Prefabrication of Material
JUNE JULY AGUST
7 14 21 28 5 12 19 26 2 9 16 23 30
Submit for Civil permit
Development
Construction Documents
Structure
Structure
OTINGS
EM/RETAINING WALLS
STEM/RETAINING WALLS
Basement SOG P1
UG MEP Basement SOG P2
Deck L2 Pour 1 1 2 3 3
1 1 1 2
UG Coordination
Level 1 OH
Level 2 OH
oordination
Shop Drawings + Layout Drawings
awing Approval
ation of Material
C
SEPTEMBER OCTOBER NOVEMBER
6 13 20 27 4 11 18 25 1 8 15 22 29
for Civil permit
Submit for Early Foundation Package
ction Documents Submit for Building perm
GMP Development
CONTINGENCY
NTP
Structure
Structure
4 4 5 5 6 6 7 7 8 8 9 10 11
2 3 4 5 6 7 8 9 10 10 10 O O
Exterior
Site/Foundations
Structure/BIM
Hang/Taping/Drywall/Grid
Exterior Envelope
Commissioning + Punch
2022
Cold Winter Months
DECEMBER JANUARY FEBRUARY
6 13 20 27 3 10 17 24 31 7 14 21 28
for Building permit
Submit for TI permit
NTINGENCY Exterior Skin Lead Time
CONTINGENCY Elevator Lead Time
Lobby Finishes
11 11 12 12
Temp Roof Install Swing Stages
r Set AHU & Install
A A A A B B
A B B C D D
Lead Time
Power On
Air On
Power O
Air On
21 22
Interiors
Erect Stair
Erect Stair
Pre-Functional Ch
B B Z Z Z Z C C C C D D D
E E F F F F G G H H I I I
physical space and time
es for the slowest trades on exterior skin
moval or fireproofing?
insulation/drywall
n construction
Elevator Cabs
Erect Stair
Pour Stair Pans
Pre-Functional Checklists
Controls
D D D D D E E E E E E F F
J K K L L
G H I
Updated: 0
Test + Certification
TAB
Commissioning
Fire Life Safety
Final Walks
G G G G
I I J K L Site Area 1
In Collaboration with:
Updated: 03/08/22
2023
Cold Winter Months
DECEMBER JANUARY FEBRUARY MARCH
5 12 19 26 2 9 16 23 30 6 13 20 27 6
Need Help in Reading this Takt Plan?
Scan QR Code Below With Smart Phone Camera
INTERIORS LEGEND
0 Remove Reshores
1 OH MEPS
2 Framing and Door Frames
3 In-Wall Rough
4 Drywall
5 Tape/Finish
6 Paint
7 MEP Trim
8 Flooring
9 Tile and Base
10 Accessories
11 Okland Pre-Punch + Clean
12 Owner Punch
O Other
INTERIORS LEGEND
0 Remove Reshores
1 Wall Layout + Top Track
2 Fire Sprinkler + Priority Walls
3 OH Ductwork
4 OH Branch Conduits and Lighting Circuits
5 OH Mechanical Piping
6 OH Electrical
7 Wall Framing
8 In wall Rough-in
9 Soffits + Ceilings
10 Soffit & Ceiling Rough
11 Drywall
12 Taping
13 Prime + First Coat
14 Data Cabling
15 Ceiling Grid
16 Casework + Doors
17 MEP Trim / Light and Devices
18 Flooring + Baseboards
19 Final Paint
20 Final Accessories
21 OCC Pre-Punch & Clean
22 Punchlist
SITEWORK LEGEND
G Layout
H Fine Grade
I Concrete
J Pavers
K Landscaping
