You are on page 1of 6

1.

Introduction
This report is to compare the Design and I/O Specifications provided by the 3 DDCs (namely
AECOM, MMSpa, SYSTRA). Each DDCs have proposed a BMS for Elevated stations as per the
need of CMRL. This report contains detailed review of all the specifics of the design provided by
DDC, the IO Devices placement and control strategies to effortlessly monitor the devices from the
BMS Workstation.

2. Background
SCADA system is inevitable for underground station since it requires constant monitoring of
proper operation of all the field devices deployed and timely control of devices especially falling
under the scope of TVS department. When it comes to Elevated station SCADA is considered to be
superfluous and hence the soaring demand for a BMS is crucial. The following are the minimum
requirements for an Elevated Station to help SCR to monitor every sections of the station in real-time:

 Monitoring of Water Tank status


 ASS, MDB incomer and tiebreaker status
 UPS healthiness and battery status
 Wind Velocity and Wind Direction status
 Interface with S&T SCADA

3. DDC1 – AECOM
AECOM proposed the Building Management System (BMS) for the Chennai Metro Rail
Limited (CMRL) Phase 2 – Corridor-4 for 18 Elevated Stations (SPH, SVP, SSG, SAS, SAN, SVV,
SKM, SAJ, SPJ, SCB, SRH, SID, SKP, SKI, SKC, SMT, SPT, SPB). AECOM provided an
architecture [1] for the CHENNAI BYPASS CROSSING station and corresponding I/O List [2] with
costing details in BOQ for the above mentioned 18 elevated stations.

3.1 IO List
 MDB 1 & 2 Circuit Breaker – Status Monitoring [MODBUS]
 MDB BUS COUPLER Circuit Breaker – Status Monitoring [MODBUS]
 Outgoing Feeder for MDB 1 & 2 (8 & 11 Respectively) – Status Monitoring
[MODBUS]
 HPFC Panel 1 & 2 – Status Monitoring [MODBUS TCP IP]
 UPS 1 & 2 – Status Monitoring [MODBUS TCP IP]
 Fire Pump Panel (FPP) – Status Monitoring & Control – [DI, DO, PLC, RIO]
 Hydrant Fire Pump – Status monitoring [MFP]
 Jockey Pump – Status Monitoring [MFP]
 Domestic Water Tank (DWT) – Level Monitoring [AI]
 Fire Water Tank (FWT) – Level Monitoring [AI]
 Pump Room Sump – Level Monitoring [DI]
 CLCP Panel – Status Monitoring & Control [MODBUS TCP]
 Lift and Escalator Parameters from RMS – Status Monitoring & Control [MODBUS]
 Escalator Parameters (4)
 Lift Parameters (3)
 Battery (2) – Status Monitoring [RS 485]
 Wind Velocity Sensor – Status Monitoring [AI]
 E&M RIO – PLC Status – Status Monitoring [Soft Link]
 Fire Alarm Control Panel (FACP) – Status Monitoring [RS 485 / MODBUS TCP/IP]
3.2 Cable Requirements

From To Cable Type Distance


PLC (UPS ROOM) VRF Central Controller (SCR) CAT-6 35
PLC (UPS ROOM) FACP CAT-6 35
PLC (UPS ROOM) UPS CAT-6 15
PLC (UPS ROOM) RMS CAT-6 35
PLC (UPS ROOM) MDB CAT-6 20
PLC (UPS ROOM) CLCP CAT-6 35
PLC (UPS ROOM) HPFC Panel CAT-6 25
PLC (UPS ROOM) Battery Cabinet CAT-6 20
PLC (UPS ROOM) Wind Velocity Sensor CAT-6 50
       
RIO (PUMP ROOM) FPP Soft Communications CAT-6 60
RIO (PUMP ROOM) FPP Hard Communications Control Cable - 4 Core 20
RIO (PUMP ROOM) Sump Levels Control Cable - 2 Core 60
RIO (PUMP ROOM) Pump Room Sump Control Cable - 2 Core 30
RIO (PUMP ROOM) FWT & DWT Control Cable - 1 Pair 40
       
