Question #1 Topic 1

A dispatcher needs to know the available staff for any given day. Laborers must track vacation time for the dispatcher to use.
Where can this be done?

A. De ne Person Availability in the People application

B. Modify Person Availability in the People application

C. De ne Person Availability in the Calendars application

D. Modify Person Availability in the Calendars application

Correct Answer: B

  sleeper166 8 months, 2 weeks ago


This answer is wrong, "Modify Person Availability" can be found in the More Actions menu in the People application so the answer is B not A.
upvoted 4 times

  joe12398 5 months, 1 week ago


it says the answer is B, unless it has been changed.
upvoted 1 times

  elma93 1 month ago


The answer is B
upvoted 1 times

Question #2 Topic 1

A company has a requirement to report on actual labor hours, materials, services and tools used as work progresses on a work order.
What is the earliest point in the basic life cycle a user can start reporting?

A. APPR

B. COMP

C. WMATL

D. WAPPR

Correct Answer: A
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21683844

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 1/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #3 Topic 1

A vendor requires a payment of 20% of the purchase price when the purchase order (PO) is sent and the company wants to withhold of the
payment until 90 days after receiving the item before nal payment is made.
How would this be accomplished?

A. A Purchase Requisition would be created and three invoices would be generated via the invoicing application. One invoice for 20%, one for
60% and one for 20%.

B. A Price Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the
time the item is received and another invoice for 20% 90 days after receipt.

C. A Blanket Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at
the time the item is received and another invoice for 20% 90 days after receipt.

D. A Purchase Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at
the time the item is received and another invoice for 20% 90 days after receipt.

Correct Answer: D

Question #4 Topic 1

A company wishes to group its location records into a hierarchy to assist users in searching for assets.
How can this be accomplished?

A. Location Groups can be created and LIVE locations added.

B. Locations can be linked by using the Related Records tab in the Locations application.

C. Location records will need to be added to a network and can only include locations with an ACTIVE status.

D. Location records need to be added a system and can only include locations with an OPERATING type.

Correct Answer: D

  Dhans 1 month ago


Reference: https://www.ibm.com/support/pages/what-difference-using-lifofifo-versus-avg-average-cost-maximo-75x
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 2/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #5 Topic 1

A company has assets at multiple locations that require maintenance. There is a requirement to have a single work order with charges rolled up to
a single GL account.
How can that be achieved?

A. Create a task work order for each asset.

B. Create a child work order for each asset.

C. Add a job plan that has the assets associated.

D. Add the assets in Multiple Assets, Locations and Cls.

Correct Answer: B
Reference:
https://www.ibm.com/developerworks/community/ les/basic/anonymous/api/library/41abc2d2-e1ec-4709-8b27-
4937d78f9909/document/ec94eee2-
7378-4241-a9c2-62499183955a/media

  MaxComp 1 month ago


Answer D
https://www.ibm.com/support/pages/using-multiple-assets-locations-and-cis-associate-assets-work-orders-use-different-gl-account
upvoted 2 times

Question #6 Topic 1

An administrator has a requirement to create 44 new assets that each share a common con guration.
Which application can do this with a single action?

A. Assets

B. Item Master

C. Classi cations

D. Asset Templates

Correct Answer: D
Reference:
http://www.ibm.com/support/knowledgecenter/SSWK4A_7.5.0/com.ibm.mame.doc/c_essentials_oview.html

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 3/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #7 Topic 1

A user belongs to two non-independent security groups, Group A and Group B. Group A has a purchasing limit of $7000 and Group B has a
purchasing limit of
$8000.
What is the purchasing limit of a user who belongs to both security groups?

A. $7000

B. $8000

C. $15000

D. $56000

Correct Answer: B

Question #8 Topic 1

What costing method should be used if the receipt cost of items that are the newest in stock is required?

A. LIFO

B. FIFO

C. Average

D. Standard

Correct Answer: A
Reference:
http://www.ibm.com/support/knowledgecenter/SSLKT6_7.5.0/com.ibm.mam.doc/glossary/glossary.html

Question #9 Topic 1

Which report option provides multiple access points for an end user to run reports including the toolbar shortcuts of Browser View, Direct Print,
Direct Print with
Attachments and direct access from application dialogs including Work Order Status Change and Inventory Reorder?

A. ERI

B. BIRT

C. Cognos

D. SQL Server

Correct Answer: B
Reference:
https://www.ibm.com/developerworks/community/wikis/home?
lang=en#!/wiki/IBM%20Maximo%20Asset%20Management/page/BIRT%20Reporting

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 4/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #10 Topic 1

An approved work order has been assigned an incorrect job plan.


How do you correct this?

A. Change the Job Plan Revision to the correct revision.

B. Clear the Job Plan eld and enter the correct job plan.

C. Create a Follow-up work order with the correct job plan.

D. Select Remove Work Plan from the More Actions menu and enter the correct job plan.

Correct Answer: D

Question #11 Topic 1

The user wants to have a new job plan reference an existing job plan so that the data in the existing job plan will be available without re-entering it.
What is the name of this feature?

A. Nested job plans

B. Job plan revisions

C. Job plan sequences

D. Attachment job plans

Correct Answer: B

Question #12 Topic 1

A custom eld has been added to the Work Order Tracking application to identify the inspector for environmental impacts of each work order.
What type of role is used to assign the work order to the environmental inspector?

A. Person

B. Person Group

C. A set of data related to the record

D. A set of data related to the login user

Correct Answer: A

  marcoagb 1 month, 3 weeks ago


If you have created a custom field for WORKORDER object and that field holds the inspector ID, then you should use (C) A SET OF DATA RELATED
TO THE RECORD, point WORKORDER as object and your custom field as the VALUE, so that will assign the records to the inspector ID of your
workorder custom field
upvoted 3 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 5/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #13 Topic 1

A supervisor is required to report actual work hours by work order number.


With which statuses can this be accomplished? (Choose two.)

A. INPRG

B. WAPPR

C. CANCEL

D. PNDREV

E. COMPLETE

Correct Answer: AE

Question #14 Topic 1

A xed-schedule PM needs to be set up.


What other setting need to be selected in addition to the frequency value?

A. Alert Lead (DAYS) must equal 0

B. Alert Lead (DAYS) must be greater than 0

C. Use Last Work Order's Start Date to Calculate Next Due Date? checked

D. Use Last Work Order's Start Date to Calculate Next Due Date? unchecked

Correct Answer: C
Reference:
http://www.ibm.com/support/knowledgecenter/SSLL8M_7.5.0/com.ibm.nuc.doc/pluspm/c_pm_frequency_schedules.html

Question #15 Topic 1

A company has a requirement to have items in the storerooms to be reordered automatically.


How can this be achieved?

A. Reorder Escalation

B. Reorder Cron Task

C. Reorder "" Reorder Items

D. Reorder Direct Issue Items/Services

Correct Answer: C

  marcoagb 1 month, 3 weeks ago


To have reorder executed automatically you must use REORDER CRONTASK (B). C option is just doing that manually which is not automate
upvoted 3 times

  MaxComp 1 month ago


REORDER CRONTASK (B)
upvoted 2 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 6/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #16 Topic 1

A company has a requirement to share calendar, classi cation, job plan, item description and PM data.
What needs to be created?

A. Single organization, single site environment

B. Multiple organizations with a shared site environment

C. Multiple organizations with one site per organization environment

D. Multiple organizations with multiple sites per organization environment

Correct Answer: A

Question #17 Topic 1

An engineer schedules a very complex asset report developed in BIRT. The engineer needs to set a feature to be able to retrieve the report
contents from within
Maximo for very large les that are restricted by the email server.
Which feature does this?

A. Direct Print

B. Email with a File URL

C. Email with a File Attachment

D. REPORTSCHEDULE cron task

Correct Answer: D

  marcoagb 1 month, 3 weeks ago


REPORTSCHEDULE crontask will run the scheduled report but 'Email with a file URL' will allow user to retrieve the report since mail server wont
deliver the attachment
upvoted 3 times

  yasar2002 1 month ago


The correct answer is "Email with a file URL"
upvoted 1 times

Question #18 Topic 1

A company has a requirement to have labor certi cates de ned.


In which application can this be done?

A. Crews

B. People

C. Certi cations

D. Quali cations

Correct Answer: D

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 7/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #19 Topic 1

A master PM can be used to do which of the following?

A. Create a job plan revision.

B. Generate work orders for associated PMs.

C. Create associated PMs for an item's location.

D. Change the status of work orders generated from associated PMs.

Correct Answer: C
Reference:
http://www.redbooks.ibm.com/redbooks/pdfs/sg247761.pdf
(page 55)

Question #20 Topic 1

An administrator has a requirement to ensure that purchase requisitions have been approved before being able to create purchase orders from
them.
Which settings control this behavior?

A. Clear the Allow PO Creation From Unapproved PR? checkbox in Purchasing Options.

B. Clear the Allow PO Creation From Unapproved PR? checkbox on the purchase requisition.

C. Check the Require PR Approval on PO Creation? checkbox during the creation of the purchase requisition.

D. Check the purchasing option Require Approval to Convert PR to PO or Contract? (checkbox in Purchasing.

Correct Answer: D

  elma93 1 month ago


Answer is correct
upvoted 1 times

Question #21 Topic 1

A maintenance planner is in the process of planning time sensitive emergency maintenance work orders for a number of assets where items need
to be reserved.
What reservation type should be used?

