Professional Documents
Culture Documents
For this assignment, we are required to perform a cost planning of the given project with both
means of cost estimation, based on the elemental breakdown, and Elemental Cost Analysis by using
Form 1 and Form 2 of the Standard Form of Elemental Cost Analysis. Our group is provided with
the drawing layout plan, the Bills of Quantities and ISM Manual to carry out all these tasks.
The project that we are required to carry out elemental breakdown is based on 2 different types of
3-story residential buildings. The type of residential building is a townhouse that consists of both
lower and upper units for the Type A1 - Intermediate Unit and Type A2 - Corner Unit. Therefore
there is a total of 4 units in the drawing plan. The Bills of Quantities for both these type of
townhouse is almost fully given. From the BQ, we are obligated to derive and extract all the related
items, quantities, and rates of the following elements of the whole building. By using all the data
and information that we had collected, we are able to perform the elemental cost analysis and cost
estimation.
Before we can start the elemental breakdown and cost analysis, the gross floor area, unenclosed
area, roof area shall be calculated beforehand from the provided drawing layout floor plan. The
GFA is the enclosed area of the building measured from the internal surface of the external wall.
The unenclosed area is measured for areas that are not covered by the ceiling, roof, or any sides of
the wall like the car porch.
We are also required to calculate the items that were not fully given in the BQ. For example, the
area, element cost for the doors and windows. The reinforced concrete, reinforcement bars, and
formwork also require additional calculation to fill up the Standard Forms of the Elemental Cost
Analysis.
The task is distributed equally among the members of the group. The tasks like calculating the GFA
area, calculation of internal, external doors and windows, calculation of the reinforcement,
formwork and concrete works, and the filling out of both forms. Each member of the group has
their own responsibilities to complete the assignment. For Task 3, we have broken down the wide
scope of topics related to cost planning of the building into divided parts. Each member has taken
one topic each to further explain the concept behind the cost planning of the building.
TASK 1
TOTAL COST
OF COST/M2
ELEMENT ELEMENT GFA
RM RM
1 Substructure
1A Piling - -
1B Work Below Lowest Floor Finish ( 106,841.80) ( 121.00)
Group Element Total ( 106,841.80) ( 121.00)
2 Superstructure
2A Frame ( 112,119.50) ( 126.98)
2B Upper Floors ( 68,420.10) ( 77.49)
2C Roof ( 102,410.30) ( 115.98)
2D Stairs ( 61,708.02) ( 69.88)
2E External Walls ( 33,602.20) ( 38.05)
2F Windows & External Doors ( 87,940.40) ( 99.59)
2G Internal Walls & Partitions ( 49,690.00) ( 56.27)
2H Internal Doors ( 22,276.85) 25.23
Group Element Total ( 538,167.37) ( 609.47)
3 Finishes
3A Internal Wall Finishes ( 60,902.94) ( 68.97)
3B Internal Floor Finishes ( 79,441.10) ( 89.97)
3C Internal Ceiling Finishes ( 14,471.00) ( 16.39)
3D External Finishes ( 50,885.22) ( 57.63)
Group Element Total ( 205,700.26) ( 232.96)
4 Fittings and Furnishings
5 Services
5A Sanitary Appliances 45,725.82 51.78
5B Plumbing Installation - -
5C Refuse Disposal - -
5D Air Conditioning & Ventilation System ( 51,500.00) ( 58.32)
