You are on page 1of 73

Government of Nepal

Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:

S.N. DESCRIPTION Amount Remarks


1 General Item 180,000.00
2 Buddha Statue 12,754,451.94
3 Water Fountain 600,000.00
4 Sitting Structure 700,000.00
5 Green Lounge 401,278.58
6 Road way 234,186.43
7 Road way 376,291.40
8 Miscellaneous 1,000,000.00

Sub Total 16,246,208.35


Contingenies (5%) 812,310.42
13% Vat 2,112,007.09

Grand Total 19,170,525.85

Total in Words: Rupees One Crore NinetyOne Lakh Seventy Thousand Five Hundred TwentyFive Paise EightyFive Only

Prepared By: Total Consultancy Pvt Ltd


Government of Nepal
Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:

S.N. DESCRIPTION Amount Remarks


A General Item
B Building
C Eletrical & Telephone
D Sanitary Wares & Toilet Requisites
E Water Fountain
F Green Lounge
G Waiting Area
H Miacellaneous

Sub Total
Contingenies (5%)
13% Vat

Grand Total

Signature of bidder/Authorized signature:


Date:
Name of Bidder:
Name of Firm:
Address:
Stamp:
Government of Nepal
Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
1 GENERAL ITEMS
Insurance for the damage and loss of works, plants and
1.1 vehicles; personal injury, death of labour, Employee & third
party insurance PS 180,000.00
Laboratory installation and Testing of materials and
1.2 workmanship in concrete mix design, concrete tests, test of
reinforcements etc. as per specifications. L.S 0
Total of General (1) 180,000.00

2 CIVIL WORKS 0
2.1 SITE CLEARENCE 0
Site clearance including collection of all construction
a debris, waster, removal of bushes, tree and disposal to
the 'designated place as directed by Engineer. Sq.m 100.00 7.20 720.00
b 137 cm dia tree cutting work No. 0.00 -
Dismantling of existing brickwork in mud mortar including
c
disposal of the debris out of site . Cum 7.43 -
2.2 EARTHWORK EXCAVATION 0.00 -
Earth work excavation in any kind of soils and soft rocks
upto the 4.8 m. depth as per drawing, specification and
instruction of Engineer. Cum 165.61 593.28 98,253.93
0.00 -
2 EARTHWORK BACKFILLING 0.00 -
Earthwork in backfilling in foundation trenches and floor
with materials, from associated excavation including
machine compaction in 15 cm layers with sprinkling water
required to obtain 95% density as per the specification and
approval of Engineer. Cum 32.55 185.40 6,034.06

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
0.00 -
2.4 EARTHWORK FILLING 0.00 -
Earthwork in filling with imported material in foundation
trenches and floor with materials, from associated
excavation including machine compaction in 15 cm layers
with sprinkling water required to obtain 95% density as per
the specification and approval of Engineer. Cum 23.24 370.80 8,617.99
0.00 -
2.6 PLAIN CEMENT CONCRETE WORK (P.C.C.) 0.00 -
Supply, mixing, placing, compacting PCC (plain cement
concrete) in foundation including materials, labour,
machine, carriage curing and curing etc, all complete as per
drawing, specification and approval of Engineer.
0.00 -
a) Blinding Concrete in one layers of 50 mm thick in
Cum
footing(1:3:6). 5.18 12,558.33 65,102.38
b) Blinding Concrete in one layers of 75 mm thick in
Cum
flooring(1:2:4) 72.42 14,444.76 1,046,089.52
-
2.7 CONCRETE WORKS 0.00 -
Supply, mixing, transporting, placing, compact, protection,
levelling and cure concrete with addition of antidespersiv
chemical admixture and synthetic fibres of approved quality
in doses as recommended by the respective manufactures
in different mixes PCC ( for RCC) for
superstructure ,foundation bases, foundation pads,
columns, beams, lintel, sill, walls and slabs completed as
per drawings, specification and approval of Engineer.

0.00 -
a) Footing, Column below plinth level,Tie beam, Beams,
Cum
Column & Slab, staircase (M20) 100.06 18,035.88 1,804,725.20
b) Lintel and Sill (M15) Cum 9.55 16,400.76 156,681.05
0.00 -

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
2.8 REINFORCEMENT (Fe 415) 0.00 -
Supply, cut, fabricate, trasportation, place and tie, ribbed
reinforcement steel bars (Fe 415) including cost of 16
gauge black annealed binding wire, spacer bars, lappings,
hooks, chair and supports and lead and lift up to 8 th floor,
complete as per drawings, specification and approval of
Engineer.
-
a. Footing, Column up to roof, Tiebeam,Beams,Column,
kg 125.17
lintel, sill, flooring & Slab 15674.05 1,961,921.26
0.00 -
2.9 FORM WORK 0.00 -
Supply, fabricate, transportation, placing, fixing, centering
and shuttering of plastic coated plywood or ready made
prefabricated board formwork for vertical for fair faced
concrete finished walls, (with necessary provision of
extension of reinforcement for wall ties ) and other RCC
works including nails, staging , propping supports and
bracings of steel pipes including lead and lift up to 8 th floor
and removal and disposal of the same all complete as per
specification, drawing and approval of Engineer.

0.00 -
a. Footing, Lintel & Sill. sqm 95.11 1,203.54 114,469.17
b. Column. sqm 199.82 1,203.54 240,496.18
c. Beams, Tie beam sqm 327.03 1,256.46 410,903.13
d. Slab Sqm 102.52 776.94 79,651.89
e. Staircase Sqm 54.10 1,203.54 65,113.92
2.10 BRICK WORKS 0.00 -
Providing and laying brick masonary using first class
chimney made bricks with cement sand mortar 1:6 including
scaffolding, curing, filling, cleaning and racking out mortar
a joints, making ducts, recesses where required including all
materials, labour, lead and lift for the foundation works as
per drawing, specification and approval of Engineer.
Cum -

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
Providing and laying brick masonary using first class bricks
with cement sand mortar 1:4 including scaffolding, curing,
filling, cleaning and racking out mortar joints, making ducts,
b recesses where required including all materials, labour,
lead and lift in the Ground floor as per drawing,
specification and approval of Engineer.

Cum -
Providing and laying brick masonary using first class bricks
with cement sand mortar 1:4 including scaffolding, curing,
filling, cleaning and racking out mortar joints, making ducts,
c recesses where required including all materials, labour,
lead and lift other than ground floor as per drawing,
specification and approval of Engineer.
Cum 121.02 18,582.15 2,248,787.39
0.00 -
2.11 DRY FLAT BRICK SOLING 0.00 -
Dry brick soling (one layer) with sand in foundation with first
class chimney made bricks complete in true line and level
as per drawing, specification and approval of Engineer.
Sqm 141.96 1,043.74 148,173.51
0.00 -
2.12 SALWOOD HANDRAIL OVER STEEL POST 0.00 -
Providing fabrication and fixing in position 1 m high 25mm
thick Steel post on staircase railing for main staircase
(internal) with 1 number of 75mm dia and 3 numbers of
50 mm dia horizontal member of 16 SWG stainless steel
and 1 number of 75 mm dia aluminium Handrail all
complete as per engineers approval
Rm 59.42 3,200.00 190,144.00
0.00
2.13 SLIDING WINDOW AND VENTILATOR 0.00

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
Supply, fabrication and fixing in position following type of
windows and ventillations made of bronze anodised
Aluminium Sections including all necessary accessories
such as French rollers, English weather brush, Japanese
hook locks, slide lock and pull including 4mm thick Glass
panal all complete as per drawing and engineer approval

0.00
Ventilator & Windows Sq.m 163.85
0.00
2.14 ALUMINIUM DOOR FRAME & SHUTTER 0.00
Supply, fabrication and fixing in position following type of
doors, windows and ventillations made of bronze anodised
Aluminium Sections including all necessary accessories
such as French rollers, English weather brush, Japanese
hook locks, slide lock and pull handle to doors French floor
springs, water drainages, silicone on foam seal with or
without 16 guage GI Fly screen on all openable windows
using following section all complete as per drawings,
specification and approval of engineer.

sq.m
0.00
2.15 SALWOOD CHAUKHAT FOR DOOR 0.00
Well seasoned salwood chaukhats for fixed/openable
door/windows with good finish of approved quality incuding
fixing in postion with necessary M.S. hold fasts as per
drawing and instruction all complete. Cum 2.69 202,362.65 545,266.16
0.00 -
2.16 FLUSH DOOR SHUTTERS 0.00 -
Supplying and fitting Ready made Teak wood Doors 38mm
thick ,ordinary (Seasoned and Poisoned treated ,one side
teak) with all neccessary hardware all complete as per
drawings, specification and approval of engineer.
0.00 -
a) Flush DoorShutter C.m 3.97 202,362.65 803,138.91

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
2.17 MOSAIC TILE WORKS (PRE FABRICATED) 0.00 -
Supply, laying and fixing mosaic tiles of approved make,
size, colour, laid in grey cement (1:4) including base
plaster, fitting and grouting of joints in white or coloured
cement as per drawing, specification and approval of
Engineer.
0.00 -
Floor and 150mm height skirting all area Sqm 261.52 3,753.47 981,599.97
0.00 -
0.00 -
2.18 PLASTERING 0.00 -
Supply, laying & fixing plaster in wall, column, beam or
ceiling including supply of materials, labour,mixing ,
levelling, curing & scaffolding etc. all complete as per
'drawing, specification and approval of Engineer. 0.00 -
a) 12.5 mm thick in 1:3 cement sand plaster(External part) Sqm 435.06 406.08 176,669.65
c) 12.5mm thick in 1:3 cement sand plaster(Ceiling part) Sqm 288.72 406.08 117,243.42
c) 20mm thick in 1:3 cement sand plaster(Internal part) Sqm 655.86 406.08 266,331.39
-
2.19 PORCELIN TILES 0.00 -
Supply, laying and fixing vitrified ceramic tiles Johnson or
equivalent make of approved size, colour, laid in grey
cement (1:4) including base plaster, fitting and grouting of
joints in white or coloured cement as per drawing,
specification and approval of Engineer.
0.00 -
a) Glazed tile on walls Sqm 65.42 2,902.79 189,902.84
b) Non slip tile on floor Sqm 18.64 2,902.79 54,108.01
Marble flooring on staircase Sqm 62.26 4,990.44 310,718.77
0.00 -
2.20 PAINT 0.00 -

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
Supply and applying one coat of primer and 3 coats of
distemper paint of high quality over plastered surface of
wall including supply of materials, labour, cleaning the
a surface, preparation of the base, painting & curing etc. in all
internal part of building all complete as per drawings and
approval of engineer
Sqm 527.97 303.05 160,001.58

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
Supply and applying one coat of primer and 2 coats of Apex
weather coat paint on external part of building of high
quality over plastered surface of wall including supply of
b materials, labour, cleaning the surface, preparation of the
base, painting & curing etc. all complete as per drawings
and approval of engineer
Sqm 425.03 322.94 137,260.09
Supply and applying one coat of primer and 2 coats of
distemper coat paint on ceiling of building of high quality
over plastered surface of wall including supply of materials,
c labour, cleaning the surface, preparation of the base,
painting & curing etc. all complete as per drawings and
approval of engineer
Sqm 288.72 303.05 87,496.60
Supply and painting two coat enamel paint over one coat
d of primer on the two sides of the rolling M/S shutter
Sqm -
0.00 -
2.21 CHAPRA PAINT 0.00 -
Supply and applying one coat of primer and 3 coats of
chapra paint of high quality over wooden door frame and
flushed door shutter including supply of materials, labour,
cleaning the surface, preparation of the base, painting &
curing etc. all complete as per drawings and approval of
engineer
Sqm 250.85 311.95 78,252.78
0.00 -
2.22 LANDSCAPING 0.00 -
Cut and fill site area for landscaping and beautifying area
with level site, seasonal plants, turfing as per drawing,
instruction and approval of Engineer. 0.00 -
a) General landscaping L.S 0.00 -
0.00 -
2.23 GLASS PANAL 0.00 -
4mm thick Glass Panal for the Wooden Doors with salwood
listee as per drawing and engineers approval Sqm 100.54 1,000.37 100,577.20

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
2.24 Main Gate
Placing and providing steel gate and column LS 1.00 100,000.00 100,000.00
Total of Civil Work (2) 12,754,451.94

3 Electrical & Telephone Systems


Complete electrical work LS 1.00 600,000.00 600,000.00
Total of Electrical Work (3) 600,000.00

4
SANITARY WARES AND TOILET REQUISITES
Complete sanitary and plumbing works LS 1.00 700,000.00 700,000.00
Total of Sanitary Work (4) 700,000.00
0.00 GRAND TOTAL 14,054,451.94

Total in Words: Rupees One Crore Fourty Lakh FiftyFour Thousand Four Hundred FiftyOne Paise NinetyFour Only

Prepared By: Total Consultancy Pvt Ltd


Government of Nepal
Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building

Contract No.:

Rate
S.N. DESCRIPTION Unit Quantity Total Remarks
In Figures In Words
1 GENERAL ITEMS
Insurance for the damage and loss of works, plants and
1.1 vehicles; personal injury, death of labour, Employee & third party
insurance PS
Laboratory installation and Testing of materials and
1.2 workmanship in concrete mix design, concrete tests, test of
reinforcements etc. as per specifications. L.S
Total of 1

2 CIVIL WORKS
2.1 SITE CLEARENCE
Site clearance including collection of all construction debris,
a waster, removal of bushes, tree and disposal to the 'designated
place as directed by Engineer. Sq.m 100.00
b 137 cm dia tree cutting work No.
Dismantling of existing brickwork in mud mortar including
c
disposal of the debris out of site . Cum 7.43
2.2 EARTHWORK EXCAVATION
Earth work excavation in any kind of soils and soft rocks upto
the 4.8 m. depth as per drawing, specification and instruction of
Engineer. Cum 165.61

2 EARTHWORK BACKFILLING
Earthwork in backfilling in foundation trenches and floor with
materials, from associated excavation including machine
compaction in 15 cm layers with sprinkling water required to
obtain 95% density as per the specification and approval of
Engineer. Cum 32.55

2.4 EARTHWORK FILLING


Earthwork in filling with imported material in foundation trenches
and floor with materials, from associated excavation including
machine compaction in 15 cm layers with sprinkling water
required to obtain 95% density as per the specification and
approval of Engineer. Cum 23.24

2.6 PLAIN CEMENT CONCRETE WORK (P.C.C.)


Supply, mixing, placing, compacting PCC (plain cement
concrete) in foundation including materials, labour, machine,
carriage curing and curing etc, all complete as per drawing,
specification and approval of Engineer.
a) Blinding Concrete in one layers of 50 mm thick in
Cum
footing(1:3:6). 5.18
Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building

Contract No.:

Rate
S.N. DESCRIPTION Unit Quantity Total Remarks
In Figures In Words
b) Blinding Concrete in one layers of 75 mm thick in
Cum
flooring(1:2:4) 72.42

2.7 CONCRETE WORKS


Supply, mixing, transporting, placing, compact, protection,
levelling and cure concrete with addition of antidespersiv
chemical admixture and synthetic fibres of approved quality in
doses as recommended by the respective manufactures in
different mixes PCC ( for RCC) for superstructure ,foundation
bases, foundation pads, columns, beams, lintel, sill, walls and
slabs completed as per drawings, specification and approval of
Engineer.

a) Footing, Column below plinth level,Tie beam, Beams, Column


Cum
& Slab, staircase (M20) 100.06
b) Lintel and Sill (M15) Cum 9.55

2.8 REINFORCEMENT (Fe 415)


Supply, cut, fabricate, trasportation, place and tie, ribbed
reinforcement steel bars (Fe 415) including cost of 16 gauge
black annealed binding wire, spacer bars, lappings, hooks, chair
and supports and lead and lift up to 8 th floor, complete as per
drawings, specification and approval of Engineer.

a. Footing, Column up to roof, Tiebeam,Beams,Column, lintel,


kg
sill, flooring & Slab 15674.05

2.9 FORM WORK


Supply, fabricate, transportation, placing, fixing, centering and
shuttering of plastic coated plywood or ready made
prefabricated board formwork for vertical for fair faced concrete
finished walls, (with necessary provision of extension of
reinforcement for wall ties ) and other RCC works including nails,
staging , propping supports and bracings of steel pipes including
lead and lift up to 8 th floor and removal and disposal of the
same all complete as per specification, drawing and approval of
Engineer.

a. Footing, Lintel & Sill. sqm 95.11


b. Column. sqm 199.82
c. Beams, Tie beam sqm 327.03
d. Slab Sqm 102.52
e. Staircase Sqm 54.10
2.10 BRICK WORKS
Providing and laying brick masonary using first class chimney
made bricks with cement sand mortar 1:6 including scaffolding,
curing, filling, cleaning and racking out mortar joints, making
a ducts, recesses where required including all materials, labour,
lead and lift for the foundation works as per drawing,
specification and approval of Engineer.
Cum
Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building

Contract No.:

Rate
S.N. DESCRIPTION Unit Quantity Total Remarks
In Figures In Words
Providing and laying brick masonary using first class bricks with
cement sand mortar 1:4 including scaffolding, curing, filling,
cleaning and racking out mortar joints, making ducts, recesses
b where required including all materials, labour, lead and lift in the
Ground floor as per drawing, specification and approval of
Engineer.
Cum
Providing and laying brick masonary using first class bricks with
cement sand mortar 1:4 including scaffolding, curing, filling,
cleaning and racking out mortar joints, making ducts, recesses
c where required including all materials, labour, lead and lift other
than ground floor as per drawing, specification and approval of
Engineer.
Cum 121.02

2.11 DRY FLAT BRICK SOLING


Dry brick soling (one layer) with sand in foundation with first
class chimney made bricks complete in true line and level as per
drawing, specification and approval of Engineer. Sqm 141.96

2.12 SALWOOD HANDRAIL OVER STEEL POST


Providing fabrication and fixing in position 1 m high 25mm thick
Steel post on staircase railing for main staircase (internal) with
1 number of 75mm dia and 3 numbers of 50 mm dia horizontal
member of 16 SWG stainless steel and 1 number of 75 mm dia
aluminium Handrail all complete as per engineers approval
Rm 59.42

2.13 SLIDING WINDOW AND VENTILATOR


Supply, fabrication and fixing in position following type of
windows and ventillations made of bronze anodised Aluminium
Sections including all necessary accessories such as French
rollers, English weather brush, Japanese hook locks, slide lock
and pull including 4mm thick Glass panal all complete as per
drawing and engineer approval