A. Soft

B. Hard

C. Urgent

D. Critical

Correct Answer: B
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21580188

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 8/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #22 Topic 1

A company wishes to create a location that is used during the receiving process when inspection occurs.
Which type of location is used?

A. A HOLDING location at the SITE level.

B. A CLEARING location at the ORG level.

C. A RECEIVING location at the SITE level.

D. An INSPECTION location at the ORG level.

Correct Answer: A

Question #23 Topic 1

A user is in the Inventory application and has enabled a record for edit mode. The user performs an operation that does not release it from edit
mode.
Which operation is it?

A. Save action

B. Moving to Start Center

C. Running a query from the list tab of the application

D. Paging through records by using the Next and Previous links

Correct Answer: D

  sleeper166 8 months, 2 weeks ago


Paging through records using the next and previous links does not keep the record locked. The correct answer is A, saving the record.
upvoted 6 times

  marcoagb 1 month, 3 weeks ago


You are right, IBM DOCUMENT on this:

https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0/com.ibm.mbs.doc/rladmin/c_edit_mode.html

The following actions release a record from edit mode:


-Starting another application by using the Go To menu.
-Returning to the List tab of the application.
-Paging through records by using the Next and Previous links.
-Logging out.
upvoted 4 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 9/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #24 Topic 1

A user has created a work order against asset ABC. A technician determines that asset ABC is faulty and it needs to be replaced. The technician
replaces asset
ABC at the operating location with asset XYZ from a repair location.
What happens after the swap?

A. Asset locations have been swapped.

B. Asset identi ers have been swapped.

C. Inventory locations of the assets have been swapped.

D. The faulty asset ABC status at the operating location gets updated to OBSOLETE.

Correct Answer: A

Question #25 Topic 1

An administrator want to create a time based escalation point to evaluate to 30 days in the future.
What is the correct value to use in the Elapsed Time Interval eld along with the Elapsed Time Attribute?

A. Today + 30

B. Sysdate + 30

C. +30 (positive 30)

D. -30 (negative 30)

Correct Answer: C

  TanweerAl 1 month, 3 weeks ago


Answer should be D. -30
https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/escalation/t_defining_escalation_pts.html
upvoted 3 times

  MaxComp 1 month ago


Answer D
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 10/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #26 Topic 1

A company would like to make full use of item assembly structures.


To which of the following records can they be applied? (Choose three.)

A. Items

B. Assets

C. Systems

D. Locations

E. Master PMs

F. Classi cations

Correct Answer: ABD

Question #27 Topic 1

The supervisor has speci ed that the job plans be constructed so that the tasks on the work order will automatically start when the preceding task
is complete.
What function on a job plan makes this possible?

A. Work ow

B. Conditions

C. Revisioning

D. Flow Control

Correct Answer: D
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21327119

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 11/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #28 Topic 1

Which of the following settings values will determine the number of items to be ordered during the reorder process?

A. Safety Stock

B. Reorder Point

C. Conversion Factor

D. Economic Order Quantity

Correct Answer: B
Reference:
ftp://ftp.software.ibm.com/software/iea/content/com.ibm.iea.mam/mam/7.5/sysappmanagement/mam_7_5_reorder_calc.pdf

  marcoagb 1 month, 3 weeks ago


This is incorrect, reorder point will tell the point that reorder process will be triggered,

ECONOMIC ORDER QUANTITY is the right answer:

Economic Order Quantity (EOQ): From a Maximo reorder point of view, EOQ is the quantity that is reordered once the reorder process is triggered
for the item.

https://www.ibm.com/support/pages/understanding-maximo-inventory-related-terminology
upvoted 4 times

  elma93 1 month ago


The given answer is incorrect, Answer is D
upvoted 1 times

  elma93 1 month ago


It says "determine the number of items to be ordered", So Answer is D.
upvoted 1 times

  yasar2002 1 month ago


Correct answer = D
upvoted 1 times

  MaxComp 1 month ago


Answer D
upvoted 1 times

Question #29 Topic 1

A company has a requirement that certain GL Accounts expire.


In which application can this be de ned?

A. Financial Periods

B. Cost Management

C. Chart of Accounts

D. Database Con guration

Correct Answer: C
Reference:
http://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.5.0/com.ibm.mam.doc/overview/c_changes_apps_7.5.html

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 12/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #30 Topic 1

What can be performed in the Assignments tab of Work Order Tracking?

A. Initiate an assignment into STARTED status.

B. Reassign from one person group to another.

C. Find an available crew for a type requirement.

D. Split an assignment to the labor code's next working shift.

Correct Answer: C
Reference:
http://publib.boulder.ibm.com/tividd/td/ITMfUtil/62_mx_tnd_ugadd/en_US/PDF/62_mx_tnd_ugadd.pdf

Question #31 Topic 1

Maintenance is required on an asset at every 6,000 miles that uses job plan JP6K, and there is an additional Job Plan, JP18K, that is used at every
18,000 miles.
This Meter-Based Frequency PM has a frequency of 6,000 miles.
What are the correct sequence values to use on the Job Plan Sequence tab?

A. JP6K = 1 JP18K = 2

B. JP6K = 1 JP18K = 3

C. JP6K = 0 JP18K = 3

D. JP6K = 6 JP18K = 18

Correct Answer: B

Question #32 Topic 1

What is the reason to specify asset relationships?

A. To deploy assets.

B. To design the asset infrastructure.

C. To de ne a logical connection between separate assets.

D. To de ne how assets are allowed to behave when work is performed on them.

Correct Answer: C

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 13/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #33 Topic 1

A company requires that laborers record the actual time they spent on a work order. The labor hours recorded are not automatically approved and
the company does not want the laborer to have access to the Work Order Tracking application.
Which application would the laborers use?

A. Invoicing

B. Time Sheets

C. Labor Reporting

D. Activities and Tasks

Correct Answer: C
Reference:
http://www.ibm.com/support/knowledgecenter/SSLKT6_7.5.0/com.ibm.mam.doc/gp_ nmgr/c_ctr_rprt_lab_use.html

Question #34 Topic 1

A planner needs to combine a number of items to be used regularly that can be tracked by a single item number and issued to work orders.
How can this be achieved?

A. Using an item assembly structure.

B. Transferring the necessary items to a single bin.

C. Changing the item number of each included item.

D. Updating the physical count of the inventory record.

Correct Answer: B

  marcoagb 1 month, 3 weeks ago


right answer is A. Using an item assembly structure.
upvoted 3 times

  yasar2002 1 month ago


correct Answer is A
upvoted 1 times

  MaxComp 1 month ago


Answer A
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 14/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #35 Topic 1

The maintenance supervisor is gathering data to use to build job plans. Only certain job plan will be carried over to the work orders based on the
conditions applied.
What data can have conditions?

A. Services, Tools, Assets

B. Labor, Tasks, Calendars

C. Labor, Services, Materials

D. Materials, Speci cations, Tools

Correct Answer: C
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21622579

Question #36 Topic 1

A forecast has been made for a PM. The decision has been made to delete that forecast.
In which case is the forecast blocked from being deleted?

A. A reforecast is pending.

B. The forecast dates are unlocked.

C. A forecast can always be deleted.

D. The forecast dates have been locked.

Correct Answer: D

  marcoagb 1 month, 3 weeks ago


D is not right, FORECAST LOCKED means new dates cant be entered, but they can be deleted

Forecasts can always be deleted

https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/gp_msc/t_deleting_forecasts.html
upvoted 5 times

  elma93 1 month ago


Answer is D
upvoted 1 times

  elma93 1 month ago


Sorry i mean, Answer is not D, it is C
upvoted 1 times

  elma93 1 month ago


Answer is C
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 15/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #37 Topic 1

An administrator has a requirement to update the address of all company records associated with a certain vendor.
How can this be achieved?

A. Update the company set with the new address.

B. Update the vendor record and select Update Related Vendors?.

C. Update the company template and check the checkbox Roll Down?.

D. Update the company master record and check the checkbox Update Related Companies?.

Correct Answer: D

  joe12398 5 months, 1 week ago


you can do it in a and d this question should be a multiple choice.
upvoted 1 times

  marcoagb 1 month, 3 weeks ago


I feel D is the most accurate one
upvoted 1 times

  elma93 1 month ago


Answer is D
upvoted 1 times

  yasar2002 1 month ago


D is the right choice
upvoted 1 times

Question #38 Topic 1

A company wants to trigger a PM based on a characteristic type meter.


How can this be accomplished?

A. Create a master PM and link to the characteristic on the Related Records tab.

B. Create a condition monitoring point and specify the PM on the upper or lower limit.

C. Create a PM against the asset and specify the meter on the Frequency tab of the PM.

D. Create an escalation based on the characteristic meter and trigger the PM via an action.

Correct Answer: B
Reference:
ftp://ftp.software.ibm.com/software/tivoli_support/misc/STE/2012_08_23_STE_Preventive_Maintenance_and_Condition_Monitoring.pdf

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 16/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #39 Topic 1

A store manager needs to make changes to an asset via the Move/Modify action.
Which of the following changes can be made? (Choose two.)

