Professional Documents
Culture Documents
Method Statement RC Retaining Wall PDF Free
Method Statement RC Retaining Wall PDF Free
Method Statement RC Retaining Wall PDF Free
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
METHOD STATEMENT:
RC RETAINING WALL
Approvals
Rev Date Description By Checked
1
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
Table of Contents
1 Introduction............................................................................................................................................3
1.1. Purpose..........................................................................................................................................3
1.2. Plant and Machinery..................................................................................................................3
1.3. Site Survey....................................................................................................................................3
2 Excavation Procedure............................................................................................................................4
2.1 Site Preparation..............................................................................................................................4
2.2 Sheet Piling Work...........................................................................................................................4
2.3 Excavation Work............................................................................................................................5
3 Construction of Base Slab......................................................................................................................6
3.1 Steel Reinforcement Installation.....................................................................................................6
3.2 Slab Formwork...............................................................................................................................6
3.3 Slab Concreting...............................................................................................................................6
4 Construction of Retaining Wall.............................................................................................................7
4.1 Steel Reinforcement Installation.....................................................................................................7
4.2 Wall Formwork...............................................................................................................................7
4.3 Wall Concreting..............................................................................................................................7
5 Personnel and Workmanship.................................................................................................................9
6 Health and Safety...................................................................................................................................9
2
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
1 Introduction
This method statement details the proposed works connected with the Reinforced
Concrete Retaining Wall using our SCS Steel Formwork System. The scope of works
until the designated level and length.
1.1 Purpose
The purpose of this method statement is to give crystal clear view about the method of
construction procedure that will be implement in order to ensure the quality and safety
of the project is assure.
Extra procedures are required for the construction of 7m height retaining wall and will
be shown in this report.
a. Excavator
b. Sheet Pile Rig
c. Sheet Pile
d. SCS Steel Formwork System
e. Timber Formwork
f. Scaffolding
g. Necessary Machinery for Concreting Work
3
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
2 Excavation Procedure
This Method Statement describes a proper work procedure shall be carried out during the excavation
stage as per specification and contract drawings .
a. Construction team would conduct an investigation and acquire information about site services
might have been placed/embedded below the ground. Services, wherever found shall be
rerouted and protected to place will not affect site activities.
b. Surveyor would conduct the site survey to mark/stake-out the lines and levels of the objective
excavation for foundations as per indicated in the approved drawing.
c. Slope trimming and site clearing will be carried before sheet pile installation.
d. The trimmed slope will be cover by a layer of plastic to prevent slope failure.
a. Sheet piling is required for deep excavation for 7m height retaining wall (Figure 1 shows the
location of sheet piling work). Refer to Section 2.3 Point a, for 3-6m height retaining wall.
b. Sheet pile will be install at 1 meter away from the edge of heel slab (Figure 2).
c. FSP-IIIA sheet pile will be used for this project.
d. The exposed height of sheet pile shall be 4 meter and the slope (ratio 1 to 1) shall be formed 2m
away from the sheet pile (Figure 2).
e. The minimum embedded depth of sheet pile shall be 3.7m as per calculation shown.
4
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
a. For 3m to 6m height retaining wall, excavation work can be carried 1 meter from edge of slab
without the installation of sheet pile.
b. The area to be excavated shall be properly marked and clear before starting the works.
c. The depth of excavation shall be periodically checked by a supervisor to avoid over
excavation.
d. The time between the excavation work and retaining wall slab construction shall be as short as
possible.
e. Site supervisor shall monitor the verticality of sheet pile periodically.
f. Sheet pile can only be removed after the construction of retaining wall was completed.
5
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
6
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
7
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
e. Concreting will be carried out using the approved design mixes and that specified for the structure.
The concrete from approved sources will be used for all concreting works.
f. Casting of wall will be separated up to 3 stages for 5-7m wall (each casting not more than
2.5m height) and 2 stages for 3-5m wall (each casting not more than 2.5m height).
The works consists of one experienced supervisor, foremen and skill workers. The foreman, experienced
in the formwork erected, representing the works, shall be present at all times whilst work is proceeding.
8
PERMOHONAN PELAN KERJA TANAH, JALAN DAN PERPARITAN MENGIKUT SEKSYEN 70A &
SEKSYEN 9, AKTAJALAN, PARIT DAN BANGUNAN (AKTA 133) DI ATAS SEBAHAGIAN PTD 168349
DAN PTD 168350, JALAN MUTIARA EMAS UTAMA / JALAN MUTIARA EMAS 8, TAMAN MOUN
AUSTIN, MUKIM TEBRAU, DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM, UNTUK TETUAN
DETIK HARTAMAS SDN. BHD.
He shall be responsible for the checking of the works accordance with this method statement. The
foreman shall be the site designated safety office, responsible for the site safety. Supervisor will
communicate with the Engineer on site for a better documentation purpose.
The site supervisor shall be responsible for site safety, he shall report to client site safety
representative. Safety measures to be implemented are as follows: -
a. Prior to any site excavation a survey of the site shall be carried out to determine the presence
[if any] of any buried cables or services.
b. Workers will be equipped with Personnel Protective Equipment [PPE] i.e. safety helmet and
safety boot.
c. Proper housekeeping at the end of the day.