Ventilator & Windows Sq.m 163.85

2.14 ALUMINIUM DOOR FRAME & SHUTTER


Supply, fabrication and fixing in position following type of doors,
windows and ventillations made of bronze anodised Aluminium
Sections including all necessary accessories such as French
rollers, English weather brush, Japanese hook locks, slide lock
and pull handle to doors French floor springs, water drainages,
silicone on foam seal with or without 16 guage GI Fly screen on
all openable windows using following section all complete as per
drawings, specification and approval of engineer.

sq.m

2.15 SALWOOD CHAUKHAT FOR DOOR


Well seasoned salwood chaukhats for fixed/openable
door/windows with good finish of approved quality incuding fixing
in postion with necessary M.S. hold fasts as per drawing and
instruction all complete. Cum 2.69
Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building

Contract No.:

Rate
S.N. DESCRIPTION Unit Quantity Total Remarks
In Figures In Words

2.16 FLUSH DOOR SHUTTERS


Supplying and fitting Ready made Teak wood Doors 38mm thick
,ordinary (Seasoned and Poisoned treated ,one side teak) with
all neccessary hardware all complete as per drawings,
specification and approval of engineer.
a) Flush DoorShutter C.m 3.97
2.17 MOSAIC TILE WORKS (PRE FABRICATED)
Supply, laying and fixing mosaic tiles of approved make, size,
colour, laid in grey cement (1:4) including base plaster, fitting
and grouting of joints in white or coloured cement as per
drawing, specification and approval of Engineer.
0.00
Floor and 150mm height skirting all area Sqm 261.52
0.00
0.00
2.18 PLASTERING 0.00
Supply, laying & fixing plaster in wall, column, beam or ceiling
including supply of materials, labour,mixing , levelling, curing &
scaffolding etc. all complete as per 'drawing, specification and
approval of Engineer.
a) 12.5 mm thick in 1:3 cement sand plaster(External part) Sqm 435.06
c) 12.5mm thick in 1:3 cement sand plaster(Ceiling part) Sqm 288.72
c) 20mm thick in 1:3 cement sand plaster(Internal part) Sqm 655.86

2.19 PORCELIN TILES


Supply, laying and fixing vitrified ceramic tiles Johnson or
equivalent make of approved size, colour, laid in grey cement
(1:4) including base plaster, fitting and grouting of joints in white
or coloured cement as per drawing, specification and approval
of Engineer.
a) Glazed tile on walls Sqm 65.42
b) Non slip tile on floor Sqm 18.64
Marble flooring on staircase Sqm 62.26

2.20 PAINT
Supply and applying one coat of primer and 3 coats of distemper
paint of high quality over plastered surface of wall including
supply of materials, labour, cleaning the surface, preparation of
a the base, painting & curing etc. in all internal part of building all
complete as per drawings and approval of engineer
Sqm 527.97
Supply and applying one coat of primer and 2 coats of Apex
weather coat paint on external part of building of high quality
over plastered surface of wall including supply of materials,
b labour, cleaning the surface, preparation of the base, painting &
curing etc. all complete as per drawings and approval of
engineer
Sqm 425.03
Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building

Contract No.:

Rate
S.N. DESCRIPTION Unit Quantity Total Remarks
In Figures In Words
Supply and applying one coat of primer and 2 coats of distemper
coat paint on ceiling of building of high quality over plastered
surface of wall including supply of materials, labour, cleaning
c the surface, preparation of the base, painting & curing etc. all
complete as per drawings and approval of engineer
Sqm 288.72
Supply and painting two coat enamel paint over one coat of
d
primer on the two sides of the rolling M/S shutter Sqm

2.21 CHAPRA PAINT


Supply and applying one coat of primer and 3 coats of chapra
paint of high quality over wooden door frame and flushed door
shutter including supply of materials, labour, cleaning the
surface, preparation of the base, painting & curing etc. all
complete as per drawings and approval of engineer
Sqm 250.85

2.22 LANDSCAPING
Cut and fill site area for landscaping and beautifying area with
level site, seasonal plants, turfing as per drawing, instruction and
approval of Engineer.
a) General landscaping L.S

2.23 GLASS PANAL


4mm thick Glass Panal for the Wooden Doors with salwood
listee as per drawing and engineers approval Sqm 100.54

2.24 Main Gate


Placing and providing steel gate and column LS 1.00

Total of Civil Work (2)

3 Electrical & Telephone Systems


Complete electrical work LS 1.00
Total of Electrical Work (3)

4 SANITARY WARES AND TOILET REQUISITES


Complete sanitary and plumbing works LS 1.00
Total of Sanitary Work (4)

5 Water Fountain LS

6 Green Lounge LS

7 Waiting Area LS
Total (1+2+3+4+5+6+7)
VAT @13%

Grand Total
Corporate Seal:
Name of Construction firm: Date:
Signtaure of bidder/Authorized Signature:
Building Detail Quantity Estimate
S.No. Description Unit No Length Breadth Height Quantity Remarks
1 Site Clearence
a Site Clearence cu.m 1 100.00 100.00
b Felling of Trees No 0 0.00

c Dismantling of exsting boundary


wall cu.m 0 0.00 0.00 0.00 0.00
2 Earthwork in Excavation
Site levelling cu.m 1 10.00 7.01 1.50 52.58
a Footing
F1 cu.m 9 1.60 1.60 1.53 35.25
F2 cu.m 3 1.60 1.60 1.53 11.75
b Trench Total 47.00
Grid A, B, C & D cu.m 4 7.01 0.50 1.53 21.45
Grid 1, 2, & 3 cu.m 3 10.36 0.50 1.53 23.78
Total 45.23
Deductions
Inner footings cu.m 2 3.20 0.50 1.53 4.90
Corner footings cu.m 4 1.60 0.50 1.53 4.90
Outer footings cu,m 6 2.40 0.50 1.53 11.02
Total deductions -20.81
Grand Total 165.61

3 Earth Filling

a Back Filling 20% of excavation of


trench cu.m 1 9.05 9.05
50% of excavation of footing Cu.ft 1 23.50 23.50
Total 32.55
Earthwork filling by imported soil cum. 1 58.10 0.40 23.24
4 Structural Concrete Works
4.1 M10 PCC work 0.05m thick
Footing
F1 cu.m 9 1.60 1.60 0.10 2.30
F2 cu.m 3 1.60 6.00 0.10 2.88
5.18
4.2 M20 PCC for RCC work
a Footing 1st step
F1 cu.m 9 1.53 1.53 0.30 6.32
F2 cu.m 3 1.53 1.53 0.30 2.11
b Footing 2nd step
F1 cu.m 9 1.00 1.00 0.30 2.70
F2 cu.m 3 1.00 1.00 0.30 0.90
c Column Below Plinth
12"x12" size Column cu.m 12 0.3 0.3 1.2 1.30
d Tie Beam & DPC
Grid A, B, C & D cu.m 8 7.01 0.23 0.23 2.97
Grid 1, 2, & 3 cu.m 6 10.36 0.23 0.23 3.29
Deductions
At columns intersection cu.m 12 0.30 0.23 0.23 -0.19
e Column
Ground floor cu.m 12 0.30 0.30 2.87 3.10
First floor cu.m 12 0.30 0.30 2.87 3.10
Second floor cu.m 12 0.30 0.30 2.87 3.10
Third floor cu.m 12 0.30 0.30 2.87 3.10
Staircase Roof cu.m 4 0.30 0.30 2.87 1.03
f Beam
Ground floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.23 1.48
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.23 1.64
Deductions
At columns intersection cu.m 12 0.30 0.23 0.23 -0.19
First floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.23 1.48
Prepared By: Total Consultancy Pvt Ltd 18
S.No. Description Unit No Length Breadth Height Quantity Remarks
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.23 1.64
Deductions
At columns intersection cu.m 12 0.30 0.23 0.23 -0.19
Second floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.23 1.48
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.23 1.64
Deductions
At columns intersection cu.m 12 0.30 0.23 0.23 -0.19
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.23 1.64
Third floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.23 1.48
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.23 1.64
Deductions
At columns intersection cu.m 12 0.30 0.23 0.23 -0.19

Staircase Roof cu.m 1 17.32 0.23 0.23 0.92

g Slab
Ground floor cu.m 1 84.66 0.13 11.01
First floor cu.m 1 84.66 0.13 11.01
Second floor cu.m 1 84.66 0.13 11.01
Third floor cu.m 1 84.66 0.13 11.01
Staircase Roof cu.m 1 20.44 0.13 2.66
Deductions
At columns intersection cu.m 12 0.30 0.30 0.13 -0.14
Grid A, B, C & D cu.m 4 7.01 0.23 0.13 -0.84
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.13 -0.93

h Stair Case
Ground Floor
Flight 1 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27
Landing 1 cu.m 1 1.27 1.27 0.13 0.21
Flight 2 cu.m 1 1.07 1.27 0.13 0.18
Steps cu.m 4 1.27 0.30 0.12 0.18
Landing 2 cu.m 1 1.27 1.27 0.13 0.21
Flight 3 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27

First Floor
Flight 1 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27
Landing 1 cu.m 1 1.27 1.27 0.13 0.21
Flight 2 cu.m 1 1.07 1.27 0.13 0.18
Steps cu.m 4 1.27 0.30 0.12 0.18
Landing 2 cu.m 1 1.27 1.27 0.13 0.21
Flight 3 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27

Second Floor
Flight 1 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27
Landing 1 cu.m 1 1.27 1.27 0.13 0.21
Flight 2 cu.m 1 1.07 1.27 0.13 0.18
Steps cu.m 4 1.27 0.30 0.12 0.18
Landing 2 cu.m 1 1.27 1.27 0.13 0.21
Flight 3 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27

Third Floor
Flight 1 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27

Prepared By: Total Consultancy Pvt Ltd 19


S.No. Description Unit No Length Breadth Height Quantity Remarks
Landing 1 cu.m 1 1.27 1.27 0.13 0.21
Flight 2 cu.m 1 1.07 1.27 0.13 0.18
Steps cu.m 4 1.27 0.30 0.12 0.18
Landing 2 cu.m 1 1.27 1.27 0.13 0.21
Flight 3 cu.m 1 2.16 1.27 0.13 0.36
Steps cu.m 6 1.27 0.30 0.12 0.27
100.06
4.3 M15 PCC for RCC work
a Lintel
Ground Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
First Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
Second Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
Third Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17

b Sill
Ground Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
First Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
Second Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
Third Floor
Grid A, B, C & D cu.m 4 7.01 0.23 0.10 0.64
Grid 1, 2, & 3 cu.m 3 10.36 0.23 0.10 0.71
Deductions
At column intsrsection cu.m 24 0.30 0.23 0.10 -0.17
9.55
3" thick M15 PCC for Flooring of Ground Floor
Hall sq.m 1 41.43 0.08 41.43
Staircase sq.m 1 15.84 0.08 15.84
Store room sq.m 1 2.61 0.08 2.61
Toilets sq.m 2 2.33 0.08 4.66
Top ceiling sq.m 1 7.88 0.08 7.88
72.42
5 Formwork
5.1 Footing
F1 Sq.m 9 6.40 0.30 17.28

Prepared By: Total Consultancy Pvt Ltd 20


S.No. Description Unit No Length Breadth Height Quantity Remarks
F2 Sq.m 3 6.40 0.30 5.76
23.04
5.2 Column
Below Tie Beam
14"x14" size Column Sq.m 12 1.2 1.44 20.74

Ground Floor
12"x12" size Column Sq.m 12 1.2 2.87 41.33
First Floor
12"x12" size Column Sq.m 12 1.2 2.87 41.33
Second Floor
12"x12" size Column Sq.m 12 1.2 2.87 41.328
Third Floor
12"x12" size Column Sq.m 12 1.2 2.87 41.33
Roof
12"x12" size Column Sq.m 4 1.2 2.87 13.78
199.82
5.3 Beams
Tie Beam & DPC beam
Grid A, B, C & D Sq.m 8 7.01 0.69 38.70
Grid 1, 2, & 3 Sq.m 6 10.36 0.69 42.89
Deductions
At inner columns sq.m 2 1.44 0.23 -0.66
At outer columns Sq.m 6 1.08 0.23 -1.49
At corner columns Sq.m 4 0.72 0.23 -0.66
Ground Floor
Grid A, B, C & D Sq.m 4 7.01 0.69 38.70
Grid 1, 2, & 3 Sq.m 3 10.36 0.69 42.89
Deductions
At inner columns sq.m 2 1.44 0.23 -0.66
At outer columns Sq.m 6 1.08 0.23 -1.49
At corner columns Sq.m 4 0.72 0.23 -0.66
Second Floor
Grid A, B, C & D Sq.m 4 7.01 0.69 38.70
Grid 1, 2, & 3 Sq.m 3 10.36 0.69 42.89
Deductions
At inner columns sq.m 2 1.44 0.23 -0.66
At outer columns Sq.m 6 1.08 0.23 -1.49
At corner columns Sq.m 4 0.72 0.23 -0.66
Third Floor
Grid A, B, C & D Sq.m 4 7.01 0.69 38.70
Grid 1, 2, & 3 Sq.m 3 10.36 0.69 42.89
Deductions
At inner columns sq.m 2 1.44 0.23 -0.66
At outer columns Sq.m 6 1.08 0.23 -1.49
At corner columns Sq.m 4 0.72 0.23 -0.66

Roof grid
grid sq.m 1 17.32 0.69 11.95
327.03
5.4 Slab
All floors
All floor slab sq.m 4 84.75 339.00
Deductions
Grid A, B, C & D sq.m 16 7.01 0.23 -112.16
Grid 1, 2, & 3 sq.m 12 10.36 0.23 -124.32
102.52
5.5 Staircase
Ground Floor
Flight 1 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
Landing 1 sq.m 1 1.27 1.27 1.61

Prepared By: Total Consultancy Pvt Ltd 21


S.No. Description Unit No Length Breadth Height Quantity Remarks
Flight 2 sq.m 1 1.07 1.27 1.36
Steps sq.m 4 1.27 0.17 0.86
Landing 2 sq.m 1 1.27 1.27 1.61
Flight 3 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
First floor
Flight 1 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
Landing 1 sq.m 1 1.27 1.27 1.61
Flight 2 sq.m 1 1.07 1.27 1.36
Steps sq.m 4 1.27 0.17 0.86
Landing 2 sq.m 1 1.27 1.27 1.61
Flight 3 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
Second floor
Flight 1 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
Landing 1 sq.m 1 1.27 1.27 1.61
Flight 2 sq.m 1 1.07 1.27 1.36
Steps sq.m 4 1.27 0.17 0.86
Landing 2 sq.m 1 1.27 1.27 1.61
Flight 3 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
Third floor
Flight 1 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
Landing 1 sq.m 1 1.27 1.27 1.61
Flight 2 sq.m 1 1.07 1.27 1.36
Steps sq.m 4 1.27 0.17 0.86
Landing 2 sq.m 1 1.27 1.27 1.61
Flight 3 sq.m 1 2.16 1.27 2.74
Steps sq.m 6 1.27 0.17 1.30
54.10
5.6 Lintel
Ground Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
First Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
Second Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
Third Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66

Prepared By: Total Consultancy Pvt Ltd 22


S.No. Description Unit No Length Breadth Height Quantity Remarks

5.7 Sill
Ground Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
First Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
Second Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
Third Floor
Grid A, B, C & D sq.m 4 7.01 0.2 5.61
Grid 1, 2, & 3 sq.m 3 10.36 0.2 6.22
Deductions
At inner columns sq.m 2 1.44 0.2 -0.66
At outer columns Sq.m 6 1.08 0.2 -1.49
At corner columns Sq.m 4 0.72 0.2 -0.66
72.07
6 BrickWork
6.1 Foundation (dwarft wall)
Grid A, B, C & D cu.m 4 7.01 0.23 1.2 7.74
Grid 1, 2, & 3 cu.m 3 10.36 0.23 1.2 8.58
Deductions
At column intersection cu.m 24 0.3 0.23 1.2 -1.99
14.33
6.2 9" thick Brick wall
Ground Floor
Grid A, B & D cu.m 3 7.01 0.23 2.87 13.88
Grid 1 & 3 cu.m 2 10.36 0.23 2.75 13.11
Staircase wall cu.m 1 3.19 0.23 2.75 2.02
Toilet partation cu.m 1 4.22 0.1 2.75 1.16
Deductions
At column intersection cu.m 19 0.3 0.23 2.75 -3.61
Staircase opening cu.m 1 3.2 0.23 2.75 -2.02
Door and Windows D1 cu.m 1 0.91 0.23 2.13 -0.45
MD cu.m 1 1.22 0.23 2.13 -0.60
D2 cu.m 2 0.76 0.23 2.13 -0.74
W1 cu.m 2 1.83 0.23 1.37 -1.15
W2 cu.m 2 1.37 0.23 1.37 -0.86
W3 cu.m 2 1.37 0.23 1.37 -0.86
Lintels cu.m -1 3.34 -3.34
Sill cu.m -1 3.34 -3.34

First Floor
Grid A, B, C & D cu.m 4 7.01 0.23 2.87 18.51
Grid 1, 2 & 3 cu.m 3 10.36 0.23 2.75 19.66
Toilet partation cu.m 1 2.03 0.23 2.75 1.28
Deductions
At column intersection cu.m 24 0.3 0.23 2.75 -4.55

Prepared By: Total Consultancy Pvt Ltd 23


S.No. Description Unit No Length Breadth Height Quantity Remarks
Staircase opening cu.m 1 3.2 0.23 2.75 -2.02
Door and Windows D1 cu.m 2 0.91 0.23 2.13 -0.89
MD cu.m 1 1.22 0.23 2.13 -0.60
D2 cu.m 2 0.76 0.23 2.13 -0.74
W1 cu.m 2 1.83 0.23 1.37 -1.15
W2 cu.m 2 1.37 0.23 1.37 -0.86
W3 cu.m 2 1.37 0.23 1.37 -0.86
Lintels cu.m -1 3.34 -3.34
Sill cu.m -1 3.34 -3.34

Second Floor
Grid A, B, C & D cu.m 4 7.01 0.23 2.87 18.51
Grid 1, 2 & 3 cu.m 3 10.36 0.23 2.75 19.66
Deductions
At column intersection cu.m 24 0.3 0.23 2.75 -4.55
Staircase opening cu.m 1 3.2 0.23 2.75 -2.02
Door and Windows D1 cu.m 2 0.91 0.23 2.13 -0.89
MD cu.m 1 1.22 0.23 2.13 -0.60
D2 cu.m 2 0.76 0.23 2.13 -0.74
W1 cu.m 2 1.83 0.23 1.37 -1.15
W2 cu.m 2 1.37 0.23 1.37 -0.86
W3 cu.m 2 1.37 0.23 1.37 -0.86
Lintels cu.m -1 3.34 -3.34
Sill cu.m -1 3.34 -3.34