A. Features

B. Storeroom

C. Asset's location

D. Class description

E. Parent/child relationship

Correct Answer: CD

  viji3281 1 month, 3 weeks ago


The correct answer should be C and E .
https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.1.1/com.ibm.mbs.doc/mbs_common/t_move_multiple_assets.html
upvoted 4 times

  elma93 1 month ago


All other sites says its C and D
upvoted 1 times

  yasar2002 1 month ago


C and E
upvoted 1 times

Question #40 Topic 1

A company is using Process Flow Control and wants to change the default values for Flow Start and Flow Complete statuses.
Where can these values be con gured?

A. System Properties

B. Work Type settings

C. WOSTATUS Domain

D. Change Work Order Options action

Correct Answer: B
Reference:
http://www.ibm.com/support/knowledgecenter/SSZRHJ/com.ibm.mbs.doc/mbs_common/c_wo_status.html

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 17/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #41 Topic 1

Which statement is true about routes?

A. A route can only be applied to a work order by a PM.

B. A route's sequence numbers are xed after it is activated.

C. A route can create work orders for locations or assets, not both.

D. Route Stops that become work order tasks cannot have job plans.

Correct Answer: A

  marcoagb 1 month, 3 weeks ago


A is not the correct one, from work order tracking application there is an action called APPLY ROUTE

The right one is D: Job plans cannot be associated with route stops.

https://www.ibm.com/support/knowledgecenter/SSFGJ4_7.6.0/com.ibm.mbs.doc/routes/c_route_options_wo_generation.html
upvoted 3 times

  elma93 1 month ago


All other sites says the answer is A
upvoted 1 times

  MaxComp 1 month ago


Answer D
upvoted 1 times

Question #42 Topic 1

To minimize Start Center load times, end users can see detailed KPI information from which application?

A. Analytics

B. KPI Viewer

C. KPI Manager

D. KPI Templates

Correct Answer: B
Reference:
http://www.ibm.com/support/knowledgecenter/SS8CCV_7.6.0.5/com.ibm.mams.doc/overview/c_new_kpis.html

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 18/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #43 Topic 1

A buyer runs a BIRT report which details Supplier Compliance. The buyer needs to further analyze the data in a spreadsheet to include an
additional graph before reviewing the information with the manager.
Which process transforms the data?

A. Export

B. Preview

C. Application Export

D. Report Transformation

Correct Answer: D

  viji3281 1 month, 3 weeks ago


It should be Export , option A . There is no such thing called Report Transformation
upvoted 5 times

Question #44 Topic 1

A work ow process has been revised and the new revision made active.
What happens to records that had already been routed into that work ow process before this was done?

A. They continue running in the earlier revision.

B. They are removed from work ow and must be restarted manually.

C. They switch to running in the new revision as that is the only active revision.

D. They are removed from work ow and are started in the new revision by a cron task.

Correct Answer: D

  marcoagb 1 month, 3 weeks ago


No such crontask exists... the records keeps running on the previous version of the workflow
upvoted 1 times

  elma93 1 month ago


All other sites say the answer is D
upvoted 1 times

  yasar2002 1 month ago


They continue running in the earlier revision.
upvoted 1 times

  MaxComp 1 month ago


Answer A
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 19/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #45 Topic 1

A company has critical and time sensitive processes and tasks foe repairing assets. The company maintenance supervisor would like to be
noti ed if any of the time sensitive tasks are overdue.
What application would the company use to con gure this?

A. Work ow

B. Escalation

C. Cron Task

D. Interaction

Correct Answer: C

  marcoagb 1 month, 3 weeks ago


An escalation is a mechanism for monitoring time-sensitive records. Escalations can take actions or send notifications when a record reaches a
defined escalation point. Your workflow administrator can specify that a task assignment has a time limit. If the assignment is not completed within
the specified time limit, an escalation can be triggered for the record.

https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/escalation/c_ctr_escalation_overview.html
upvoted 4 times

  MaxComp 1 month ago


Answer B
upvoted 1 times

Question #46 Topic 1

The business analyst for the purchasing department of a company is creating a work ow process for purchase requisitions. A requirement is to
branch the process to different approval groups based on a cost evaluation.
Which method is used to implement this in Work ow Designer?

A. A condition node with an expression.

B. A manual input with a custom action list.

C. An interaction node to review the PR lines.

D. A call out to the purchasing thresholds of the roles.

Correct Answer: A

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 20/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #47 Topic 1

A company wants to refuse receipt on 2 of 7 items from a single PO Line which does not require inspection.
Which procedure will accomplish this and maintain the correct inventory balance?

A. Save the Receipt, Click the Select Receipts to Void button, Change the quantity to 5.

B. Save the Receipt, Click the Select Items for Return button on the PO Line, Change the quantity to 2.

C. Save the Receipt, Click the Select Receipts to Void button, Select the PO Line, Change the Quantity to 5.

D. Save the Receipt, Click the Select Items for Return button on the PO Line, Save the receipt, Receive the PO again, but change the Quantity
due to 5.

Correct Answer: C
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg1IV75811

  marcoagb 1 month, 3 weeks ago


VOID is to correct wrong receivings.... to reject I would use SELECT ITEMS TO RETURN (option B)

1. Items/Services may be returned back to vendor due to rejection. Receipts transactions that are returned will be considered for invoice.

2. Store Keeper will void the receipt due to incorrect entry. A receipt that is voided is similar to a return, with the exception that a receipt that is
voided cannot be considered for use on a credit invoice. Receipt transactions that are voided are not included on invoices.

http://surenmaximoworks.blogspot.com/2014/03/select-receipts-to-void-vs-select-items.html
upvoted 3 times

  rasmagao 3 days, 6 hours ago


B.
https://www.ibm.com/support/pages/best-practice-rejected-quantities-maximo-7
upvoted 1 times

  elma93 1 month ago


I guess the keyword here is "Refuse", this means that the store did not receive these items. So, according to me, the answer is C.
upvoted 1 times

Question #48 Topic 1

A company is creating an ad hoc report indicating the number of days to complete a work order. This eld is not in the database.
Which feature enables this eld to be added to the report?

A. Format

B. Content

C. Calculate

D. Summaries

Correct Answer: C

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 21/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #49 Topic 1

An administrator needs to enable a prompt in the Organizations application for users to enter the Failure Class when completing or closing work
orders.
Which option is used to enable this?

A. PM

B. Asset

C. Work Type

D. Safety Plan

Correct Answer: C

Question #50 Topic 1

A quantity of 5 is received on a PO Line which has a quantity of 10. The user performed this receipt in error and wants to reverse the transaction.
Which is the most accurate statement?

A. The Select Receipts to Void function can be used.

B. The Select Receipts to Void function cannot be used when a partial receipt has been made.

C. The Select Items for Return function will not allow the user to receive the PO Line at the Later time.

D. The Select Receipts to Void function will not allow the user to receive the PO Line at a later time.

Correct Answer: A

Question #51 Topic 1

A supervisor has a requirement to group labor transactions by work order number while creating invoices in Labor Reporting.
How can this be achieved?

A. Check the Consolidate by Work Order checkbox for each transaction.

B. Enter the work order number, then enter each associated transaction.

C. Check the Group Labor by Work Order checkbox for each transaction.

D. Create an invoice for each work order, then enter each associated transaction.

Correct Answer: B

  viji3281 1 month, 3 weeks ago


I think the answer should be A. https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.1.1/com.ibm.mbs.doc/labrep/t_create_invoices.html
upvoted 2 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 22/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #52 Topic 1

A company needs to add the unit of measures for items, tool and services.
In which application can this be done?

A. Receiving

B. Storerooms

C. Asset Templates

D. Request for Quotations

Correct Answer: A
Reference:
http://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.0/com.ibm.mbs.doc/mbs_common/t_creating_unit_of_measure.html

  marcoagb 1 month, 3 weeks ago


A & D are correct, you can confirm from maximo preview

https://www.ibm.com/support/pages/maximo-asset-management-760-preview-site
upvoted 2 times

Question #53 Topic 1

A company has users which perform a variety of roles from Planning, Purchasing, Maintenance and Management. The administrator needs to
de ne which security groups to access which KPIs.
What application is used for this?

A. Users

B. KPI Manager

C. KPI Templates

D. Security Groups

Correct Answer: D

  turpin2020 8 months, 2 weeks ago


the answer is B
upvoted 3 times

  joe12398 5 months, 1 week ago


yeah there are few answers on this, I would reccomend that you sense check them!
upvoted 1 times

  marcoagb 1 month, 3 weeks ago


"Multiple new features are added to the KPI Manager application
[...]
You can also set security privileges on individual KPIs to restrict user access in the new KPI Viewer application. "

https://www.ibm.com/support/knowledgecenter/en/SS8CCV_7.6.0.5/com.ibm.mams.doc/overview/c_new_kpis.html
upvoted 1 times

  MaxComp 1 month ago


Answer B
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 23/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #54 Topic 1

Incorrect meter readings have been taken for gauge meters and characteristic meters. The system administrator has been asked to correct the
mistake.
How can the meter readings be corrected?

