PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &

SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 1 of 9


1.2 SPMSB

METHOD STATEMENT:
RC RETAINING WALL

Approvals
Rev Date Description By Checked

00 8/7/2019 First Issue SPMSB


01 16/7/2019 Revision 1 SPMSB
02 22/7/2019 Revision 2 SPMSB

1
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 2 of 9


1.2 SPMSB

Table of Contents

1 Introduction............................................................................................................................................3
1.1. Purpose..........................................................................................................................................3
1.2. Plant and Machinery..................................................................................................................3
1.3. Site Survey....................................................................................................................................3
2 Excavation Procedure............................................................................................................................4
2.1 Site Preparation..............................................................................................................................4
2.2 Sheet Piling Work...........................................................................................................................4
2.3 Excavation Work............................................................................................................................5
3 Construction of Base Slab......................................................................................................................6
3.1 Steel Reinforcement Installation.....................................................................................................6
3.2 Slab Formwork...............................................................................................................................6
3.3 Slab Concreting...............................................................................................................................6
4 Construction of Retaining Wall.............................................................................................................7
4.1 Steel Reinforcement Installation.....................................................................................................7
4.2 Wall Formwork...............................................................................................................................7
4.3 Wall Concreting..............................................................................................................................7
5 Personnel and Workmanship.................................................................................................................9
6 Health and Safety...................................................................................................................................9

2
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 3 of 9


1.2 SPMSB

1 Introduction

This method statement details the proposed works connected with the Reinforced
Concrete Retaining Wall using our SCS Steel Formwork System. The scope of works
until the designated level and length.

1.1 Purpose
The purpose of this method statement is to give crystal clear view about the method of
construction procedure that will be implement in order to ensure the quality and safety
of the project is assure.
Extra procedures are required for the construction of 7m height retaining wall and will
be shown in this report.

1.2 Plant and Machinery

a. Excavator
b. Sheet Pile Rig
c. Sheet Pile
d. SCS Steel Formwork System
e. Timber Formwork
f. Scaffolding
g. Necessary Machinery for Concreting Work

1.3 Site Survey

a. Surveyor is appointed to carry out site survey.


b. All location of manhole and the alignment of pipes are demarcated on the
ground.

3
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 4 of 9


1.2 SPMSB

2 Excavation Procedure

This Method Statement describes a proper work procedure shall be carried out during the excavation
stage as per specification and contract drawings .

2.1 Site Preparation

a. Construction team would conduct an investigation and acquire information about site services
might have been placed/embedded below the ground. Services, wherever found shall be
rerouted and protected to place will not affect site activities.
b. Surveyor would conduct the site survey to mark/stake-out the lines and levels of the objective
excavation for foundations as per indicated in the approved drawing.
c. Slope trimming and site clearing will be carried before sheet pile installation.
d. The trimmed slope will be cover by a layer of plastic to prevent slope failure.

2.2 Sheet Piling Work

a. Sheet piling is required for deep excavation for 7m height retaining wall (Figure 1 shows the
location of sheet piling work). Refer to Section 2.3 Point a, for 3-6m height retaining wall.
b. Sheet pile will be install at 1 meter away from the edge of heel slab (Figure 2).
c. FSP-IIIA sheet pile will be used for this project.
d. The exposed height of sheet pile shall be 4 meter and the slope (ratio 1 to 1) shall be formed 2m
away from the sheet pile (Figure 2).
e. The minimum embedded depth of sheet pile shall be 3.7m as per calculation shown.

4
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 5 of 9


1.2 SPMSB

2.3 Excavation Work

a. For 3m to 6m height retaining wall, excavation work can be carried 1 meter from edge of slab
without the installation of sheet pile.
b. The area to be excavated shall be properly marked and clear before starting the works.
c. The depth of excavation shall be periodically checked by a supervisor to avoid over
excavation.
d. The time between the excavation work and retaining wall slab construction shall be as short as
possible.
e. Site supervisor shall monitor the verticality of sheet pile periodically.
f. Sheet pile can only be removed after the construction of retaining wall was completed.

