Professional Documents
Culture Documents
Block
Cave
Mine
2020
–
Case
study
on
a
continuously
operated
Mega
Mine
Jens
Steinberg
(Speaker)
Caterpillar
Global
Mining
Markus
Frenzel
Caterpillar
Global
Mining
Dr.
Johannes
Krings
Caterpillar
Global
Mining
Abstract
As
global
demand
for
raw
materials
continues
to
increase,
mining
companies
are
looking
for
ways
to
increase
production
capacity.
As
visible
in
actual
green
field
projects
around
the
world,
the
trend
in
block
caving
goes
to
production
rates
up
to
160,000
tonnes
per
day.
This
development
in
mine
design
correlated
with
the
capacity
change
of
mine
output
figures
and
the
actual
market
situation
in
mind
as
well,
this
paper
analyzes
the
limits
of
current
block
cave
mines
and
points
out
an
approach
for
maximized
production
capacities
in
future
block
caving
mines.
Hereby,
the
paradigm
shift
from
discontinuous
common
hard
rock
mining
to
continuous
operating,
high-‐performance
block
caving
operations
is
discussed.
1
Introduction
The
intention
of
this
paper
is
to
analyze
the
bottle
necks
in
the
different
processes
when
it
comes
to
block
caving
mines
rated
at
160,000
tonnes
per
day
production
and
to
discuss
new
technical
concept
aimed
at
overcoming
these
bottle
necks.
First
step
of
this
investigation
was
to
define
a
mine
design
related
to
adequate
rock
properties
and
to
set
a
proper
production
rate
for
the
case
study.
Following,
bottlenecks
–
generated
by
the
evaluated
case
study
parameters
–
must
be
identified
and
eliminated
for
the
strived
mining
operation.
2
Case
Study
Mine
design
For
this
study,
the
mine
design
was
set
for
a
panel
caving
operation
with
a
typical
draw
point
spacing
of
15
x
15
m
and
a
characteristic
average
block
height
of
560
m.
The
ore
density
is
set
to
ρ=
2.7
t/m³.
A
challenge
in
terms
of
increasing
the
extraction
rate
is
balancing
the
different
phases
of
the
mining
sequence
(reaping,
spreading
and
development
of
new
areas)
in
order
to
achieve
a
constant
output
of
production
and
to
avoid
stand
still
waiting
times.
The
extraction
rate
of
the
initial
phase
(spreading)
of
the
caving
process
(τs)
is
restricted
to
low
values
in
order
to
prevent
undesired
events
such
as
high
seismic
activities
or
sudden
air
blasts.
Therefore
the
mean
extraction
rate
(τm)
can
only
be
raised
by
increasing
the
production
rate
in
the
regular
phase
(reaping)
(τr),
formula
1
describes
this
relationship:
τm
=
(n
*
τs
+
τr)
/
(n+1)
(1)
τm
=
mean
extraction
rate
τs
=
extraction
rate
spreading
phase
τr
=
extraction
rate
of
regular
caving
n
=
number
of
blocks
in
initial
phase
τm
is
calculated
under
consideration
of
the
extraction
rate
during
initial
caving
phase
(τs)
and
the
extraction
rate
of
regular
caving
(τr)
as
a
function
of
number
of
blocks
in
initial
phase
(n).
For
this
case
study
it
was
assumed,
that
the
spreading
rate
(τs)
is
limited
to
0.45
tpd/m²,
when
applying
pre-‐conditioning
methods.
According
to
the
paper
“Mechanized
continuous
drawing
system:
A
technical
answer
to
increase
production
capacity
for
large
block
caving
mines”
presented
by
V.
Encina
et
al
at
the
MassMin
2008,
the
optimum
ratio
of
no.
of
reaping
blocks
to
no.
of
spreading
blocks
is
1:
3.
1.60
Mean
producFon
rate
[t/d
m²]
1.50
1.40
1.30
1.20
1.10
1.00
0.90
0.80
0.70
1
2
3
4
5
6
No.
of
blocks
in
spreading
per
reaping
block
Figure
1:
Interdependence
of
mean
production
rate
to
spreading
blocks
per
reaping
block
As
figure
1
shows,
the
mean
production
rate
can
only
be
increased
marginally
when
more
than
3
blocks
in
spreading
are
applied
per
block
in
reaping.
Accordingly
the
ration
1:3
is
used
in
this
case
study
as
an
economical
optimum.