A. Add a new meter reading in the Assets application.

B. Add the correct meter readings in the Meters application.

C. Add the correct meter readings in the Meter Reading application.

D. Add the correct meter readings in the Preventive Maintenance application.

Correct Answer: A
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21970621

Question #55 Topic 1

A planner is creating a list of various types of records that will eventually be added to work orders on the Plans tab to provide technicians with the
required components to complete their work.
What types of non-set related records can be added? (Choose two.)

A. Items

B. Tools

C. Services

D. Materials

E. Standard Services

Correct Answer: CD
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21976012

Question #56 Topic 1

A company has a requirement to temporarily give a user the privilege to run the application's manual status change actions and specify this in a
work ow process.
Which of the following actions would be used?

A. PVSTATUS and NOSTATUS

B. OKSTATUS and PVSTATUS

C. NOSTATUS and OKSTATUS

D. PVSTATUS, NONSTATUS and OKSTATUS

Correct Answer: A
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21368390

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 24/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #57 Topic 1

The organizational rules allow for labor hours entered by internal laborers to be automatically approved. An internal laborer records 44 hours of
actual labor when only 4 hours were completed.
How can this be corrected?

A. Duplicate the work order and delete the incorrect entry.

B. This can be edited using the Labor Reporting application.

C. Record another labor transaction for that laborer subtracting 40 hours (-40)

D. Record another labor transaction for that laborer subtracting 40 hours (-40) and generate an Invoice.

Correct Answer: C

  marcoagb 1 month, 3 weeks ago


https://www.ibm.com/support/pages/correcting-labor-hours-after-labor-approved
upvoted 4 times

Question #58 Topic 1

The planner identi ed that the pump required four widgets as material on the work plan. An electrician was issued a quantity of four widgets from
the storeroom and was able to complete the work using only two of the four widgets. The two unused widgets were recorded as returned.
How would this be re ected on the Actuals Tab of the Work Order?

A. There would be a single line Item entry with a Transaction Type of ISSUE.

B. There would be a single line Item entry with a Transaction Type of RETURN.

C. There would be a single line Item entry with a Transaction Type of ISSUE/RETURN.

D. There would be two line items entries one with a Transaction Type of ISSUE and another with a Transaction Type of RETURN.

Correct Answer: D

Question #59 Topic 1

A company purchased many non-rotating as well as rotating assets and needs to understand the differences between them.
Which of the following are true? (Choose two.)

A. Rotating assets allow for maintaining an inventory of serialized components.

B. Both asset types allow for maintaining an inventory of serialized components.

C. Non-rotating assets allow for maintaining an inventory of serialized components.

D. Rotating assets can be held in inventory prior to moving to an operating location.

E. Non-rotating assets can be held in inventory prior to moving to an operating location.

Correct Answer: AE

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 25/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #60 Topic 1

A rotating asset has been inspected and approved. The asset is then found to be faulty and needs to be returned to the vendor.
What will happen to the asset after it has been returned? (Choose two.)

A. Asset status will change to DECOMMISSIONED.

B. Asset record will be deleted after it has been returned.

C. Returned to Vendor checkbox has been selected and made read-only.

D. Asset status will change to INACTIVE when there is no inventory balance.

E. Asset will be changed to a non-rotating asset and no longer reside in the storeroom.

Correct Answer: AE

  turpin2020 8 months, 2 weeks ago


Answer A and C
upvoted 3 times

  marcoagb 1 month, 3 weeks ago


https://www.ibm.com/support/pages/return-rotating-asset-vendor
upvoted 1 times

  elma93 1 month ago


A and C
upvoted 1 times

Question #61 Topic 1

A storeroom clerk is processing items to be shipped to various locations. In the Inventory Usage application, while processing one of these items,
the Split Usage
Quantity dialog is displayed and the clerk selects the Auto-Split option.
What is validated?

A. A rotating item is requested and the quantity is more than one.

B. The inventory balance for the item is greater than the ordered quantity.

C. A lotted item with the same quantity has been selected on another usage line.

D. The quantity in a storage bin already meets the required quantity on the Inventory Usage line.

Correct Answer: C

  marcoagb 1 month, 3 weeks ago


Right answer is A

The Auto-Split feature checks the following item attributes and assigns the
available stocked items:

A rotating item is requested and the quantity is more than one.

https://www.ibm.com/support/pages/split-usage-quantity-inventory-usage-application
upvoted 3 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 26/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #62 Topic 1

A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks
grouped with a new parent work order.
Which option will group the tasks?

A. Select the task work orders and Create Work Package.

B. Select the task work orders Create Job Plan from Work Plan.

C. Create a new work order and add the task work orders on the Plans tab.

D. Create a new work order and add the child work orders on the Plans tab.

Correct Answer: A

  joe12398 5 months, 1 week ago


the answer is A
upvoted 2 times

Question #63 Topic 1

Which application must be used to create services that can be selected from a value list on a purchase order?

A. Service Items

B. Service Records

C. Common Services

D. Standard Services

Correct Answer: A

Question #64 Topic 1

A user has created a request for quotation and sent it to vendors. After receiving the responses from the vendors, the user will need to create a
purchase order.
What action must be performed before a purchase order can be created?

A. Purchase requisitions must rst be created.

B. Status of the request for quotation must be APPR.

C. Request for quotation lines must be awarded to a vendor.

D. Vendor quotation receipt transactions must be completed.

Correct Answer: C

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 27/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #65 Topic 1

A company has acquired a contract for an asset covering labor, materials and tools.
What must be created to capture this information?

A. A Master Contract

B. A Warranty Contract

C. A Purchase Contract

D. A Labor Rate Contract

Correct Answer: A
References:
http://www.ibm.com/support/knowledgecenter/SSLKT6_7.5.0/com.ibm.mam.doc/mods_apps/c_ctr_mam_mod_contracts.html

  marcoagb 1 month, 3 weeks ago


https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mam.doc/mods_apps/c_ctr_mam_mod_contracts.html
upvoted 1 times

  marcoagb 1 month, 3 weeks ago


Master contract
A way to associate many contract types together for the same vendor and define terms and conditions for the relationship with the vendor. A
master contract lists all contracts that you have with a particular vendor. For example, a master contract might list rental contracts for tools or
equipment, purchase contracts for materials, a labor rate contract, and a warranty on parts and labor. Master contracts are created in the Master
Contracts application.
upvoted 2 times

Question #66 Topic 1

A company is training on the use of the material status elds on work orders.
What are the possible status values available for these elds?

A. WMATL, AVAIL, NONE

B. COMP, NONE, PARTIAL

C. ONORDER, PAVAIL, READY

D. AVAIL, NOTAVAIL, PARTAVAIL

Correct Answer: B
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21683844

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 28/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #67 Topic 1

An Administrator needs to return a rotating asset to a vendor. When clicking on Select Rotating Assets for Return, there are no records to be
returned.
Why are the records missing?

A. The asset is not a rotating asset.

B. The rotating asset has not been received.

C. The rotating asset was a direct issue item.

D. The rotating asset was received and has been moved.

Correct Answer: D

Question #68 Topic 1

A company has a requirement to identify and characterize similar assets.


In which application can this be done?

A. Sets

B. Actions

C. Domains

D. Classi cations

Correct Answer: D

  turpin2020 8 months, 2 weeks ago


Answer D
upvoted 2 times

Question #69 Topic 1

Which con guration could be used by a company with two organizations to allow only one of them to see a speci c item record?

A. Create two company sets and only create the item record in one of them.

B. Create two item sets containing both organizations and only add the item to one of them.

C. Create one item set and activate the item only for those organizations they wish to use it.

D. Create one company set but only activate the item for the organizations they wish to use it.

Correct Answer: C

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 29/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #70 Topic 1

Cutover work from cooling to heating is performed on the air handling units during the month of October each year. A requirement is to have the
PM record generate Work Orders every Sunday during October.
What settings are necessary?

A. Frequency = 1, Frequency Units = MONTHS, and Active Dates values entered on the Seasonal Dates tab

B. Frequency = 7, Frequency Units = DAYS, and Active Days and Dates values entered on the Seasonal Dates tab

C. Frequency = 7, Frequency Units = DAYS, and Generate Work Order When Meter Frequency is Reached checked

D. Frequency = 1, Frequency Units = WEEKS, and Use Last Work Order's Start Date to Calculate Next Due Date checked

Correct Answer: B

Question #71 Topic 1

A company wishes to track items previously used for maintenance work on assets so they can easily be identi ed in the future.
How can this be accomplished?

A. Non-Rotating Assets can be listed on the Spare Parts tab on the asset record.

B. Rotating items can be recorded on the Subassembly table on the asset record.

C. Non-Rotating items can be recorded on the Spare Parts tab on the asset record.

D. Consumable items can be recorded in the Spare Parts application against the asset record.

Correct Answer: D

  joe12398 1 month, 3 weeks ago


The answer on here is C!
upvoted 2 times

Question #72 Topic 1

A company wants to create a rotating (serialized) tool to issue to a Labor or Work Order.
Which of the following tasks are necessary?

A. Insert new record in the Tools application, check the Rotating checkbox, add to Storeroom.

B. Insert new record in the Stocked Tools application, check the Rotating checkbox, add to Storeroom.

C. Insert new record in the Item Master application, check the Rotating checkbox, add the record to Tools application.

D. Insert new record in the Item Master application, check the Rotating checkbox, add the record to Stocked Tools application.

