You are on page 1of 4

• Bolt Tensioning Systems

Page 1 The following tensioning procedures are only for use with
Hydraulic Bolt Tensioners and are specifically compiled for
Topside Bolt Tensioning
tension tightening of standard pressure containing flanged Procedure Using 25%
Tool Coverage
joints. The object of each procedure is to accurately achieve
a pre-determined residual bolt stress.

SAFETY: Prior to commencement of bolt tensioning ensure


STAGE 5
that:
Move tensioning tools to first set of even numbered bolts
(ensuring that the tensioners are equally spaced) and apply
• All necessary safety precautions have been carried out
the ‘Pressure B’ as indicated in the bolt tensioning data. Turn
• Personnel involved in bolt tensioning are competent and
down the flange nuts.
fully trained in the use of bolt tensioners and tightening
Release the system pressure and re-apply twice further, i.e.
techniques.
apply ‘Pressure B’ and turn down nuts three times.
• The procedure and data to be used is authorised by a
responsible Engineer.
STAGE 6
• The joints / pipework to be worked on are not ‘live’.
Move the tensioning tools to the remaining un-tightened even
Joints must be at zero pressure and free from hazardous
numbered bolts, and apply the ‘Pressure B’ as indicated in the
substances.
bolt tensioning data. Turn down the flange nuts.
• Bolt tensioning pressures, specific to the flanged joint to be
Release the system pressure and re-apply twice further, i.e.
tightened, are available.
apply ‘Pressure B’ and turn down nuts three times.

STAGE 1
STAGE 7
Number each bolt 1, 2, 3 etc.
Due to the number of tensioning tool passes, it is inevitable
that load losses will have occurred between each pass. It is
STAGE 2
therefore advisable to re-assemble the tensioning tools
Square up the flanged joint using hand tools, or if
back to the bolts tightened in STAGES 3 and 4 (and if
necessary bolt tensioners.
necessary STAGES 5 and 6), apply ‘Pressure 2’ and turn down
the flange nuts.
STAGE 3
This MUST be constantly repeated until there is no further nut
Assemble tensioning tools to the first 25% of the bolts
movement.
(i.e. select odd numbered bolts, equally spacing the
tensioners) and apply the ‘Pressure A’ as indicated in the
STAGE 8
bolt tensioning data.
As a final check, using a hammer, ‘ring’ each bolt to ensure
Whilst maintaining the system under pressure, turn down the
that no loose bolts remain.
flange nuts using a toggle bar.
Always tap the toggle bar using a hammer to firmly seat the
nut against the flange surface.
Release the system pressure and re-apply twice further, i.e.
apply ‘Pressure A’ and turn down nuts three times.

STAGE 4
Move the tensioning tools to the remaining un-tightened
odd numbered bolts, and apply the ‘Pressure A’ as
indicated in the bolt tensioning data. Turn down the flange Tentec Limited
nuts. Plymouth House
Release the system pressure and re-apply twice further, i.e. Guns Lane
West Bromwich. West Midlands
apply ‘Pressure A’ and turn down nuts three times.
United Kingdom. B70 9HS
Internet: www.tentec.net
NOTE: It is often advisable to continuously repeat STAGE email:tech@tentec.net
3 and 4, especially with Ring Type Joints, until no further Telephone: +44(0)121 524 1990

movement of the flange nuts can be obtained. Also, it Telefax: +44(0)121 525 1999

may be beneficial to allow a few minutes between each


pressurisation to allow the gasket to bed in.
Tentec products are subject to continual development and Tentec reserve the right to make changes in the
specification and design of there products without prior notice.
All rights reserved. Reproduction in whole or in part without the permission of Tentec Limited is prohibited.