L Punchlist
MARCH APRIL MAY JUNE
13 20 27 3 10 17 24 1 8 15 22 29 5 12 19
JUNE JULY AUGUST SEPTEMBER OCTOB
26 3 10 17 24 31 7 14 21 28 4 11 18 25 2
2024
Cold Winter Months
OCTOBER NOVEMBER DECEMBER JANUARY
9 16 23 30 6 13 20 27 4 11 18 25 1 8
24
Winter Months
JANUARY FEBRUARY MARCH APRIL
15 22 29 5 12 19 26 4 11 18 25 1
APRIL MAY JUNE
8 15 22 29 6 13 20 27 3 10 17 24
JULY AUGUST SEPTEMBER
1 8 15 22 29 5 12 19 26 2 9 16
Cold Winter M
PTEMBER OCTOBER NOVEMBER DECEMBER
23 30 7 14 21 28 4 11 18 25 2 9
Cold Winter Months
DECEMBER
16 23 30
Col
SEPTEMBER OCTOBER NOVEMBER
7 14 21 28 5 12 19 26 2 9 16 23 30
Milestone Summary
ASSUMPTIONS
Critical Procurement
Description
Lead Time (wks) Date Needed
Risks
Opportunities
GUIDELINES
Identify the throughput of the system
Identify bottlenecks
Check the stagger of areas
Coordinate everything
Consistent layout
GOALS
Find the rhythm of the project
3
e Needed
MARCH APRIL MAY
8 15 22 29 5 12 19 26 3 10 17 24 31
akt Plan?
Phone Camera
JUNE JULY AGUST
7 14 21 28 5 12 19 26 2 9 16 23 30
C
SEPTEMBER OCTOBER NOVEMBER
6 13 20 27 4 11 18 25 1 8 15 22 29
2022
Cold Winter Months
DECEMBER JANUARY FEBRUARY
6 13 20 27 3 10 17 24 31 7 14 21 28
MARCH APRIL MAY
7 14 21 28 4 11 18 25 2 9 16 23 30
Updated: 03/08/22
Ideal Integrated B
TAKT Phas
1 Surface Work (Control, F
2 Stud Work & Vert. Fire S
3 Hydronic Piping
4 Stud Work
5 Drywall One-side & Fire
6 In-wall Electrical A
7 In-wall Elec B, IW Plum
8 Control, Inspections, & B
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Takt Zone 1 1 1 2 2 2 3 3
Takt Zone 1 1 1 2 2
Takt Zone 1 1
Takt Zone
Buffer M
Takt Zone 1 1 2 2 3 3 4 4
Takt Zone 1 1 2 2 3 3
Takt Zone 1 1 2 2
Takt Zone 1 1
Takt Zone
Takt Zone
Out Takt Phase
3 4 4 4 5 5 5 6 6 6 7 7 7 8 8 8
2 3 3 3 4 4 4 5 5 5 6 6 6 7 7 7 8
1 2 2 2 3 3 3 4 4 4 5 5 5 6 6 6 7
Takt Zone 1 1 1 2 2 2 3 3 3 4 4 4 5 5 5 6
Takt Zone 1 1 1 2 2 2 3 3 3 4 4 4 5
uffer Management
B 5 5 6 6 B 7 7 8 8
4 4 B 5 5 6 6 B 7 7 8 8
3 3 4 4 B 5 5 6 6 B 7 7 8 8
2 2 3 3 4 4 B 5 5 6 6 B 7 7 8 8
1 1 2 2 3 3 4 4 B 5 5 6 6 B 7 7 8
Takt Zone 1 1 2 2 3 3 4 4 B 5 5 6 6 B 7
Takt Zone 1 1 2 2 3 3 4 4 B 5 5 6 6
Takt Zone 1 1 2 2 3 3 4 4 B 5 5
2
M
Scan QR
kt Plan
September
23 30 6 13
TH F M T W TH F M T W TH F M T W TH F
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
Proper Sequence - Right Size - Able to Learn
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
Proper Sequence - Right Size - Able to Learn
ACTIVITY 1
ACTIVITY 2
ACTIVITY 3
ACTIVITY 4
ACTIVITY 5
ACTIVITY 6
ACTIVITY 7
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