Correct Answer: A
Reference:
https://www.ibm.com/developerworks/community/blogs/a9ba1efe-b731-4317-9724-a181d6155e3a/entry/
from_the_maximo_support_desk_the_tools_and_stocked_tools_applications?lang=en

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 30/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #73 Topic 1

If the status of an item record is modi ed in the Item Master application, which two other records need to be updated in order for the item to be
purchase and stocked? (Choose two.)

A. the item's Company status

B. the item's Organizational status

C. the status of the item for the Set

D. the status of the item for the Site

E. the status of the item in inventory

Correct Answer: CE

Question #74 Topic 1

A user tries to edit a meter in the Manage Meter Reading History dialog in the Assets application but nds that all the elds are read only.
Which of these meter types can be modi ed through this dialog?

A. DIAL

B. GAUGE

C. CONTINUOUS

D. CHARACTERISTIC

Correct Answer: C
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21970621

Question #75 Topic 1

Which delivered report option enables a user to dynamically interact with rendered report content including ltering of data, and changing of
graphs, chart sizes and colors?

A. BIRT

B. Cognos

C. SQL Server

D. QBR Reporting

Correct Answer: A
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21694285&aid=1

  MaxComp 4 weeks, 1 day ago


Answer B
BIRT reports are static not dynamic to change color and graphs.
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 31/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #76 Topic 1

A company wishes to con gure Maximo so that meter readings automatically create work orders based on condition monitoring points. The
company has already con gured the system in Organizational settings and created the appropriate condition monitoring points.
What additionally needs to be con gured for this be accomplish?

A. Any meter should be added to the asset and the ConditionMonWoGenCronTask should be active e

B. A continuous type meter should be added to an asset and the PMWOGenCronTask should be active.

C. A gauge type meter should be added to an asset and the MeasurePointWoGenCronTask should be active.

D. A characteristic type meter should be added to an asset and the ConditionMonWoGenCronTask should be active.

Correct Answer: B

  marcoagb 1 month, 3 weeks ago


right answer is C

https://www.ibm.com/support/pages/setting-measure-point-wogen-crontask
upvoted 2 times

  elma93 1 month ago


Answer is B, Continuous meter is cumulative.
upvoted 1 times

Question #77 Topic 1

A user has entered a material receipt in error and wishes to correct it.
Which action should be performed?

A. Void Receipt

B. Credit Invoice

C. Return Material

D. Cancel Receipt

Correct Answer: A
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg1IV61712

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 32/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #78 Topic 1

A company is using Process Flow Control to ensure the tasks are done in the proper order.
By default, which status indicated the next task to be worked on?

A. APRP

B. COMP

C. INPRG

D. WPCOND

Correct Answer: C
Reference:
https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.0.9/com.ibm.mbs.doc/mbs_common/c_wo_status.html

Question #79 Topic 1

A user wants to create an ad hoc report with details of a set of assets. The user wants to build and display the report content as the nal report
design is built.
What feature enables the user to do this?

A. the Share? eld

B. the Public? eld

C. the Preview report button

D. the Run and Save Completed Report button

Correct Answer: B

  PCHELA_MATKA 1 month ago


I can not find the Public field. I think the correct answer is C.
upvoted 2 times

  MaxComp 4 weeks, 1 day ago


Answer D
upvoted 2 times

Question #80 Topic 1

An administrator wishes to create company records without rst creating company master records.
Which setting will allow this functionality?

A. In the Companies applies, check the Create Company Master from Company? checkbox.

B. On the company set, check the Automatically Add Companies to CompanyMaster? checkbox.

C. In the Company Master application, uncheck the Bypass Company Master for Companies? checkbox.

D. In the Organizations application, check the Allow Creation of Companies without a Company Master?checkbox.

Correct Answer: B

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 33/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #81 Topic 1

A forecast for a monthly PM has been generated for 6 minutes. A new data has been entered for the second row and saved. When the Process
Pending
Reforecast button is clicked, the following error appears: BMXAT0217E-There is no reforecast pending to process.
What would cause this error?

A. The reforecast dates are locked

B. The PM is not in the Active status

C. The reforecast cron task is set to run every 3 days

D. The Reforecast Subsequent Dates? checkbox was not checked before the forecast was generated.

Correct Answer: D
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg1IV55903

Question #82 Topic 1

A user gets an error when trying to move a rotating asset via the Move/Modify Asset action from a storeroom to an operating location. The error
message indicates that a rotating asset cannot be moved from a storeroom.
Which of the following can accomplish the move?

A. issue the asset from the Locations application

B. transfer the asset from the Storeroom application

C. issue the asset from the Inventory Usage application

D. issue the asset from the Work Order Tracking application

Correct Answer: C
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21584524

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 34/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #83 Topic 1

A company has business units that each have different GL account structures from each other.
What needs to be created?

A. One organization for each business unit.

B. One organization with a site for each business unit.

C. One organization with a currency code for each business unit.

D. One organization with different GL account structure de nitions for each business unit.

Correct Answer: B

  marcoagb 1 month, 3 weeks ago


Answer A is the right one, GL Account Structure are the same across all sites from same organization
upvoted 1 times

Question #84 Topic 1

An administrator has a requirement to add a new meter to 100 existing assets that each share a common con guration.
Which application can do this with a single action?

A. Assets

B. Meters

C. Item Master

D. Asset Templates

Correct Answer: D
Reference:
https://www.ibm.com/support/knowledgecenter/en/SSLL9Z_7.6.2/com.ibm.trn.doc/plusttmplt/t_generate_asset_template.html

Question #85 Topic 1

An asset has an associated meter, RUNHOURS, and the Reading Type is set to ACTUAL. The asset will require maintenance every 500 hours of
operation.
What must the PM con guration include?

A. Associate the Asset to the PM, associate the RUNHOURS meter to the PM, Meter Frequency = 500

B. Associate the RUNHOURS Meter, Meter Frequency = 500, Generate Work Order Based on Meter Readings (Do Not Estimate)? checked

C. Modify the Meter's Reading Type to DELTA, Meter Frequency = 500, Generate Work Order When Meter Frequency is Reached? checked

D. Modify the Meter's Reading Type to DELTA, Meter Frequency = 500, Generate Work Order Based on Meter Readings (Do Not Estimate)?
checked

Correct Answer: A

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 35/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #86 Topic 1

A supervisor has a requirement in Labor Reporting to report labor hours for work that has been completed.
What are the options available to report labor?

A. labor, craft, company, and work order

B. labor, crew, vendor/contract, work order and ticket

C. labor, crew, vendor/contract, work order and ticket group

D. labor, crew, vendor/contract, work order, activity and task

Correct Answer: A

  rasmagao 1 month ago


Answer is B

You can record daily attendance when you specify labor transactions by work order, by ticket, by crew, by labor, or by contract/vendor
upvoted 1 times

Question #87 Topic 1

Which setting is used to ensure that an inventory item has a positive balance in a storeroom at all times?

A. Safety Stock

B. Critical On Hand

C. Storeroom Minimum Stock

D. Minimum Balance Required

Correct Answer: A
Reference:
ftp://ftp.software.ibm.com/software/iea/content/com.ibm.iea.mam/mam/7.5/sysappmanagement/mam_7_5_reorder_calc.pdf

Question #88 Topic 1

A company has a requirement to present an informational dialog box to the user at run time.
Which of the following would be used in the work ow process design?

A. a wait node

B. an interaction node

C. an accept action with a noti cation

D. a manual input with a long description

Correct Answer: D

  MaxComp 4 weeks, 1 day ago


Answer B
Interaction will present a dialog with message to user
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 36/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #89 Topic 1

The Receipt Tolerance for an item as set in Item Master to be 10% but the user is still able to receive it for more than 10% of the purchase order?

A. The user's limit and tolerance allows it

B. The Receipt Tolerance set in the User's Security Group allows it.

C. The Receipt Tolerance set on the Inventory record for the item allows it.

D. The Receipt Tolerance set in the Item's Item/Org Details dialog allows it

Correct Answer: C

Question #90 Topic 1

A company recently had to do a massive overhaul of a pump asset. The planner has to enter hundreds of tasks, sequence those tasks, and identify
the labor, material, services and tools used on each task.
The planner knows that this work will occur again as the company has numerous pumps of the same type.
What must the planner do so that the work plan does not have to be re-entered?

A. Create a Job Plan

B. Create a follow-up work order

C. Acquire an extended warranty for the overall work

D. Use the Create Job Plan from Work Plan functionality

Correct Answer: A
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0.9/com.ibm.mbs.doc/jobplan/c_job_plans_and_work_orders.html

  marcoagb 1 month, 3 weeks ago


right answer is D

https://www.ibm.com/support/pages/automatically-generating-job-plans
upvoted 2 times

Question #91 Topic 1

A company is using PM work orders and wants to specify the work order default status. How is this done?

A. Modify the PM WOGEN process

B. Set the option, Work Order Default Status

C. Set the Work Order Status on the PM record

D. Set the System Property, Work Order Default Status

Correct Answer: C
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21994744

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 37/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #92 Topic 1

A company has a requirement to segment accounting periods by specifying the start date and close date.
In which application can this be done?

