Professional Documents
Culture Documents
Estimated Instrumentation
DOCUMENT HISTORY
Rev. Date Modification Approval
0 2010-03-03 Initial version FB
BURMEISTER & WAIN E NERGY A/S • J ÆGERSBORG A LLÉ 164 • DK-2820 G ENTOFTE • D ENMARK • WWW. BWE . DK
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
Table of Contents
1.0 INTRODUCTION ....................................................................................................................4
1.1 PURPOSE .................................................................................................................................4
2.0 TEMPERATURE MEASUREMENTS..................................................................................5
2.1 TEMPERATURE IN WATER/STEAM SYSTEM. ............................................................................5
2.1.1 95 of Remote measurement – typical zCT001B..............................................................5
2.1.2 35 of Spare measurement – typical zCT601U.................................................................6
2.2 TEMPERATURE IN AIR/FLUE GAS SYSTEM. ..............................................................................6
2.2.1 52 of Remote measurement – typical zCT301B..............................................................6
2.2.2 50 of Spare measurement – typical zCT602U.................................................................7
2.3 TEMPERATURE SURFACE. .......................................................................................................7
2.3.1 100 of Material tube surface temperature........................................................................7
2.4 TEMPERATURE DIFFERENCE IN MATERIALS. ...........................................................................8
2.4.1 7x2 of Remote measurement – typical zCT004B............................................................9
3.0 PRESSURE MEASUREMENTS ..........................................................................................10
3.1 PRESSURE IN WATER/STEAM SYSTEM ...................................................................................10
3.1.1 36 of Remote measurement – typical zCP001B ............................................................10
3.1.2 2 of Remote measurement (delta P) – typical zCP005B ..............................................11
3.1.3 2 of Local measurement – typical zCP401P..................................................................12
3.2 PRESSURE IN STEAM PIPES, NOT ACCESSIBLE FROM UNDERNEATH ......................................13
3.2.1 4 of Remote measurement – typical zCP001B ..............................................................14
3.2.2 2 of Local measurement – typical zCP401B .................................................................15
3.3 PRESSURE IN AIR/FLUE GAS SYSTEM.....................................................................................15
3.3.1 33 of Remote measurement – typical zCP002B ............................................................16
3.3.2 26 of Remote measurement (delta P) – typical zCP005B ............................................17
3.3.3 3 of Local measurement – typical zCP402P..................................................................18
3.3.4 136 of Spare measurement – typical zCP602U .............................................................18
3.4 PRESSURE IN FURNACE. ........................................................................................................19
3.4.1 3 of Remote measurement – typical zCP002B ..............................................................19
3.4.2 5 of Spare measurement – typical zCP602U .................................................................20
3.5 PRESSURE IN AUXILIARY AIR SYSTEMS. ...............................................................................20
3.5.1 43 of Remote measurement – typical zCP003B ............................................................20
3.5.2 2 of Local measurement – typical zCP403P..................................................................21
3.6 PRESSURE IN LIGHT DIESEL OIL SYSTEMS. ............................................................................22
3.6.1 3 of Remote measurement – typical zCP003B ..............................................................22
3.7 PRESSURE IN HEAVY OIL SYSTEMS. ......................................................................................22
3.7.1 3 of Remote measurement – typical zCP003B ..............................................................22
3.8 PRESSURE IN GAS SYSTEMS. .................................................................................................22
3.8.1 45 of Remote measurement – typical zCP003B ............................................................22
3.8.2 15 of Remote measurement (delta P)– typical zCP003B ..............................................22
4.0 LEVEL MEASUREMENTS .................................................................................................23
4.1 LEVEL BOILER START UP VESSEL ........................................................................................23
4.1.1 4 of Remote measurement (analogue) – typical zCL001B............................................23
4.1.2 3 of Remote measurement level limiters at boiler drum (binary) – typical zCL101F ...24
4.1.3 2 of Local level measurement boiler drum – typical zCL001P ....................................25
5.0 FLOW MEASUREMENTS ..................................................................................................26
5.1 FLOW WATER/STEAM SYSTEM .............................................................................................26
5.1.1 3 of Remote measurement, water type – typical zCF001. .............................................26
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Table of Contents
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 2 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Table of Contents
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 3 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1.0 INTRODUCTION
1.1 PURPOSE
This document describes typical basic requirements for boiler instrument hook-ups.
The description does not comprise information for dimensioning, strength calculations, basic
engineering or number of equipment and services to perform the scope of supply.
