Professional Documents
Culture Documents
net/publication/271848003
CITATION READS
1 626
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Zhen Chen on 14 November 2017.
Prince Boateng
Dr Z. Chen
Prof. S.O. Ogunlana
30 options drawn up
Proposed Route of the Edinburgh Trams - Source: The City of Edinburgh Council, 2013.
o £ 40 million
o 27 vehicles
o 250 capacity
Construction (cont’d)
May 2008 – Turnkey Infrastructure Construction
contract (INFRACO) awarded to Bilfinger
Berger & Siemens (BBS) Consortium
o Initial estimated costs £498 million
TEST VERSION
ONLY
Business Case
Utilities
Tram construction
(Tramco)
Infrastructure
construction (Infraco)
Legend: Plan
Actual
TEST VERSION
50
0
Infrastructure Tram Utilities Design Project Land and Contingency
construction construction diversion management compensation
Causes of Time & Cost Overruns
Social risks CEC, TS, TEL,
Demand Lothian Buses, TIE,
o Dispute side MPs, Ministers
Internal
o Legal actions Supply BBS, CAF, Trandev,
side T&T, Parson, Alfred
o Multi-level decision McAlpine
making bodies
o Stakeholders’ Edinburgh residents, Scotland
pressure residents, UK residents, cycling
Private groups, Business owners,
media, other private transport
External operators
o Construction disruption
Causes of Time & Cost Overruns (cont’d)
Economic risks
o Economic downturn
o Delays of all types
o Changes in project governing body
o Quality deficiency/rework
Causes of Time & Cost Overruns (cont’d)
Environmental risks
o 2009/2010 & 2010/2011 – Freezing
temperature halted construction
Causes of Time & Cost Overruns (cont’d)
Political risks
o Lack of political support
o Political indecision
o Contractual disputes
2009- BBS demand additional £50-£80 mil before
beginning work on Princes Street.
Tie refused
2010- BBS announced 30 months delay to 2014
o 2011- Tie released from managing project
o 2011 - Cost revised from £545 to £776 mil
o 2012- T&T appointed to manage project
Changes and Disputes to date.
816 notice of
251 – Still Claims
hanging
677 continued
139 withdrawn
with
426 Estimates
Cost of disputes to date submitted
£ 23.8 m
198 settled 228 not settled
£ £ £
3.7m 3.5m 4.0m
Hierarchy of Identified Risk Areas in ETN Project
Level 1 STEEP Risks in Megaproject Construction
Level 3 Social grievances Ambiguity of project scope/ Change in government Environmental issues from Change in government funding
Scope change funding policy works (Pollution) policy
Multi -level decision Ground conditions on given Taxation changes Unfavourable climate Political opposition
making bodies project sites conditions (Snow, rain,
wind etc.)
Disputes Inadequate project complexity Change in government Government discontinuity
analysis
Legal Actions Unforeseen modification to Wage inflation Lack of political support
project
Stakeholder's pressure Inaccurate project cost Local inflation change Political indecision
estimate
Treats to person & asset Failure to meet specified Foreign exchange rate Project termination
security standards
Social Issues Technical difficulties in Material price changes Delay in obtaining consent/
utilities diversions Approval
24/67
Data source Database
Risks identification and categorization
· Literature on STEEP
ANP route SD route
· Data from source List of
documents of past potential risks Initial model development
similar projects
MV
1 n
· Feedback structure
n i 1 E i ( C ,T ,Q ) · Casual flow diagram
Model verification
· Expert opinion
Conduct pairwise Comparison
1 R 12
... R 1n
R ... R ...
