1. A and B can do a piece of work in 10 and 15 work .In how many days whole work will be
days. They together will do the work in how completed.
many days? (A) 12 (B) 10
(A) 5 days (B) 6 days (C) 6 (D) 4
(C) 10 days (D) 7 days
6. A can do a piece of work in 20 days and B can
2. A and B can do piece of work in 20 and 30 do the same work in 25 days. Both of them
days. They together will do the same work in start the work but after some days B left the
how many days? work and whole work is completed in 16 days.
(A) 12 (B) 10 After how many days B left the work?
(C) 6 (D) 14 (A) 16 (B) 10
(C) 5 (D) 12
3. A, B and C can do a work in 10, 15 and 30
days. They all together will do the work in 7. A can do a piece of work in 20 days and B can
how many days? do the same work in 25 days. In how many
(A) 6 (B) 10 days whole work will be completed. If B left
(C) 5 (D) 12 11 days before the completion of the work
(A) 11 (B) 5
4. A can do a piece of work in 20 days and B can (C) 12 (D) 16
do the same work in 25 days. Both of them
start the work together but B leaves the work 8. A can do a piece of work in 10 days and B can
after 5 days. In how many days remaining do the same work in 15 days. In how many
work will be completed? days whole work will be completed .If A left 5
(A) 11 (B) 16 days before the completion of the work
(C) 10 (D) 9 (A) 9 (B) 5
(C) 7 (D) 12
5. A can do a piece of work in 12 days and B can
do the same work in 15 days. Both of them 9. A, B and C can do a piece of work in 10 ,20
start the work but after 4 days A leaves the and 30 days. They all together start the work
but A left 5 days before and B left the work 3
Answer key
1. B 5. B 9. B 13. A 17. C
2. A 6. C 10. A 14. A 18. D
3. C 7. D 11. C 15. C 19. C
4. A 8. A 12. D 16. D 20. B
Explanations
Sol 4. (A) 1
One day work of B =
25
1
One day work of A = A worked for 16 Days
20
1 4
1 16
One day work of B = 20 5
25
4 1
One day work of A & B = Remaining work was done by B = 1
5 5
1 1 54 9
1 25
20 25 100 100 5
5 1
9 9
5 days work of A & B = 5
100 20
Sol 7. (D)
9 11
Remaining work = 1 Let work is finished in = x days
20 20
Number of Days B worked = (x -11)
Remaining Work will be done by A’ Alone
x x 11
1
11 20 25
=
20
5 x 4 x 44
1 1
100
20
9 x 44 100
11 20
11 days 9 x 144
20 1
x 16 Ans.
Sol 5. (B)
Sol. 8 (A)
1
One day Work of A = Let work in finished in = x Days
20
Number of days A worked = (x-5) days.
1 4
16 days Work of A = 16 x5 x
20 5 1
10 15
4 1
Remaining Work = 1 3 x 15 2 x
5 5 1
30
1 5 x 15 30
Work was done by B.
5
5 x 45
1 1 25
5 days Ans. 45
5 5 1 x 9 Days
5
1
25
11x 39 60 1
1
1
3 x 2 x 12
11x 99
x 9 days 23 1
6x 12
5 1
Sol 10. (A) 6 x 12
A:B x 10
Work Efficiency 5 : 7 Days Taken by A = 3 10 30 days
Days/Time 7: 5
7x, 5x Sol. 14 (A)
2x =12 A:B
x=6 Work Efficiency 80 : 100 4: 5
A’ Alone = 7 x 6 =42 Days Answer
Days/Time 5:4
5x, 4x
Sol 11. (C)
1 1 1
A:B
5 x 4 x 20
Work Efficiency 3: 5 45 1
Days/Time 5: 3 20 x 20
5x, 3 x 45 1
20 x 20
1 1 1
x9
5 x 3 x 60
35 1 A’ Alone will do in = 5 9 45 Days
15 x 60 B’ Alone will do in = 4 9 = 36 Days
8 1
15 x 60
x 32 Sol 15. (C)
A B