For some measurements it is not possible to specify a general hook up. The hook up varies
dependent on point of installation, choice of measuring principle and manufacture of the sensor.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Introduction
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 4 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
2
1 4 5
3
Note that pos. 4, 5 and 6 are supplied assembled.
190
50
3 Stub..
4 Extension pipe
5 Sensor head
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - temperature measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 5 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
7
6
5
4
2
30° 1
3 Nozzle,
5 Extension pipe
6 Sensor head
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - temperature measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 6 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - temperature measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 7 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - temperature measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 8 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
2 Stub.
4 Thermowell.
5 Extension pipe
6 Sensor head
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - temperature measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 9 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
Horizontal pipes
Consider height difference
when adjusting.
8
1
7
-
P 2
6
3
5
4
min 100
3 190
9 50
When mounted in horizontal pipes the pipe tap must be placed in these areas.
50
Vertical pipes
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 10 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1 Pipe tap,
3 Welding fitting.
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure transmitter.
8 Instrument rack.
9 Drain valve.
7 -
same level same level
P
6
1
5 2
3 3
min 100
3 min 100 4
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 11 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1 Pipe tap,
3 Welding fitting.
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure transmitter.
8 Instrument rack.
9 Drain valve.
Horizontal pipes
Consider height difference
when installing.
8
1
7
2
6
3
5
4
min 100
3
190
9
50
When mounted in horizontal pipes the pipe tap must be placed in these areas.
50
Vertical pipes
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 12 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1 Pipe tap,
3 Welding fitting.
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure indicator.
8 Instrument rack.
9 Drain valve.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 13 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
4
Consider height difference
when installing.
3
8
1
7
-
P
6
1 Pipe tap
3 Welding fitting.
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure transmitter.
8 Instrument rack.
9 Drain valve.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 14 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
4
Consider height difference
when installing.
3
8
1
7
1 Pipe tap
3 Welding fitting.
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure indicator.
8 Instrument rack.
9 Drain valve.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 15 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
The nozzle must be long enough to ensure that the primary shut off valves are well clear of the
insulation.
When installing the instrument pipes sufficient flexibility to absorb the movement of the primary
shut off valves due to thermal expansion of the hanging boiler must be ensured. Approximately 0,4
m movement of the measurement connection must be absorbed by loops in the instrument piping.
The instrument pipes must be installed with positive slope all the way from the tapping point to the
transmitter. Horizontal instrument pipes must be avoided.
6 -
P
4
5
4
0
min 10
3
30°
1
1 Duct wall.
2 Nozzle,
4 Fitting.
5 Instrument pipe.
6 Instrument valve.
7 Bracket.
8 Pressure transmitter.
9 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 16 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
10
-
P
9
7
OVAL FLAGE THREADED
5 AND SEAL WELDING
3
INSTR
INSTR
Primary shut-off valve Primary shut-off valve
.
50 50 .
PIPING
PIPING
1 1
30 30
2 2
1 Duct wall.
2 Nozzle,
4 Fitting.
5 Instrument pipe.
6 Instrument valve.
7 Bracket.
8 Pressure transmitter.
9 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 17 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
4
5
4
0
min 10
3
30°
1
1 Duct wall.
2 Nozzle
4 Fitting.
5 Instrument pipe.
6 Instrument valve.
7 Bracket.
8 Pressure indicator.
9 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 18 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
6 -
P
4
5
min 100
3
30°
1
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 19 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1 Duct wall.
2 Nozzle
4 Fitting.
5 Instrument pipe.
6 Instrument valve.
7 Bracket.
8 Pressure transmitter.
9 Instrument rack.
7
P
4 min 100
When mounted in horizontal pipes the pipe tap must be placed in these areas.
50
190
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 20 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1 Pipe tap
3 Fitting
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure transmitter.
8 Instrument rack.
4 min 100
When mounted in horizontal pipes the pipe tap must be placed in these areas.
50
190
1 Pipe tap
3 Fitting
4 Instrument pipe.
5 Instrument valve.
6 Bracket.
7 Pressure indicator.
8 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 21 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - pressure measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 22 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
13
1 3 3 5
4
2 3
3
3
min 10 % fall 12
12
3 7 7
3
+ -
P
-
8 9 10 11
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - level measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 23 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
1 Stand pipe.
3 Welding fitting.
4 Balance vessel.
6 Instrument pipe.
7 Drain valve.
8 Instrument valves.
9 Bracket.
11 Instrument rack.
12 Dirt trap
13 Filling funnel
4
6 8 13
3
7 14
12 11 10 9
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - level measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 24 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - level measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 25 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
Horizontal
installation
2 1 2
4 4
6 MIN 7,5°
5 DOWNWARD
MIN 7,5°
DOWNWARD
7 4 1
min 10 % fall
4 4 3
8
7
9 Consider
level of axis.