Third Floor
Grid A, B & D cu.m 3 7.01 0.23 2.87 13.88
Grid 1 & 3 cu.m 2 10.36 0.23 2.75 13.11
Staircase wall cu.m 1 3.19 0.23 2.75 2.02
Toilet partation cu.m 1 4.22 0.1 2.75 1.16
Deductions
At column intersection cu.m 19 0.3 0.23 2.75 -3.61
Staircase opening cu.m 1 3.2 0.23 2.75 -2.02
Door and Windows D1 cu.m 1 0.91 0.23 2.13 -0.45
MD cu.m 1 1.22 0.23 2.13 -0.60
D2 cu.m 2 0.76 0.23 2.13 -0.74
W1 cu.m 2 1.83 0.23 1.37 -1.15
W2 cu.m 2 1.37 0.23 1.37 -0.86
W3 cu.m 2 1.37 0.23 1.37 -0.86
Lintels cu.m -1 3.34 -3.34
Sill cu.m -1 3.34 -3.34

Staircase walls cum 1 8.66 0.23 2.75 5.48


At column intersection cu.m 8 0.3 0.23 2.75 -1.52
Door cu.m 1 0.76 0.23 2.13 -0.37
Compound wall cu.m 1 78 0.23 2 35.88

106.69

7 Cement sand Plaster (1:4)


7.1 Building Exeternal Part
East Part sq.m 1 98.32 98.32
North Part sq.m 1 151.87 151.87
Deduction W1 sq.m 4 1.83 1.37 -5.01
W2 sq.m 8 1.37 1.37 -7.51
West Part sq.m 1 108.55 108.55
Deduction D2 sq.m 8 0.76 2.13 -6.48
South sq.m 1 151.16 151.16
Deduction W1 sq.m 4 1.83 1.37 -5.01
W2 sq.m 8 1.37 1.37 -7.51
Staircase opening sq.m 4 10.83 -43.32
435.06

Prepared By: Total Consultancy Pvt Ltd 24


S.No. Description Unit No Length Breadth Height Quantity Remarks
7.2 Internal Plaster
7.2.1 Wall
Ground Floor
Hall sq.m 1 25.76 2.75 70.84
Staircase sq.m 1 16.02 2.75 44.06
Store room sq.m 1 6.74 2.75 18.54
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -2.51
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -1.88
W3 sq.m 2 1.37 1.37 -1.88
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -2.60
Staircase opening sq.m 1 3.2 2.75 -4.40

First Floor
Service room sq.m 2 16.37 2.75 90.04
Waiting room sq.m 1 6.74 2.75 18.54
Lobby sq.m 1 10.26 2.75 28.22
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -2.51
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -1.88
W3 sq.m 2 1.37 1.37 -1.88
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -2.60
Staircase opening sq.m 1 3.2 2.75 -4.40

Second Floor
Service room sq.m 2 16.37 2.75 90.04
Waiting room sq.m 1 6.74 2.75 18.54
Lobby sq.m 1 10.26 2.75 28.22
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -2.51
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -1.88
W3 sq.m 2 1.37 1.37 -1.88
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -2.60
Staircase opening sq.m 1 3.2 2.75 -4.40

Third Floor
Hall sq.m 1 25.76 2.75 70.84
Staircase sq.m 1 16.02 2.75 44.06
Store room sq.m 1 6.74 2.75 18.54
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -2.51
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -1.88
W3 sq.m 2 1.37 1.37 -1.88
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -2.60
Staircase opening sq.m 1 3.2 2.75 -4.40
Staircase covering sq.m 1 16.02 2.75 44.06
655.86
7.2.2 Ceiling
Ground Floor
Hall sq.m 1 41.43 41.43
Staircase sq.m 1 15.84 15.84
Store room sq.m 1 2.61 2.61
Toilets sq.m 2 2.33 4.66
Top ceiling sq.m 1 7.88 7.88

Prepared By: Total Consultancy Pvt Ltd 25


S.No. Description Unit No Length Breadth Height Quantity Remarks

First Floor
Service room sq.m 2 15.79 31.58
Waiting room sq.m 1 2.61 2.61
Lobby sq.m 1 6.19 6.19
Toilets sq.m 2 7.88 15.76
Top ceiling sq.m 1 7.88 7.88

Second Floor
Service room sq.m 2 15.79 31.58
Waiting room sq.m 1 2.61 2.61
Lobby sq.m 1 6.19 6.19
Toilets sq.m 2 7.88 15.76
Top ceiling sq.m 1 7.88 7.88

Third floor
Hall sq.m 1 41.43 41.43
Staircase sq.m 1 15.84 15.84
Store room sq.m 1 2.61 2.61
Toilets sq.m 2 2.33 4.66
Top ceiling sq.m 1 7.88 7.88
Staircase cover sq.m 1 15.84 15.84
288.72
8 a) Wall primer
Building Exeternal Part
East Part sq.m 1 98.32 98.32
North Part sq.m 1 151.87 151.87
Deduction W1 sq.m 4 1.83 1.37 -10.03
W2 sq.m 4 1.37 1.37 -7.51
W3 sq.m 4 1.37 1.37 -7.51
West Part sq.m 1 108.55 108.55
Deduction D2 sq.m 8 0.76 2.13 -6.48
South sq.m 1 151.16 151.16
Deduction W1 sq.m 4 1.83 1.37 -10.03
W2 sq.m 4 1.37 1.37 -7.51
W3 sq.m 4 1.37 1.37 -7.51
Staircase opening sq.m 4 10.83 -43.32
410.02
8 b) Exterior Imulsion
Building Exeternal Part
East Part sq.m 1 98.32 98.32
North Part sq.m 1 151.87 151.87
Deduction W1 sq.m 4 1.83 1.37 -10.03
W2 sq.m 4 1.37 1.37 -7.51
West Part sq.m 1 108.55 108.55
Deduction D2 sq.m 8 0.76 2.13 -6.48
South sq.m 1 151.16 151.16
Deduction W1 sq.m 4 1.83 1.37 -10.03
W2 sq.m 4 1.37 1.37 -7.51
Staircase opening sq.m 4 10.83 -43.32
425.03
9 a) Wall primer (interior)
Ground Floor
Hall sq.m 1 25.76 2.75 70.84
Staircase sq.m 1 16.02 2.75 44.06
Store room sq.m 1 6.74 2.75 18.54
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -2.51
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -1.88
W3 sq.m 2 1.37 1.37 -1.88
D1 sq.m 1 0.91 2.13 -1.94

Prepared By: Total Consultancy Pvt Ltd 26


S.No. Description Unit No Length Breadth Height Quantity Remarks
D2 sq.m 2 1.22 2.13 -2.60
Staircase opening sq.m 1 3.2 2.75 -4.40

First Floor
Service room sq.m 2 16.37 2.75 90.04
Waiting room sq.m 1 6.74 2.75 18.54
Lobby sq.m 1 10.26 2.75 28.22
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -5.01
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -3.75
W3 sq.m 2 1.37 1.37 -3.75
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -5.20
Staircase opening sq.m 1 3.2 2.75 -8.80

Second Floor
Service room sq.m 2 16.37 2.75 90.04
Waiting room sq.m 1 6.74 2.75 18.54
Lobby sq.m 1 10.26 2.75 28.22
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -5.01
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -3.75
W3 sq.m 2 1.37 1.37 -3.75
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -5.20
Staircase opening sq.m 1 3.2 2.75 -8.80

Third Floor
Hall sq.m 1 25.76 2.75 70.84
Staircase sq.m 1 16.02 2.75 44.06
Store room sq.m 1 6.74 2.75 18.54
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -5.01
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -3.75
W3 sq.m 2 1.37 1.37 -3.75
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -5.20
Staircase opening sq.m 1 3.2 2.75 -8.80
Staircase covering sq.m 1 16.02 2.75 -44.06
527.97
9 b) Distemper
Ground Floor
Hall sq.m 1 25.76 2.75 70.84
Staircase sq.m 1 16.02 2.75 44.06
Store room sq.m 1 6.74 2.75 18.54
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -2.51
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -1.88
W3 sq.m 2 1.37 1.37 -1.88
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -2.60
Staircase opening sq.m 1 3.2 2.75 -4.40

First Floor
Service room sq.m 2 16.37 2.75 90.04
Waiting room sq.m 1 6.74 2.75 18.54
Lobby sq.m 1 10.26 2.75 28.22
Toilets sq.m 2 6.48 2.75 35.64

Prepared By: Total Consultancy Pvt Ltd 27


S.No. Description Unit No Length Breadth Height Quantity Remarks
Deductions W1 sq.m 2 1.83 1.37 -5.01
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -3.75
W3 sq.m 2 1.37 1.37 -3.75
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -5.20
Staircase opening sq.m 1 3.2 2.75 -8.80

Second Floor
Service room sq.m 2 16.37 2.75 90.04
Waiting room sq.m 1 6.74 2.75 18.54
Lobby sq.m 1 10.26 2.75 28.22
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -5.01
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -3.75
W3 sq.m 2 1.37 1.37 -3.75
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -5.20
Staircase opening sq.m 1 3.2 2.75 -8.80

Third Floor
Hall sq.m 1 25.76 2.75 70.84
Staircase sq.m 1 16.02 2.75 44.06
Store room sq.m 1 6.74 2.75 18.54
Toilets sq.m 2 6.48 2.75 35.64
Deductions W1 sq.m 2 1.83 1.37 -5.01
MD sq.m 1 1.22 2.13 -2.60
W2 sq.m 2 1.37 1.37 -3.75
W3 sq.m 2 1.37 1.37 -3.75
D1 sq.m 1 0.91 2.13 -1.94
D2 sq.m 2 1.22 2.13 -5.20
Staircase opening sq.m 1 3.2 2.75 -8.80
Staircase covering sq.m 1 16.02 2.75 -44.06
527.97

9c Ceiling
Ground Floor
Hall sq.m 1 41.43 41.43
Staircase sq.m 1 15.84 15.84
Store room sq.m 1 2.61 2.61
Toilets sq.m 2 2.33 4.66
Top ceiling sq.m 1 7.88 7.88

First Floor
Service room sq.m 2 15.79 31.58
Waiting room sq.m 1 2.61 2.61
Lobby sq.m 1 6.19 6.19
Toilets sq.m 2 7.88 15.76
Top ceiling sq.m 1 7.88 7.88

Second Floor
Service room sq.m 2 15.79 31.58
Waiting room sq.m 1 2.61 2.61
Lobby sq.m 1 6.19 6.19
Toilets sq.m 2 7.88 15.76
Top ceiling sq.m 1 7.88 7.88

Third floor
Hall sq.m 1 41.43 41.43
Staircase sq.m 1 15.84 15.84
Store room sq.m 1 2.61 2.61

Prepared By: Total Consultancy Pvt Ltd 28


S.No. Description Unit No Length Breadth Height Quantity Remarks
Toilets sq.m 2 2.33 4.66
Top ceiling sq.m 1 7.88 7.88
Staircase cover sq.m 1 15.84 15.84
Total 288.72
10 Chapra Paint
Frame 4"
Door and Windows MD sq.m 4 5.48 0.30 6.58
D1 sq.m 5 5.17 0.30 7.76
D2 sq.m 8 4.57 0.30 10.97
W1 sq.m 8 6.4 0.30 15.36
W2 sq.m 8 5.48 0.30 13.15
W3 sq.m 8 5.48 0.30 13.15
66.96
38mm Thick Door Shutter
Door and Windows MD sq.m 4 1.22 2.28 22.25
D1 sq.m 5 1.83 2.28 41.72
D2 sq.m 8 1.22 2.28 44.51
W1 sq.m 8 1.83 2.75 30.20
W2 sq.m 8 1.37 2.75 22.61
W3 sq.m 8 1.37 2.75 22.61
183.89
11 Flooring works
11.1 1 layer flat Brick soling
Grid A, B, C & D cu.m 4 7.01 0.50 14.02
Grid 1, 2, & 3 cu.m 3 10.36 0.5 15.54
Foundation F1 cu.m 9 1.60 1.60 23.04
F2 cu.m 3 1.60 1.53 7.34
Deductions
Inner footings cu.m 2 1.60 0.50 1.60
Corner footings cu.m 4 1.60 0.50 3.20
Outer footings cu,m 6 1.60 0.50 4.80

Soling on room floor


Hall sq.m 1 41.43 41.43
Staircase sq.m 1 15.84 15.84
Store room sq.m 1 2.61 2.61
Toilets sq.m 2 2.33 4.66
Top ceiling sq.m 1 7.88 7.88
141.96
11.3 Ceramic Tiles For Toilets
Ground Floor Floor sq.m 2 2.33 4.66
Wall sq.m 2 5.38 1.52 16.36
First Floor Floor sq.m 2 2.33 4.66
Wall sq.m 2 5.38 1.52 16.36
Second Floor Floor sq.m 2 2.33 4.66
Wall sq.m 2 5.38 1.52 16.36
Third Floor Floor sq.m 2 2.33 4.66
Wall sq.m 2 5.38 1.52 16.36
Wall 65.42
Floor 18.64
11.4 Mosaic Tiles Flooring
Ground Floor
Hall sq.m 1 41.43 41.43
Skirting 6" height sq.m 1 25.76 0.15 3.86
Staircase sq.m 1 15.84 15.84
Skirting 6" height sq.m 1 16.02 0.15 2.40
Store room sq.m 1 2.61 2.61
Skirting 6" height sq.m 1 6.74 0.15 1.01
Top ceiling sq.m 1 7.88 7.88

First Floor
Service room sq.m 2 15.79 31.58

Prepared By: Total Consultancy Pvt Ltd 29


S.No. Description Unit No Length Breadth Height Quantity Remarks
Skirting 6" height sq.m 2 16.37 0.15 4.91
Waiting room sq.m 1 2.61 2.61
Skirting 6" height sq.m 1 6.74 0.15 1.01
Lobby sq.m 1 6.19 6.19
Skirting 6" height sq.m 1 10.26 0.15 1.54
Top ceiling sq.m 1 7.88 7.88

Second Floor
Service room sq.m 2 15.79 31.58
Skirting 6" height sq.m 2 16.37 0.15 4.91
Waiting room sq.m 1 2.61 2.61
Skirting 6" height sq.m 1 6.74 0.15 1.01
Lobby sq.m 1 6.19 6.19
Skirting 6" height sq.m 1 10.26 0.15 1.54
Top ceiling sq.m 1 7.88 7.88

Hall sq.m 1 41.43 41.43


Skirting 6" height sq.m 1 25.76 0.15 3.864
Staircase sq.m 1 15.84 15.84
Skirting 6" height sq.m 1 16.02 0.15 2.403
Store room sq.m 1 2.61 2.61
Skirting 6" height sq.m 1 6.74 0.15 1.011
Top ceiling sq.m 1 7.88 7.88
261.518
11.5 Marble flooring in staircase
Flight 1 steps rise sq.m 6 1.27 0.17 1.30
Flight 1 steps thread sq.m 5 1.27 0.25 1.59
Landing 1 sq.m 1 1.27 1.27 1.61
Flight 2 steps rise sq.m 4 1.27 0.17 0.86
Flight 2 steps thread sq.m 3 1.27 0.25 0.95
Landing 2 sq.m 1 1.27 1.27 1.61
Flight 3 steps rise sq.m 6 1.27 0.17 1.30
Flight 3 steps thread sq.m 5 1.27 0.25 1.59
Landing part sq.m 1 3.66 1.3 4.76
62.26

12 Wood Work
12.1 Sal Wood Chaukhat
Door and Windows MD cu.m 4 5.48 0.1 0.1 0.22
D1 cu.m 5 5.17 0.1 0.1 0.26
D2 cu.m 8 4.57 0.1 0.1 0.37
W1 cu.m 8 9.14 0.1 0.1 0.73
W2 cu.m 8 7 0.1 0.1 0.56
W3 cu.m 8 7 0.1 0.1 0.56
2.69
12.2 38mm Thick Door Shutter
Door and Windows MD cu.m 4 1.22 2.28 0.05 0.56
D1 cu.m 5 1.83 2.28 0.05 1.04
D2 cu.m 8 1.22 2.28 0.05 1.11
W1 cu.m 8 1.83 2.75 0.05 0.50
W2 cu.m 8 1.37 2.75 0.05 0.38
W3 cu.m 8 1.37 2.75 0.05 0.38
3.97
Total saal wood 6.66
13 Aluminium work
Handrail
Stair Case R.m 1 28.00 28.00
Railing all around R.m 3 13.39 13.39
Railing at roof R.m 1 18.03 18.03
59.42
14 Glass panal for wooden windows
W1 sq.m 8 1.83 2.75 40.26

Prepared By: Total Consultancy Pvt Ltd 30


S.No. Description Unit No Length Breadth Height Quantity Remarks
W2 sq.m 8 1.37 2.75 30.14
W3 sq.m 8 1.37 2.75 30.14
100.54

Prepared By: Total Consultancy Pvt Ltd 31


32
Reinforcement Calcuation Sheet of Building
Total No.
Dia. Of Total Nominal
No. of Total No. of Length Length in
S.N. Details of Work Bar in length in Mass
Item of Bars adopted in ft m
mm m (Kg/m)
Bars
1 Footing
F1 3 23 69 12.00 6.00 1.83 126.18 0.889
F2 9 26 234 12.00 6.00 1.83 427.92 0.889

2 Columns up to Roof
C1 12 8 96 16 40.00 12.19 1170.37 1.580
Upto plinth level
C2 12 8 96 16 8.00 2.44 234.07 1.580

Stirrups
Plinth level to roof level 12 120 1440 8 3.33 1.01 1461.51 0.395
12 120 1440 8 2.33 0.71 1022.62 0.395
Upto plinth level
12 24 288 8 3.33 1.01 292.30 0.395
12 24 288 8 2.33 0.71 204.52 0.395

3 Tie Beam
3.1 Lower
B1 3 6 18 16 34.00 10.36 186.53 1.580
B2 4 6 24 16 25.00 7.62 182.87 1.580

Stirrups 8mm 3 102 306 8 2 0.71 217.31 0.395


4 75 300 8 2 0.71 213.04 0.395
3.2 Upper(Plinth)
B1 3 6 18 16 34.00 10.36 186.53 1.580
B2 4 6 24 16 25.00 7.62 182.87 1.580

Stirrups 8mm 3 102 306 8 2 0.71 217.31 0.395


4 75 300 8 2 0.71 213.04 0.395
4 Beams
4.1 Beams Ground Floor
B1 3 6 18 16 34.00 10.36 186.53 1.580
B2 4 6 24 16 25.00 7.62 182.87 1.580