The
correlations
described
above
indicate,
that
with
the
given
maximum
spreading
rate,
the
reaping
rate
can
be
raised
to
a
maximum
of
4.05
tpd/m²
and
that
the
mean
production
rate
equals
to
1,35
tpd/m²
consequently.
In
order
to
achieve
a
daily
production
rate
of
160,000
tonnes
per
day
at
this
mean
extraction
rate,
a
foot
print
of
29,630
m²
per
one
of
four
blocks
is
required
(formula
1).
With
the
assumed
draw
point
spacing
of
15
m
by
15
m,
which
leads
to
a
draw
point
plane
of
225
m²,
132
draw
points
are
required
per
block.
At
a
block
height
of
500
m
and
a
rock
density
of
ρ=2.7
t/m³
each
draw
point
has
a
tonnage
of
300
*
10³
t.
The
two
main
questions
that
arise
from
this
case
are:
? How
can
the
performance
of
the
haulage
system
be
increased
to
the
level
of
4.05
tpd/m²
for
the
reaping
block?
? How
can
the
speed
of
mine
development
as
well
as
the
speed
of
undercut
development
be
increased
in
order
to
keep
up
with
the
increased
production
rate?
Production
The
intention
of
this
case
study
is
to
discuss
methods
being
suited
for
raising
the
production
rate
of
future
block
caving
mines
to
160,000
tonnes
ore
per
day.
Compared
to
present
block
cave
mines,
this
output
rate
shows
an
enormous
increase
of
the
reaping
rate
while
the
same
production
would
require
an
extremely
large
footprint
when
conventional
mining
technologies
are
applied.
Main
bottleneck
for
a
significant
increase
of
production
are
the
limits
of
the
haulage
system.
Assuming
that
the
draw
point
extraction
is
done
by
LHDs,
the
maximum
extraction
rate
reaches
0.4
-‐
0.5
tpd/m².
With
this
performance
and
a
limitation
of
the
LHD
fleet
by
traffic
stream
and
the
deposit
footprint,
this
discontinuously
working
haulage
system
is
inadequate
for
upcoming
mega
mines.
Therefore,
new
concepts
for
block
caving
operations
were
developed
between
Codelco
and
Caterpillar
and
will
be
presented
in
the
following
chapters.
Moreover,
high
performances
in
the
production
likewise
lead
to
increased
efforts
for
development
and
preparatory
works
at
production
level
and
in
the
undercut
level,
as
well.
These
required
rapid
development
rates
demand
new
concepts
and
suitable
techniques,
too.
In
this
paper,
these
challenges,
coming
along
with
future
high
performance
mines,
will
be
discussed
in
detail.
2
Haulage
System
In
conventional
LHD
block
caving
operations
less
than
10%
of
the
active
mining
area
is
used
for
production
due
to
the
fact
that
the
LHD
can
extract
the
ore
only
from
one
draw
point
per
production
drift
at
a
time.
This
in
mind,
the
maximal
achievable
mean
extraction
rate
(τm)
is
considered
to
be
in
the
range
of
0.4
to
0.5
tpd/m²
for
block
caving
operations,
working
with
a
discontinuous
LHD
haulage
system.
To
achieve
a
significant
raise
in
production
either
the
active
area
of
the
panel
must
be
extended
or
extraction
rate
has
to
be
multiplied.
Concept
A
very
significant
increase
of
the
draw
rate
can
be
achieved
by
converting
the
haulage
system
from
batch
type
operation
to
continuous
haulage
(Continuous
Mining
Concept
of
Codelco).
The
continuous
mining
system
consists
of
mobile
feeders,
referred
to
as
dozer
feeders,
which
are
installed
in
each
draw
point,
see
figure
2.
The
dozer
feeder
is
pushed
into
the
draw
point
–
filled
with
caved
ore
–
by
means
of
a
hydraulic
pushing
device.
The
dozer
pushes
the
caved
material
by
a
dozer
plate
onto
a
chain
conveyor,
installed
in
the
production
drift.
The
chain
conveyor
transports
the
material
to
a
primary
crusher,
followed
by
a
regular
belt
conveyor
(figure
3).
Figure
2:
Mobile
Feeder
For
the
installation
of
the
system,
the
production
level
design
was
modified.
Service
drifts
provide
access
for
the
installation
and
for
the
supply
of
the
dozer
feeder
units
from
one
site
of
the
draw
point,
whereas
the
production
drift
with
the
chain
conveyor
is
located
on
the
opposite.
Both
the
service
and
production
drifts
are
used
for
draw
points
to
either
side.