5E Electrical Installation ( 259,707.60) ( 294.12)
5F Fire Protection Installation - -
5G Lift & Conveyor Installation - -
5H Communication Installation -
5J Special Installation - -
5K Builder's Profit & Attendance
on Services - -
5L Builder's Work in Connection
With Services ( 14,004.00) ( 15.86)
Group Element Total ( 370,937.42) ( 420.08)
Sub-total exc. External Works,
Preliminaries & Provisional Sum ( 1,221,646.85) ( 1,383.51)
6 External Works
6A Site Work ( 731,857.40) ( 762.92)
6B Drainage - -
6C External Services - -
6D Ancillary Buildings - -
6E Recreational Facilities - -
Group Element Total ( 731,857.40) ( 762.92)
Preliminaries ( 137,942.25) ( 156.22)
TOTAL (less Contigencies) ( 2,091,446.50) ( 2,302.65)
2 SHOW UNITS AND 2 MOCK-UP UNITS OF 3-STOREY TOWNHOUSES
TYPE A1 - INTERMEDIATE UNIT & TYPE A2 - CORNER UNIT
Superstructure
2 First Floor Plan 311
3 Second Floor Plan 291
4 Water Tank Plan 50
1 Usable Area
Bedroom 3 2.45 3.09 7.57
2.27 3.62 8.22
Dining Room 3.38 4.24 14.33
Living Room 3.80 4.24 16.11
Dry Kitchen 3.38 3.56 12.03
58.26
2 Ancillary Area
Utility 2.15 1.85 3.98
Wet Kitchen 4.00 1.77 7.08
Bath 4 1.85 1.85 3.42
Bath 3 1.95 1.78 3.47
1.23 1.03 1.27
1 Usable Area
Bedroom 3 3.70 2.19 8.10
3.02 2.45 7.40
Dining Room 4.37 5.48 23.95
Living Room 3.73 4.24 15.82
Dry Kitchen 4.15 3.49 14.48
69.75
2 Ancillary Area
Utility 2.15 1.77 3.81
Wet Kitchen 3.93 1.84 7.23
Bath 4 1.78 1.77 3.15
Bath 3 1.85 1.95 3.61
1.10 0.50 0.55
0.75 1.03 0.77
Storeroom 2.56 1.29 3.30
22.42
3 Circulation Area
Foyer
Lower Unit 2.12 1.62 3.43
Upper Unit 2.04 1.23 2.51
Yard 1.35 3.61 4.87
Staircase
Lower Unit 2.20 1.33 2.93
1.25 2.19 2.74
Upper Unit 2.91 1.29 3.75
20.23
Total : 112.40
1 Usable Area
A1 58.26
A2 69.75
128.01
2 Ancillary Area
A1 23.51
A2 22.42
45.93
3 Circulation Area
A1 36.83
A2 20.23
57.06
Total: 231.00
1 Usable Area
A1 90.88
A2 94.36
185.24
2 Ancillary Area
A1 29.26
A2 30.33
59.59
3 Circulation Area
A1 34.27
A2 31.62
65.89
Total: 310.72
SECOND FLOOR PLAN TYPE A1 & TYPE A2
87.74
2 Ancilary Area
Bath 3 2.53 1.93 4.88
20.52
3 Circulation Area
Corridor - LU 3.6 1.67 6.01
1.47 4.24 6.23
2 Ancilliary Area
Bath 3 2.46 1.93 4.75
3 Circulation Area
Corridor - LU 3.6 1.67 6.01
1.47 4.24 6.23
2 Ancilary Area
A1 20.52
A2 20.68
41.20
3 Circulation Area
A1 35.76
A2 35.42
71.18
Total: 291.21
ROOF AREA
LOCATION : SHAH ALAM, SELANGOR DARUL EHSAN. TENDER DATE : August 2021
Type of Contract : PAM CONTRACT 2018 WITH QUANTITIES Cost Fluctuation : Yes RM Int(Jv)/L
The objective of the cost planning is to let the client receive value for money, not
necessarily lower than the initial cost. There must be a balance between quality, usage suitability,
initial cost, and life-cycle cost for the entire life span of the element. A reasonable expenditure
between sections of the building by relating the design and the specification to the client’s budget
so that a more balanced design is obtained. The overall disbursement of the project is within the
client's budget. Besides that, the amount that the client agreed shall not be exceeded in the tender
that received
There are two main characteristics of cost planning. The project’s overall budget is the first
characteristic. The project’s overall budget is the estimated total cost of the project. It is derived
using several types and is dependent on the expectation in the scope and design of the project.