Proper Sequence - Right Size - Able to Learn
4
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
Proper Sequence - Right Size - Able to Learn
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
Proper Sequence - Right Size - Able to Learn
ASSIGNMENT DESCRIPTION
Criteria for release of assignments
MANPOWER (# of Crews/ Crew Size)
Defined - Sound -
Proper Sequence - Right Size - Able to Learn
wcrete, Painting)
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
RESPONSIBLE
ORGANIZATION COMMENTS
PARTY
1 2
1 2
Vertical Fire Sprinkler
1 2
X
X
X
X X
X X
X
X
Hydronic Piping
1 2
1 2
1 2
1 2
x
x
x
x x
x
x x x
Description
ea
D
p
ro
Spec Section Scope of Work Takt Zone Trade Partner
D
**ITEMS IN RED ARE IN TROUBLE**
D
ro
p
D
ea
A d
ct
ua R
el
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
l ea
Su Re se
bm lea TP
itt sed D
al
Pr T P
at
e
e p F o
R W rS
ec
ei K ub
S m
Submittals
ve
Su itt
al
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
bm
Su i tta
bm l
itt
al
Se
nt R
ev
To ie
w
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
D D W
es e sig K
ig n S
n T
A Te ea
ct
ua am m
lA A
R pp ppr
eq ro o
ui ve val
re
d d
Su Wk
Su
bm
Su S
bm bm
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
i it t i tt
al
Le ttal al
ad O A
Ti ver pp
m / ro
Sh e W Un va
ip KS der l
D D
at ay
e s
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
Le al al
a d O A
Ti ver pp
m / ro
Sh e W Un va
ip KS der l
D D
at ay
e s
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
D
el
iv
er
y
Procurement
W
EE
K
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Bu S
ffe
rD
A ur
ct at
ua io
lD n
at W
R e o
EE
n K
eq S S
ui
re i te
d
M O
at n
er Jo
ia b
lO (G
ve et
r/ Su
U pe
nd ri
er nt
D en
A de
Y
S nt
I np
ut
C !)
om
m
en
ts
( Is
su
Tuesday, March 8, 2022
es
,w
ho
ne
e ds
th
e
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
LAST DATE REVIEWED W/ SUPER: ?????
m
en
ts
( Is
su
es
,w
ho
ne
e ds
th
e ap
pr
ov
e d
su
bm
itt
al
, et
c)
UPER: ?????
RI
Best Practice is to have this and an exhibit for Fresh Eyes Meetings & Continuous Team Huddle System.
This is a living document so
updating will be on-going
through-out the project life
cycle (Project
Development/Estimating/OPS/
Closeout
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
RISK REGISTER & ANAL
& Continuous Team Huddle System.
PROBABILITY
RISK CATEGORY IMPACT DESCRIPTION
LEVEL
ER & ANALYSIS
Rate Rate
1 -None (0) 1 - Minimal
Avoid, Recognize &
2 - Low (1-10) 2 - Low
Ignore, Accept &
3 -Mod. (10-20) 3 - (IMPACT X PROBABILITY)
Leverage, Accept &
Moderate Address highest first.