• Technical Information Published: May 2003


© 2003 - Tentec Limited Document No: 021624
• Bolt Tensioning Systems
Page 2
The following tensioning procedures are only for use with
Hydraulic Bolt Tensioners and are specifically
Topside Bolt Tensioning
compiled for tension tightening of standard pressure Procedure Using 50%
containing flanged joints. The object of each procedure
is to accurately achieve a pre-determined residual bolt stress.
Tool Coverage
STAGE 6
SAFETY: Prior to commencement of bolt tensioning Release the system pressure and repeat STAGE 5 twice
ensure that: further, i.e. apply ‘Pressure B’ and turn down nuts three times.
• All necessary safety precautions have been carried out
• Personnel involved in bolt tensioning are competent and STAGE 7
fully trained in the use of bolt tensioners and As a check to see if an excessive load has been lost in the
tightening techniques. initial 50% of bolts tightened (odd numbered bolts), assemble
• The procedure and data to be used is authorised by a two tensioning tools to randomly selected but diametrically
responsible Engineer. opposite odd numbered bolts. Apply ‘Pressure B’ and attempt
• The joints / pipework to be worked on are not ‘live’. Joints to further tighten the flange nuts. If the nuts cannot be further
must be at zero pressure and free from tightened, then tensioning is complete and the tensioners
hazardous substances. may be removed.
• Bolt tensioning pressures, specific to the flanged joint to be If the flange nuts can be further tightened, then reassemble
tightened, are available. the tensioning tools onto all of the odd numbered bolts. Apply
‘Pressure B’ and turn down the flange nuts once more.
STAGE 1 The bolt tensioners may now be removed.
Number each bolt 1, 2, 3, etc.

STAGE 8
STAGE 2 As a final check, using a hammer, ‘ring’ each bolt to ensure that
Square up the flanged joint using hand tools, or if necessary no loose bolts remain
bolt tensioners.

STAGE 3
Assemble the tensioning tools to 50% of the bolts (i.e. all
odd numbered bolts) and apply the ‘Pressure A’ as indicated
in the bolt tensioning data. Whilst maintaining the system
under pressure, turn down the flange nuts using a toggle bar.
Always tap the toggle bar using a hammer to firmly seat the
nut against the flange surface.

Tentec Limited
STAGE 4 Plymouth House
Release the system pressure and repeat STAGE 3 twice Guns Lane
West Bromwich. West Midlands
further, i.e. apply ‘Pressure A’ and turn down nuts three times.
United Kingdom. B70 9HS
NOTE: It is often advisable to continuously re-apply Internet: www.tentec.net
‘Pressure A’, especially with Ring Type Joints, until no email:tech@tentec.net
Telephone: +44(0)121 524 1990
further movement of the flange nuts can be obtained. Also,
Telefax: +44(0)121 525 1999
it may be beneficial to allow a few minutes between each
pressurisation to allow the gasket to bed in.

STAGE 5
Move the tensioning tools onto the remaining 50% of bolts
(all even numbered bolts) and apply the ‘Pressure B’ as
indicated in the bolt tensioning data. Turn down the flange
nuts.

• Technical Information Published: May 2003


© 2003 - Tentec Limited Document No: 021624
• Bolt Tensioning Systems
Page 3 The following tensioning procedures are only for use with Topside Bolt Tensioning
Procedure Using 100%
Hydraulic Bolt Tensioners and are specifically
compiled for tension tightening of standard pressure
containing flanged joints. The object of each procedure
Tool Coverage
is to accurately achieve a pre-determined residual bolt
stress.
NOTE: It is often advisable to continuously re-apply ‘Pressure
B’, especially with Ring Type Joints, until no further movement
of the flange nuts can be obtained. Also, it may be beneficial to
SAFETY: Prior to commencement of bolt tensioning
allow a few minutes between each pressurisation to allow the
ensure that:
gasket to bed in.
• All necessary safety precautions have been carried out
• Personnel involved in bolt tensioning are competent and
STAGE 5
fully trained in the use of bolt tensioners and
As a check, apply ‘Pressure B’ once more and attempt to
tightening techniques.
further tighten the flange nuts. If the nuts cannot be further
• The procedure and data to be used is authorised by a
tightened, then tensioning is complete and the tensioning tools
responsible Engineer.
may be removed.
• The joints / pipework to be worked on are not ‘live’. Joints
If the flange nuts can be further tightened, then ‘Pressure B’
must be at zero pressure and free from
must be continuously re-applied until no further movement of
hazardous substances.
the flange nuts can be obtained.
• Bolt tensioning pressures, specific to the flanged joint to be
The bolt tensioners may now be removed
tightened, are available.

STAGE 6
As a final check, using a hammer, ‘ring’ each bolt to ensure that
STAGE 1
no loose bolts remain
Square up the flanged joint using hand tools, or if necessary
bolt tensioners.