Stirrups 8mm 3 102 306 8 2 0.71 217.31 0.395


4 75 300 8 2 0.71 213.04 0.395

4.2 Beams First Floor


B1 3 6 18 16 34.00 10.36 186.53 1.580
B2 4 6 24 16 25.00 7.62 182.87 1.580

Stirrups 8mm 3 102 306 8 2 0.71 217.31 0.395


4 75 300 8 2 0.71 213.04 0.395

4.3 Beams Second Floor


B1 3 6 18 16 34.00 10.36 186.53 1.580
B2 4 6 24 16 25.00 7.62 182.87 1.580

Stirrups 8mm 3 102 306 8 2 0.71 217.31 0.395


4 75 300 8 2 0.71 213.04 0.395

4.4 Beams Third Floor


B1 3 6 18 16 34.00 10.36 186.53 1.580
B2 4 6 24 16 25.00 7.62 182.87 1.580

Stirrups 8mm 3 102 306 8 2 0.71 217.31 0.395


4 75 300 8 2 0.71 213.04 0.395

4.5 Beams staircase roof


B1 2 6 12 16 12.83 3.91 46.92 1.580
B2 2 6 12 16 15.58 4.75 56.98 1.580

Prepared By: Total Consultancy Pvt Ltd


33
Total No.
Dia. Of Total Nominal
No. of Total No. of Length Length in
S.N. Details of Work Bar in length in Mass
Item of Bars adopted in ft m
mm m (Kg/m)
Bars
Stirrups 8mm 2 38 77 8 2 0.71 54.67 0.395
2 47 93 8 2 0.71 66.38 0.395

5 Slab
5.1 Slab Ground Floor
Slab 1 1 61 61 10 26.00 7.92 479.43 0.62
1 78 78 10 20.17 6.15 479.43 0.62
Slab 2 1 48 48 10 23.00 7.01 336.48 0.62
1 69 69 10 16.00 4.88 336.48 0.62
Extra bars 1 100 100 10 4.50 1.37 137.15 0.62
Lapping 1 250 250 10 2.00 0.61 152.39 0.62

5.2 Slab First Floor


Slab 1 1 61 61 10 26.00 7.92 479.43 0.62
1 78 78 10 20.17 6.15 479.43 0.62
Slab 2 1 48 48 10 23.00 7.01 336.48 0.62
1 69 69 10 16.00 4.88 336.48 0.62
Extra bars 1 100 100 10 4.50 1.37 137.15 0.62
Lapping 1 250 250 10 2.00 0.61 152.39 0.62

5.3 Slab Second Floor


Slab 1 1 61 61 10 26.00 7.92 479.43 0.62
1 78 78 10 20.17 6.15 479.43 0.62
Slab 2 1 48 48 10 23.00 7.01 336.48 0.62
1 69 69 10 16.00 4.88 336.48 0.62
Extra bars 1 100 100 10 4.50 1.37 137.15 0.62
Lapping 1 250 250 10 2.00 0.61 152.39 0.62

5.4 Slab Third Floor


Slab 1 1 61 61 10 26.00 7.92 479.43 0.62
1 78 78 10 20.17 6.15 479.43 0.62
Slab 2 1 48 48 10 23.00 7.01 336.48 0.62
1 69 69 10 16.00 4.88 336.48 0.62
Extra bars 1 100 100 10 4.50 1.37 137.15 0.62
Lapping 1 250 250 10 2.00 0.61 152.39 0.62

5.5 Slab Staircase roof Floor


Slab 1 1 47 47 10 18.58 5.66 267.57 0.62
1 56 56 10 15.75 4.80 267.57 0.62
Extra bars 1 50 50 8 4.50 1.37 68.58 0.40

6 Staircase
main bar 3 11 33 12 16.00 4.88 160.93 0.89
3 11 33 12 17.00 5.18 170.98 0.89
3 11 33 12 16.00 4.88 160.93 0.89
Transverse bars 3 16 48 8 5.00 1.52 73.15 0.40
3 13 39 8 5.00 1.52 59.43 0.40
3 16 48 8 5.00 1.52 73.15 0.40
steps 3 120 360 7 3.00 0.91 329.17 0.30

7 Lintel
Lintel
MD 4 4 16 12 13.00 3.96 63.40 0.89
D1 5 4 20 12 6.00 1.83 36.57 0.89
D2 8 4 32 12 5.50 1.68 53.64 0.89
W1 4 4 16 12 16.00 4.88 78.02 0.89
W2 5 4 20 12 14.50 4.42 88.39 0.89
W3 2 4 8 12 13.00 3.96 31.70 0.89

Prepared By: Total Consultancy Pvt Ltd


34
Total No.
Dia. Of Total Nominal
No. of Total No. of Length Length in
S.N. Details of Work Bar in length in Mass
Item of Bars adopted in ft m
mm m (Kg/m)
Bars
Stirrups8mm@ 150mm c/c 1 230 230 8.00 1.83 0.56 128.28 0.40
8 Sill
W1 4 2 8 12 16.00 4.88 39.01 0.89
W2 5 2 10 12 14.50 4.42 44.19 0.89
W3 2 2 4 12 13.00 3.96 15.85 0.89

9 Strap Beam
longtidunal bars 3 6 18 16 10.50 3.20 57.60 1.58
stirrups 3 25 75 8 4.50 1.37 102.86 0.40
Total
additional 5% extra for wastage
Grand Total

Prepared By: Total Consultancy Pvt Ltd


35

Total
Weight
(Kg)

112.16
380.37

1849.48

369.90

577.38
404.00

115.48
80.80

294.76
288.98

85.85
84.17

294.76
288.98

85.85
84.17

294.76
288.98

85.85
84.17

294.76
288.98

85.85
84.17

294.76
288.98

85.85
84.17

294.76
288.98

85.85
84.17

74.15
90.05

Prepared By: Total Consultancy Pvt Ltd


36

Total
Weight
(Kg)
21.60 1210
26.23 1507

295.95
295.95
207.71
207.71
84.66
94.07

295.95
295.95
207.71
207.71
84.66
94.07

295.95
295.95
207.71
207.71
84.66
94.07

295.95
295.95
207.71
207.71
84.66
94.07

165.17
165.17
27.09

143.05
151.99
143.05
28.90
23.48
28.90
99.56

56.35
32.51
47.68
69.36
78.57
28.18

Prepared By: Total Consultancy Pvt Ltd


37

Total
Weight
(Kg)
50.68

34.68
39.28
14.09

91.03
40.64
14927.67
746.38
15674.05

Prepared By: Total Consultancy Pvt Ltd


Government of Nepal
Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
No. Description Unit Quantity Unit Rate Amount(NRs) Remarks

1 CIVIL WORKS
1.1 SITE CLEARENCE
Site clearance including collection of all construction
a debris, waster, removal of bushes, tree and disposal to Sq.m 13.00 7.2 93.6
the 'designated place as directed by Engineer.
1.2 EARTHWORK EXCAVATION
Earth work excavation in any kind of soils and soft rocks
upto the 4.8 m. depth as per drawing, specification and Cum 6.50 593.28 3856.32
instruction of Engineer.
1.3 Soling
Dry brick soling (one layer) with sand in foundation with first
class chimney made bricks complete in true line and level
as per drawing, specification and approval of Engineer. Cum 3.25 593.28 1928.16

1.4 PLAIN CEMENT CONCRETE WORK (P.C.C.)


Supply, mixing, placing, compacting PCC (plain cement
concrete) in foundation including materials, labour,
machine, carriage curing and curing etc, all complete as per
drawing, specification and approval of Engineer.

a) Blinding Concrete in one layers of 75 mm thick in


Cum 1.95 14444.76 28167.282
flooring(1:2:4)

Prepared By: Total Consultancy Pvt Ltd


Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
No. Description Unit Quantity Unit Rate Amount(NRs) Remarks

1.5 CONCRETE WORKS


Supply, mixing, transporting, placing, compact, protection,
levelling and cure concrete with addition of antidespersiv
chemical admixture and synthetic fibres of approved quality
in doses as recommended by the respective manufactures
in different mixes PCC ( for RCC) for
superstructure ,foundation bases, foundation pads,
columns, beams, lintel, sill, walls and slabs completed as
per drawings, specification and approval of Engineer.

a) M20 Concrete in foundation of water fountain Cum 6.50 18035.88 117233.22

2 Water Fountain LS 1 250000 250000

GRAND TOTAL 401278.582

Total in Words: Rupees Four Lakh One Thousand Two Hundred SeventyEight Paise FiftyEight Only

Prepared By: Total Consultancy Pvt Ltd


Government of Nepal
Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
Description Unit Quantity Unit Rate Amount(NRs) Remarks
No.
1 CIVIL WORKS
1.1 SITE CLEARENCE
Site clearance including collection of all construction
a debris, waster, removal of bushes, tree and disposal to Sq.m 198.00 7.2 1425.6
the 'designated place as directed by Engineer.
1.2 EARTHWORK EXCAVATION
Earth work excavation in any kind of soils and soft rocks
upto the 4.8 m. depth as per drawing, specification and Cum 59.40 593.28 35240.832
instruction of Engineer.
1.3 Compound Wall
Placing concrete block including 1:4 cement ratio mortar at
piece 792.00 60 47520
the compound of the Green Lounge

2 Natural dubbo LS 1 150000 150000

GRAND TOTAL 234186.432

Total in Words: Rupees Two Lakh ThirtyFour Thousand One Hundred EightySix Paise FourtyThree Only

Prepared By: Total Consultancy Pvt Ltd


Government of Nepal
Barhabise Municipality
Sindupalchok, Province-03

Bill of Quantities (BOQ)

Name of Project: Barhabise Municipality Building


Contract No.:
Item
No. Description Unit Quantity Unit Rate Amount(NRs) Remarks

1 CIVIL WORKS
1.1 SITE CLEARENCE
Site clearance including collection of all construction
a debris, waster, removal of bushes, tree and disposal to Sq.m 50.00 7.2 360
the 'designated place as directed by Engineer.
1.2 EARTHWORK EXCAVATION
Earth work excavation in any kind of soils and soft rocks
upto the 4.8 m. depth as per drawing, specification and Cum 10.00 593.28 5932.8
instruction of Engineer.
1.3 Soling
Dry brick soling (one layer) with sand in foundation with first
class chimney made bricks complete in true line and level
as per drawing, specification and approval of Engineer. Cum 12.50 593.28 7416

Prepared By: Total Consultancy Pvt Ltd


1.4 PLAIN CEMENT CONCRETE WORK (P.C.C.)
Supply, mixing, placing, compacting PCC (plain cement
concrete) in foundation including materials, labour,
machine, carriage curing and curing etc, all complete as per
drawing, specification and approval of Engineer.

a) Blinding Concrete in one layers of 75 mm thick in


Cum 5.00 14444.76 72223.8
flooring(1:2:4)
1.5 CONCRETE WORKS
Supply, mixing, transporting, placing, compact, protection,
levelling and cure concrete with addition of antidespersiv
chemical admixture and synthetic fibres of approved quality
in doses as recommended by the respective manufactures
in different mixes PCC ( for RCC) for
superstructure ,foundation bases, foundation pads,
columns, beams, lintel, sill, walls and slabs completed as
per drawings, specification and approval of Engineer.

a) M20 Concrete in foundation of waiting area Cum 10.00 18035.88 180358.8

2 Sitting Chair piece 44 2500 110000

GRAND TOTAL 376291.4

Total in Words: Rupees Three Lakh SeventySix Thousand Two Hundred NinetyOne Paise Fourty Only

Prepared By: Total Consultancy Pvt Ltd


Water Fountain, Green Lounge & Waiting area Quantity Estimate
S.No. Description Unit No Length Breadth Height Quantity Remarks
1 Water Fountain
1a Site Clearence
Site Clearence cu.m 1 13.00 13.00
1b Earthwork in Excavation
Site levelling cu.m 1 13.00 0.50 6.50
1c Soling
Water fountain foundation cu.m 1 13.00 0.25 3.25
1d Plain Cement Concrete
Water fountain foundation cu.m 1 13.00 0.15 1.95
1e M20 Concrete cu.m 1 13.00 0.50 6.50

2 Green Lounge
2a Site Clearence
Site Clearence cu.m 1 198.00 198.00
2b Earthwork in Excavation
Site levelling cu.m 1 198.00 0.30 59.40
1c Compound wall Blocks
Blocks Nos 1 198.00 0.25 792.00

3 Waiting Area
3a Site Clearence
Site Clearence cu.m 1 50.00 50.00
3b Earthwork in Excavation
Site levelling cu.m 1 50.00 0.20 10.00
3c Soling
Water fountain foundation cu.m 1 50.00 0.25 12.50
3d Plain Cement Concrete
Water fountain foundation cu.m 1 50.00 0.10 5.00
3e M20 Concrete cu.m 1 50.00 0.20 10.00

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
1 SITE CLEARANCE
Felling of trees including cutting branches, sawing and carrying up to 15m away
from the site. For Each
1.01 1,1,ka Girth of tree 12 - 30cm Each 93.60
1.02 1,1,kha Girth of tree 31 - 60cm Each 280.80
1.03 1,1,ga Girth of tree 61 - 90cm Each 705.60
1.04 1,1,gha Girth of tree 91 - 120cm Each 0.00
1.05 1,1,ng Girth of tree 121 - 180cm Each 0.00
1.06 1,1,cha Girth of tree 181 - 240cm Each 0.00
1.07 1,1,chha Girth of tree 241 - 300cm Each 0.00
1.08 1,1,ja Girth of tree over 301cm Each 0.00
Tree root digging, lifting it and carrying up to 15m away from the site. For Each
1.09 1,2,ka Girth of tree 12 - 30cm Each 288.00
1.10 1,2,kha Girth of tree 31 - 60cm Each 381.60
1.11 1,2,ga Girth of tree 61 - 90cm Each 1814.40
1.12 1,2,gha Girth of tree 91 - 120cm Each 0.00
1.13 1,2,ng Girth of tree 121 - 180cm Each 0.00
1.14 1,2,cha Girth of tree 181 - 240cm Each 0.00
1.15 1,2,chha Girth of tree 241 - 300cm Each 0.00
1.16 1,6 Bamboo cutting,root digging,removel of bamboo from site (Dug-pit
dimension to be measured).For 1m3 cum 2016.00
1.17 1,7 Surface dressing work,cutting and filling earthwork,including levelling
ground surface(service road etc.). For 1m2 sqm 7.20
1.18 1 ,8 Excavation 15-20 cm of the top soil including disposal
out side of the construction site. For 1 m2 sqm 115.20
2 EARTHWORK
Earthwork in excavation including a lead of 10m and a lift of 1.5m in:
2.01 2,1 Soft Clay : For 1 cum cum 519.12
2.02 2,2 Hard clay mixed boulder less than 30cm size :.For 1cum cum 593.28
2.03 2 ,10 Soft Rock : For 1 cum cum 1854.00
2.04 2 ,4 Medium Rock without blasting : For 1 cum cum 2224.80
2.05 2 ,6ka Hard Rock without chiselling : For 1 cum cum 3708.00
Earthwork in filling including watering & ramming every 20cm th. Layers For 1cum :
2.06 2 ,25ka With Ordinary Soil cum 370.80
Earthwork in filling including ramming every 15cm th. Layers (without watering )For 1cum :
2.07 2 ,25kha With Ordinary Soil cum 185.40
Turfing work Including cutting, hauling for 10m and watering For 1sqm :
2.08 2 , 40 Turfing work cum 37.08
3 STONE WORK
Stone (rubble) masonry work up to 5 m ht. Of wall including collection of stones,
preparation of mortar and a lead of 10 m. For 1 cum :
3.01 6,1,ka,2 In 1:4 Cement Sand Mortar cum 11730.00
3.02 6,1ka,3 In 1:6 Cement Sand Mortar cum 10686.84

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
3.03 6 ,2.1 Dry Stone Masonry cum 4400.82
3.04 6 ,2.2 Mud Mortar Stone Masonry cum 4729.03

Stone (rubble) masonry work 5 to 10 m ht. Of wall including collection of stones,


preparation of mortar and a lead of 10 m.For 1 cum :
3.05 6,1,ka,2 In 1:4 Cement Sand Mortar cum 12572.40
3.06 6,1,ka,3 In 1:6 Cement Sand Mortar cum 11529.24
3.07 6 ,2.2 Mud Mortar Stone Masonry cum 5571.43
Stone (rubble) masonry work in arch or in sloping plane including collection of stones,
preparation of mortar and a lead of 30 m. For 1cum:
3.08 6,3,2 In 1:4 Cement Sand Mortar cum 12528.00
3.09 6,3,3 In 1:6 Cement Sand Mortar cum 11484.84
3.10 6,3,4 Stone (rubble) masonry work in (1:2) lime sand mortar For 1cum: cum 11677.04
Stone (One side dressed) masonry work including collection of stones, preparation of
mortar and a lead of 30m. For 1cum:
3.11 6,3,5 In 1:6 Cement Sand Mortar cum 14537.31
Stone (Three side dressed) masonry work including collection of stones, preparation
of mortar and a lead of 30m. For 1cum:
3.12 6,3,5 In 1:6 Cement Sand Mortar cum 21723.72
Stone (Five side dressed) masonry work including collection of stones, preparation of
mortar and a lead of 30m. For 1cum:
3.13 6,3,5 In 1:6 Cement Sand Mortar cum 31758.36
4 BRICK WORK
Brick work including collection of brick, preparation of mortar and transportation of
materials upto 30 m lead. For 1 cum :
Machine made brick ( size 224*108*57 mm) in :
4.01 5,1,ka,2 Cement mortar 1:4 cum 18582.15
4.02 5,1,ka,4 Cement mortar 1:6 cum 18047.71
Chimney made brick( size 224*108*57 mm) in:
4.03 5,1,kha,2 Cement mortar 1:4 cum 17112.04
4.04 5,1,kha,3 Cement mortar 1:6 cum 16547.61
4.05 5,1,kha,6 Mud mortar cum 13469.01
Extra work for scaffolding for 1cum
4.06 5,2,ka For ground floor cum 148.32
4.07 5,2,kha For above one floor cum 519.12
5 CEMENT CONCRETE WORK
Cement Ccncrete work in foundation,wall includingcollection of materials and a lead
of 30 m. For 1 cum
5.01 7 ,2 Ga With P.C.C ( 1:3:6 ) cum 12558.33
5.02 7 ,2 Gha With P.C.C. ( 1:2:4 ) cum 14444.76
5.03 With P.C.C. ( 1:1.5:3 ) cum 16079.88