A. Financial Periods

B. Cost Management

C. Chart of Accounts

D. Database Con guration

Correct Answer: C
Reference:
https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.0/com.ibm.mt.doc/chrtacct/t_specify_ nancial_periods_general_ledgers.html

Question #93 Topic 1

A company wants non-rotating items that are issued to assets to automatically show up as a spare part of the asset record.
How can this be achieved?

A. Check the Add as Spare part checkbox on the asset record

B. Check the Add as Spare part checkbox on the item master record

C. Check the Attach to Parent Asset on Issue checkbox on the asset record

D. Check the Attach to Parent Asset on Issue checkbox on the item master record

Correct Answer: D
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg1IJ00163

  marcoagb 1 month, 3 weeks ago


right answer is B
upvoted 2 times

  MaxComp 4 weeks, 1 day ago


Answer B
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 38/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #94 Topic 1

Where can an end user see in-depth details of a KPI, including its long description, communication logs and con gurable historical trending?

A. KPI Viewer

B. Start Center

C. KPI Manager

D. KPI Template

Correct Answer: C
Reference:
https://www.ibm.com/support/knowledgecenter/en/SS8CCV_7.6.0.5/com.ibm.mams.doc/overview/c_new_kpis.html

Question #95 Topic 1

A company has a number of complex leased assets and wishes to stop child assets that are part of the subassembly from being moved. How can
this be accomplished?

A. Check the Maintain Hierarchy checkbox on the asset record

B. Check the Lock Asset checkbox on the Lease Rental Contract

C. Check the Maintain Hierarchy checkbox on the rotating item record

D. Check the Maintain Hierarchy checkbox on both the asset and the item record

Correct Answer: A

  rasmagao 1 month ago


https://www.ibm.com/support/pages/functionality-maintain-asset-hierarchy-checkbox
upvoted 1 times

Question #96 Topic 1

A company wants the escalation action and noti cation to be applied to an expired purchase contract. Which of the following must be de ned?

A. Site

B. Organization

C. Escalation Point

D. Escalation Group

Correct Answer: C
Reference:
https://www.ibm.com/developerworks/community/blogs/a9ba1efe-b731-4317-9724-a181d6155e3a/entry/
maximo_sccd_escalations_your_friend_and_mine1?lang=en

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 39/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #97 Topic 1

A planner has developed an ad hoc report with information speci c to a variety of locations and assets. The planner wants to automatically run
and receive this report every Monday at 7am as well as having it sent to a maintenance supervisor.
What reporting feature enables this?

A. Escalation

B. No Request Page

C. Maximo Scheduler

D. Scheduling and Emailing

Correct Answer: D

Question #98 Topic 1

An administrator has been informed that a direct issue item for a work order is not required and need to be returned.
What does the administrator need to do?

A. From the Receiving application select items for Return

B. From the Storerooms application select Return Item to Main Storeroom

C. Form the Work Order Tracking application select Return Direct Issue Item

D. Create a return transaction type for the item in the Work Order Tracking application

Correct Answer: D
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21976014

  Vahee 1 month ago


Answer is A
upvoted 1 times

  elma93 1 month ago


For direct issue items, the answer given is correct. It is D
upvoted 1 times

  MaxComp 4 weeks, 1 day ago


Answer A
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 40/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #99 Topic 1

A company wants to ignore storeroom availability for work order status changes. Where is the setting that controls this function?

A. Organizations > System Settings > Work Order

B. Organizations > Work Order Options > Edit Rules

C. Organizations > Work Order Options > Work Type

D. Organizations > Work Order Options > Other Organization Options

Correct Answer: D
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg1IV84044

Question #100 Topic 1

An administrator has decided to use the Calendar Based? Checkbox on a work ow assignment. Which other eld is affected by this?

A. the assignment time limit

B. the assignment noti cation

C. the assignment escalation role

D. the auto-accept assignment action

Correct Answer: A

Question #101 Topic 1

An administrator needs to report failures that are occuring on a monthly basis. There is a requirement to use the Failure Class to report these
failures.
Which applications can accomplish this?

A. Hazards, Precautions, Job Plans

B. Assets, Locations, Work Order Tracking

C. Job Plans, Routes, Work Order Tracking

D. Preventive Maintenance, Condition Monitoring, Safety Plans

Correct Answer: B

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 41/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #102 Topic 1

A user is searching for a classi cation to add to a record in Work Order Tracking and is unable to nd the known existing classi cation. What
could cause this?

A. Work Order record is in WAPPR status

B. User does not see the Classi cations application

C. WORKORDER is not a Use With object for that classi cation

D. The classi cation is not associated with the work order's location

Correct Answer: D

  sjmaximo 1 month ago


answer is C
upvoted 2 times

  MaxComp 4 weeks, 1 day ago


answer is C
upvoted 1 times

Question #103 Topic 1

A planner has a high priority work order which is going to consume an item with limited availability and wants to ensure that the item is dedicated
to this work order. What type of reservation should the planner use?

A. SOFT

B. HARD

C. APSOFT

D. BACKORDER

Correct Answer: B
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21683654

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 42/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #104 Topic 1

A new revision of a work ow subprocess has been created for a work ow process that has used earlier revisions of that subprocess. When the
new revision is complete, the administrator wants to make those change active for new records started into work ow.
What procedure needs to be done?

A. Add a new subprocess node that references the new version

B. Choose View Synchronized Processes from the More Actions menu

C. Choose Resynchronize an Active Work ow Process from the More Actions menu

D. Choose Activate Process from the Common Actions menu to activate the subprocess.

Correct Answer: C
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21662443

Question #105 Topic 1

An administrator wants to create multiple individual KPI records from a single KPI template.
What action must be taken?

A. Save Record

B. Generate KPI

C. Schedule KPI

D. Run KPICRON tasks

Correct Answer: B
Reference:
https://www.ibm.com/support/knowledgecenter/en/SS8CCV_7.6.0.5/com.ibm.mams.doc/overview/c_new_kpis.html

Question #106 Topic 1

At what level are service items de ned?

A. Set

B. Site

C. System

D. Organization

Correct Answer: A
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0.5/com.ibm.mbs.doc/pdf_mbs_multiple_site.pdf

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 43/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #107 Topic 1

A company has identi ed three tasks (10, 20 and 30) and these tasks must be accomplished in a speci c order to prevent damage to the asset.
Task 10 must be complete before task 20 can begin, task 20 must be complete before task 30 can begin.
How can the planner facilitate this requirement?

A. Use the Sequence Column to identity the sequence

B. Enable Flow Control on the Work Order and use the Sequence Column to identify the sequence

C. Enable Flow Control on the Work order and identify the sequence for each task in the Predecessors eld of the task

D. Use the Sequence Column to identify the sequence and setup Flow Actions that change the task status to Complete and Approved

Correct Answer: C
Reference:
ftp://ftp.software.ibm.com/software/iea/content/com.ibm.iea.mam/mam/7.1/work_management/con g_auto_wo_status_change.pdf

Question #108 Topic 1

A company wishes to apply an item assembly structure to a location.


Which eld on the location record is required for this to take place?

A. Asset

B. Spare Parts

C. Rotating Item

D. Hierarchical System

Correct Answer: C
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0/com.ibm.mbs.doc/mbs_common/c_item_assembly_struct.html

Question #109 Topic 1

A company has multiple crews that work different days and hours. The administrator must de ne these work schedules. Where can this be done?

A. Crew De nition in the Labor application

B. De ne/Apply Shifts in the Crews application

C. Crew De nition in the Calendars application

D. De ne/Apply Shifts in the Calendars application

Correct Answer: D
Reference:
https://www.ibm.com/developerworks/community/blogs/a9ba1efe-b731-4317-9724-a181d6155e3a/entry/
From_The_Maximo_Support_Desk_Introduction_To_Using_Crews_On_Work_Orders?lang=en

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 44/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #110 Topic 1

A company purchasing agent would like to have the company purchase contracts set to expired upon the purchase contract's expiration date. The
agent would like to use the Escalation application to de ne the condition to check for the purchase contract expiration.
Where can the expiration contract information be speci ed?

A. Actions

B. Condition Evaluation

C. Escalation Condition

D. Escalation Point Elapsed Time Attribute

Correct Answer: A
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21497180

  marcoagb 1 month, 3 weeks ago


according to the reference, the answer is D
upvoted 2 times

  elma93 1 month ago


From the "select actions" menu, we activate the escalation.
upvoted 1 times

Question #111 Topic 1

A company needs to ensure that the manufacturer's recommended maintenance schedule is accomplished for each asset associated to a
warranty contract. How can this be done?

A. Attaching the Master PM Schedule to the Contract using Document Links

B. Identify the Unit of Measure and Meter Duration on the Contract Lines Tab

C. Entering the recommended maintenance schedule on the Terms and Conditions Tab

D. Entering the meter reading in the Master Section for the asset on the Warranty Contract.

Correct Answer: A

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 45/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #112 Topic 1

An administrator is setting up security to enforce site speci c restrictions.


What type of security group does the administrator need to create?