STAGE 2
Assemble one tensioning tool to each bolt. Occasionally,
depending upon the pitch of the bolting, the tensioners
may be able to be assembled on one side of the flange.
Otherwise, 50% of the tensioners are to be assembled to
one side of the joint with the remaining on the opposite.
Upon hose connection ensure that tensioners from both
sides of the flange are connected into the hydraulic hose
harness.
Tentec Limited
STAGE 3 Plymouth House
Guns Lane
Apply the ‘Pressure B’ as indicated in the bolt tensioning
West Bromwich. West Midlands
data. Whilst maintaining the system under pressure, turn United Kingdom. B70 9HS
down the flange nuts using a toggle bar. Always tap the Internet: www.tentec.net

toggle bar using a hammer to firmly seat the nut against the email:tech@tentec.net
Telephone: +44(0)121 524 1990
flange surface.
Telefax: +44(0)121 525 1999

STAGE 4
Release the system pressure and repeat STAGE 3 twice
further, i.e. apply ‘Pressure B’ and turn down nuts three
times.

• Technical Information Published: May 2003


© 2003 - Tentec Limited Document No: 021624
• Bolt Tensioning Systems
Page 4 When de-tensioning, specific tool pressures are not
normally available as it is not always possible to
Topside Bolt Tensioning
calculate the pressure at which the flange nut will break De-Tensioning Procedure
free. As a guide, if the original flange bolt tightening
pressures are available, the de-tensioning pressure is STAGE 5
usually marginally higher than the original tensioning Remove the bolt tensioners. If the pulling sleeve cannot be
pressure (but not always) unscrewed and the flange nut is also tight, then the thread insert
has locked onto the top face of the flange nut - see STAGE 6.
SAFETY: Prior to commencement of bolt de- If the thread insert cannot be unscrewed but the flange nut is free,
tensioning ensure that: then the thread insert has locked onto the piston - see STAGE 7.
• All necessary safety precautions have been carried out
• Personnel involved in bolt tensioning are competent STAGE 6
and fully trained in the use of bolt tensioners and Thread Insert locked onto top face of nut - If the flange nut is
tightening techniques. unscrewed further than that indicated in STAGE 3, it can cause
• The procedure and data to be used is authorised by a the nut to become locked onto the thread insert when bolt tension
responsible Engineer. is released. To release the thread insert / flange nut, the hydraulic
• The joints / pipework to be worked on are not ‘live’. pressure must be re-applied and the flange nut rotated clockwise
Joints must be at zero pressure and free from (to tighten) half a turn (3 holes on the nut rotating socket). Upon
hazardous substances. de-pressurisation the thread insert should be free to rotate.
• The maximum pressure that can be applied has been
calculated to ensure that either 95% of bolt STAGE 7
material yield is not exceeded or the maximum tool Thread Insert locked onto piston - This occurs if the pulling sleeve
pressure is not exceeded, whichever is the lower. has not been unscrewed sufficiently in STAGE 1 (half a turn may
Pump must be pre-set to achieve this. be insufficient for fine threaded bolts) causing the pulling sleeve
to become locked onto the piston as the tension is released in the
STAGE 1 bolt. To release the pulling sleeve, re-apply the hydraulic pressure
Assemble the tensioning tools to the bolts. With the and turn down the flange nut. Upon depressurisation, the pulling
thread insert component fully screwed down and seated sleeve should freely rotate. Unscrew the pulling sleeve a further
on the piston, unscrew the thread insert through one half half turn and repeat STAGES 2 to 5.
turn. This will prevent the pulling sleeve becoming locked
onto the piston when the bolt tension is released.

STAGE 2
Insert a toggle bar through the tensioner bridge window
and into a hole in the nut rotating socket.
Apply hydraulic pressure to the system until the flange
nuts can be rotated, ensuring that the piston does not
exceed maximum stroke or system pressure does not Tentec Limited
Plymouth House
exceed that indicated in the safety notes above.
Guns Lane
West Bromwich. West Midlands
STAGE 3 United Kingdom. B70 9HS
Internet: www.tentec.net
Turn back each flange nut through one full turn (6 holes
email:tech@tentec.net
on the nut rotating socket).
Telephone: +44(0)121 524 1990
Telefax: +44(0)121 525 1999

STAGE 4
De-pressurise the system and check to see that the
flange nuts are still free to rotate.

• Technical Information Published: May 2003


© 2003 - Tentec Limited Document No: 021624

You might also like