Professional Documents
Culture Documents
1. Bonded overlays
2. Un-bonded overlay or conventional
whitetopping
BONDED WHITETOPPING
Bonded overlays are normally used for resurfacing and minor rehabilitation
of the distressed pavements. The thicknesses of these overlays vary from
50mm (two inches) to 150 mm (six inches). Based on thickness, these
overlays are further divided into two groups, thin and ultrathin.
□ Thin White topping (TWT) – which has PCC overlay between 100 – 200 mm.
It is designed either considering bond between overlay & underlying
bituminous layer or without consideration of bond. High strength concrete (M
40 or higher) is normally used to take care of flexure requirement. Joints are
at shorter spacing of 0.6 to 1.25 m.
□ Ultra-Thin White topping (UTWT) – which has PCC overlay of less than 100
mm. Bonding between overlay & underlying bituminous layer is mandatory.
To ensure this, the existing layer of bitumen is either milled (to a depth of 25
mm) or surface scrapped (with a non-impact scrapper) or gently chiseled.
Joints are provided at a spacing of 0.6 to 1.25 m.
UNBONDED/CONVENTIONAL
WHITETOPPING
These overlays are generally much thicker than bonded
overlays. The thickness of unbonded whitetopping varies
between 200 mm and 275 mm and is not bonded to the
pavement. Basically, these overlays are constructed as a new
pavement on an existing pavement which acts as a stable base.
Figure 2a Figure 2b
Figure 3a Figure 3b
✔ If the existing road surface is good & only a few localized potholes
/ cracks exist, they can be repaired with a bituminous mix before
concreting is done.
✔ If potholes/ cracks are wider than 3 mm, they have to be treated
with bituminous emulsion, slurry seal after trimming them to shape and
cleaning out loose fragments with compressed air. Milling of the existing
surface also addresses this problem.
3.LAYING AND FINISHING:
Concrete used for laying should be made either in an RMC plant or in a weigh
batching plant. Use of either fixed form pavers or slip form paver machines is an
essential ingredient for getting a good quality pavement. In the current project, a
fixed form paver was used with a fixed side formwork with 16mm diameter steel
rods of 1 m length as tie rods @ 500mm c/c and the paver had gang mounted
vibrators equally spaced with variable rpm and three integral steel tubes with 8
Tonnes vibratory rollers for screeding, levelling, compaction and finishing.
Finishing of the surface is mostly achieved by the paver itself. But to achieve
uniform finish, a simple hand operated bull float is used when concrete is still in its
fresh state. After the bull float operation, uniform surface texture is provided by
using steel wire brush.
To avoid evaporation of surface water from concrete surface wax based curing
compound is sprayed. As an additional measure, plastic sheets are spread over the
pavement surface till normal curing process starts.
Contraction joints are provided by cutting groves at a depth of 150 mm at a
spacing of 1.2 m in longitudinal as well as transverse directions. The joints
are cut using electrical grove machines within about 8 to 10 hours of
pouring concrete. These joints are sealed with high quality sealant (either
bitumen or poly sulphides) to prevent moisture and incompressible
infiltration into the overlay system.