A. Maxadmin

B. Independent

C. Administrator

D. Allow restrictions

Correct Answer: A
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg21635810

  marcoagb 1 month, 3 weeks ago


answer is B
upvoted 1 times

Question #113 Topic 1

The buyer for a vendor received an offer to acquire a speci c item and if a certain quantity is ordered, a speci c cost for that item will be given.
Which purchase contract type needs to be created?

A. Price

B. Master

C. Blanket

D. Purchase

Correct Answer: D

  rasmagao 4 weeks, 1 day ago


i think answer is A

https://www.ibm.com/support/knowledgecenter/pt/SSLKT6_7.6.0/com.ibm.mbs.doc/contpurch/c_price_contracts.html?pos=2
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 46/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #114 Topic 1

Which technique or setting will an administrator use to prevent a PM from being modi ed by its Master PM?

A. The Override Updates ag on the PM

B. The PM options dialog of Organizations

C. A data restriction on the Master PM object

D. The Lock Forecast Dates action on the PM

Correct Answer: A
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21699399

Question #115 Topic 1

A company has decided to discontinue the use of job plan revisioning. What application is used to accomplish this?

A. Job Plans

B. Organizations

C. System Properties

D. Application Designer

Correct Answer: A

  marcoagb 1 month, 3 weeks ago


answer is B

While job plan revisions is the default setting it can be disabled from the Organizations application in the dialogue box called System Settings.
Scroll down until you find the section called Job Plans and uncheck “Revision Control for Job Plans?”.

https://maximosecrets.com/2017/01/10/job-plan-
revisions/#:~:text=Disabling%20Revision%20Control%20of%20Job,Control%20for%20Job%20Plans%3F%E2%80%9D.
upvoted 3 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 47/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #116 Topic 1

A user needs to return a rotating asset from a repair location to an inventory location.
What is the correct step to achieve this?

A. Use the Move/Modify action in the Assets application

B. Use the Move/Modify action in the Locations application

C. Use the Select rotating asset for return in the Receiving application

D. Use the Move/Swap/Modify action in the Preventive Maintenance application

Correct Answer: A
Reference:
https://www.ibm.com/developerworks/community/blogs/a9ba1efe-b731-4317-9724-a181d6155e3a/entry/
Comparison_between_moving_Rotating_Assets_from_Storeroom_to_SALVAGE_location_vs_moving_Rotating_Asset_to_Repair_Facility?lang=en

  MaxComp 4 weeks, 1 day ago


https://www.ibm.com/support/pages/comparison-between-moving-rotating-assets-storeroom-salvage-location-vs-moving-rotating-asset-repair-
facility
upvoted 1 times

Question #117 Topic 1

An administrator must store information such as address and phone number about individuals.
In which application can this be done?

A. Users

B. People

C. Persons

D. Person Groups

Correct Answer: B
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg22013586

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 48/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #118 Topic 1

A maintenance planner is trying to determine the priority of scheduled work orders as well as the need for various items to complete that work.
The planner determines that soft reservations should be made for these items. What is a characteristic of these reservations?

A. reservations are prioritized

B. does not reduce available balance

C. cannot be superseded by other reservation types

D. de ned by the need for the items within a speci c time frame

Correct Answer: D

  elma93 1 month ago


Answer is correct
https://www.ibm.com/support/pages/hard-and-soft-reservations-maximo-75
upvoted 1 times

  Vahee 1 month ago


Answer is B
upvoted 3 times

Question #119 Topic 1

An administrator is setting up inventory items in storerooms and the company only wants certain items to be reordered. Which eld is used to
accomplish task?

A. Reorder

B. Issue Unit

C. Reorder Point

D. Economic Order Quantity

Correct Answer: C
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg1IJ01576

  sjmaximo 1 month ago


Answer is A. Reorder checkox.
upvoted 2 times

  MaxComp 4 weeks, 1 day ago


Answer is A
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 49/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #120 Topic 1

Which tab provides a graphical representation of an asset and its relationships?

A. Features

B. Topology

C. Relationships

D. Speci cations

Correct Answer: B
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0.6/com.ibm.mbs.doc/asset/c_asset_topology.html

  joe12398 5 months, 1 week ago


this doesn't actually exist no more but the answer none the less is b
upvoted 2 times

Question #121 Topic 1

Which of the following describes the work list section in the Assignment Manager application?

A. A work order closing center

B. A joined view of work orders and assignments

C. A list of work orders by priority and response time.

D. A list of unassigned work plan labor and crew requirements

Correct Answer: C
Reference:
https://www.ibm.com/support/knowledgecenter/en/SSLL9Z_7.6.1/com.ibm.trn.doc/plustwrkmn/c_assign_mgr_app_trn.html

  Vahee 1 month ago


Answer is D
upvoted 2 times

  MaxComp 4 weeks, 1 day ago


Answer is D
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 50/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #122 Topic 1

From within the Purchase Order application, a user runs the Purchase Order Details report. The report's request page displays with scheduling and
emailing information only. Why is the parameter information missing in the request page?

A. The report runs against the entire database.

B. The report runs against the application's current query.

C. The user does not have security privileges to the parameters.

D. Parameters are not available for only of the Purchasing applications.

Correct Answer: C

  Vahee 1 month ago


answer is B
upvoted 2 times

Question #123 Topic 1

When a route is applied to a work order, which of the following is possible result?

A. A multilevel work order hierarchy

B. Job plan tasks under work order tasks

C. A report of work order operational steps

D. Entries in the Assets, Locations and CI applications

Correct Answer: D

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 51/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #124 Topic 1

A user makes changes to a work order record and saves. The screen shows an error dialog that displays "Record has been updated by another
user, refetch and try again.".
How can the user avoid this error?

A. Use edit mode for the mode order

B. Save the work order before making changes

C. Send a bulletin board message to other users

D. Ask the database administrator to lock the work order

Correct Answer: B

  Vahee 1 month ago


answer is A
upvoted 2 times

  rasmagao 4 weeks, 1 day ago


Answer is A

https://www.ibm.com/support/pages/using-edit-mode-lock-record
upvoted 1 times

Question #125 Topic 1

New centrifugal pumps have been acquired. These new assets need to be tracked and kept in the storeroom. How can this be accomplished?

A. Issue assets to a storeroom location

B. Move the assets to a storeroom location

C. Track the asset via the storeroom application

D. Associate the assets with an existing rotating item

Correct Answer: C
Reference:
https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&uact=8&ved=2ahUKEwjuivnFs-
_fAhUCtRoKHXAgBXkQFjAAegQIChAC&url=https%3A%2F%2Fwww.ibm.com%2Fdeveloperworks%2Fcommunity%2F les%2Fform%2Fanonymous
%2Fapi%
2Flibrary%2Fe3d6dd23-e19b-4a1e-89e8-2654d80082c8%2Fdocument%2F2c2f2edd-693d-4043-9bad-44ca34673042%2Fmedia&usg=AOvVaw2o-
Jq8xCK46YHZy9IjhTo8

  Vahee 1 month ago


I think answer should be D
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 52/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #126 Topic 1

A company wants to receive rotating items that require inspection. What is the order of tasks necessary to do this?

A. Receive Rotating Items, Change Inspection Status, Assign Asset number

B. Change Inspection Status, Receive Rotating Items, Assign Asset number

C. Change Inspection Status, Assign Asset number, Receive Rotating items

D. Receive Rotating Items, Assign Asset number, Change Inspection Status

Correct Answer: D
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0.9/com.ibm.mbs.doc/receipts/t_receive_material_rotate.html

  Vahee 1 month ago


answer is B
upvoted 2 times

  rasmagao 4 weeks ago


https://www.ibm.com/support/pages/receiving-rotating-items-maximo
upvoted 1 times

Question #127 Topic 1

A company has an asset that has failed and an administrator needs to create a work plan that includes exact steps and descriptions that need to
be followed to get the asset in operating status. Which option does the administrator need to follow?

A. Create follow up work orders

B. Create Job Plan from Work Plan

C. Create a work order and add actuals

D. Create a work order, add tasks and populate the summary eld

Correct Answer: D
Reference:
https://www.google.com/url?
sa=t&rct=j&q=&esrc=s&source=web&cd=9&ved=2ahUKEwiY24aB3u_fAhUMlhQKHUkzDsQQFjAIegQICBAC&url=https%
3A%2F%2Fwww.ibm.com%2Fdeveloperworks%2Fcommunity%2F les%2Fform%2Fanonymous%2Fapi%2Flibrary%2F41abc2d2-e1ec-4709-8b27-
4937d78f9909%2Fdocument%2Fd5e8bd60-bf34-4e12-99d6-9e6181f2dad2%2Fmedia%2F007%2520-%2520Job%2520Plans%
2520Chapter_U1.pdf&usg=AOvVaw08sRWzdeKB2kTOuBsYyi0V

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 53/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #128 Topic 1

A company orders and receives a case containing 36 light bulbs which are issued one at a time. What is created for this relationship?

A. Multiplier

B. Issue Unit

C. Issue Type

D. Conversion

Correct Answer: B
You order light bulbs in bulk and the unit of measure is a case, with a quantity received of 36. However, when you issue the item, you issue it
one at a time. In this case, you can de ne a measure unit of CASE and another measure unit of EACH. You de ne a conversion ratio from CASE
to EACH with a factor of 36. When you receive an order of bulbs into a storeroom, the received order unit of one CASE is converted into the
storeroom issue unit of 36 EACH.
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0.9/com.ibm.mbs.doc/mbs_common/c_measurement_units_conversion_factors.
html

Question #129 Topic 1

A company wants to issue a tool with an hourly rate to a work order. Which applications can be used to do this?