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
Cement Concrete work in supper structure, deck slab,beams including collection of
materials and a lead of 30 m. For 1 cum
5.04 7,4,ka With P.C.C. ( 1:2:4 ) cum 16400.76
5.05 7,4,kha With P.C.C. ( 1:1.5:3 ) cum 18035.88
5.06 7,4,ga With P.C.C. ( 1:1:2 ) cum 22376.82
6 IRON WORK
6.01 7 ,5 Reinforcement bar cutting, binding, placing in position according to drawing & binding
for RCCwork including a lead of 30m. For 1kg. kg 125.17
6.02 M/S angle including making hole, cutting in required
length and shape. Per 1 kg kg 149.47
7 FORM WORK
7.01 8 ,2 Ka Preparation of formwork including selection,collection of materials cutting, nailing, fixing in
position, removel & disposal etc. as per drawing and a lead of 30 m.
For floor & slab. For 1 SQM : Sqm 776.94
7,02 Formwork for Ferrocement :For 1 SQM Sqm 369.39
Formwork for Column including nailing, fixing in position,removing and a lead of
30 m. For 1sqm :
7.03 8,3,ka Perimeter of column 0 - 2 m Sqm 1203.54
Form work for structural beam including selection, fixing,nailing,oiling,removel and
disposal with a lead of 30 m.For 1sqm :
7.04 8,4,ka Height of beam upto 0.30 m Sqm 1256.46
8 FLOORING
8.01 Preparation of Concrete-floor in 1:2:4, complete with cement punning. For 1.0 Sqm
11, ka a. 25 mm (1") Thick Sqm 512.51
11, kha b. 38 mm (1 / 2") Thick
1
Sqm 704.05
11, ga c. 50 mm (2") Thick Sqm 868.30
11, gha d. 75 mm (3") Thick Sqm 1190.60
8.02 11 ,20 3 mm th.cement Punning in For 1 SQM Sqm 284.73
8.03 11 ,16 Stone Soling with sand For 1cum cum 7610.42
8.04 11 ,16 Dry stone soling For 1 cum cum 5480.82
8.05 11,15,ka Brick soling with sand - On Flat For 1sqm Sqm 1043.74
8.06 Brick soling without sand - On Flat For 1sqm Sqm 953.76
8.07 11,15,kha Brick soling with sand - On Edge For 1 sqm Sqm 2032.46
8.08 Brick soling without sand - On Edge For 1 sqm Sqm 1819.50
8.09 11,8,ka Paving of 50 mm thick flagstone in (1:4) C/M : For 1sqm Sqm 1953.01
8.10 11, 9 Paving of 37.5 mm thick flagstone in (1:4) C/M : For 1sqm Sqm 1826.61
8.11 11, 10 Paving of 25 mm thick flagstone in (1:4) C/M : For 1sqm sqm 1704.23
8.12 11, 12 Paving brick, flat on cement sand mortar, complete with
1:2 cement sand pointing. For 1.0 Sqm Sqm 1545.08
8.13 11, 13 Paving brick, on - edge on 1:6 C / M, complete with
1:2 cement sand pointing. For 1.0 Sqm Sqm 2106.43
8.14 11, 21 Planking work of 25mm th. Local salwood planks on 600*600mm
frame of 50mm*75mm Local salwood. For 1.0 sqm Sqm 6982.30

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
8.15 11, 21 Planking work of 25mm th. Local soft wood planks on 600*600mm
frame of 50mm*75mm Local salwood. For 1.0 sqm Sqm 2577.47

8.16 11,3 Laying of 25mm th. Mosaic flooring, 20mm th. C/ P in 1:2 and on th top of that 6mm th. White cement
and marble ( in 1:1) coat, complete with polishing. For 1.00 sqm Sqm 3753.47
8.17 11, 5 Paving 25mm th. Oiled terrazo tiles on 1:2 Surkhi mortar complete
with 1:1 cement sand pointing. For 1.0 Sqm Sqm 2111.37
8.18 11, 7 Laying of procelain glaxed tiles on 1:4 cement sand
mortar. For 1.0 sqm sqm 2902.79
8.19 11, 6 Laying of 25mm th. 450*450mm Marble on 20mmth. 1:4 surkhi mortar,
complete with polishing. For 1.00 sqm Sqm 4990.44
Filling work including watering and compaction.For 1cum:
8.20 11,19,ka With sand cum 3962.38
8.21 11,19,kha With 15 -150 mm broken bricks cum 3381.70
9 CEMENT PLASTERING
12.5 mm thick Cement Sand plaster For 1 sqm
9.01 12 , 1 ka In 1:2 cement sand mortar Sqm 461.52
9.02 12 ,1 Kha In 1:3 cement sand morter Sqm 406.08
9.03 12 ,1 Ga In 1:4 cement sand mortar Sqm 393.37
9.04 12,1,gha In 1:6 cement sand mortar Sqm 364.20
20 mm thick cement sand plaster For 1 sqm
9.05 12 ,4 ka In 1:3 cement sand morter Sqm 537.90
9.06 12 ,4 Kha In 1:4 cement sand mortar Sqm 514.18
9.07 12,4,ga In 1:6 cement sand mortar Sqm 468.73
9.08 12,5 25mm th. Mud plaster.For 1 sqm: Sqm 405.22
9.09 12, 6 12.5mm th. Mud plaster.For 1 sqm: Sqm 312.26
9.10 Flush pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 265.87
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 245.91
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 235.36
9.11 Flush ruled pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 309.07
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 289.11
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 278.56
9.12 Flush ruled pointing work on boulder stone masonry wall.
14,2, ka a. With 1:1 cement sand mortar. For 1.00 sqm Sqm 343.08
14,2, kha b. With 1:2 cement sand mortar. For 1.00 sqm Sqm 304.82
14,2, ga c. With 1:3 cement sand mortar. For 1.00 sqm Sqm 285.39
9.13 14,3 Flush ruled pointing work with 1:3 c/ m on ashler
stone masonry wall. For 1.0 sqm Sqm 182.50
10 PAINTING WORK
10.01 13 ,11 Three coats chapra resin polishing.For 1sqm Sqm 177.80

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
10.02 Distempering painting
13,3, ka a. Lining. For 1 sqm Sqm 54.83
13,3, kha b. First one coat. For 1 sqm Sqm 52.18 For rate to
estimate
13,3, ga c. 2nd coat and additional coats. For 1 sqm Sqm 44.69 add a, b & c
10.03 13,6 Applying 1 coat lining and 2 coats of aluminum
paint. For 1.00sqm Sqm 289.32
10.04 13,5ka-ga 1Coat primer & 2 Coat enamel paint. For 1sqm Sqm 311.95
10.05 13,5ka-ga
1Coat primer & 2 Coat weather coat(exterior)emulsion paint. For 1sqm sqm 322.94
10.06 1 Coat primer & 2 Coat emulsion paint.(Interior) For 1sqm sqm 303.05
11 7 line hori. and 2 line diago. barbed wire fencing on m/s angle
(50*50*6mm),at a spacing 2m c/c.For 1m Rm 466.64
12 ROOFING WORK
White CGI sheet roofing including collection of materials.
12.01 9 ,1 For 1 SQM (CGI sheet 24 SWG): Sqm 1058.56
12.02 9 ,1 For 1 SQM (CGI sheet 26 SWG): Sqm 871.90
12.03 9 ,1 For 1 SQM (CGI sheet 28 SWG): Sqm 747.40
Color CGI sheet roofing including collection of materials.
12.04 9 ,1 For 1 SQM (CGI sheet 24 SWG): sqm 1091.38
12.05 9 ,1 For 1 SQM (CGI sheet 26 SWG): sqm 921.71
12.06 9 ,1 For 1 SQM (CGI sheet 28 SWG): sqm 793.33
12.07 9 ,2 White GI Plain sheet ridge fixing 24 SWG. For 1 M m 852.47
12.08 9 ,2 White GI Plain sheet ridge fixing 26 SWG. For 1 M m 762.33
12.09 9 ,2 White GI Plain sheet ridge fixing 28 SWG. For 1 M m 702.40
12.10 9 ,2 Color GI Plain sheet ridge fixing 24 SWG. For 1 M m 913.64
12.11 9 ,2 Color GI Plain sheet ridge fixing 26 SWG. For 1 M m 815.15
12.12 9 ,2 Color GI Plain sheet ridge fixing 28 SWG. For 1 M m 737.15
12.13 9,5 Slate roofing . For 1Sqm Sqm 2512.19
12.14 9,9,kha Thatch roofing.For 1sqm: Sqm 4677.09
12.15 9,6 Clay tiles (Chimney made) roofing. For 1sqm : Sqm 514.00
12.16 9,7 Clay tile as ridge (Chimney made) plate fixing. For 1m: m 430.44
13 WOOD WORK
13.01 10 ,1 a.Local salwood work for frames including fixing.For 1 cum cum 202362.65
10 ,1 b.Local soft wood work for frames.For 1 cum cum 87272.30
13.02 10 ,2 38mm th. wood frame for panelled door shutter. For 1 no
(shutter size -1.07*1.982 = 2.12sqm)
a.With Local salwood Sqm 11538.15
10,2 b.With Local softwood Sqm 7392.53
13.03 10 ,3 38*75mm size wood frame using 3mm plain glass for glazed shutter. For 1no.(shutter
size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Sqm 8221.99
10 ,3 b.With Local softwood Sqm 5923.00
13.04 10 ,3 38*75mm size wood frame using 4mm plain glass for glazed shutter. For 1no.(shutter

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Sqm 8320.47
10 ,3 b.With Local softwood Sqm 6021.48
13.05 10 ,9 38mm wood frame using 26 SWG Plain GI sheet on both side. For 1 no.(shutter size -
1.092*2.058 = 2.247sqm)
a.With Local salwood sqm 6792.27
10,9 b.With Local softwood sqm 5181.18
13.06 10 ,10 38mm wood frame using 24 SWG GI wire mesh mosquito proof shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 4568.82
10 ,10 b.With Local softwood Sqm 3358.17
13.07 10,7 38mm wood frame using 3mm plywood both side for flush shutter. For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 6642.38
b.With Local softwood Sqm 5031.29
13.08 38mm wood frame using 3mm plywood one side for flush shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 5642.14
b.With Local softwood Sqm 4031.05
13.09 10,7 38mm wood frame using 6mm plywood both side for flush shutter. For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 7406.87
b.With Local softwood Sqm 5795.78
13.10 38mm wood frame using 6mm plywood one side for flush shutter .For 1 no.
(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Sqm 6024.38
b.With Local softwood Sqm 4413.29
13.11 Fixing glass of different thichness in window frame including fixing of wooden listis.
For 1sqm with :
10,11,ka a.3 mm thick glass Sqm 797.96
b 4 mm thick glass Sqm 1000.37
13.12 10 ,17 Wood work for beam and joist including fixing .For 1cum
a.With Local salwood cum 175217.76
b.With Local softwood cum 65358.79
13.13 10,18 a.Local salwood work for truss fixing.For 1M3 cum 201669.51
b.Local soft wood work for truss fixing.For 1M3 cum 91810.54
13.14 10 ,19 a.Local salwood work for 25mm th. Eaves board including fitting.
For 1SQM Sqm 4297.76
10 ,19 b.Local hardwood work for 25mm th. Eaves board including fitting.
For 1SQM Sqm 1420.50
13.15 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm
plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2859.99

Prepared By: Total Consultancy Pvt Ltd


SUMMARY OF RATE
Amanat Rate of F.Y. 2076/077 For Different Project without Road
Rate Analysis base on "Construction Norm's 2041"
Norms Rate per Unit
SN No. Description Unit Rs Remarks
b. With Local soft wood Sqm 1831.06
13.16 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm
plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2391.82
b. With Local softwood Sqm 1362.89
13.17 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm
plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 3638.48
b. With Local soft wood Sqm 2609.55
13.18 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm
plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2781.06
b. With Local softwood Sqm 1752.13
13.19 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 3mm plywood for different
type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 2936.15
b. With Local soft wood Sqm 1613.24
13.20 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 6mm plywood for different
type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Sqm 3325.39
b. With Local soft wood Sqm 2002.48
14 DEMOLIITIONS AND REPAIR WORK
14.01 19-1 Demolishing mud mortar masonry and disposing the
materials to a distance of 10m. For 1cum: cum 763.20
14.02 19-2 Demolishing cement or lime surkhi mortar masonry and disposing
the materials to a distance of 10m.For 1cum : cum 1526.40
14.03 19 - 3 Demolishing RCC or RBC work and disposing
materials to a distance of 10m. For 1cum : cum 7920.00
14.04 19 - 4 Demolishing PCC or lime surkhi concrete and disposing
the materials to a distance of 10m.For 1cum : cum 2880.00
14.05 19 - 5 Demolishing cement or lime surkhi plaster and disposing
the materials to a distance of 10m.For 1cum : cum 77.76
14.06 19 -6 Demolishing tiled roof and stacking the tiles, wood etc.
properly at a distance of 10m. For 1cum : cum 113.40
END

Prepared By: Total Consultancy Pvt Ltd


Page 51 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks

1 SITE CLEARANCE
Felling of trees including cutting branches, sawing and carrying up to 15m away from the site. For Each
1.01 1,1,ka Girth of tree 12 - 30cm Unskill 0.13 720.00 93.60 93.60
1.02 1,1,kha Girth of tree 31 - 60cm Unskill 0.39 720.00 280.80 280.80
1.03 1,1,ga Girth of tree 61 - 90cm Unskill 0.98 720.00 705.60 705.60
1.04 1,1,gha Girth of tree 91 - 120cm Unskill 0.98 0.00 0.00 0.00
1.05 1,1,ng Girth of tree 121 - 180cm Unskill 4.00 0.00 0.00 0.00
1.06 1,1,cha Girth of tree 181 - 240cm Unskill 4.00 0.00 0.00 0.00
1.07 1,1,chha Girth of tree 241 - 300cm Unskill 10.40 0.00 0.00 0.00
1.08 1,1,ja Girth of tree over 301cm Unskill 41.67 0.00 0.00 0.00
Tree root digging, lifting it and carrying up to 15m away from the site. For Each
1.09 1,2,ka Girth of tree 12 - 30cm Unskill 0.40 720.00 288.00 288.00
1.10 1,2,kha Girth of tree 31 - 60cm Unskill 0.53 720.00 381.60 381.60
1.11 1,2,ga Girth of tree 61 - 90cm Unskill 2.52 720.00 1814.40 1814.40
1.12 1,2,gha Girth of tree 91 - 120cm Unskill 2.52 0.00 0.00 0.00
1.13 1,2,ng Girth of tree 121 - 180cm Unskill 12.00 0.00 0.00 0.00
1.14 1,2,cha Girth of tree 181 - 240cm Unskill 12.00 0.00 0.00 0.00
1.15 1,2,chha Girth of tree 241 - 300cm Unskill 29.60 0.00 0.00 0.00
1.16 1,6 Bamboo cutting,root digging,removel of bamboo from site (Dug-pit
dimension to be measured).For 1m3 Unskill 2.80 720.00 2016.00 2016.00
1.17 1,7 Surface dressing work,cutting and filling earthwork,including levelling
ground surface(service road etc.). For 1m2 Unskill 0.01 720.00 7.20 7.20
1.18 1 ,8 Excavation 15-20 cm of the top soil including disposal
out side of the construction site. For 1 m2 Unskill 0.16 720.00 115.20 115.20
2 EARTHWORK
Earthwork in excavation including a lead of 10m and a lift of 1.5m in:
2.01 2,1 Soft Clay : For 1 cum Unskill 0.70 720.00 504.00 T.&P.@ 3% Of Labour Cost 15.12 519.12
2.02 2,2 Hard clay mixed boulder less than 30cm size :.For 1cum Unskill 0.80 720.00 576.00 T.&P.@ 3% Of Labour Cost 17.28 593.28
2.03 2 ,10 Soft Rock : For 1 cum Unskill 2.50 720.00 1800.00 T.&P.@ 3% of Labour Cost 54.00 1854.00
2.04 2 ,4 Medium Rock without blasting : For 1 cum Unskill 3.00 720.00 2160.00 T.&P.@ 3% of Labour Cost 64.80 2224.80
2.05 2 ,6ka Hard Rock without chiselling : For 1 cum Unskill 5.00 720.00 3600.00 T.&P.@ 3% of Labour Cost 108.00 3708.00
Earthwork in filling including watering & ramming every 15cm th. Layers For 1cum :

Prepared By: Total Consultancy Pvt Ltd


Page 52 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
2.06 2 ,25ka With Ordinary Soil Unskill 0.50 720.00 360.00 T.&P.@ 3% of Labour Cost 10.80 370.80
Earthwork in filling including ramming every 15cm th. Layers (without watering )For 1cum :
2.07 2 ,25, kha With Ordinary Soil Unskill 0.25 720.00 180.00 T.&P.@ 3% of Labour Cost 5.40 185.40
Turfing work Including cutting, hauling for 10m and watering For 1sqm :
2.08 2 , 40 Turfing work Unskill 0.050 720.00 36.00 T.&P.@ 3% of Labour Cost 1.08 37.08
3 STONE WORK
Stone (rubble) masonry work up to 5 m ht. Of wall including collection of stones, preparation of mortar and a lead of 10 m.For 1 cum :
3.01 6,1,ka,2 In 1:4 Cement Sand Mortar Skill 1.50 1020.0 1530.00 Cement bag 3.18 1040.70 3309.43
Unskill 5.00 720.00 3600.00 Sand cum 0.45 2999.44 1349.75
Stone cum 1.10 1764.38 1940.82
Total 5130.00 Total 6600.00 11730.00
3.02 6,1ka,3 In 1:6 Cement Sand Mortar Skill 1.50 1020.0 1530.00 Cement bag 2.12 1040.70 2206.28
Unskill 5.00 720.00 3600.00 Sand cum 0.47 2999.44 1409.74
Stone cum 1.10 1764.38 1940.82
Total 5130.00 Total 5556.84 10686.84
3.03 6 ,2.1 Dry Stone Masonry Skill 1.00 1020.0 1020.00 Stone cum 1.10 1764.38 1940.82
Unskill 2.00 720.00 1440.00
Total 2460.00 Total 1940.82 4400.82
3.04 6 ,2.2 Mud Mortar Stone Masonry Skill 1.00 1020.0 1020.00 Stone cum 1.10 1764.38 1940.82
Unskill 2.25 720.00 1620.00 Mud cum 0.42 352.88 148.21
Total 2640.00 Total 2089.03 4729.03
Stone (rubble) masonry work 5 to 10 m ht. Of wall including collection of stones, preparation of mortar and a lead of 10 m.For 1 cum :
3.05 6,1,ka,2 In 1:4 Cement Sand Mortar Skill 1.50 1020.0 1530.00 Cement bag 3.18 1040.70 3309.43
Unskill 6.17 720.00 4442.40 Sand cum 0.45 2999.44 1349.75
Stone cum 1.10 1764.38 1940.82
Total 5972.40 Total 6600.00 12572.40
3.06 6,1,ka,3 In 1:6 Cement Sand Mortar Skill 1.50 1020.0 1530.00 Cement bag 2.12 1040.70 2206.28
Unskill 6.17 720.00 4442.40 Sand cum 0.47 2999.44 1409.74
Stone cum 1.10 1764.38 1940.82
Total 5972.40 Total 5556.84 11529.24
3.07 6 ,2.2 Mud Mortar Stone Masonry Skill 1.00 1020.0 1020.00 Stone cum 1.10 1764.38 1940.82
Unskill 3.42 720.00 2462.40 Mud cum 0.42 352.88 148.21
Total 3482.40 Total 5571.43
2089.03
Stone (rubble) masonry work in arch or in sloping plane including collection of stones, preparation of mortar and a lead of 30 m. For 1cum:

