Fire Protection Works Schedule Overview

This document provides a revised schedule for fire protection works on the GH Tower project located in Greenhills, San Juan City. It outlines the planned start and finish dates for valve installation, fire hose cabinets and extinguishers, and sprinkler heads on each floor from the basement to the roof deck over a period of 33 days in total, requiring a workforce of 4 to 8 people depending on the tasks. The schedule was prepared by the project in charge of fire protection works and noted by the project manager and area manager.

Uploaded by

Kevin John
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views1 page

Fire Protection Works Schedule Overview

This document provides a revised schedule for fire protection works on the GH Tower project located in Greenhills, San Juan City. It outlines the planned start and finish dates for valve installation, fire hose cabinets and extinguishers, and sprinkler heads on each floor from the basement to the roof deck over a period of 33 days in total, requiring a workforce of 4 to 8 people depending on the tasks. The schedule was prepared by the project in charge of fire protection works and noted by the project manager and area manager.

Uploaded by

Kevin John
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

DATE : March 10, 2022

COMPANY : Citiaire Industrial Services Corporation


PROJECT : GH Tower
LOCATION : Greenhills, Ortigas Avenue, San Juan City
SUBJECT : Revised Catch up Schedule - Fire Protection Works

2ND FIX 3RD FIX 3RD FIX


BOH / BOH / BOH /
FLOOR/ LEVEL Duration Valves & Ancilliaries Valves & Ancilliaries Manpower Duration FHC & Fire Extinguisher FHC & Fire Extinguisher Manpower Duration Sprinkler Heads Sprinkler Heads Manpower
FOH FOH FOH
Actual / Forecast Start Actual / Forecast Finish Actual / Forecast Start Actual / Forecast Finish Actual / Forecast Start Actual / Forecast Finish

BASEMENT 3 5 BOH 18-Apr-22 23-Apr-22 4 5 21-May-22 26-May-22 4 30 15-Apr-22 15-May-22 6


BASEMENT 2 5 BOH 22-Apr-22 27-Apr-22 4 5 27-May-22 1-Jun-22 4 30 25-Apr-22 25-May-22 6
BASEMENT 1 6 BOH 26-Apr-22 2-May-22 4 5 3-Jun-22 8-Jun-22 4 30 5-May-22 4-Jun-22 6
LOWERGROUND 5 BOH 30-Apr-22 5-May-22 4 5 9-Jun-22 14-Jun-22 4 0 0
GROUND FLOOR 5 BOH 3-May-22 8-May-22 4 5 15-Jun-22 20-Jun-22 4 30 15-May-22 14-Jun-22 6
2ND FLOOR 5 BOH 7-May-22 12-May-22 4 5 21-Jun-22 26-Jun-22 4 0 0
3RD FLOOR 5 BOH 11-May-22 16-May-22 4 5 27-Jun-22 2-Jul-22 4 0 0
4TH FLOOR 5 BOH 15-May-22 20-May-22 4 5 3-Jul-22 8-Jul-22 4 0 0
5TH FLOOR 5 BOH 18-May-22 23-May-22 4 5 9-Jul-22 14-Jul-22 4 0 0
6TH FLOOR 5 BOH 22-May-22 27-May-22 4 5 15-Jul-22 20-Jul-22 4 30 30-May-22 29-Jun-22 8
7TH FLOOR 5 BOH 25-May-22 30-May-22 4 5 10-Mar-22 15-Mar-22 4 30 8-May-22 7-Jun-22 8
8TH FLOOR 5 BOH 28-May-22 2-Jun-22 4 5 16-Mar-22 21-Mar-22 4 30 15-May-22 14-Jun-22 8
9TH FLOOR 5 BOH 3-Jun-22 8-Jun-22 4 5 22-Mar-22 27-Mar-22 4 30 22-May-22 21-Jun-22 8
10TH FLOOR 5 BOH 14-Jun-22 19-Jun-22 4 3 22-Mar-22 25-Mar-22 4 30 29-May-22 28-Jun-22 8
11TH FLOOR 5 BOH 20-Jun-22 25-Jun-22 4 5 28-Mar-22 2-Apr-22 4 30 5-Jun-22 5-Jul-22 8
12TH FLOOR 4 BOH 26-Jun-22 30-Jun-22 4 3 29-Mar-22 1-Apr-22 4 30 10-Jun-22 10-Jul-22 8
13TH FLOOR 4 BOH 30-Jun-22 4-Jul-22 4 5 3-Apr-22 8-Apr-22 4 30 15-Jun-22 15-Jul-22 8
14th FLOOR 5 BOH 5-Jul-22 10-Jul-22 4 5 9-Apr-22 14-Apr-22 4 30 20-Jun-22 20-Jul-22 8
15th FLOOR 5 BOH 11-Jul-22 16-Jul-22 4 5 15-Apr-22 20-Apr-22 4 30 25-Jun-22 25-Jul-22 8
16th FLOOR 5 BOH 17-Jul-22 22-Jul-22 4 5 21-Apr-22 26-Apr-22 4 30 30-Jun-22 30-Jul-22 8
17th FLOOR 5 BOH 23-Jul-22 28-Jul-22 4 5 27-Apr-22 2-May-22 4 30 7-Jul-22 6-Aug-22 8
18th FLOOR 5 BOH 29-Jul-22 3-Aug-22 4 5 3-May-22 8-May-22 4 30 17-Jul-22 16-Aug-22 8
19th FLOOR 5 BOH 4-Aug-22 9-Aug-22 4 5 9-May-22 14-May-22 4 30 27-Jul-22 26-Aug-22 8
20th FLOOR 5 BOH 10-Aug-22 15-Aug-22 4 5 15-May-22 20-May-22 4 30 6-Aug-22 5-Sep-22 8
ROOFDECK
33 BOH 25-Jul-22 27-Aug-22 8 0 4 0 0
(Pumps & Valves)

Prepared by:

Jomar Gabuya
Project in Charge
Fire Protection Works

Noted by:

Wilson Dotarot Jun Adamos


Project Manager Area Manager