Other than that, the time used in the construction project will affect the cost is another characteristic
of cost planning. The longer the construction period, the higher the cost used. The budget that is
located in the cost planning is for a certain period only. So when preparing the cost planning, it
must consider the actual occurrence in the project schedule and pay the cost of time.
Moreover, there are two methods of cost planning which are Elemental Cost Planning and
Comparative Cost Planning System. Elemental Cost Planning is also described as “designing to a
cost”. This is because, in the Elemental Cost Planning System, the Architect will design the
building with a cost limit. There is a standard form of cost analysis which is also called ‘elemental
cost analysis’ for the Elemental Cost Planning System which is to segregate the costing and
compare it in a common format. In addition, the Comparative Cost Planning System also refers to
‘costing a design’. This is because based on the Comparative Cost Planning System, the Architect
can start a design without a fixed price but the Quantity Surveyor has the responsibility to ensure
that the cost of the Architect design is in the amount that the client can carry out.
Elemental cost planning is carried out in our task 1 which applies the concept of
breaking down the elements in a building. As a Quantity Surveyor in charge, we have to confirm
that the construction cost has been distributed in several components and finishes consciously and
economically. By using elemental cost planning we can get a better value at the desired level of
expenses. First of all, we sketch the drawings and calculate the total price by using an approximate
method. For example, cost per meter square of floor area. Then, we categorized the building into
several elements such as a wall, floor, ceiling, and so on. Those elements will be assigned a cost
based on the previous similar project’s cost analysis. Besides that, we total up the cost of the
elements from the Bill of Quantities. The total cost of those elements that we get is not to exceed
the total estimated cost.
From this assignment, we learned that there are many advantages and disadvantages to
using cost planning. One of the advantages is the client knows the financial budget of the project so
that the client grants to secure the proper financing and business plan. Besides that, the client won't
know about the profitability of the project without cost planning. In addition, the disadvantage of
cost planning is the time taken. Cost planning will take more time in preparation in the early design
stage. Moreover, the requirement of knowledge of pricing and design of the quantity surveyor will
be higher. A Quantity Surveyor has to clearly understand the factors that affect the cost when
preparing a cost planning.
Ashworth (1999) defined cost modeling as techniques used for forecasting the estimated cost
of a proposed construction project. Therefore, all methods, techniques, or procedures used by
Quantity Surveyors for cost estimation or cost forecast may be termed as cost models. The
estimation method before construction (stages 0-4) is roughly divided into two types that are
budget-setting techniques and budget-distributing techniques. Moreover, cost planners must be
cautious of the method's details, the pros and cons, and their applicability in the various phases of
the project.
The first estimate (budget or cost limit) is determined at the early stages of the project for most
of the projects in budget-setting techniques. Budget-setting techniques are used to estimate the
project budget (or cost limit), moreover Superficial Method or Floor Area Method (GFA),
developer’s budget, and functional unit are the techniques used.
The developer’s budget is used for calculating the maximum amount that is going to be spent
on the buildings if the cost of land is known. Gross Development Value (GDV) is the estimated
property value (including two types of capital once the construction work has been completed.
Moreover, the superficial method or floor area method is one of the favorable methods of
estimating, and it is commonly used in the early stages of the content of project stages 0 and 1.
When measuring residential housing, schools, and other similar story height, this method is often
used. If the difference is very different in the finish quality of the building, it is recommended to
apply different unit prices depending on the floor area. The pros of it are that most projects with
cost-effectiveness are related to floor area. On the other hand, its cons is the inability to directly
consider the planned shape or total variation in building height.
The principle of Elemental Cost Analysis is applied for this assignment briefly in Task 2.