A
schematic
overview
of
the
installed
system
is
given
in
figure
3.
Figure
3:
Continuous
haulage
system
at
production
level
The
continuous
haulage
system
was
setup
for
the
following
configuration:
Each
production
conveyor
is
rated
with
a
mean
load
capacity
of
700
tph,
fed
by
10
Dozer
Feeder
units
with
an
average
extraction
rate
of
260
tph.
The
system
utilization
rate
is
calculated
to
approximately
42%.
Even
if
feeding
units
have
downtimes
for
maintenance
reasons
or
caused
by
hang-‐ups,
the
daily
production
rate
is
covered
by
this
utilization
rate.
To
meet
the
daily
production
target,
this
configuration
is
installed
14
times
within
the
panel.
So
all
140
draw
points
within
a
regular
operation
phase
are
mined
out
with
the
continuous
haulage
system.
The
additional
draw
points
in
the
preparation
field
are
calculated
with
n=3
to
420.
These
extraction
points
will
be
extracted
per
conventional
LHDs
as
the
LHD
extraction
rate
nearly
matches
the
needed
extraction
rate
(τs)
rate,
so
the
new
high
performance
system
must
not
necessarily
be
installed
at
that
time.
With
these
mining
sequences,
the
block
life
span
can
be
calculated
to
900
working
days
wherein
675
days
of
initial
caving
phase
and
225
of
regular
extraction
are
contained.
The
panel
design
and
schematic
panel
pattern
gives
figure
3.
schematic
panel
pattern
225 225 225 225 225 225 225 …
The
roadway
heading
per
draw
point
is
calculated
to
35m
per
draw
point,
according
to
a
draw
point
spacing
of
15m.
On
this
basis,
the
daily
advance
rate
for
the
entire
panel
development
is
calculated
to:
!"#∗!"#
Production level: = 21m/d
!!"#
133 ∗ 35m ∑total 43 m/d
Undercut level: = 21m/d
225d
7 ∗ 35m
Infrastructure: = 1m/d
225d
This
required
advance
rate
is
hardly
achievable
by
drill
and
blast
operations.
Against
the
background
of
mining
related
technical
publications
from
the
last
years,
there
are
currently
different
approaches
in
development
to
initially
replace
discontinuous
road
heading
operations
in
hard
rock
mining.
New
hard
rock
cutting
technologies
try
to
provide
higher
advance
rates
due
to
continuous
operation,
a
reduction
of
emissions
and
safer
working
conditions.
Process
steps
like
Cutting,
Loading
and
Hauling
and
Roof
Supporting
take
place
uninterrupted
and
simultaneously
which
leads
to
higher
Performance
and
lower
Cost.
So
these
systems
–
standard
in
soft
rock
mining
-‐
would
substitute
the
major
drawbacks
of
D&B
operations
by
one
continuous
working
system
with
its
benefits:
-‐ High
safety
due
to
replacement
of
both
explosives
(and
their
trade
and
storage)
as
well
as
manual
operations
by
automation
-‐ Rising
heading
performance
at
lower
staff
cost,
capex
and
opex
-‐ Continuous
operation,
lack
of
ventilation
breaks
after
blasting
-‐ Selective
road
heading
true
to
the
roadway
profile
-‐ Equipment
TCO/utilization:
1
road
header
replaces
5-‐6
D&B
vehicles
-‐ No
negative
blasting
effects
into
surrounding
rock
With
an
assumed
performance
of
12
m/d
heading
speed
for
a
hard
rock
road
header
a
fleet
of
4-‐6
machines
could
provide
the
required
daily
advance.
Result
would
be
a
massive
reduction
of
active
underground
operating
sections
at
higher
performance
compared
to
drill&blast
operations.
Within
2012
and
2013
a
couple
of
prototypes
will
be
tested
by
mining
OEMs.
This
promising
technology
leads
in
a
paradigm
shift
in
hard
rock
road
heading
to
enable
the
vision
of
Block
Caving
2020.
4
Development
of
Undercut
Level
by
a
hard
rock
longwall
system
Along
with
the
road
heading
operations
to
prepare
the
production
level,
road
heading
works
must
be
even
done
in
undercut
level
as
well.
At
current
Block
Caving
operations
the
undercut
level
is
opened
up
by
a
close
meshed
network
of
roadways
and
cross
cuts.
A
huge
number
of
vehicles
and
staff
is
needed
to
handle
this
massive
road
heading
activities,
side
effects
are
f.e.
drawbacks
like
thousands
of
roof
bolts
that
have
to
be
installed
–
and
separated
from
the
muck
after
extraction.
