You are on page 1of 3

Plastering work

Measurment in ft
Sl no. Description Nos Qty Remarks
Length Breath Depth
Ground floor
4 1/2" thick wall

1 Gents Toilet 1 2 15 10 300.00


1 2 4.83 10 96.60
1 2 8.455 10 169.10
D/c Door 1 -2 2.75 7.5 -41.25
2 Consulting room 1 2 3 7.5 45.00
3 Ladies toilet 2 3 4.83 10 289.80
2 1 12.163 10 243.26
D/c Door 1 -3 2.75 8 -66.00

Total Qty of R C C Concrete 1,036.51 Sft

9" Thick Brick Work

1 MRI system room 1 2 13 11 286.00

Total Qty of 9" Thick Brick Work 286.00 Cft

1 st floor
4 1/2" thick wall

1 Labour Ward Toilet wall 2 2 4.5 10.5 189.00


2 ICU toilets 1 2 9.75 10.5 204.75
2 2 6 10.5 252.00
D/c Door 1 -1 2.75 7.5 -20.63
Existing Door 1 2 6.5 8 104.00

Total Qty of R C C Concrete 729.13 Sft

9" Thick Brick Work

1 Monitor room Door 1 2 7.25 7.5 108.75


2 Store room wall 1 1 15.08 11.5 173.42
D/c Door 1 -1 3.5 7.5 -26.25
4 Lift 1 2 6.75 11.5 155.25

Total Qty of 9" Thick Brick Work 411.17 Cft

2nd floor
4 1/2" thick wall

1 Bed 01 & 02
Toilets 2 2 7.666 11.5 352.64
Plastering work

2 2 6 11.5 276.00
D/c Door 1 -2 3.5 7.5 -52.50
Existing Door 1 2 3.75 7.5 56.25
2 Dialysis Room
Toilets 2 2 10.83 10 433.20
2 2 6.375 10 255.00
D/c Door 1 -2 3 7.5 -45.00
Existing Door 1 2 6.5 7.5 97.50
3 Nurse Station 1 2 6 7.5 90.00
4 Toilets 2 3 4.5 10 270.00
2 1 4.5 11.5 103.50
2 1 4.335 11.5 99.71
2 1 13.005 10 260.10
D/c Door 2 -4 2.75 7.5 -165.00
James 1 4 17.75 0.375 26.63
Shower room 2 2 4 10 160.00
2 1 2.5 10 50.00
2 1 14.206 10 284.12
D/c Door 2 -3 2.75 7.5 -123.75
James 1 3 17.75 0.375 19.97
Existing Door 2 1 4.25 7.5 63.75
2 1 3.5 7.5 52.50
Female ward
Existing Door 1 2 6 7.5 90.00

Total Qty of R C C Concrete 2,654.60 Sft

9" Thick Brick Work

1 Bed 01 & 02
Existing Door 1 2 3.75 7.5 56.25
2 Dialysis Room 1 2 25.705 11 565.51

Total Qty of 9" Thick Brick Work 621.76 Cft

3rd floor
4 1/2" thick wall

1 Bed 01 & 02
Toilets 2 2 7.666 10.5 321.97
2 2 6 10.5 252.00
D/c Door 1 -2 3.5 7.5 -52.50

2 Meeting room
Entrance door 2 2 2.5 10 100.00
Plastering work

3 Nurse Station 1 2 6 7.5 90.00


4 Toilets 2 3 4.5 10 270.00
2 1 4.5 11.5 103.50
2 1 4.335 11.5 99.71
2 1 13.005 10 260.10
D/c Door 2 -4 2.75 7.5 -165.00
James 1 4 17.75 0.375 26.63
Shower room 2 2 4 10 160.00
2 1 2.5 10 50.00
2 1 14.206 10 284.12
D/c Door 2 -3 2.75 7.5 -123.75
James 1 3 17.75 0.375 19.97
Existing Door 2 1 4.25 7.5 63.75
2 1 3.5 7.5 52.50
Male ward
Existing Door 2 2 6 7.5 180.00

Total Qty of R C C Concrete 1,992.99 Sft

9" Thick Brick Work

1 Bed 01 & 02
Existing Door 1 1 3.75 8 30.00
2 Lift W 1 1 4 6 24.00

Total Qty of 9" Thick Brick Work 54.00 Cft