A. Inventory | Tools

B. Stocked Tools, Inventory

C. Tools, Work Order Tracking

D. Stocked Tools, Work Order Tracking

Correct Answer: A
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21672597

  elma93 1 month ago


Set the Hourly Rate for a Tool:
1. Go To Inventory | Tools
2. Open the tool record
3. Select Action | Tool/Organization Details
4. In the Tool Rate field enter an hourly cost for this tool's usage
upvoted 1 times

  Vahee 1 month ago


Answer is D.
upvoted 2 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 54/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #130 Topic 1

A company wishes to make a system the Primary System.


Where can this be accomplished?

A. Within the Systems application

B. From the Classi cations application

C. Using the Manage Systems actions in the Locations application

D. Using the Associate Systems with Location action in the Locations applications

Correct Answer: C
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21663686

  elma93 1 month ago


Primary system is the default hierarchy of locations. Each site is allowed to have only one primary system. Your primary system must be hierarchical;
that is, there must be a single top- level location that is the parent of all other locations in the system. If assets in different locations are part of an
asset hierarchy, their locations must exist in the primary system. Site is a work location, such as a plant or facility. A site belongs to a single
organization. System is a grouping of locations, organized into either hierarchical or network relationships. A hierarchical system could define
location relationships of a plant, having a plant
upvoted 2 times

Question #131 Topic 1

The job plan coordinator needs to add new tasks to an existing job plan which is currently revision 2. The coordinator selects Revise Job Plan
from the More
Actions menu and now has a new job plan version, revision 3. What is the status of revision 2?

A. ACTIVE

B. PNDREV

C. REVISED

D. INACTIVE

Correct Answer: C

  TanweerAl 1 month, 3 weeks ago


Answer should be A- Active.
When you select 'Revise Job Plan' new revised job plan get status 'PNDREV' and old one remain 'ACTIVE' until unless revised (new) job plan is
activated.
upvoted 2 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 55/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #132 Topic 1

A work ow process design requires that the record be sent to the QA group if the QA Required eld (a custom eld) is checked. Otherwise it can
continue on to the production department.
What type of node is used to enable this?

A. Decision

B. Condition

C. Interaction

D. Subprocess

Correct Answer: B
Reference:
https://www.ibm.com/support/knowledgecenter/en/SSLKT6_7.6.0/com.ibm.mbs.doc/pdf_mbs_work ow.pdf?view=kc
(11)

Question #133 Topic 1

An item has been agged as rotating by mistake. The rotating checkbox is read-only and the rotating item has been associated with assets. How
can the rotating item be changed to a non-rotating item?

A. Remove the Item Number from the assets. Ensure that there is no inventory balance.

B. Move the assets to non-inventory locations. Ensure that there is no inventory balance.

C. Issue the assets to non-inventory locations. Ensure that there is no inventory balance.

D. Transfer the assets to non-inventory locations. Ensure that there is no inventory balance.

Correct Answer: A

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 56/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #134 Topic 1

An asset requires a diagnostic evaluation every 3 months and an oil change every 18 months. It has been decided to use Job Plan sequencing to
generate the work orders at the appropriate interval where Job Plan A represents the 3-month diagnostic and Job Plan B represents the 18-month
oil change.
What are the Job Plan sequence values to accomplish this?

A. Job Plan A=1 and Job Plan B=6

B. Job Plan A=3 and Job Plan B=6

C. Job Plan A=1 and Job Plan B=18

D. Job Plan A=3 and Job Plan B=18

Correct Answer: D

  Vahee 1 month ago


Answer should be A
upvoted 2 times

Question #135 Topic 1

After creating and approving a non-contract related invoice for a previously received item, it was found that the item was defective and returned to
the vendor.
Which process should be used to correct the invoice?

A. Cancel the invoice

B. Create a credit invoice

C. Create a reverse invoice

D. Cancel the associated purchase order

Correct Answer: C
Reference:
https://www.ibm.com/developerworks/community/blogs/a9ba1efe-b731-4317-9724-a181d6155e3a/entry/reverse_invoice10?lang=en

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 57/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #136 Topic 1

A work order has the Originating Record eld populated.


What Relationship would be seen for the work order listed on the Related Records tab?

A. PARENT

B. RELATED

C. FOLLOWUP

D. ORIGINATOR

Correct Answer: B

  rasmagao 4 weeks ago


Answer is D

https://www.ibm.com/support/knowledgecenter/SSWT9A_7.6.1.2/com.ibm.mbs.doc/wotrack/c_record_relationships_wos.html
upvoted 1 times

Question #137 Topic 1

A storeroom clerk is considering using item kits to group items together that can be issued to work orders. Which of the following statements are
true? (Choose two.)

A. Can be assembled or disassembled across storerooms

B. Must contain condition-enabled, rotating, and lotted items

C. Are assembled in the Inventory or Inventory Usage applications

D. Disassembling decreases the balance of the item kit record and increases the balance of the individual components in the storeroom.

E. When adding to a storeroom, if the kit's component items do not exist in the storeroom, inventory records are created for these items.

Correct Answer: AE
Reference:
http://www-01.ibm.com/support/docview.wss?uid=swg22008251

  Vahee 1 month ago


Answer is D&E
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 58/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #138 Topic 1

An asset requires maintenance on a monthly, quarterly and annual basis. Three job plans have been created to meet this requirement called
MONTHLY,
QUARTERLY and ANNUAL. What is the correct job plan sequence that needs to be used?

A. MONTHLY=1, QUARTERLY=4, ANNUAL=1

B. MONTHLY=12, QUARTERLY=4, ANNUAL=1

C. MONTHLY=3, QUARTERLY=4, ANNUAL=12

D. MONTHLY=1, QUARTERLY=3, ANNUAL=12

Correct Answer: A

  TanweerAl 1 month, 3 weeks ago


Answer should be D
https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/pm/c_seq_num_pm_job_plan.html
upvoted 2 times

  elma93 1 month ago


Answer is D
upvoted 2 times

Question #139 Topic 1

After a job plan has been applied to a work order the user nds that 2 more tasks are required to perform the work on the work order.
How does the user add those 2 tasks?

A. Add the tasks to a follow up job plan

B. Add the tasks directly on the work order's Plans table

C. Change the job plan's status to INACTIVE and add the tasks

D. Create a new job plan revision and add the tasks to the new revision

Correct Answer: B
Reference:
https://www.ibm.com/support/knowledgecenter/SSLKT6_7.6.0.9/com.ibm.mbs.doc/jobplan/t_add_tasks_job_plans.html

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 59/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #140 Topic 1

What costing method should be used if the receipt cost of items that are the oldest in stock is required?

A. LIFO

B. FIFO

C. Average

D. Standard

Correct Answer: B
Reference:
https://www-01.ibm.com/support/docview.wss?uid=swg21384733

Question #141 Topic 1

A technician has completed a job and observed that more work is needed on the same asset. A new record is required to have the same asset,
location and GL account. What action needs to be taken?

A. Select Create Follow-up action from the completed work order

B. Select Create Work Order action from the completed work order

C. Select Create Work Package action from the completed work order

D. Click on the Plans tab, and add a new child work order from the completed work order

Correct Answer: A
Reference:
https://www.ibm.com/support/knowledgecenter/pt-br/SSANHD_7.6.0/com.ibm.mbs.doc/wotrack/c_record_relationships_wos.html

  MaxComp 4 weeks, 1 day ago


Answer B
upvoted 2 times

Question #142 Topic 1

A planner has a requirement to track records via the Inventory application as well as the Assets application. What type of item can be used to
track these records?

A. rotating

B. material

C. standard

D. non-rotating

Correct Answer: A
Reference:
https://www.slideshare.net/BrunoPortaluri/maximo-training-inventory-management
(slide 4)

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 60/61
8/25/2020 C2010-555 Exam – Free Actual Q&As, Page 1 | ExamTopics

Question #143 Topic 1

A storeroom manager is trying to determine what transactions have been completed for a given storeroom using the Inventory Usage application.
What types of transactions can the storeroom manager see using this application? (Choose two.)

A. items issued

B. items deleted

C. items created

D. items transferred

E. item status changes

Correct Answer: AE

  sjmaximo 1 month ago


answer is A,D.
upvoted 2 times

  elma93 1 month ago


Answer is A and D
upvoted 2 times

Question #144 Topic 1

A supervisor has a requirement to record daily attendance of the labor or crew performing work.
Which applications can be used to record this information? (Choose two.)

A. Labor

B. Crews

C. Person Groups

D. Labor Reporting

E. Work Order Tracking

Correct Answer: BD
Reference:
https://www.ibm.com/support/knowledgecenter/en/SSMAZG_7.5.1/com.ibm.mms.doc/pdfs/pdf_mwm_user.pdf
(p.23)

  rasmagao 4 weeks ago


I think D&E
upvoted 1 times

https://www.examtopics.com/exams/ibm/c2010-555/custom-view/ 61/61

You might also like