Element Cost Analysis is normally planned and processed for the usage of the designer and the
client for future projects. This cost analysis shall act as a benchmark for the comparison of the cost
of future new buildings. The Elemental Cost Analysis contains brief project cost information,
specifications, and overall project information which is obtained from the BQ. The cost from
Elemental Cost Analysis shall not be taken into account as the actual price of the project,
consideration from the aspect of conditions, details, quality, and quantity of works of the overall
project shall be noted.
The main purpose of this Elemental Cost Analysis is to allow the client and the designers to
identify and understand how is the cost fairly distributed among the functional elements of a
building. For example, the cost for the substructure, superstructure, external works, and more is
calculated and shown. By understanding where are the costs allocated in a building, the designers
and client may take into consideration of the building design to achieve a cost-efficient building.
Besides that, the elemental cost analysis also indicates which elements should be reconsidered for
further reductions to keep within the limited budget. Elemental Cost Analysis is also used as an
assistance for the cost planning of future projects by comparison.
Before a cost analysis is carried out, preparation should be done first. In Malaysia, the
designers and clients should obtain elemental cost analysis from the Building Cost Information
Centre (BCIC), ISM. This corporate publishes the standard regulations for the preparation of
elemental cost analysis, like the ISM Manual for the Preparation of Elemental Cost Analysis. The
cost analysis shall be prepared accordingly to the tender sum instead of the final account due to its
simplicity, short process, and flexibility.
There are a few documents required for the process of cost analysis. A valid cost analysis
shall include the following documents, which are complete contract documents, successful tender
which includes a detailed full-priced BQ, working drawings and specifications, tender report,
manual for preparation of cost analysis, standard form like Form 1, Form 2, and Form 3.
According to the ISM Manual of Elemental Cost Analysis, there are a few guidelines listed
out and shall be followed during the preparation of Elemental Cost Analysis. First, we need to
identify if the buildings within the project are separated. If the buildings are not separated, then
plan drawings will be analyzed to separate the areas within the building into circulation area, usable
area, ancillary area, roof area, unenclosed spaces area. The area of circulation, usable and ancillary
areas shall be considered as the gross floor area of the building. Then according to the information
provided from the drawing and BQ, the cost analysis shall proceed to the next stage where more
total cost details will be implied. The mentioned cost must be equal to the cost of the relevant
groups.
The Standard Forms of Elemental Cost Analysis are then later used to fill up all the
information that has been obtained. In Form 1, there are two sections, where the first section
provides the overall information of the building project while the second section providing the
information and analysis of the building. This form is necessary for the client and designer to
interpret the summarised information of a building project. In Form 2, the systematical breakdown
of the elements in the building is shown. This form indicates the cost for more than 20 groups
including the main groups and subgroups. Besides the total cost of the element, other additional
information like the cost per m2, element unit quantity, element unit rate, the ratio of element per
GFA, etc. Therefore, all these realistic estimations shall be used as cost comparisons for future
similar projects. In Form 3, a brief specification like the types and quality of each element shall be
listed out in this section.
Conclusion :
Through this assignment, we are able to perform cost estimation and cost analysis based on
information like the BQ and drawing plan that is provided to the group. We are able to understand
the concept and the importance of carrying out a cost plan before a construction project, which is to
prevent exceeding in cost. Elemental Cost Analysis is one of the popular ways for the preparation
of an estimated cost. Before constructing a new project, a cost comparison shall be made with the
previous similar type of project to identify how the costs are distributed equally among the
elements in the building. A cost-cutting exercise will be used if any unusual cost or exceeding cost
is identified during the elemental breakdown of the cost of elements. Cost-efficiency buildings shall
be achieved if all the methods of controlling the cost are adapted.
References:
<https://www.slideshare.net/KaiYun96/eca-workshop-brief>.