PRw
21 ij
... R 1 .... 1
ji
R ij R 1n Model development
R n1
... ... 1 · Develop formulae for flow diagrams
w
i 1
i
1
Test passed
List of Top n
“priority risks”
Test not
Model validation passed
Testing of model structure &
behaviour
SDANP Framework
Software application
Test passed
PR4: Environmental
Options PR1: Social risks PR2:Technical Risks PR3: Economic risks PR5: Political risks
risks
Options TV1 TV2 TV3 TV4 TV5 TV6 TV7 TV8 TV9 TV10 TV11 TV12
PR4:Environmental
risks Options ENV1 ENV2
ENV1, ENV2
Inner
dependencies
ANP Network Models for STEEP Risks Prioritization
Comparison Matrices
Project objective Potential
MVR PR1 PR2 PR3 PR4 PR5 TPV Priorities R
Risks (PR)
4 PR1 1 1/2 1/2 1 1/2 0.13 0.13 4
Cost
λmax = 5.00 5 PR2 2 1 1 2 1 0.25 0.25 2
CI = 0.00 5 PR3 2 1 1 2 1 0.25 0.25 1
RI = 1.11 4 PR4 1 1/2 1/2 1 1/2 0.13 0.13 5
CR = 0.00 5 PR5 2 1 1 2 1 0.25 0.25 3
1.01 1.01
4 PR1 1 1/2 1/2 1 1 0.14 0.14 3
Time
λmax = 5.00 5 PR2 2 1 1 2 2 0.29 0.29 2
CI = 0.00 5 PR3 2 1 1 2 2 0.29 0.29 1
RI = 1.11 4 PR4 1 1/2 1/2 1 1 0.14 0.14 5
CR = 0.00 4 PR5 1 1/2 1/2 1 1 0.14 0.14 4
1.00 1.00
3 PR1 1 1/3 1/2 1/2 1 0.11 0.11 4
Quality
λmax = 5.08 5 PR2 3 1 2 2 3 0.37 0.37 1
CI = 0.02 4 PR3 2 1/2 1 1 2 0.21 0.21 2
RI = 1.11 4 PR4 2 1/2 1 1 2 0.21 0.21 3
CR = 0.02 3 PR5 1 1/3 1/2 1/2 1 0.11 0.11 5
1.01 1.01
Legend: λmax = maximum eigenvalue, CI = Consistency Index, RI = Random Index, CR = Consistency ratio, TPV = Total priority value,
NPV = Normal priority value, IPV = Ideal priority value R = Ranking
Results of Final Mode ANP Decision Making Priorities
Political Political - +
Project +
+
Social
+ -
Political opposition
-
<Political
-
to the project +
acceptability support>
+
SD models for STEEP risks in ETN project
SOCIAL
Environ. Factors
SUBSYSTEM
Effects of Project
Air emission
TECHNICAL
Habitat destruction
POLICAL
SUBSYSTEM
SUBSYSTEM
Waste generation
MegaDS Pollution (air/ water)
Comfort disturbances
Health & safety
ENVIRON. ECONOMIC Effects on Project
SUBSYSTEM SUBSYSTEM
Critical weather conditions
Design
(snow, rain, wind etc..)
Temperature
Model structure
Landslide, etc.
Model Boundary
Risk Code Risk Type
Type I: Endogenous Risk Variables
PR4 Environmental risks
ENV3 Cost of legal action
ENV4 Disputes
ENV5 Environmental regulation enforcement
ENV6 Environmental certainties
ENV7 Environmental uncertainties
ENV8 Error generation
ENV9 Escalation to project cost overrun
ENV10 Escalation to project time overrun
ENV11 Legal action
ENV12 Multi decision making bodies involvement
ENV13 Project quality deficiency
ENV14 Risks of project cost overrun
ENV15 Risks of project time overrun
ENV16 Social issues
ENV17 Social grievances
ENV18 Worksite coordination problems
Type II: Exogenous Risk Variables
ENV1: Environmental issues from works
ENV2 Unfavourable climate conditions
System Dynamics: Dynamic Hypothesis (CLD)
+
{Pollution (Air, water, Worksite coordination
soil & noise)} problems
Environmental issues + Information
Error flow, e.g.
from works R8
+
how environmental
generation
+ R4 Project quality
+
+ deficiency uncertainties
+
affect
<Legal
Environmental
uncertainties R1
Environmental
risks
actions>
+
R7 project time
+
- R6
+ Escalation to project
R3
cost overrun
+ + Risks of project
- cost overrun +
Environmental Cost of legal + +
certainties action +
Unfavourable
R9
climatic conditions R2 -
Risks of project
-Snowfall; time overrun R5
+
-Heavy rainfall; Escalation to project
time overrun
-Flood; +
-Temperature <Environmental issues + +
from works>
-Heat waves; +
Disputes Legal Multilevel decision
-Drought;
+ actions making bodies
-Dust & Wind storms; + +
+ involvement
-Hurricane;
Social Environmental
-Thunder and Lightning; Social
grievances regulation
-Earthquake; issues
enforcement
Legend: +
+
. .. A casual relationship
-
+ (-) signs at the arrowheads indicate that the effect is
` related to the cause.
positively (negatively)
R denotes reinforcing loop
SD: Stock & Flow Model Diagram
<Project quality
deficiency> Risks of project
<Risks of project Information links,
time overrun>
Escalation to project
cost overrun expressing
Flow, here an cost overrun Project quality
deficiency
dependencies
inflow <Error
generation> Worksite coordination
Cost of legal problems
action Error
Risks of project
Escalation to project generation
time overrun
time overrun
. Flow
; `
Accumulation of
Environmental
risks risks
Environmental issues Environmental Environmental
from works Represents ANP
uncertainties certainties
Priority Index
0.20
Stock, cumulated Valve
by of flow
..