P
-
10
190
Vertical
11 installation
50
When mounted in horizontal pipes the pipe tap must be placed in these areas.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - flow measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 26 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
2 Pipe tap.
3 Balance point.
4 Welding fittings.
6 Instrument pipe.
7 Drain valve.
8 Instrument valves.
9 Bracket.
11 Instrument rack.
Horizontal
installation
3 2 1 2 3
Consider
level of axis.
4 4
MIN 7,5°
MIN 7,5° 5 DOWNWARD
DOWNWARD
7 4 1
min 10 % fall
4 4 3
8
7
9 Consider
level of axis.
P
-
10
Vertical
11 installation
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - flow measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 27 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
2 Pipe tap.
3 Balance vessel.
4 Welding fittings.
6 Instrument pipe.
7 Drain valve.
8 Instrument valves.
9 Bracket.
11 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - flow measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 28 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
-
11
+
10
-
9 P
MIN 7,5°
8 DOWNWARD
MIN 7,5°
12 DOWNWARD
Flow
Vertical
installation
7 6
6
4
4 5 5
4 3
3
2
+ - 3
2 2
Flow
1 1
Horizontal
installation
Ring chamber and tapping points
Vertical installation
3
Up
4
Ring chamber and tapping points
Horizontal installation
2
1
2 Pipe tap.
3 Ring chamber.
4 Cleaning stud.
5 Fitting.
7 Instrument pipe.
8 Instrument valves.
9 Bracket.
11 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - flow measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 29 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
5.2.2 0 of Remote measurement, multiple port pitot tube type – typical zCF002B.
8
-
7 P
MIN 7,5°
10 DOWNWARD
3
5
4 4
3
1
2
D
eter
Diam
4 Fitting.
5 Instrument pipe.
6 Instrument valves.
7 Bracket.
9 Instrument rack.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - flow measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 30 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - flow measurements
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 31 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
10x2mm GS001
GU001
KA10
KH01 TIS
CT401
PI
CP002
QRIA QRIA
CQ001 CQ002
QR03
KZ01
SC
CC
KZ02
KZ03
The diagram shows the sample cooler panel for one sample media. The individual sample cooler
panels belonging to the boiler are assembled at a common rack which has a common cooling water
distribution.
The sample cooler panels and the sample cooler rack are factory assembled. Division of the rack into
transportable subsections by bolted flange connections may become necessary. The number of
sections depends on the total number of sample coolers at the entire rack.
The primary valves and the sample probe lines from the sample point in the process to the sample
cooler rack are installed at site.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Sample Extraction / analyses
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 32 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
7 6 5 4 3 2 1
8 9 10
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Sample Extraction / analyses
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 33 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
Sourc D B E F E B D
Receive
e r
1
J
G I G H
A C C A 2
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Sample Extraction / analyses
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 34 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
7.1.2 3 of Coal Mill (PID BWE Doc. No. 160002-0100226 + 00227 + 00228)
It is expected that the supplier of the coal mill is supplying all
instrumentation related to the coal mill.
7.2 FANS
7.3 BURNERS
7.4 RAPH
7.4.3 2x1 of Lubrication oil station (PID BWE Doc. No. 160002-00253)
It is expected that the supplier of this system is supplying all
instrumentation related to the system.
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Additional instrumentation
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 35 of 36
Project: 160002 - E S TI M A T E D I N S TR U M E N T A T I O N Created 2010-03-03
Doc.No.: 160002 9000100-00 INSTRUMENT AND HOOK-UP Modified 2010-03-03
7.5.1 ?? of Instruments
It is expected that the supplier of this system is supplying all
instrumentation related to the system.
7.6.1 ?? of Instruments
It is expected that the supplier of this system is supplying all
instrumentation related to the system.
----------------------------------------------------------End of Document-----------------------------------------------------------------
All rights © 2005, Burmeister & Wain Energy A/S Estimated Instrumentation - Additional instrumentation
T:\160002_Essar_Hazira2x500tph\09_Drafts\El+I&C\160002-9000100-0.doc Page 36 of 36