|G pansegeaenLeaRca eee | em@Ke — SINGHYDRO CORPORATION LIMITED POWERCHINA Date: 05" January 2022 Our Ref: L-KNPIWSP-PD-2022-2160 Mr. DV Medawatte Project Director, Kandy North Pathadumbara Integrated Water Supply Project, Pahala Kondadenlya, Katugastota. KANDY NORTH PATHADUMBARA INTEGRATED WATER SUPPLY PROJECT Contract No. P&P/DB/PATHADUMBARA/2013 Dear Sir, Subject: Roads to be handed over It is pleasure to inform you that around 10 Km of roads (ANNEX) have been prepared for handing over to respective road authorities after completion of the pipe laying work, Itis much appreciated if you could make necessary arrangement to hand over these roads to the respective road authorities. Your early attention in this regard is highly appreciated. Yours faithfully, wie Shi Zhifeng Project Manager Sinohydro (SL) Kandy North Pathadumbara Integrated Water Supply Project ANNEX -To be handed over road list Hotel Sunrieh Medeniya Kandy,Sri Lanka mall: kandynor2017@163.com