PLC (UPS ROOM) RIO (PUMP ROOM) OFC - 6 Core 290
PLC (UPS ROOM) Workstation Cum Server CAT-6 80
PLC (UPS ROOM) Printer CAT-6 40
       
CABLE TYPE CABLE LENGTH
CAT-6 400
OFC 260
1 PAIR 40
2 PAIR 50
2 CORE 90
4 CORE 20

4. DDC2 – MMSpa
MMSpa proposed the Building Management System (BMS) for the Chennai Metro Rail
Limited (CMRL) Phase 2 – Corridor – 5 – E&M 04 for 18 Elevated Stations. MMSpa provided an
architecture [3] for the CHENNAI TRADE CENTER (CTC) station and corresponding I/O List [4].
The following section discuss about IO List of the proposal and the communication and controlling
method to be deployed.

4.1 IO List – PLC Panel


 MDB 1 & 2 – Status Monitoring [MODBUS]
 HPFC Panel 1 & 2 – Status Monitoring [MODBUS]
 Essential Power Panel (EPP) (W, BU) – Status Monitoring and Control
 Incoming Circuit Breaker (from MDB 1 & 2) [DI, DO, RS 485]
 Escalator 03, 04, 05, 06 – [MODBUS]
 Lift 1, 2, 3, 4 – [MODBUS]
 ACDB Battery Charger (ASS 01, ASS 02) – [MODBUS]
 Jockey Pump – [MODBUS]
 Sump Pump (Lift Pit – 1, 2) – [MODBUS]
 Out Door Unit (ODU) – 1 & 2 – [MODBUS]
 VAC-DB-01 – [MODBUS]
 UPS Input Panel (BU, W) – Status Monitoring – [MODBUS]
 UPS Output Panel – Status Monitoring
 Incoming Circuit Breaker (from MDB 1 & 2) - [DI, MODBUS]
 Tie Circuit Breaker – [DI]
 AFC (Main Feeder, Backup Feeder) – [MODBUS]
 Signalling (Backup Feeder, Main Feeder) – [MODBUS]
 Telecom – [MODBUS]
 PSD – [MODBUS]
 ULDB-01,02,03 – [MODBUS]
 UPDB – [MODBUS]
 Main Lighting Panel (MLP) – Status Monitoring – [MODBUS]
 Incoming Circuit Breaker - [DI, MODBUS]
 LDB-01, 02, 03, 04 - [MODBUS]
 Signage DB – 01, 02 - [MODBUS]
 Solar Panel 1 & 2 – Status Monitoring – [MODBUS]
 Fire Hydrant Pump 1 & 2 (W&S) – Status Monitoring – [MODBUS]
 EV Charging Station – 1&2 (S&W) – Status Monitoring – [MODBUS]
 Tie Breaker – Status Monitoring – [MODBUS]
 SMDB – Status Monitoring – [MODBUS]
 Incoming Circuit Breaker - [DI, MODBUS]
 PDB – 01, 02 - [MODBUS]
 VAC - DB – 02 – [MODBUS]
 ADDB - 01, 02 – [MODBUS]
 Hydro pneumatic Domestic Water Pump – [MODBUS]
 Sump Pump (Pump Room) – [MODBUS]
 Escalator 01, 02 – [MODBUS]
 BTS Feeder – Status Monitoring – [MODBUS]
 UPS System – Status Monitoring
 UPS 01, 02 – [MODBUS]
 Battery – [MODBUS]
 Fire Alarm Control Panel (FACP) – Status Monitoring – [MODBUS]
 LIFT (1-4) – Status Monitoring & Control – [MODBUS]
 Escalator (1-6) – Status Monitoring & Control – [MODBUS]
 LCP – Status Monitoring & Control – [MODBUS]
 Field Devices – Temperature & Humidity Sensor – SCR, CER, SER, UPS – Status
Monitoring [AI]
 VRF Central Controller – Status Monitoring & Control – [MODBUS]
 HPFC 01 & 02 – Status Monitoring – [DI, MODBUS]