Transfer, Accept &
4 - High (20-40) 4 - High
Manage
5 - Significant 5-
(40+) Significant
DATE
MITIGATION NOTES OWNER MITIGATION
COMPLETED
Adjust here if you want a different scale
RISK REGISTER SCALE
5 5 10 15 20
PROBABILITY
4 4 8 12 16
3 3 6 9 12
2 2 4 6 8
1 1 2 3 4
1 2 3 4
IMPACT
Impact and Probability Scale
1
cale
2
3
25 4
20 5
15
10
5
5
Risk Types Risk Categories Mitigation Strategies
Schedule Capacity Avoid
Client
Cost Relationship Recognize & Ignore
Management
Compliance
(OSHA) Accept & Leverage
Contracting Accept & Transfer
Cost
Escalation Accept & Manage
Equipment
Material
Availability
Process
Reliability
Resource
Allocation
Safety
Performance
Self Perform
Reliance
Strategy
Execution
Sub-
Contracting
Trade
Partnership
Reliability
Weather
Event
JUNE
7 14 21 28
Remove Reshores 0 0 1 1 1
OH MEPS 1 0 0 1 1
In-Wall Rough 3 0 0 0 0
Drywall 4 0 0 0 0
Tape/Finish 5 0 0 0 0
Paint 6 0 0 0 0
MEP Trim 7 0 0 0 0
Flooring 8 0 0 0 0
Accessories 10 0 0 0 0
Owner Punch 12 0 0 0 0
Other O 0 0 0 0
0 1 2
0 1
Move these around to 0
test
JULY AGUST
5 12 19 26 2 9 16 23
2 1 1 0 0 0 0 0
1 2 1 1 0 0 0 0
1 1 2 1 1 0 0 0
1 1 1 2 1 1 0 0
0 1 1 1 2 1 1 0
0 0 1 1 1 2 1 1
0 0 0 1 1 1 2 1
0 0 0 0 1 1 1 2
0 0 0 0 0 1 1 1
0 0 0 0 0 0 1 1
0 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
3 4 5 6 7 8 9 10
2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8
0 1 2 3 4 5 6 7
0 1 2 3 4 5 6
0 1 2 3 4 5 6 7
0 1 2 3 4 5
SEPTEMBER OCTOBER
30 6 13 20 27 4 11 18
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
1 1 0 0 0 0 0 0
2 1 1 0 0 0 0 0
1 2 1 1 0 0 0 0
1 1 2 1 1 0 0 0
1 1 1 2 1 1 0 0
0 1 1 1 2 1 1 0
0 0 1 1 1 2 1 1
11 12 O
10 11 12 O
9 10 11 12 O
8 9 10 11 12 O
7 8 9 10 11 12 O
8 9 10 11 12 O
6 7 8 9 10 11 12 O
BER NOVEMBER DECEMBER
25 1 8 15 22 29 6 13
0
0
DECEMBER
20 27
Project Progress
CATEGORIES OF VARIANCE TOTAL ACTIVITIES 0
1 Contracts/CO's 8 Qualified Staff Availability ACTIVITIES COMPLETED 0
2 Client Change 9 Materials/supplies availability PERCENT PLANNED
#DIV/0!
3 Submittals 10 Equipment COMPLETE
4 Arch/Eng/Design/RFI 11 Weather
5 Equip Availability 12 Site Conditions
MANPOWER (# of
ORGANIZATION
Crews/ Crew Size)
RESPONSIBLE
6 Prior Work Complete - Others 13 Incorrect Time Estimate
SITE/AREA
PARTY
Criteria for release of assignments Defined - COMMENTS STARTING ON Week #
FLOOR
Cate-
gory
30-Dec 31-Dec 1-Jan 2-Jan 3-Jan 4-Jan 5-Jan Y/N REASONS FOR VARIANCE
ACTIVITY 1 X
ACTIVITY 2 X
ACTIVITY 3 X
ACTIVITY 4 X X
ACTIVITY 5 X X
ACTIVITY 6 X
ACTIVITY 7 X
MANPOWER (# of
ORGANIZATION
Crews/ Crew Size)
RESPONSIBLE
6 Prior Work Complete - Others 13 Incorrect Time Estimate
SITE/AREA
PARTY
Criteria for release of assignments Defined - COMMENTS STARTING ON Week #
FLOOR
Cate-
gory
30-Dec 31-Dec 1-Jan 2-Jan 3-Jan 4-Jan 5-Jan Y/N REASONS FOR VARIANCE
Workable Backlog
Seqeunces
Efficientcy Parameter
Takt Buffers
End Buffers
The Takt Stability Parameter