FIGURE 1: Proposed Sheet Pile for Deep Excavation

5
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 6 of 9


1.2 SPMSB

3 Construction of Base Slab


Timber formwork is selected for base slab construction. Before the installation of reinforcement,
subgrade shall be laid and compacted and level with lean concrete according to drawing specification.

3.1 Steel Reinforcement Installation


a. Bend and cut to size rebar is selected for this project.
b. The cover to reinforcement shall be maintained by using concrete blocks.
c. Engineers shall inspect and check the reinforcement before covered with formwork.

3.2 Slab Formwork


a. Side formwork shall be 12mm thick of plywood with necessary support.
b. The formwork surface will be applied with release agent such as mould oil prior to fixing.
c. The formwork that have been installed will be checked for cleanliness, tightness and dimension.

3.3 Slab Concreting


a. All rebar and formwork will be cleaned for debris and foreign materials before pouring.
b. The concrete will be deposited continuously or in layers of such thickness so that cold joints are
not formed.
c. After placing, the concrete will be consolidated by using mechanical or electrical vibrators, which
will be operated by competent workmen.
d. Concrete will not be placed during rain.
e. Concreting will be carried out using the approved design mixes and that specified for the structure.
The concrete from approved sources will be used for all concreting works.
f. The concrete will be laid in layers not exceeding 300mm in thickness; each layer
compacted separate before the next is laid.

6
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 7 of 9


1.2 SPMSB

4 Construction of Retaining Wall


SCS System formwork is selected for wall construction. Before the installation of reinforcement,
falsework and working platform shall be prepared. Casting schedule is shown as below:

Height of RC Retaining Wall Length of Each Casting


7m Height 4.8m
6m Height 4.8m
5m Height 4.8m
4m Height 7.2m
3.97m Height 7.2m

4.1 Steel Reinforcement Installation


a. Bend and cut to size rebar is selected for this project.
b. The cover to reinforcement shall be maintained by using concrete blocks.
c. Engineers shall inspect and check the reinforcement before covered with formwork.

4.2 Wall Formwork


a. Sizes and Shapes of SCS Steel Formwork will be selected to suite the site condition.
b. Formworks (near & far face) were connected using form tie (tie rod, wing nut, nut, hex nut and
washer).
c. Adjustable props will be used for maintaining formwork verticality.
d. The installed formwork shall be check by respective party/person for cleanliness, tightness and
dimension before concreting.

4.3 Wall Concreting


a. All rebar and formwork will be cleaned for debris and foreign materials before pouring.
b. The concrete will be deposited continuously or in layers of such thickness so that cold joints are
not formed.
c. After placing, the concrete will be consolidated by using mechanical or electrical vibrators, which
will be operated by competent workmen.
d. Concrete will not be placed during rain.

7
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 8 of 9


1.2 SPMSB

e. Concreting will be carried out using the approved design mixes and that specified for the structure.
The concrete from approved sources will be used for all concreting works.
f. Casting of wall will be separated up to 3 stages for 5-7m wall (each casting not more than
2.5m height) and 2 stages for 3-5m wall (each casting not more than 2.5m height).

FIGURE 2: Typical R.C. Wall Formwork

5 Personnel and Workmanship

The works consists of one experienced supervisor, foremen and skill workers. The foreman, experienced
in the formwork erected, representing the works, shall be present at all times whilst work is proceeding.

8
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.

Management Procedure PROJECT INTEGRATED MANAGEMENT SYSTEM Issue No. 01


Document Title METHOD STATEMENT Revision No. 01
RC RETAINING WALL Issue Date 22-JULY-19

Procedure Number Page 9 of 9


1.2 SPMSB

He shall be responsible for the checking of the works accordance with this method statement. The
foreman shall be the site designated safety office, responsible for the site safety. Supervisor will
communicate with the Engineer on site for a better documentation purpose.

6 Health and Safety

The site supervisor shall be responsible for site safety, he shall report to client site safety
representative. Safety measures to be implemented are as follows: -
a. Prior to any site excavation a survey of the site shall be carried out to determine the presence
[if any] of any buried cables or services.
b. Workers will be equipped with Personnel Protective Equipment [PPE] i.e. safety helmet and
safety boot.
c. Proper housekeeping at the end of the day.