4.2 IO List – RIO Panel


 Fire Hydrant Pump Controller – 01, 02 - Status Monitoring & Control – HARD [DI,
DO] & SOFT [MODBUS]
 Jockey Pump - Status Monitoring – HARD [DI] & SOFT [RS 485]
 Hydro pneumatic Domestic Water Pump – Pump Controller - Status Monitoring &
Control – HARD [DI] & SOFT [RS 485]
 Sump Pit Level (Pump Room) - Status Monitoring – HARD [DI]
 Domestic Water Tank – 01, 02 - Status Monitoring – HARD [DI]
 Fire water Tank – 01, 02 - Status Monitoring – HARD [DI]

5. DDC3 – SYSTRA
SYSTRA proposed two different Building Management System (BMS) [5, 6] for the Chennai
Metro Rail Limited (CMRL) Phase 2 – Corridor – 5 – E&M 03 for the Elevated Stations. Out of the
two Proposed architecture the second architecture [6] found to be Cost effective and adequate. The
preferable architecture for the ANNA NAGAR WEST METRO station and corresponding I/O List [7]
is considered for discussion in the following section.

5.1 IO List
 MDB Circuit Breaker Incomer (ACB) 1 & 2 – Status Monitoring [DI, MODBUS]
 Outgoing Breaker for MDB – 1 & 2 (12, 10 MCCB) – Status Monitoring [AI, DI]
 SMDB – Incomer from MDB-1 – Status Monitoring [DI, DO, MODBUS]
 Outgoing Breaker for SMDB (1-16 MCCB) – Status Monitoring [AI, DI, MODBUS]
 EPP Panel – Incomer 1 & 2 – Status Monitoring & Control [DI, DO, MODBUS]
 Outgoing Breaker from EPP Panel (1-8 & 9-22) – Status Monitoring [AI, DI]
 UPS Input Panel – Incomer 1 & 2 – Status Monitoring & Control [DI, DO, MODBUS]
 Outgoing Breaker from UPS Input Panel (1-3) – Status Monitoring [DI]
 UPS Panel – Incomer 1 & 2 – Status Monitoring [DI, MODBUS]
 UPS Panel – Bus Coupler Circuit Breaker – Status Monitoring [DI]
 UPS Panel – Outgoing Panel (1-16) – Status Monitoring [DI]
 MLP – IC – MCCB – Status Monitoring & Control [DI, DO, MODBUS]
 UPS Panel – Outgoing Breaker 1-2 – Status Monitoring [DI]
 UPS 1, 2 – Status Monitoring [RS 485]
 Battery – Status Monitoring [RS 485]
 LDB Status (1-4) – Status Monitoring [DI]
 Escalator Status (1-6) – Status Monitoring [DI]
 Lift Status (1-4) – Status Monitoring [DI]
 IDU (Variable) & ODU (2) – Status Monitoring [RS 485]
 Fire Hydrant Pump – Control Panel – Status Monitoring & Control [AI, DI]
 Jockey Pump - 01 – Control Panel – Status Monitoring & Control [AI, DI]
 Hydro Pneumatic – Control Panel – Status Monitoring & Control [AI, DI, DO]
 Borewell Water Pump – 01 – Status Monitoring [AI, DI]
 Sump Pump for Escalator and Lift Pit – Status Monitoring & Control [AI, DI, DO]
 Fire Alarm Control Panel – Status Monitoring [MODBUS]
 Tanks Level Status – Status Monitoring [DI]
6. DDC 1 vs DDC 2 vs DDC 3 - Comparison
AECOM MMS pa S YS TRA
PLC Panel - Location 1 - UPS ROOM 1 - SCR 1 - ASS ROOM