APPENDIX
REINFORCEMENT
ITEM DESCRIPTION UNIT A1 A2 THICKNESS TOTAL
NO.1 ELEMENT NO.1 - WORK BELOW FLOOR FINISH QTY TOTAL QTY
M3
REINFORCED CONCRETE RAFT FOUNDATION M2 186 225 411.00 0.30 123.30
APRON SLAB M2 29 29.00 0.10 2.90
THICK SLAB
300MM M2 43 53 96.00 0.30 28.80
325MM M2 13 11 24.00 0.33 7.92
350MM M2 18 23 41.00 0.35 14.35
400MM M2 103 100 203.00 0.40 81.20
THICKENING M3 3 4 7.00 7.00
TOTAL REINFORCED CONCRETE = 265.47
KG
REINFORCEMENT BARS HT BARS
10MM KG 79 319 398.00 398.00
12MM KG 1861 1800 3661.00 3661.00
16MM KG 3721 3719 7440.00 7440.00
20MM KG 862 1035 1897.00 1897.00
25MM KG 553 553 1106.00 1106.00
BRC
A7 M2 35 35.00 3.02 105.70
TOTAL REINFORCEMENT = 14607.70
M2
FORMWORK Sides of RF M2 13 29 42.00 42.00
Edge M 40 42 82.00 0.10 8.20
TOTAL FORMWORK = 50.20
HT BARS
20MM KG 172 106 278.00 278.00
16MM KG 804 908 1712.00 1712.00
12MM KG 510 441 951.00 951.00
BRC
A7 M2 299 302 601.00 3.02 1815.02
A8 M2 200 224 424.00 3.95 1674.80
A9 M2 97 117 214.00 4.99 1067.86
A10 M2 33 37 70.00 6.16 431.20
TOTAL REINFORCEMENT = 5654.88
M2
FORMWORK SOFFIT M2 257 281 538.00 538.00
EXTRAOVER M 20 27 47.00 0.01 0.29
TOTAL FORMWORK = 538.29
HT BARS
16MM KG 423 422 845.00 845.00
12MM KG 128 75 203.00 203.00
BRC
A8 M2 181 253 434.00 3.95 1714.30
TOTAL REINFORCEMENT = 2072.30
M2
FORMWORK SOFFIT - SUSPENDED M2 76 79 155.00 155.00
SOFFIT - GUTTER M2 19 19 38.00 38.00
TOTAL FORMWORK = 193.00
HT
10MM KG 357 423 780.00 780.00
12MM KG 55 30 85.00 85.00
TOTAL REINFORCEMENT = 1136.00
M2
FORMWORK SIDES M2 76 82 158.00 158.00
TOTAL FORMWORK = 158.00
HT
10MM KG 458 523 981.00 981.00
12MM KG 134 104 238.00 238.00
TOTAL REINFORCEMENT = 1616.00
M2
FORMWORK SIDES M2 112 121 233.00 233.00
TOTAL FORMWORK = 233.00
Internal Doors
Item Description Rate Quantity Total Cost of Element (RM)
Internal Doors D2 184.00 8 1472.00
D2A & D8 196.00 4 784.00
D6 178.00 4 712.00
D3 178.00 12 2136.00
D5 184.00 4 736.00
D7 190.00 4 760.00
D4 253.00 4 1012.00
D9 311.00 4 1244.00
7 %
SIMILARITY INDEX
6%
INTERNET SOURCES
1%
PUBLICATIONS
%
STUDENT PAPERS
PRIMARY SOURCES
1
www.scribd.com
Internet Source 3%
2
bic.utm.my
Internet Source 2%
3
docplayer.net
Internet Source 1%
4
Cheng Sim Lim, Tien Choon Toh, Wah Peng
Lee, See Seng Ng, Chin Khian Yong, Kai Chen
<1 %
Goh. "The Effect of Different Groupings of
Building Elements on Cost Significant
Elements and their Cost Contributions to the
Total Building Cost of a Block of Medium Cost
Apartments in Malaysia", Applied Mechanics
and Materials, 2013
Publication