Prepared By: Total Consultancy Pvt Ltd


Page 53 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
3.08 6,3,2 In 1:4 Cement Sand Mortar Skill 2.00 1020.0 2040.00 Cement bag 3.18 1040.70 3309.43
Unskill 5.40 720.00 3888.00 Sand cum 0.45 2999.44 1349.75
Stone cum 1.10 1764.38 1940.82
Total 5928.00 Total 6600.00 12528.00
3.09 6,3,3 In 1:6 Cement Sand Mortar Skill 2.00 1020.0 2040.00 Cement bag 2.12 1040.70 2206.28
Unskill 5.40 720.00 3888.00 Sand cum 0.47 2999.44 1409.74
Stone cum 1.10 1764.38 1940.82
Total 5928.00 Total 5556.84 11484.84
3.10 6,3,4 Stone (rubble) masonry work in (1:2) lime sand mortar Skill 1.50 1020.0 1530.00 Lime kg 160.00 26.39 4222.40
For 1cum: Unskill 4.20 720.00 3024.00 Sand cum 0.32 2999.44 959.82
Total 4554.00 Stone cum 1.10 1764.38 1940.82
Total 7123.04 11677.04
Stone dressed masonry work including collection of stones, preparation of mortarand a lead of 30m. For 1cum:
3.11 6,3,5 In 1:6 Cement Sand Mortar (One side dressed) : Skill 1.50 1020.0 1530.00 Cement bag 2.80 1040.70 2913.96
Unskill 3.00 720.00 2160.00 Sand cum 0.42 2999.44 1259.76
Total 3690.00 Dressed stone cum 1.10 6066.90 6673.59
Total 10847.31 14537.31
3.12 6,3,5 In 1:6 Cement Sand Mortar (Three side dressed) : Skill 1.50 1020.0 1530.00 Cement bag 2.80 1040.70 2913.96
Unskill 3.00 720.00 2160.00 Sand cum 0.42 2999.44 1259.76
Total 3690.00 Dressed stone cum 1.10 12600.00 13860.00
Total 18033.72 21723.72
3.13 6,3,5 In 1:6 Cement Sand Mortar (Five side dressed) : Skill 1.50 1020.0 1530.00 Cement bag 2.80 1040.70 2913.96
Unskill 3.00 720.00 2160.00 Sand cum 0.42 2999.44 1259.76
Total 3690.00 Dressed stone cum 1.10 21722.40 23894.64
Total 28068.36 31758.36
4 BRICK WORK
Brick work including collection of brick, preparation of mortar and transportation of materials upto 30 m lead. For 1 cum :
Machine made brick ( size 224*108*57 mm) in :
4.01 5,1,ka,2 Cement mortar 1:4 Skill 1.50 1020.0 1530.00 Brick no 530.00 23.73 12576.90
Unskill 2.20 720.00 1584.00 Cement bag 2.00 1040.70 2081.40
Total 3114.00 Sand cum 0.27 2999.44 809.85
Total 15468.15 18582.15

Prepared By: Total Consultancy Pvt Ltd


Page 54 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
4.02 5,1,ka,4 Cement mortar 1:6 Skill 1.50 1020.0 1530.00 Brick no 530.00 23.73 12576.90
Unskill 2.20 720.00 1584.00 Cement bag 1.40 1040.70 1456.98
Total 3114.00 Sand cum 0.30 2999.44 899.83
Total 14933.71 18047.71
Chimney made brick( size 224*108*57 mm) in:
4.03 5,1,kha,2 Cement mortar 1:4 Skill 1.50 1020.0 1530.00 Brick no 560 19.78 11076.80
Unskill 2.20 720.00 1584.00 Cement bag 2.00 1040.70 2081.40
Total 3114.00 Sand cum 0.28 2999.44 839.84
Total 13998.04 17112.04
4.04 5,1,kha,3 Cement mortar 1:6 Skill 1.50 1020.0 1530.00 Brick no 560.00 19.78 11076.80
Unskill 2.20 720.00 1584.00 Cement bag 1.40 1040.70 1456.98
Total 3114.00 Sand cum 0.30 2999.44 899.83
Total 13433.61 16547.61
4.05 5,1,kha,6 Mud mortar Skill 1.00 1020.0 1020.00 Brick no 560 19.78 11076.80
Unskill 1.70 720.00 1224.00 Mud cum 0.42 352.88 148.21
Total 2244.00 Total 11225.01 13469.01
Extra work for scaffolding for 1cum
4.06 5,2,ka For ground floor Unskill 0.20 720.00 144.00 Scaffolding 3 % of Labour cost 4.32 148.32
4.07 5,2,kha For above one floor Unskill 0.70 720.00 504.00 Scaffolding 3 % of Labour cost 15.12 519.12
5 CEMENT CONCRETE WORK
Cement Ccncrete work in foundation,wall includingcollection of materials and a lead of 30 m. For 1 cum
5.01 7 ,2 Ga With P.C.C ( 1:3:6 ) Skill 1.00 1020.0 1020.00 Cement bag 4.40 1040.70 4579.08
Unskill 4.00 720.00 2880.00 Aggregate - 40mm cum 0.65 2999.44 1949.64
Total 3900.00 Aggregate - 20mm cum 0.24 2999.44 719.87
Sand cum 0.47 2999.44 1409.74
Total 8658.33 12558.33
5.02 7 ,2 Gha With P.C.C. ( 1:2:4 ) Skill 1.00 1020.0 1020.00 Cement bag 6.40 1040.70 6660.48
Unskill 4.00 720.00 2880.00 Aggregate - 40mm cum 0.52 2999.44 1559.71
Total 3900.00 Aggregate - 20mm cum 0.22 2999.44 659.88
Aggregate - 10mm cum 0.11 2999.44 329.94
Sand cum 0.445 2999.44 1334.75
Total 10544.76 14444.76

Prepared By: Total Consultancy Pvt Ltd


Page 55 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
5.03 With P.C.C. ( 1:1.5:3 ) Skill 1.00 1020.0 1020.00 Cement bag 8.00 1040.70 8325.60
Unskill 4.00 720.00 2880.00 Aggregate - 20mm cum 0.57 2999.44 1709.68
Total 3900.00 Aggregate - 10mm cum 0.29 2999.44 869.84
Sand cum 0.425 2999.44 1274.76
Total 12179.88 16079.88
Cement Concrete work in supper structure, deck slab,beams including collection of materials and a lead of 30 m. For 1 cum
5.04 7,4,ka With P.C.C. ( 1:2:4 ) Skill 0.80 1020.0 816.00 Cement bag 6.40 1040.70 6660.48
Unskill 7.00 720.00 5040.00 Aggregate - 40mm cum 0.52 2999.44 1559.71
Total 5856.00 Aggregate - 20mm cum 0.22 2999.44 659.88
Aggregate - 10mm cum 0.11 2999.44 329.94
Sand cum 0.445 2999.44 1334.75
Total 10544.76 16400.76
5.05 7,4,kha With P.C.C. ( 1:1.5:3 ) Skill 0.80 1020.0 816.00 Cement bag 8.00 1040.70 8325.60
Unskill 7.00 720.00 5040.00 Aggregate - 20mm cum 0.57 2999.44 1709.68
Total 5856.00 Aggregate - 10mm cum 0.29 2999.44 869.84
Sand cum 0.425 2999.44 1274.76
Total 12179.88 18035.88
5.06 7,4,ga With P.C.C. ( 1:1:2 ) Skill 0.80 1020.0 816.00 Cement bag 12.20 1040.70 12696.54
Unskill 7.00 720.00 5040.00 Aggregate - 20mm cum 0.64 2999.44 1919.64
Total 5856.00 Aggregate - 10mm cum 0.21 2999.44 629.88
Sand cum 0.425 2999.44 1274.76
Total 16520.82 22376.82
6 IRON WORK
6.01 7 ,5 Reinforcement bar cutting, binding, placing in position according to drawing & binding
for RCCwork including a lead of 30m. For 1kg. Skill 0.012 1020.0 12.24 M/S Bar kg 1.05 98.29 103.20
Unskill 0.012 720.00 8.64 bind. Wire kg 0.01 109.18 1.09
Total 20.88 Total 104.29 125.17
6.02 M/S angle including making hole, cutting in required
length and shape. Per 1 kg Skill 0.03 1020.0 30.60
Unskill 0.03 720.00 21.60 M/S Angle kg 1.05 92.64 97.27
Total 52.20 Total 97.27 149.47
7 FORM WORK
7.01 8 ,2 Ka Preparation of formwork including selection,collection of materials cutting, nailing, fixing in position,removel & disposal etc. as per drawing and a lead of 30 m.
For floor & slab. For 1 SQM : Skill 0.172 1020.0 175.44 Local soft Wood cum 0.0088 43580.13 383.51

Prepared By: Total Consultancy Pvt Ltd


Page 56 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Unskill 0.257 720.00 185.04 Nail kg 0.25 131.78 32.95
Total 360.48 Total 416.46 776.94
7,02 Formwork for Ferrocement :For 1 SQM Skill 0.167 1020.0 170.34 Bamboo No. 0.333 325.00 108.23
Unskill 0.111 720.00 79.92 Nail Kg 0.014 131.78 1.84
Total 250.26 Bind.wire Kg 0.083 109.18 9.06
Total 119.13 369.39
Formwork for Column including nailing, fixing in position,removing and a lead of 30 m. For 1sqm :
7.03 8,3,ka Perimeter of column 0 - 2 m Skill 0.3748 1020.0 382.30 Local soft Wood cum 0.0088 43580.13 383.51
Unskill 0.5622 720.00 404.78 Nail Kg 0.250 131.78 32.95
Total 787.08 Total 416.46 1203.54
Form work for structural beam including selection, fixing,nailing,oiling,removel and disposal with a lead of 30 m.For 1sqm :
7.04 8,4,ka Height of beam upto 0.30 m Skill 0.40 1020.0 408.00 Local soft Wood cum 0.0088 43580.13 383.51
Unskill 0.60 720.00 432.00 Nail kg 0.25 131.78 32.95
Total 840.00 Total 416.46 1256.46
8 FLOORING
8.01 Preparation of Concrete-floor in 1:2:4, complete with cement punning. For 1.0 Sqm
11,1, ka a. 25 mm (1") Thick Skill 0.11 1020.0 112.20 Cement bag 0.18 1040.70 187.33
Unskill 0.15 720.00 108.00 Aggregate - 12mm cum 0.023 2999.44 68.99
Sand cum 0.012 2999.44 35.99
Total 220.20 Total 292.31 512.51
11, 1, kha b. 38 mm (11 / 2") Thick Skill 0.125 1020.0 127.50 Cement bag 0.26 1040.70 270.58
Unskill 0.20 720.00 144.00 Aggregate - 12mm cum 0.036 2999.44 107.98
Sand cum 0.018 2999.44 53.99
Total 271.50 Total 432.55 704.05
11,1, ga c. 50 mm (2") Thick Skill 0.125 1020.0 127.50 Cement bag 0.34 1040.70 353.84
Unskill 0.25 720.00 180.00 Aggregate - 12mm cum 0.046 2999.44 137.97
Sand cum 0.023 2999.44 68.99
Total 307.50 Total 560.80 868.30
11,1, gha d. 75 mm (3") Thick Skill 0.125 1020.0 127.50 Cement bag 0.52 1040.70 541.16
Unskill 0.30 720.00 216.00 Aggregate - 12mm cum 0.068 2999.44 203.96
Sand cum 0.034 2999.44 101.98
Total 343.50 Total 847.10 1190.60
8.02 11 ,20 3 mm th.cement Punning in For 1 SQM Skill 0.10 1020.0 102.00 Cement bag 0.1064 1040.70 110.73

Prepared By: Total Consultancy Pvt Ltd


Page 57 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Unskill 0.10 720.00 72.00
Total 174.00 Total 110.73 284.73
8.03 11 ,16 Stone Soling with sand For 1cum Skill 1.00 1020.0 1020.00 Stone cum 1.10 1764.38 1940.82
Unskill 3.50 720.00 2520.00 Sand cum 0.71 2999.44 2129.60
Total 3540.00 Total 4070.42 7610.42
8.04 11 ,16 Dry stone soling For 1 cum Skill 1.00 1020.0 1020.00 Stone cum 1.10 1764.38 1940.82
Unskill 3.50 720.00 2520.00
Total 3540.00 Total 1940.82 5480.82
8.05 11,15,ka Brick soling with sand - On Flat For 1sqm Skill 0.05 1020.0 51.00 Brick no. 42.00 19.78 830.76
Unskill 0.10 720.00 72.00 Sand cum 0.030 2999.44 89.98
Total 123.00 Total 920.74 1043.74
8.06 11,15,ka Brick soling without sand - On Flat For 1sqm Skill 0.05 1020.0 51.00 Brick no. 42.00 19.78 830.76
Unskill 0.10 720.00 72.00
Total 123.00 Total 830.76 953.76
8.07 11,15,kha Brick soling with sand - On Edge For 1 sqm Skill 0.10 1020.0 102.00 Brick no. 75.00 19.78 1483.50
Unskill 0.325 720.00 234.00 Sand cum 0.071 2999.44 212.96
Total 336.00 Total 1696.46 2032.46
8.08 11,15,kha Brick soling without sand - On Edge For 1 sqm Skill 0.10 1020.0 102.00 Brick no. 75.00 19.78 1483.50
Unskill 0.325 720.00 234.00
Total 336.00 Total 1483.50 1819.50
8.09 11,8,ka Paving of 50 mm thick flagstone in (1:4) C/M : For 1sqm Skill 0.20 1020.0 204.00 50mm stone sqm 1.10 1129.63 1242.59
Unskill 0.45 720.00 324.00 Cement bag 0.126 1040.70 131.13
Total 528.00 Sand cum 0.0171 2999.44 51.29
Total 1425.01 1953.01
8.10 11, 9 Paving of 37.5 mm thick flagstone in (1:4) C/M : For 1sqm Skill 0.20 1020.0 204.00 37.5mm stone sqm 1.10 1022.04 1124.24
Unskill 0.45 720.00 324.00 Cement bag 0.120 1040.70 124.88
Total 528.00 Sand cum 0.0165 2999.44 49.49
Total 1298.61 1826.61
8.11 11, 10 Paving of 25 mm thick flagstone in (1:4) C/M : For 1sqm Skill 0.15 1020.0 153.00 25mm stone sqm 1.10 968.25 1065.08
Unskill 0.45 720.00 324.00 Cement bag 0.112 1040.70 116.56
Total 477.00 Sand cum 0.0152 2999.44 45.59
Total 1227.23 1704.23
8.12 11, 12 Paving brick, flat on cement sand mortar, complete with

Prepared By: Total Consultancy Pvt Ltd


Page 58 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
1:2 cement sand pointing. For 1.0 Sqm Skill 0.225 1020.0 229.50 Brick No. 43.00 19.78 850.54
Unskill 0.325 720.00 234.00 Cement bag 0.1560 1040.70 162.35
Total 463.50 Sand cum 0.0229 2999.44 68.69
Total 1081.58 1545.08
8.13 11, 13 Paving brick, on - edge on 1:6 C / M, complete with
1:2 cement sand pointing. For 1.0 Sqm Skill 0.110 1020.0 112.20 Brick No. 75.00 19.78 1483.50
Unskill 0.180 720.00 129.60 Cement bag 0.2420 1040.70 251.85
Total 241.80 Sand cum 0.0431 2999.44 129.28
Total 1864.63 2106.43
8.14 11, 21 Planking work of 25mm th. Local sal wood planks on 600*600mm
frame of 50mm*75mm sal wood. For 1.0 sqm Skill 0.65 1020.0 663.00 Sal wood cum 0.0421 148207.72 6239.55
Unskill 0.065 720.00 46.80 Nails kg 0.2500 131.78 32.95
Total 709.80 Total 6272.50 6982.30
8.15 11, 21 Planking work of 25mm th. Local soft wood planks on 600*600mm
frame of 50mm*75mm sal wood. For 1.0 sqm Skill 0.65 1020.0 663.00 Local soft wood cum 0.0421 43580.13 1834.72
Unskill 0.065 720.00 46.80 Nails kg 0.2500 131.78 32.95
Total 709.80 Total 1867.67 2577.47
8.16 11,3 Laying of 25mm th. Mosaic flooring, 20mm th. C/ P in 1:2 and on th top of that 6mm th. White cement and marble chips
( in 1:1) coat, complete with polishing. For 1.00 sqm Skill 0.35 1020.0 357.00 Cement bag 0.2420 1040.70 251.85
Unskill 3.60 720.00 2592.00 Sand cum 0.0165 2999.44 49.49
Total 2949.00 White cement kg 6.9000 38.27 264.06
3mm marble chips cum 0.0047 26417.98 124.16
Oxalic acid kg 0.0340 138.26 4.70
Wax polish kg 0.0118 394.77 4.66
Turpentine Lit. 0.0500 250.43 12.52
Carburundum kg 0.2000 465.13 93.03
Total 804.47 3753.47
8.17 11, 11 Paving 25mm th. Oiled terrazo tiles on 1:2 Surkhi mortar complete
with 1:1 cement sand pointing. For 1.0 Sqm Skill 0.45 1020.0 459.00 Oiled terrazo tiles No. 44.00 17.75 781.00
Unskill 0.45 720.00 324.00 Lime kg 12.20 26.39 321.96
Total 783.00 Surkhi cum 0.0244 6521.37 159.12
Cement bag 0.0320 1040.70 33.30
Sand cum 0.0110 2999.44 32.99

