Professional Documents
Culture Documents
340.0 mm
(13.39”) A. R5000 Power Supply Unit
115.5 mm 320.0 mm B. Power cable (CEE 7/7, IEC C13)
(4.54”) (12.60”)
C. Fuse, 2x
D. Radar processor power cable, 3 m (9.84 ft.)
R5000 Power Supply Unit E. Terminals and heat shrink tube kit
Installation Guide
108.6 mm
250.0 mm
(4.28”)
(9.84”)
A B
C D
200.0 mm
(7.87”)
E
¼¼ Note: The LEDs at the front are flashing during the startup sequence.
Grounding the unit Internal connections
J11 J10 J4
J2
+ GND - + GND - - - - + +
24V_1 Out 24V_2 Out 52V Out
52V Out
A B A B A B
J4 J4 J4
52 V DC output
- - - ++ - - - ++ - - - ++
To SRT LAN J2 J2 J2
¼¼ Note: It is recommended that the power supply unit ground is connected to the vessels bonded ground or a non-bonded RF A. DC negative (black)
ground at the closest possible location, using 12 AWG wire (or thicker).
B. 24 V DC (red) C C
C. Ground (protect the shield
with heat shrink tube)
1 2 3
+ GND - + GND -
24 V DC output 24 V DC output
To radar monitor A B To radar processor A B
C
A. 24 V DC (red) A. 24 V DC (red)
B. DC negative (black) B. DC negative (black)
C. Ground (green)
Connectors
¼¼ Note: The power supply must be installed on a vertical surface with the cables exiting downwards.
ABC D E F
¼¼ Note: Inadequate ventilation and subsequent overheating of the unit may cause unreliable operation and reduced service A. Power switch with power indicator
life. Exposing the unit to conditions that exceed the specifications could invalidate your warranty. B. Fuse holder
C. V AC power input
Recommended pilot holes for self-tapping screws: D. 24V_1 Out cable gland
O