Site Photos – Achievements

Cycle Track- sub base compaction Cycle Track- spreading gravel between
between RAs 3-4 RAs 13-14
1

Site Photos – Achievements

Cycle Track- Fixing plastic edge and MSH 08 – Laying of sub base for Parking
spreading sweet soil between RAs 12-13 area at KCB 01
1

Site Photos – Achievements

MSH 08 KCB 01- Compaction of sub MSH 08 KCB 02 – Laying of Material


base at parking area Type V
1

Site Photos – Achievements

MSH 11 Fixing - Interlocking Tiles for MSH 9 - Sewer manhole and pipe laying
Parking at KCB 16 works at KCB 4
1

Site Photos – Achievements

MSH23 SS1 LV load transfer works MSH 11 - Preparation for installation Tiles
at KCB 17
1

Site Photos – Achievements

Waterproofing and Steel Reinforcement works for Slab (3)


1

Site Photos – Achievements

Waterproofing system for slab (6)


1

Site Photos – Achievements

Concrete casting and Curing works for slab (1)