Prepared By: Total Consultancy Pvt Ltd


Page 59 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Total 1328.37 2111.37
8.18 11, 7 Laying of procelain glaxed tiles on 1:4 cement sand Skill 1.30 1020.0 1326.00 Procelain glazed tiles sqm 1.1000 980.26 1078.29
mortar. For 1.0 sqm Unskill 0.45 720.00 324.00 Cement bag 0.1120 1040.70 116.56
Total 1650.00 Sand cum 0.0152 2999.44 45.59
White cement kg 0.3228 38.27 12.35
Total 1252.79 2902.79
8.19 11, 6 Laying of 25mm th. 450*450mm Marble on 20mmth. 1:4 surkhi mortar,
complete with polishing. For 1.00 sqm Skill 0.20 1020.0 204.00 16mm th. Marble sqm 1.10 2490.38 2739.42
Unskill 2.15 720.00 1548.00 Lime kg 9.1000 26.39 240.15
Total 1752.00 Surkhi cum 0.0183 6521.37 119.34
Oxalic acid kg 0.0370 138.26 5.12
Wax polish kg 0.0118 394.77 4.66
Turpentine Lit. 0.0538 250.43 13.47
Carburundum kg 0.2500 465.13 116.28
Total 3238.44 4990.44
Filling work including watering and compaction.For 1cum:
8.20 11,19,ka With sand Skill 0.65 1020.0 663.00 Sand cum 1.10 2999.44 3299.38 3962.38
8.21 11,19,kha With 15 -150 mm broken bricks Skill 1.00 1020.0 1020.00 Broken bricks cum 1.10 2147.00 2361.70 3381.70
9 CEMENT PLASTERING
12.5 mm thick Cement Sand plaster For 1 sqm
9.01 12 , 1 ka In 1:2 cement sand mortar Skill 0.12 1020.0 122.40 Cement bag 0.180 1040.70 187.33
Unskill 0.16 720.00 115.20 Sand cum 0.0122 2999.44 36.59
Total 237.60 Total 223.92 461.52
9.02 12 ,1 Kha In 1:3 cement sand morter Skill 0.12 1020.0 122.40 Cement bag 0.125 1040.70 130.09
Unskill 0.16 720.00 115.20 Sand cum 0.0128 2999.44 38.39
Total 237.60 Total 168.48 406.08
9.03 12 ,1 Ga In 1:4 cement sand mortar Skill 0.12 1020.0 122.40 Cement bag 0.1076 1040.70 111.98
Unskill 0.16 720.00 115.20 Sand cum 0.0146 2999.44 43.79
Total 237.60 Total 155.77 393.37
9.04 12,1,gha In 1:6 cement sand mortar Skill 0.12 1020.0 122.40 Cement bag 0.0764 1040.70 79.51
Unskill 0.16 720.00 115.20 Sand cum 0.0157 2999.44 47.09
Total 237.60 Total 126.60 364.20
20 mm thick cement sand plaster For 1 sqm

Prepared By: Total Consultancy Pvt Ltd


Page 60 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
9.05 12 ,4 ka In 1:3 cement sand morter Skill 0.14 1020.0 142.80 Cement bag 0.192 1040.70 199.81
Unskill 0.19 720.00 136.80 Sand cum 0.0195 2999.44 58.49
Total 279.60 Total 258.30 537.90
9.06 12 ,4 Kha In 1:4 cement sand mortar Skill 0.14 1020.0 142.80 Cement bag 0.162 1040.70 168.59
Unskill 0.19 720.00 136.80 Sand cum 0.022 2999.44 65.99
Total 279.60 Total 234.58 514.18
9.07 12,4,ga In 1:6 cement sand mortar Skill 0.14 1020.0 142.80 Cement bag 0.114 1040.70 118.64
Unskill 0.19 720.00 136.80 Sand cum 0.0235 2999.44 70.49
Total 279.60 Total 189.13 468.73
9.08 12,5 25mm th. Mud plaster.For 1 sqm: Skill 0.20 1020.0 204.00 Mud cum 0.03 352.88 10.59
Unskill 0.25 720.00 180.00 Husk(bhoos) kg 0.10 10.33 1.03
Total 384.00 Cow -dung kg 1.20 8.00 9.60
Total 21.22 405.22
9.09 12, 6 12.5mm th. Mud plaster.For 1 sqm: Skill 0.15 1020.0 153.00 Mud cum 0.015 352.88 5.29
Unskill 0.20 720.00 144.00 Husk(bhoos) kg 0.50 10.33 5.17
Total 297.00 Cow -dung kg 0.60 8.00 4.80
Total 15.26 312.26
9.10 Flush pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Skill 0.105 1020.0 107.10 Cement bag 0.0632 1040.70 65.77
Unskill 0.12 720.00 86.40 Sand cum 0.0022 2999.44 6.60
Total 193.50 Total 72.37 265.87
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Skill 0.105 1020.0 107.10 Cement bag 0.0420 1040.70 43.71
Unskill 0.12 720.00 86.40 Sand cum 0.0029 2999.44 8.70
Total 193.50 Total 52.41 245.91
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Skill 0.105 1020.0 107.10 Cement bag 0.031 1040.70 32.26
Unskill 0.12 720.00 86.40 Sand cum 0.0032 2999.44 9.60
Total 193.50 Total 41.86 235.36
9.11 Flush ruled pointing work on bricks masonry wall.
14,1, ka a. With 1:1 cement sand mortar. For 1.00 sqm Skill 0.105 1020.0 107.10 Cement bag 0.0632 1040.70 65.77
Unskill 0.18 720.00 129.60 Sand cum 0.0022 2999.44 6.60
Total 236.70 Total 72.37 309.07
14,1, kha b. With 1:2 cement sand mortar. For 1.00 sqm Skill 0.105 1020.0 107.10 Cement bag 0.0420 1040.70 43.71
Unskill 0.18 720.00 129.60 Sand cum 0.0029 2999.44 8.70

Prepared By: Total Consultancy Pvt Ltd


Page 61 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Total 236.70 Total 52.41 289.11
14,1, ga c. With 1:3 cement sand mortar. For 1.00 sqm Skill 0.105 1020.0 107.10 Cement bag 0.031 1040.70 32.26
Unskill 0.18 720.00 129.60 Sand cum 0.0032 2999.44 9.60
Total 236.70 Total 41.86 278.56
9.12 Flush ruled pointing work on boulder stone masonry wall.
14,2, ka a. With 1:1 cement sand mortar. For 1.00 sqm Skill 0.10 1020.0 102.00 Cement bag 0.1224 1040.70 127.38
Unskill 0.14 720.00 100.80 Sand cum 0.0043 2999.44 12.90
Total 202.80 Total 140.28 343.08
14,2, kha b. With 1:2 cement sand mortar. For 1.00 sqm Skill 0.10 1020.0 102.00 Cement bag 0.0816 1040.70 84.92
Unskill 0.14 720.00 100.80 Sand cum 0.0057 2999.44 17.10
Total 202.80 Total 102.02 304.82
14,2, ga c. With 1:3 cement sand mortar. For 1.00 sqm Skill 0.10 1020.0 102.00 Cement bag 0.0612 1040.70 63.69
Unskill 0.14 720.00 100.80 Sand cum 0.0063 2999.44 18.90
Total 202.80 Total 82.59 285.39
9.13 14,3 Flush ruled pointing work with 1:3 c/ m on ashler
stone masonry wall. For 1.0 sqm Skill 0.08 1020.0 81.60 Cement bag 0.0220 1040.70 22.90
Unskill 0.10 720.00 72.00 Sand cum 0.0020 2999.44 6.00
Total 153.60 Total 28.90 182.50
10 PAINTING WORK
10.01 13 ,11 Three coats chapra resin polishing.For 1sqm Skill 0.10 1020.0 102.00 Chapra kg 0.02 1451.32 29.03
Unskill 0.05 720.00 36.00 Spirit Lit 0.10 107.72 10.77
Total 138.00 Total 39.80 177.80
10.02 Distempering painting
13,3, ka a. Lining. For 1 sqm Skill 0.02 1020.0 20.40 Lining Lit. 0.080 250.43 20.03
Unskill 0.02 720.00 14.40
Total 34.80 Total 20.03 54.83 For rate to
estimate
13,3, kha b. First one coat. For 1 sqm Skill 0.02 1020.0 20.40 Distemper Lit. 0.065 267.38 17.38 add a, b &
Unskill 0.02 720.00 14.40 c
Total 34.80 Total 17.38 52.18
13,3, ga c. 2nd coat and additional coats. For 1 sqm Skill 0.018 1020.0 18.36 Distemper Lit. 0.050 267.38 13.37
Unskill 0.018 720.00 12.96
Total 31.32 Total 13.37 44.69

Prepared By: Total Consultancy Pvt Ltd


Page 62 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
10.03 13,6 Applying 1 coat lining and 2 coats of aluminum Skill 0.1075 1020.0 109.65 Primer Lit. 0.081 431.23 34.93
paint. For 1.00sqm Unskill 0.1075 720.00 77.40 Aluminum paint Lit. 0.1076 623.33 67.07
Total 187.05 Sand paper No. 0.04 6.83 0.27
Total 102.27 289.32
10.04 13,5ka-ga 1Coat primer & 2 Coat enamel paint. For 1sqm Skill 0.12 1020.0 122.40 Primer Lit 0.081 431.23 34.93
Unskill 0.08 720.00 57.60 Enamel Lit 0.160 606.38 97.02
Total 180.00 Total 131.95 311.95
10.05 13,5ka-ga 1 Coat primer & 2 Coat weather coat(exterior) Skill 0.12 1020.0 122.40 Cement Primer Lit 0.081 321.32 26.03
emulsion paint. For 1sqm Unskill 0.08 720.00 57.60 Emulsion Lit 0.160 730.68 116.91
Total 180.00 Total 142.94 322.94
10.06 13,5ka-ga 1 Coat primer & 2 Coat emulsion paint.(Interior) Skill 0.12 1020.0 122.40 Cement Primer Lit 0.081 321.32 26.03
For 1sqm Unskill 0.08 720.00 57.60 Emulsion Lit 0.160 606.38 97.02
Total 180.00 Total 123.05 303.05
11 7 line hori. and 2 line diago. barbed wire fencing on m/s angle
(50*50*6mm),at a spacing 2m c/c.For 1m Skill 0.06 1020.0 61.20 Barbed 0.00
Unskill 0.15 720.00 108.00 wire kg 2.67 111.40 297.44
Total 169.20 Total 297.44 466.64
12 ROOFING WORK
CGI sheet roofing including collection of materials.
12.01 9 ,1 For 1 SQM (CGI sheet 24 SWG): Skill 0.11 1020.0 112.20 CGI sheet sqm 1.20 651.29 781.55
Unskill 0.125 720.00 90.00 Bolt & Nut no 3.00 13.33 39.99
Total 202.20 J hook no 2.50 12.74 31.85
Bitumen washer no 5.50 0.54 2.97
Total 856.36 1058.56
12.02 9 ,1 For 1 SQM (CGI sheet 26 SWG): Skill 0.11 1020.0 112.20 CGI sheet sqm 1.20 495.74 594.89
Unskill 0.125 720.00 90.00 Bolt & Nut no 3.00 13.33 39.99
Total 202.20 J hook no 2.50 12.74 31.85
Bitumen washer no 5.50 0.54 2.97
Total 669.70 871.90
12.03 9 ,1 For 1 SQM (CGI sheet 28 SWG): Skill 0.11 1020.0 112.20 CGI sheet sqm 1.20 391.99 470.39
Unskill 0.125 720.00 90.00 Bolt & Nut no 3.00 13.33 39.99
Total 202.20 J hook no 2.50 12.74 31.85

Prepared By: Total Consultancy Pvt Ltd


Page 63 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Bitumen washer no 5.50 0.54 2.97
Total 545.20 747.40
Color CGI sheet roofing including colle. of materials.
12.04 9 ,1 For 1 SQM (CGI sheet 24 SWG): Skill 0.11 1020.0 112.20 CGI sheet sqm 1.20 678.64 814.37
Unskill 0.125 720.00 90.00 Bolt & Nut no 3.00 13.33 39.99
Total 202.20 J hook no 2.50 12.74 31.85
Bitumen washer no 5.50 0.54 2.97
Total 889.18 1091.38
12.05 9 ,1 For 1 SQM (CGI sheet 26 SWG): Skill 0.11 1020.0 112.20 CGI sheet sqm 1.20 537.25 644.70
Unskill 0.125 720.00 90.00 Bolt & Nut no 3.00 13.33 39.99
Total 202.20 J hook no 2.50 12.74 31.85
Bitumen washer no 5.50 0.54 2.97
Total 719.51 921.71
12.06 9 ,1 For 1 SQM (CGI sheet 28 SWG): Skill 0.11 1020.0 112.20 CGI sheet sqm 1.20 430.27 516.32
Unskill 0.125 720.00 90.00 Bolt & Nut no 3.00 13.33 39.99
Total 202.20 J hook no 2.50 12.74 31.85
Bitumen washer no 5.50 0.54 2.97
Total 591.13 793.33
12.07 9 ,2 GI Plain sheet ridge fixing 24 SWG. For 1 M Skill 0.20 1020.0 204.00 GI Plain sheet m 1.20 315.96 379.15
Unskill 0.30 720.00 216.00 Bolt & nut no 4.00 13.33 53.32
Total 420.00 Total 432.47 852.47
12.08 9 ,2 GI Plain sheet ridge fixing 26 SWG. For 1 M Skill 0.20 1020.0 204.00 GI Plain sheet m 1.20 240.85 289.01
Unskill 0.30 720.00 216.00 Bolt & nut no 4.00 13.33 53.32
Total 420.00 Total 342.33 762.33
12.09 9 ,2 GI Plain sheet ridge fixing 28 SWG. For 1 M Skill 0.20 1020.0 204.00 GI Plain sheet m 1.20 190.90 229.08
Unskill 0.30 720.00 216.00 Bolt & nut no 4.00 13.33 53.32
Total 420.00 Total 282.40 702.40
12.10 9 ,2 Color GI Plain sheet ridge fixing 24 SWG. For 1 M Skill 0.20 1020.0 204.00 GI Plain sheet m 1.20 366.93 440.32
Unskill 0.30 720.00 216.00 Bolt & nut no 4.00 13.33 53.32
Total 420.00 Total 493.64 913.64
12.11 9 ,2 Color GI Plain sheet ridge fixing 26SWG. For 1 M Skill 0.20 1020.0 204.00 GI Plain sheet m 1.20 284.86 341.83
Unskill 0.30 720.00 216.00 Bolt & nut no 4.00 13.33 53.32
Total 420.00 Total 395.15 815.15
12.12 9 ,2 Color GI Plain sheet ridge fixing 28 SWG. For 1 M Skill 0.20 1020.0 204.00 GI Plain sheet m 1.20 219.86 263.83
Unskill 0.30 720.00 216.00 Bolt & nut no 4.00 13.33 53.32
Total 420.00 Total 317.15 737.15
12.13 9,5 Slate roofing . For 1Sqm Skill 0.40 1020.0 408.00 Slate sqm 2.40 699.29 1678.30

Prepared By: Total Consultancy Pvt Ltd


Page 64 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Unskill 0.50 720.00 360.00 Nails kg 0.50 131.78 65.89
Total 768.00 Total 1744.19 2512.19
12.14 9,9,kha Thatch roofing.For 1sqm: Skill 0.20 1020.0 204.00 Thatch bun. 16.60 105.00 1743.00
Unskill 0.20 720.00 144.00 Bamboo no. 4.00 325.00 1300.00
Total 348.00 Rope kg 0.50 300.00 150.00
Mat sqm 1.20 946.74 1136.09
Total 4329.09 4677.09
12.15 9,6 Clay tiles (Chimney made) roofing. For 1sqm : Skill 0.05 1020.0 51.00 Clay tile no. 12.50 28.40 355.00
Unskill 0.15 720.00 108.00
Total 159.00 Total 355.00 514.00
12.16 9,7 Clay tile ridge (Chimney made) plate fixing. For 1m: Skill 0.05 1020.0 51.00 Clay tile ridge no. 8.00 42.93 343.44
Unskill 0.05 720.00 36.00
Total 87.00 Total 343.44 430.44
13 WOOD WORK
13.01 10 ,1 a. Local sal wood work for frames including fixing.For 1 Skill 34.00 1020.0 34680.00 salwood cum 1.10 148207.72 163028.49
cum Unskill 3.40 720.00 2448.00 Hold fast no 92.00 21.24 1954.08
Total 37128.00 Screws no 184.00 1.37 252.08
Total 165234.65 202362.65
10 ,1 b.Local soft wood work for frames.For 1 cum Skill 34.00 1020.0 34680.00 Local soft wood cum 1.10 43580.13 47938.14
Unskill 3.40 720.00 2448.00 Hold fast no 92.00 21.24 1954.08
Total 37128.00 Screws no 184.00 1.37 252.08
Total 50144.30 87272.30
13.02 10 ,2 38mm th. wood frame for panelled door shutter. For 1 no(shutter size -1.07*1.982 = 2.12sqm)
a.With Local sal wood Skill 10.00 1020.0 10200.00 Salwood cum 0.084 148207.72 12449.45
Unskill 1.00 720.00 720.00 hinge 150mm no 6.00 63.77 382.62
Total 10920.00 Tower bolt 150mm no 1.00 75.91 75.91
Tower bolt 300mm no 1.00 121.30 121.30
Locking set set 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw &nail no 80.00 1.37 109.60
Total 13540.88 24460.88
13.02 10,2 b.With Local softwood Skill 10.00 1020.0 10200.00 Local soft wood cum 0.084 43580.13 3660.73
Unskill 1.00 720.00 720.00 hinge 150mm no 6.00 63.77 382.62
Total 10920.00 Tower bolt 150mm no 1.00 75.91 75.91
Tower bolt 300mm no 1.00 121.30 121.30
Locking set set 1.00 295.28 295.28

