Professional Documents
Culture Documents
Staffing and
Directing or
Planning Organising Provisioning Controlling
Leading
Resources
Project task, cost and schedules for project is used Project control: the objective is to measure the
as a benchmark and check-points that are actual values of the variable and determine if the
necessary for comparing actual accomplishments to project is meeting the targeted work plan and to
planned accomplishments, so that the project could make any necessary adjustment to meet project
be measured, evaluated and controlled. objectives.
WHAT ARE PROJECT CONTROLS?
The important of control system: is to allow project manager to develop the project
information routinely collected, verified, evaluated and communicated to all
participants in a project. (progress meeting (weekly/monthly) and….
To ensure the project meeting project objectives within its time and budget.
Monitoring
Communication Meetings Reviews Record Keeping
control
WHY WE NEED PROJECT CONTROL SYSTEM?
• Coding system: used a code number which to be assigned to each work item
that identifies variety of information.
• For example: work phase, type of work, responsible person.
WBS CODING
4–9
CONTROL SCHEDULE FOR TIME AND
COST
FIGURE 5.1
5–12
ADVANTAGES OF NETWORK
DIAGRAMS
• Bar Charting (Gantt Chart) are still the most common form of
scheduling and the most widely used.
• The chart shows activities represented by horizontal bars drawn to a
common time scale showing a sequence for all the operations within
the contract.
• Use for:
For relative simple project;
For short term and weekly programming for which they are ideal;
For communication;
For showing hierarchies of summary schedules up and down the WBS;
To provide graphic medium on which milestones can be entered.
ADVANTAGES OF BAR CHART:
• Simple;
• Easy to prepare, understand and interpret by all
levels of personnel;
• Excellent for showing progress and delays;
• Resources and Cash flow can be easily abstracted
and presented against the programmed.
DISADVANTAGES OF BAR CHART
Use as a way to determine the overall status of a project. It can be used for any size
of project.
Only requires a amount information that readily available in the work package.
The status of project could be measured as any one of three variables: cost, work-
hours or physical quantity of work.
Planned work vs
actual work
PROGRESS MEASUREMENT
100%
100%
5–25
FIGURE 5.1
• Is applicable to any control account that includes subtasks that must be handled in
sequence.
• The task is segmented into subtasks and each is assigned an increment of progress
for the entire task.
Incremental
milestone • Completing a subtask is the achievement of a milestone.
• The milestone percentage is normally based, on the number of work-hours
required
The start/finish % only applicable to those activities that lack readable definable
START/FINISH milestones, or the effort and time required is difficult to estimates.
(Budget at completion BAC) (Budgeted Cost for Work Performed BCWP)
31