M DB 1,2 M DB 1,2 M DB
HPFC 1,2 HPFC 1,2
UPS 1,2 UPS 1,2 UPS 1,2
PLC: SM DB
- PSU 1& 2
EPP EPP
- CPU
- IO Cards M LP
- Com. M odule ACPP
PAP
EM LP
ESPP
RIO Panel - Location 1 - PUM P ROOM 1 - PUM P ROOM 1 - PUM P ROOM
Wind Speed
Wind Velocity Sensor NO
Wind Direction
FPP Fire Hydrant Pump 1,2 Fire Panel
FWT FWT FWT
DWT DWT DWT
RIO: Sump Level
-PSU 1 & 2
Pump Room Sump Level WPP Panel
- IO Cards
- Com. M odule Pump Room Sump Sump Pump
Temp & RH
Temp & RH
- SCR
- SCR
- SER
NO - SER
- CER
- CER
- UPS
- UPS
-SM R
FACP SCR SCR SCR
VRV Controller SCR SCR NO
RM S for L&E SCR SCR
CLCP CLCP - SCR LCP - SCR, ASS ROOM 1, DB ROOM M LP - ASS ROOM
1 - ASS ROOM 1
M DB 1,2 - UPS ROOM 1 - ASS ROOM
2 - ASS ROOM 2
SM DB 1 - ASS ROOM
1 - ASS ROOM 1
HPFC 1,2 - UPS ROOM NO
2 - ASS ROOM 2
UPS 1,2 - UPS ROOM 1,2 - UPS ROOM 1 - ASS ROOM
BC UPS ROOM UPS ROOM 1 - ASS ROOM
M LP 1 - ASS ROOM 1 1 - ASS ROOM
EPP NO DB ROOM ASS ROOM
Wind Velocity Yes Yes NO
7. BOQ Analysis – Per Station
AECOM M MSpa, SYSTRA
S l.No Description QUANTITY AMOUNT (In INR) Total QUANTITY AMOUNT (In INR) Total
1 BMS Colour Monitor (24"monitor) 1 25058 25057.5
2 BMS PRINTER 1 62323 62322.5
3.1 OFC Ethernet Switches-L2 , 12 port (M anaged) 2 44333 88665
3.2 OFC Ethernet Switches-L3 - 8 port (UnManaged ) 4 34438 137752
4.1 PLC Programming software 1 122075 122075
4.2 BMS Software 1 472880 472880
5.1.1 CPU 1 228666 228665.75
5.1.2 DI(32 Ch) 1 43690 43690
5.1.3 DO(8 Ch) 1 27628 27627.5
5.1.4 Serial Communciation M odule 1 22488 22487.5
5.1.5 PLC Enclousure 1 83525 83525
5.1.6 Communciation Module 1 167693 167692.5
5.1.7 M isceleneous components 1 32125 32125
5.2.1 Communication Module 1 167693 167692.5
5.2.2 DI(24 Ch) 1 43690 43690
5.2.3 DO(8 Ch) 1 27628 27627.5
Awaiting From DDC
5.2.4 AI(8 Ch) 1 57986 57985.625
5.2.5 Serial Communciation M odule 1 22488 22487.5
5.2.6 PLC Enclousure 1 83525 83525
5.2.7 M isceleneous components 32125 32125
6.1 Water Level Switch 2 18890 37779
6.2 Ultasonic level sensor 2 38165 76329
6.3 WIND VELOCITY Sensor 1 126573 126572.5
7.1 100 mm wide x 50 mm deep 50 0
7.2 50 mm wide x 50 mm deep 20 703 14057.9
7.3 25 mm GI Conduit 200 173 34695
8.1.1 1 Pair Cable * 1.0 S Q.mm 40 170 6784.8
8.1.2 2 Pair Cable * 1.0 S Q.mm 50 247 12336
8.1.3 2 Core Cable * 1.0 S Q.mm 90 170 15265.8
8.1.4 4 Core Cable * 1.0 S Q.mm 20 247 4934.4
9 OFC 260 159 41428.4
10 CAT 6 , 6e cable 500 96 48187.5
Per S tation Cost 2368068.675

8. GC Recommendation
Reference
[1] DDC-P2C4-05-MEP-DR-SCB-64003-01.pdf
[2] SCB-IO LIST.xlsx
[3] DDC-P2C5-ECV02-MEP-SCT-57001-01.pdf
[4] CTC IO SUMMARY.pdf
[5] CMRL ISMS SLD 1.pdf
[6] CMRL ISMS SLD 2.pdf
[7] DDC503-DD-UG-ISMS-ELEVATED-69901-A1.pdf