Prepared By: Total Consultancy Pvt Ltd


Page 65 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Handle no 2.00 53.36 106.72
Screw &nail no 80.00 1.37 109.60
Total 4752.16 15672.16
13.03 10 ,3 38*75mm size wood frame using 3mm plain glass for glazed shutter. For 1no.(shutter size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Skill 9.00 1020.0 9180.00 Salwood cum 0.049 148207.72 7262.18
Unskill 0.90 720.00 648.00 Glass 3mm sqm 1.085 648.90 704.06
Total 9828.00 Hinge 75mm no 8.00 17.20 137.60
Tower bolt 100mm no 4.00 45.35 181.40
Handle no 2.00 53.36 106.72
Screw & nail no 84.00 1.37 115.08
Total 8507.04 18335.04
10 ,3 b.With Local softwood Skill 9.00 1020.0 9180.00 Local soft wood cum 0.049 43580.13 2135.43
Unskill 0.90 720.00 648.00 Glass 3mm sqm 1.085 648.90 704.06
Total 9828.00 Hinge 75mm no 8.00 17.20 137.60
Tower bolt 100mm no 4.00 45.35 181.40
Handle no 2.00 53.36 106.72
Screw & nail no 84.00 1.37 115.08
Total 3380.29 13208.29
13.04 10 ,3 38*75mm size wood frame using 4mm plain glass for glazed shutter. For 1no.(shutter size - 1.892*1.22 = 2.23sqm)
a.With Local salwood Skill 9.00 1020.0 9180.00 Salwood cum 0.049 148207.72 7262.18
Unskill 0.90 720.00 648.00 Glass 4mm sqm 1.085 851.31 923.67
Total 9828.00 Hinge 75mm no 8.00 17.20 137.60
Tower bolt 100mm no 4.00 45.35 181.40
Handle no 2.00 53.36 106.72
Screw & nail no 84.00 1.37 115.08
Total 8726.65 18554.65
13.04 10 ,3 b.With Local softwood Skill 9.00 1020.0 9180.00 Local soft wood cum 0.049 43580.13 2135.43
Unskill 0.90 720.00 648.00 Glass 4mm sqm 1.085 851.31 923.67
Total 9828.00 Hinge 75mm no 8.00 17.20 137.60
Tower bolt 100mm no 4.00 45.35 181.40
Handle no 2.00 53.36 106.72
Screw & nail no 84.00 1.37 115.08
Total 3599.90 13427.90

Prepared By: Total Consultancy Pvt Ltd


Page 66 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
13.05 10 ,9 38mm wood frame using 26 SWG Plain GI sheet on both side. For 1 no.(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Skill 7.00 1020.0 7140.00 Salwood cum 0.0346 148207.72 5127.99
Unskill 0.70 720.00 504.00 GI Plain sheet sqm 4.65 392.53 1825.26
Total 7644.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set set 1.00 295.28 295.28
Handle no 1.00 53.36 53.36
Screw & nail no 50.00 1.37 68.50
Total 7618.24 15262.24
10,9 b.With Local softwood Skill 7.00 1020.0 7140.00 Local soft wood cum 0.0346 43580.13 1507.87
Unskill 0.70 720.00 504.00 GI Plain sheet sqm 4.65 392.53 1825.26
Total 7644.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set set 1.00 295.28 295.28
Handle no 1.00 53.36 53.36
Screw & nail no 50.00 1.37 68.50
Total 3998.12 11642.12
13.06 10 ,10 38mm wood frame using 24 SWG GI wire mesh mosquito proof shutter .For 1 no.(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Skill 5.00 1020.0 5100.00 Salwood cum 0.026 148207.72 3853.40
Unskill 0.50 720.00 360.00 Wire mesh sqm 2.13 145.04 308.94
Total 5460.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Spring no. 1.00 220.72 220.72
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 4806.13 10266.13
13.06 10 ,10 b.With Local softwood Skill 5.00 1020.0 5100.00 Local soft wood cum 0.026 43580.13 1133.08
Unskill 0.50 720.00 360.00 Wire mesh sqm 2.13 145.04 308.94
Total 5460.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Spring no. 1.00 220.72 220.72
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 2085.81 7545.81
13.07 10,7 38mm wood frame using 3mm plywood both side for flush shutter. For 1 no.(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Skill 7.00 1020.0 7140.00 Sal wood cum 0.0346 148207.72 5127.99

Prepared By: Total Consultancy Pvt Ltd


Page 67 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Unskill 0.70 720.00 504.00 Plywood 3mm th. sqm 4.65 308.62 1435.08
Total 7644.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 7281.42 14925.42
10,7 b.With Local softwood Skill 7.00 1020.0 7140.00 Local soft wood cum 0.0346 43580.13 1507.87
Unskill 0.70 720.00 504.00 Plywood 3mm th. sqm 4.65 308.62 1435.08
Total 7644.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 3661.30 11305.30
13.08 10,7 38mm wood frame using 3mm plywood one side for flush shutter .For 1 no.(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Skill 5.50 1020.0 5610.00 Sal wood cum 0.0346 148207.72 5127.99
Unskill 0.70 720.00 504.00 Plywood 3mm th. sqm 2.325 308.62 717.54
Total 6114.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 6563.88 12677.88
13.08 10,7 b.With Local softwood Skill 5.50 1020.0 5610.00 Local soft wood cum 0.0346 43580.13 1507.87
Unskill 0.70 720.00 504.00 Plywood 3mm th. sqm 2.325 308.62 717.54
Total 6114.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 2943.76 9057.76
13.09 10,7 38mm wood frame using 6mm plywood both side for flush shutter. For 1 no.(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Skill 7.00 1020.0 7140.00 Sal wood cum 0.0346 148207.72 5127.99
Unskill 0.70 720.00 504.00 Plywood 6mm th. sqm 4.65 678.04 3152.89

Prepared By: Total Consultancy Pvt Ltd


Page 68 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Total 7644.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 8999.23 16643.23
b.With Local softwood Skill 7.00 1020.0 7140.00 Local soft wood cum 0.0346 43580.13 1507.87
Unskill 0.70 720.00 504.00 Plywood 6mm th. sqm 4.65 678.04 3152.89
Total 7644.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 5379.11 13023.11
13.10 10,7 38mm wood frame using 6mm plywood one side for flush shutter .For 1 no.(shutter size - 1.092*2.058 = 2.247sqm)
a.With Local salwood Skill 5.50 1020.0 5610.00 Sal wood cum 0.0346 148207.72 5127.99
Unskill 0.70 720.00 504.00 Plywood 6mm th. sqm 2.325 678.04 1576.44
Total 6114.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 7422.78 13536.78
13.10 10,7 b.With Local softwood Skill 5.50 1020.0 5610.00 Local soft wood cum 0.0346 43580.13 1507.87
Unskill 0.70 720.00 504.00 Plywood 6mm th. sqm 2.325 678.04 1576.44
Total 6114.00 Hinge 100mm no 3.00 32.01 96.03
Tower bolt 150mm no 2.00 75.91 151.82
Locking set no. 1.00 295.28 295.28
Handle no 2.00 53.36 106.72
Screw & nail no 50.00 1.37 68.50
Total 3802.66 9916.66
Fixing glass of different thichness in window frame including fixing of wooden listis. For 1sqm with :
13.11 10,11,ka a.3 mm thick glass Skill 0.06 1020.0 61.20 3 mm glass sqm 1.00 648.90 648.90
Unskill 0.006 720.00 4.32 Wooden listi m 4.05 19.00 76.95
Total 65.52 Nails 0.05 131.78 6.59
Total 732.44 797.96

Prepared By: Total Consultancy Pvt Ltd


Page 69 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
b 4 mm thick glass Skill 0.06 1020.0 61.20 4 mm glass sqm 1.00 851.31 851.31
Unskill 0.006 720.00 4.32 Wooden listi m 4.05 19.00 76.95
Total 65.52 Nails 0.05 131.78 6.59
Total 934.85 1000.37
13.12 10 ,17 Wood work for beam and joist including fixing .For 1cum
a.With Local salwood Skill 17.65 1020.0 18003.00 Salwood cum 1.05 148207.72 155618.11
Unskill 1.76 720.00 1267.20 Nails no 2.50 131.78 329.45
Total 19270.20 Total 155947.56 175217.76
b.With Local softwood Skill 17.65 1020.0 18003.00 Local soft wood cum 1.05 43580.13 45759.14
Unskill 1.76 720.00 1267.20 Nails no 2.50 131.78 329.45
Total 19270.20 Total 46088.59 65358.79
13.13 10,18 a.Local salwood work for truss fixing.For 1M3 Skill 17.65 1020.0 18003.00 Salwood cum 1.05 148207.72 155618.11
Unskill 26.00 720.00 18720.00 Iron plates l.s. 10.00 532.84 5328.40
Total 36723.00 Nuts & Bolts l.s. 1.00 3000.00 3000.00
Nails l.s. 1.00 1000.00 1000.00
Total 164946.51 201669.51
b.Local soft wood work for truss fixing.For 1M3 Skill 17.65 1020.0 18003.00 Local soft wood cum 1.05 43580.13 45759.14
Unskill 26.00 720.00 18720.00 Iron plates l.s. 10.00 532.84 5328.40
Total 36723.00 Nuts & Bolts l.s. 1.00 3000.00 3000.00
Nails l.s. 1.00 1000.00 1000.00
Total 55087.54 91810.54
13.14 10 ,19 a. Local salwood work for 25mm th. Eaves board including fitting.
For 1SQM Skill 0.143 1020.0 145.86 Salwood cum 0.0275 148207.72 4075.71
Unskill 0.0143 720.00 10.30 Nails no 0.50 131.78 65.89
Total 156.16 Total 4141.60 4297.76
10 ,19 b. Local soft wood work for 25mm th. Eaves board including fitting.
For 1SQM Skill 0.143 1020.0 145.86 Local soft wood cum 0.0275 43580.13 1198.45
Unskill 0.0143 720.00 10.30 Nails no 0.50 131.78 65.89
Total 156.16 1420.50
Total 1264.34
13.15 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Skill 23.00 1020.0 23460.00 Sal wood cum 0.35 148207.72 51872.70
Unskill 2.30 720.00 1656.00 Plywood 3mm sqm 75.00 308.62 23146.50
Total 25116.00 Listi m 80.00 19.00 1520.00
Nails kg 1.00 131.78 131.78
Total 76670.98 101786.98
b. With Local soft wood Skill 23.00 1020.0 23460.00 Local soft wood cum 0.35 43580.13 15253.05
Unskill 2.30 720.00 1656.00 Plywood 3mm sqm 75.00 308.62 23146.50
Total 25116.00 Listi m 80.00 19.00 1520.00

Prepared By: Total Consultancy Pvt Ltd


Page 70 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Nails kg 1.00 131.78 131.78
Total 65167.33
40051.33
13.16 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 3mm plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Skill 19.00 1020.0 19380.00 Sal wood cum 0.35 148207.72 51872.70
Unskill 2.00 720.00 1440.00 Plywood 3mm sqm 37.50 308.62 11573.25
Total 20820.00 Listi m 40.00 19.00 760.00
Nails kg 0.75 131.78 98.84
Total 64304.79 85124.79
b. With Local softwood Skill 19.00 1020.0 19380.00 Local soft wood cum 0.35 43580.13 15253.05
Unskill 2.00 720.00 1440.00 Plywood 3mm sqm 37.50 308.62 11573.25
Total 20820.00 Listi m 40.00 19.00 760.00
Nails kg 0.75 131.78 98.84
Total 27685.14 48505.14
13.17 10,14,ka 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm plywood both side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Skill 23.00 1020.0 23460.00 Sal wood cum 0.35 148207.72 51872.70
Unskill 2.30 720.00 1656.00 Plywood 6mm sqm 75.00 678.04 50853.00
Total 25116.00 Listi m 80.00 19.00 1520.00
Nails kg 1.00 131.78 131.78
Total 104377.48 129493.48
b. With Local soft wood Skill 23.00 1020.0 23460.00 Local soft wood cum 0.35 43580.13 15253.05
Unskill 2.30 720.00 1656.00 Plywood 6mm sqm 75.00 678.04 50853.00
Total 25116.00 Listi m 80.00 19.00 1520.00
Nails kg 1.00 131.78 131.78
Total 92873.83
67757.83
13.18 0.61*0.915m size wooden frame (wood size 38*75mm) work for partation using 6mm plywood one side(partation size - 9.75*3.65m=35.59sqm)
a. With Local salwood Skill 19.00 1020.0 19380.00 Sal wood cum 0.35 148207.72 51872.70
Unskill 2.00 720.00 1440.00 Plywood 6mm sqm 37.50 678.04 25426.50
Total 20820.00 Listi m 40.00 19.00 760.00
Nails kg 0.75 131.78 98.84
Total 78158.04 98978.04
b. With Local softwood Skill 19.00 1020.0 19380.00 Local soft wood cum 0.35 43580.13 15253.05
Unskill 2.00 720.00 1440.00 Plywood 6mm sqm 37.50 678.04 25426.50
Total 20820.00 Listi m 40.00 19.00 760.00
Nails kg 0.75 131.78 98.84

Prepared By: Total Consultancy Pvt Ltd


Page 71 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
Total 41538.39 62358.39
13.19 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 3mm plywood for different type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Skill 23.00 1020.0 23460.00 Sal wood cum 0.45 148207.72 66693.47
Unskill 2.30 720.00 1656.00 3mm plywood sqm 37.50 308.62 11573.25
Total 25116.00 Listi m 50.00 19.00 950.00
Nails kg 1.25 131.78 164.73
Total 79381.45 104497.45
b. With Local soft wood Skill 23.00 1020.0 23460.00 Local soft wood cum 0.45 43580.13 19611.06
Unskill 2.30 720.00 1656.00 3mm plywood sqm 37.50 308.62 11573.25
Total 25116.00 Listi m 50.00 19.00 950.00
Nails kg 1.25 131.78 164.73
Total 57415.04
32299.04
13.20 10,16,ka 0.60*0.90m size wooden frame (wood size50*75mm)using 6mm plywood for different type false ceilings( ceilings size=9.75*3.65m=35.59sqm)
a. With Local salwood Skill 23.00 1020.0 23460.00 Sal wood cum 0.45 148207.72 66693.47
Unskill 2.30 720.00 1656.00 Plywood 6mm sqm 37.50 678.04 25426.50
Total 25116.00 Listi m 50.00 19.00 950.00
Nails kg 1.25 131.78 164.73
Total 93234.70 118350.70
b. With Local soft wood Skill 23.00 1020.0 23460.00 Local soft wood cum 0.45 43580.13 19611.06
Unskill 2.30 720.00 1656.00 Plywood 6mm sqm 37.50 678.04 25426.50
Total 25116.00 Listi m 50.00 19.00 950.00
Nails kg 1.25 131.78 164.73
Total 46152.29 71268.29
14 DEMOLIITIONS AND REPAIR WORK
14.01 19-1 Demolishing mud mortar masonry and disposing the
materials to a distance of 10m. For 1cum: Unskill 1.06 720.00 763.20 763.20
14.02 19-2 Demolishing cement or lime surkhi mortar masonry and disposing
the materials to a distance of 10m.For 1cum : Unskill 2.12 720.00 1526.40 1526.40
14.03 19 - 3 Demolishing RCC or RBC work and disposing
materials to a distance of 10m. For 1cum : Unskill 11.00 720.00 7920.00 7920.00
14.04 19 - 4 Demolishing PCC or lime surkhi concrete and disposing
the materials to a distance of 10m.For 1cum : Unskill 4.00 720.00 2880.00 2880.00
14.05 19 - 5 Demolishing cement or lime surkhi plaster and disposing
the materials to a distance of 10m.For 1cum : Unskill 0.108 720.00 77.76 77.76

Prepared By: Total Consultancy Pvt Ltd


Page 72 of 73

ANALYSIS OF RATE
Rate Analysis base on "Construction Norm's 2041" Amanat Rate of F.Y. 2076/077 For Different Project without Road
SN Labour (L) Materials (M) Rate per Unit
Norms Category Man Rate Amount Type Unit Quantity Rate Amount
No. Description Day Rs Rs Rs Rs Rs Remarks
14.06 19 -6 Demolishing tiled roof and stacking the tiles, wood etc.
properly at a distance of 10m. For 1cum : Skill 0.054 1020.0 55.08
Unskill 0.081 720.00 58.32
Total 113.40 113.40
15 COLLECTION OF MATERIAL
Making rough blocks of required size from boulder, without blasting , one side dressing hauling distance 10m and stacking For 1cum :
15.01 3 , 7 Making blocks (one side dressing) Unskill 9.63 720.00 6933.60 6933.60
Making blocks of required size from boulder, with Chisel , hauling distance 10m and stacking For 1cum :
15.02 3 , 9ka Making 3 sides rough squares and 1 side smooth Unskill 20.00 720.00 14400.00 14400.00
15.03 3 , 9kha Making 5 sides rough squares and 1 side smooth Unskill 34.48 720.00 24825.60 24825.60
END

Prepared By: Total Consultancy Pvt Ltd


Page 73 of 73

TRANSPORTATION OF MATERIALS AT SITE


Amanat Rate of F.Y. 2076/077 For Different Project without Road

Rate Analysis base on "Construction Norm's 2041"

Distance from kathmandu to Barabise : 84.00 km( black top surface)


Distance from Barabise to Project Site : 15 km [Earthern]

Rate analysis based on Government of Nepal approved Norms 2041(Including 2nd revision) & approved district rate of Sindhupalchowk & Kathmandu for fiscal year 2076/077.

1.Transportation for Convenient Materials :-


By Vehicles By Vehicles Load & Unload
Black topped road Earthern road By Manual

Rate per Rate per Rate per Rate per Total Cost
S.N. From To Mt./km Distance Amount Mt./km Distance Amount kg./kosh Distance Amount 50 kg Amount per kg
1 Kathmandu Barabise 32.00 84.000 2.69 46.00 0.000 0.00 4.00 0.000 0.00 20.00 0.40 3.09
2 Barabise Project Site 32.00 0.000 0.00 46.00 18.000 0.83 4.00 0.250 1.00 0.00 0.00 1.83
3 Kathmandu Project Site 32.00 84.000 2.69 46.00 18.000 0.83 4.00 0.250 1.00 20.00 0.40 4.92

2.Transportation for Inconvenient Materials :-


By Vehicles By Vehicles
Black topped road Earthern road By Manual Load & Unload

Rate per Rate per Rate per Rate per Total Cost
S.N. From To Mt./km Distance Amount Mt./km Distance Amount kg./kosh Distance Amount 50 kg Amount per kg
1 Kathmandu Barabise 43.00 84.000 3.61 55.00 0.000 0.00 5.00 0.000 0.00 30.00 0.60 4.21
2 Barabise Project Site 43.00 0.000 0.00 55.00 18.000 0.99 5.00 0.250 1.25 0.00 0.00 2.24
3 Kathmandu Project Site 43.00 84.000 3.61 55.00 18.000 0.99 5.00 0.250 1.25 30.00 0.60 6.45

Prepared By: Total Consultancy Pvt Ltd

You might also like