0.79 Unfavourable Environmental risks cluster inflows and de- Source or Sink
climatic conditions priority index from ANP
cumulated by
outflows
Environmental risks
0.2
1
1
1 1 1
1 Dynamic pattern (Actual)
18.7% (max)
2 2 2 2 1
12 2
2 1 Initial RPI for
0.15 2
2 1 PR4 = 16%
2 1
Max. PR4 impact 2 1
Max. PR4 @
9.9% (min)
Dmnl
0.1 level @ year 2 1
0% ENV2 2010 = 18.7% 2
1
impact level 2
1 Min risk impact
0.05 in year
Dynamic pattern @ level for PR4 =
2009.25 =
ENV2 = 0% impact level 0.07 (7%)
17%
0
2008 2009 2010 2011 2012 2013 2014 2015
Time (Year)
Environmental risks : Current (Actual) 1 1 1 1 1 1 1 1 1 1 1
Environmental risks : Baserun@ 0% ENV2 impact level 2 2 2 2 2 2 2 2 2
a: Baserun and actual scenario simulation patterns for environmental risks Project completion
time - 10/2013
Risks of project time overrun
0.6
1 Max. ENV15 @ 20%
Behaviour pattern for ENV15 1
ENV1 and 79%
based on 20% of ENV1 and 0% of 1
0.45 1 impact level =
ENV2 impact levels 1 2
55.4%
2
1 2
Level of 1 2
48% (max)
Dmnl
0.3 1 2
ENV15 in 2 Max. ENV15 @ 20%
1
2008 = 0% 2
1 2 Actual dynamic ENV1 and 0% ENV2
2 impact level = 41%
0.15 1
2 pattern for Risks
1 2
1 2
of project time
12 overrun
0 12
2008 2009 2010 2011 2012 2013 2014 2015
Time (Year)
Risks of project time overrun : Current (Actual) 1 1 1 1 1 1 1 1 1 1
Risks of project time overrun : Baserun@ 0% ENV2 impact level 2 2 2 2 2 2 2 2
b: Baserun and actual scenario simulation patterns for risks of project time overrun
Risks of project cost overrun
0.4
Max. ENV14 @ 20%
1
Actual dynamic behaviour pattern ENV1 and 79%
0.3 2 impact level = 35%
1
Behaviour pattern for 0% impact level
1 2
Dmnl
0.2 2 Max. ENV14 @ 20%
1
Level of 1
2 ENV1 and 79%
2
ENV14 in 1 2 impact level = 28%
0.1 1 2
2008 = 0% 12
12
0 1 2
1 2 12
12
12
23% (max)
12
2008 2009 2010 2011 2012 2013 2014 2015
Time (Year)
Risks of project cost overrun : Current (Actual) 1 1 1 1 1 1 1 1 1 1
Risks of project cost overrun : Baserun@ 0% ENV2 impact level 2 2 2 2 2 2 2 2
c: Baserun and actual scenario simulation patterns for risks of project cost overrun
1 Max. ENV13 @
Actual dynamic
Dmnl
d: Baserun and actual scenario simulation patterns for project quality deficiency
Social risks
0.6
DSBP @ 0% of SV7 1 DSBP @ 100% of SV7
1
1 1 2
0.3 3
1 3 4 2 1 1 2
12 3 4 3
45 5 2 5
3
5 5 2 45 5 5
2
Dmnl
0 2 4 1
4 4 3
2 3 4 3
3
-0.3
DSBP @ 25% of SV7 DSBP @ 75% of SV7 DSBP @ 50% of SV7
-0.6
2008 2009 2010 2011 2012 2013 2014 2015
Time (Year)
Social risks : Current (Actual) 1 1 1 1 1 1
Social risks : Current scenario 3 2 2 2 2 2 2
Social risks : Current scenario 2 3 3 3 3 3 3
Social risks : Current scenario 1 4 4 4 4 4 4 4
Social risks : Current (Risk free scenario) 5 5 5 5 5 5
0.2 2 1
pattern (0% pattern impact level.
1 (Actual)
impact level) 2
0.1 2 1
2010.13
2 1
2 1
0 2 1 Min risk impact
2
2008 2009 2010 2011 2012 2013 2014 2015 level for PR3 =
Time (Year) 1.72%
Economic risks : Current (Actual) 1 1 1 1 1 1 1 1 1 1 1 1
Economic risks : Base run@ 0% (Exogenous) risk impact level 2 2 2 2 2 2 2 2
50% chance that the level of political risks will be between 15% and 55%
75% and the 95% confidence bounds suggest that the level of political
risks could range from 10% to 65% and 5% to 80% respectively.
Behaviour Mode (Actual)
50% 75% 95% 100%
"Political risks."
1
0.75
0.5
0.25
0
2008 2009 2010 2011 2012 2013 2014 2015
Time (Year)
Original Project Information (OPI)
Cost (£ Million) Planned Project Budget (PPB) 545
Revised Project Budget (RPB) 776
Project Cost Variation (PCV) 231
Year of Completion Original Planned Date (OPD) 2011 (3 Years)
Cost (C) Time (T) Quality (Q) Total Impact Cost (£ million) Time (year)
clear site
install manhole
Time-dep. Risks
43/67
Well defined research methodology
44/67
SBE Heriot-Watt University
Edinburgh Trams
45/67
Thank You
View publication stats