Function
of
the
undercut
is
to
initiate
the
caving
process
by
extracting
a
slice
of
material
between
block
and
production
level.
This
task
is
comparable
to
mining
of
tabular
deposits
like
hard
coal
seams.
So
–
following
the
great
success
of
longwall
systems
in
soft
rock
applications
–
the
main
idea
is
to
undercut
the
block
with
a
longwall
system,
comparable
with
common
systems
used
in
coal
seams
but
adapted
for
hard
rock
applications
with
all
the
benefits
of
cutting
technology
as
described
in
chapter
3,
combined
with
the
advantages
of
a
manless,
fully
automated
longwall
system.
Very
important
advantage
of
a
longwall
system
is,
that
the
undercut
is
always
completely
extracted
in
contrast
to
conventional
undercutting,
where
pillars
may
remain
due
to
misfire
with
the
effect,
that
thousands
of
tons
of
ore
maybe
lost.
This
also
avoids
the
danger
of
additional
rock
stress
on
the
haulage
roadways
due
to
these
pressure
peaks
under
the
unwanted
pillars.
Hydraulic
shield
support
and
conveyor
systems
are
well-‐known
and
reliable
technology,
the
shearer
loader
will
be
replaced
by
a
hard
rock
shearer,
cutting
bi-‐directional
slices
out
of
the
front
wall.
The
adaption
of
this
well-‐known
equipment
in
combination
with
hard
rock
cutting
technology
opens
up
the
scenario
to
eliminate
the
huge
road
heading
efforts
within
the
undercut
and
substitute
the
road
heading
by
a
one-‐pass
longwall
system
(figure
5).
Figure
5:
Hard
rock
longwall
in
undercut
level
The
longwall
–
195
m
long
–
is
installed
between
two
parallel
entry
roadways,
each
on
one
side
of
the
block,
prepared
in
advance.
It
follows
these
roadways
in
mining
direction,
undercutting
the
deposit
block
by
block
prior
to
the
extraction
phase.
Behind
the
longwall,
the
hanging
wall
collapses
controlled
by
the
shield
support
to
initiate
the
caving
process.
After
the
longwall
has
passed
the
designated
position
of
the
draw
points,
a
raise
is
drilled
upwards
from
the
production
level
to
the
caving
zone
using
a
boxhole
boring
machine.
The
draw
points
are
then
fully
developed
by
blasting
out
the
funnels.
During
the
first
phase
of
caving
(spreading)
the
ore
is
then
removed
by
LHDs,
which
are
later
replaced
by
continuous
feeders
and
the
conveyor
system
as
described
above.
On
basis
of
the
case
study
calculations,
a
longwall
face
advance
of
180
m
per
225
days
is
needed,
which
is
a
realistic
hard
rock
longwall
performance.
5
Résumé
and
Outlook
As
discontinuous
mining
technologies
have
been
replaced
by
continuous
systems
in
soft
rock
applications
within
the
last
decades,
there
are
currently
different
promising
developments
in
progress
to
lead
in
a
paradigm
shift
in
hard
rock
mining
to
continuous
operations,
rising
performance
and
safety
benefits.
A
faster
access
to
the
deposits
and
higher
production
rates
ensure
a
faster
ROI,
effecting
in
higher
NPV.
Highly
automated
continuous
mining
technologies
reduce
the
number
of
active
underground
operating
areas
and
therefore
cost
for
staff,
ventilation,
air
conditioning,
infrastructure
and
underground
bunker
capacities
amongst
others.
Optimized
technology
allows
better
caving
controls
and
selective
mining.
The
scenario
opened
up
within
this
study
substitutes
the
major
drawbacks
of
the
current
state-‐of-‐the
art
Block
Caving
technologies
by
a
comprehensive
mining
solution
for
Block
Caving
2020:
Continuous
operations
in
preparation
and
excavation
areas
at
highest
performance
on
a
great
safety
level.
References
Encina,
Baez,
Geister
&
Steinberg
(2008),
Mechanized
continuous
drawing
system:
A
technical
answer
to
increase
production
capacity
for
large
block
caving
mines.
In
H.
Schunnesson
&
E.
Nordlund
(Eds.),
5th
International
Conference
&
Exhibition
on
Mass
Mining
(pp.
553-‐562),
Luleå,
Sweden:
Division
on
Mining
and
Geotechnical
Engineering,
Luleå
University
of
Technology,
Luleå,
Sweden.