7 Shortage
8 Net Total Wastage (in bags) 172.00 [8 = 5-6]
CONTRACTOR REP. ASL PROJECT MANAGER / PROJECT INCHARGE GRN DEPT. CONTRACT DEPARTMENT
BOQ Description Grade of Quantity Executed Unit Cement Theoretical
S.No. Concrete Consumption per value of Cement
unit (in bags) (Bags) for this
quantity
I Mullions, Bands,
N Coping
Brickwork
P
O Blockwork (1:5) mix cum. 0.676 0.00
(600x200x200 mm )
External Plaster (1:4 & 1:3) mix 2710.49 sqm. 0.317 859.22
Chajja Plaster (1:4 & 1:3) mix 427.64 sqm. 0.317 135.56
Waterproofing sqm. 0.115 77.40
Plaster 673.01
Protective plaster 122.12 sqm. 0.115 14.04
Gutter Plaster 373.42 sqm. 0.115 42.94
0.00