Professional Documents
Culture Documents
net/publication/12277535
CITATIONS READS
14 825
4 authors, including:
Some of the authors of this publication are also working on these related projects:
Bioactive food ingredients for safe and health-promoting functional foods View project
All content following this page was uploaded by Charles I Onwulata on 23 December 2013.
The milk fat encapsulation process consisted of four equipment. The heated slurry was homogenized with
operations: ingredient blending and heating, homoge- standard double-stage unit 10 and 17.2 MPa, de-
nization, spray-drying, and packaging. The processing pending on the encapsulant selected.
sequence was as follows: The selected encapsulant was Spray-drying was a multistep operation. A three-
first dry-blended with NDM and dispersed in water at stage air spray dryer equipped with an internal sweep
24°C to form a slurry about 25% TS. The anhydrous in the drying chamber and a fluidized bed was re-
butter oil or cream was warmed and combined with quired. The homogenized slurry was sprayed into a
the emulsifier. After the two blends were combined to stream of hot air where moisture is reduced to <10%;
produce a mixture with about 25% TS, the slurry was powder particles drop to a fluidized-bed below the dry-
stirred vigorously for 5 min with a milk stirrer, heated ing chamber for additional drying to <5% moisture;
to 63°C with continued stirring, homogenized at 17.2 the powder is discharged into a fluidized-bed/cooler,
MPa, and spray dried (inlet air temperature 193 to where the product was cooled to 30°C and the final
196°C and outlet air temperature 82 to 87°C). Details moisture content of <4% was attained. The cooled pow-
of the powder formation process were given by Onwu- der was collected into holding tanks, and then fed onto
lata et al. (10). After drying and cooling, we assumed the packaging line, and packaged into standard 22.7-
that the powder would be packaged in paper bags for kg poly-lined brown paper bags for storage. The air
shipping and storage. from the drying chamber was exhausted into a bag
filter for recovery of fines and into a heat exchanger
Physical Plant Costs for heat recovery. Recovered heat can be used to pre-
heat air blown into the spray dryer or a fluidized bed.
We assumed that a facility for encapsulation would Because a building was needed to house the equip-
be integrated into a larger dairy processing plant. ment and personnel, building costs were included at
Costs of the facility included the costs for purchasing $645/m2 for a 36.6- × 18.3-m processing facility and a
and installing the processing equipment, the building 18.3- × 18.3-m packaging and storage facility.
to house this equipment, and all necessary materials, A contingency allowance of 15% of all the other capi-
labor, and technical support required to ensure proper tal costs is included to cover any additional equipment
operation. Not included were additional costs common costs or process refinements that may be required.
to the entire plant: raw milk unloading and storing,
cream separation, and pasteurization. In addition,
land, quality control facilities, administrative offices, Labor
and the plant utility system were assumed to be part
Labor costs for three plant operators per shift, main-
of the total facility and were not addressed.
tenance personnel, and one supervisor per day were
Specific equipment would be needed for each of the
included. The maintenance force was included at 3%
four unit operations described. Equipment would also
of the capital cost for the plant, which averaged about
be needed for CIP systems for process control, and
for monitoring to prove sanitation and conformation two per shift. Plant operator wages were estimated to
to regulations. be $10/h plus 35% fringe benefits.
The ingredient blending and heating area consisted
of storage bins, jacketed mixing tanks, solids feeders, Utilities and Other Costs
mixing devices, and material handling systems. Stain-
less steel holding tanks were required for the tempo- Natural gas, electricity, steam, and water were the
rary storage of the encapsulant, NDM, butter oil or utilities required. Electric requirements were esti-
cream, and emulsifier. Jacketed, stainless steel tanks mated at 408 kW at an annual cost of $121,000, while
equipped with agitators of food-grade construction 7.4 MM BTU/h of natural gas were needed at an an-
were needed to blend and heat the ingredients. The nual cost of $121,300. Steam and water costs were
first mixing tank was used to blend the encapsulant small by comparison and, combined, were less than
and NDM; the dry blend was fed into a second tank $50,000/yr.
where ambient temperature water was added to form Cost for maintenance materials and operating sup-
the slurry. The third mixing tank blended the slurry plies was calculated at $267,000/yr as a percentage of
with the previously warmed source of milk fat blended plant capital cost and operating labor cost; $431,000
with emulsifier. The process stream was heated to was included for general and administrative produc-
about 63°C in this tank. tion overhead, property taxes, and insurance.
Materials handling systems were also needed to The capital cost of the physical plant was spread
transport solids and liquids to and from the processing over 10 yr and prorated over the plant output.
Potable water
Dairy cream
Cream with
$1.07
$2.24
$1.84
$0.00
alternate sources of milk fat. All-purpose flour, modi-
sucrose
21,000
67,300
50,500
57,000
85,000
1700
1400
Sugar
Potable water
Dairy cream
Cream with
$1.07
$2.24
$1.84
$0.00
pending on geographical location and season of the
22,000
67,300
51,100
57,000
85,000
1700
Dairy cream
$1.07
$2.24
$1.84
$0.00
67,300
51,100
57,000
87,000
1700
1400
Potable water
tion cost.
$0.64
$2.06
$2.24
$1.84
$0.00
Butteroil
24,100
29,400
82,100
57,000
83,000
2800
1400
Sugar
Potable water
$2.06
$2.24
$1.84
$0.00
29,400
82,000
57,000
84,000
2800
1400
All-purpose flour
all-purpose flour
Potable water
$2.06
$2.24
$1.84
$0.00
29,400
82,200
57,000
85,000
2800
1400
pose flour.
Additional factors must be considered to qualify
Expelled water-qty kg/d
Plant outputs
Encapsulant
Material
Material
Material
Material
Butteroil with Butteroil with Butteroil with Cream with all- Cream with Cream with
all-purpose flour modified cornstarch sucrose purpose flour modified cornstarch sucrose
Investment cost
Equipment & facilities cost $7,235,000 $7,235,000 $7,235,000 $7,235,000 $7,235,000 $7,235,000
Economic life-years 10 10 10 10 10 10
Unit capital cost $0.05 $0.05 $0.05 $0.05 $0.05 $0.05
Depreciated over 10 years
Operating cost
Raw materials
Encapsulant $0.13 $1.12 $0.27 $0.11 $0.98 $0.24