Sr.
Stages of progress Date of Criteria of monitoring
No. Monitoring
1 Orientation 22 – 07 -2020 orientation
2 Market survey for project 29 – 07 - 2020 To visit different industries and
places
3 Project Definition 05 – 08 -2020 Project selection
4 Details Collection 19 – 08 -2020 Basic introduction and details
collection
5 Literature survey 02 – 09 - 2020 Study of Research paper
6 Problem Definition 16 – 09 - 2020 Find out problem
7 Data collection 23 – 09 - 2020 Data collection from research
papers
8 Evaluation 07 – 10 - 2020 Justify methodology
9 Calculation 21 – 10 - 2020 Theory and Calculation from
books and research papers
10 Design and Development 11 – 11 - 2020 Using Design software
11 Market survey for components 25 – 11 - 2020 Estimation and costing
12 Purchase of components 02 – 12 – 2020 to Estimation and costing
04 – 01 - 2021
13 Machining and welding 06 – 01 - 2021 performance
14 Assembling 27 – 01 - 2021 Final project product
15 Testing of project 10 – 02 - 2021 Check weather collected data
16 Implementation 24 – 02 - 2021 Check validated result
17 Taking data 10 – 03 - 2021 Check validate data
18 Documentation 08 – 04 - 2021 Report writing
19 Presentation 22 -04 -2020 To make power point
presentation
GOVERNMENT POLYTECHNIC, GODHRA
MECHANICAL ENGINEERING DEPARTMENT
NAME OF PROJECT: DEVELOPMENT OF INTELLIGENT BRAKING SYSTEM
FOR MOTORCYCLE
MONITORING SCHEDULE