Professional Documents
Culture Documents
RISK PROBABILITY
Continue Operation
Cancel Operation
Risk Probability
RISK SEVERITY
Risk Severity
RISK INDEX
Risk Index
RESPONSIBLE
NO HIRA NO. ACTIVITY HAZARD POTENTIAL RISK MITIGATION
MITIGATION
Remove / Install There are additional work for Do remove/install the interior panel refer to the
10 HIR200410 Part of the interior ceiling panels broken 2 C 2C X 1 C 1C MRO, PPC
Interior repair interior damage Manual affected ( EO and AMM )
Continue Operation
Cancel Operation
Risk Probability
RISK SEVERITY
Risk Severity
RISK INDEX
Risk Index
RESPONSIBLE
NO HIRA NO. ACTIVITY HAZARD POTENTIAL RISK MITIGATION
MITIGATION
Personnel Error during Riveting Damage to skin, stringer or Do riveting process by Senior Personnel,
13 HIR200413 Riveting Process 2 C 2C X 1 C 1C MRO, PPC
Process other structural components always completed the by the Task card,
Dent in skin area caused of error in the Aircraft aerodynamics are Do the riveting order accordingly to task card,
14 HIR200414 Riveting Process 2 C 2C X 1 C 1C MRO, PPC
riveting process procedure disrupted use a standard riveting tools
Do FOD cleaning every after carrying out
Fail in the Mechanical
The presence of FOD due to negligent riveting process, Final Checking the by QA
15 HIR200415 Riveting Process System or hydraulic system 4 B 4B X 1 B 2B QA, SAA
of personnel dan safety for FOD in each of the end of
of the Aircraft
reveting process
Storaging Removable Unproper storage of aircraft removed damage will occurred to the Prepare the suitable storage for storaging
16 HIR200416 3 D 3D X 1 D 1D PPC
Parts parts removable parts removable part
Leak of the Skin, Corrotion Do sealing process according to task card, Use
can accur, and there is a Material Sealant according to the Correct
18 HIR200418 Sealing process Failure in the sealant process 4 C 4C X 1 C 2C PPC MRO
possibility of interference Specification, Do Sealing process by
with cabin Presurre experience Personeel
It is possible that an
Spread of flammable paint particles Position the plane as close as possible to the
explosion occurred in the
20 HIR200420 Painting Process which allows sticking to mercury lamps 4 C 4C hangar door, Complete the painting process 2 C 2C MRO, FACILITY
hangar lights and resulted in
1000 Watt with the exhaust blower
a fire
Remove / Install Tail down caused change of central of Damage Elevator or End Add ballast in area of Nose (STA 358 - STA
22 HIR200422 3 C 3C X 1 C 1C PPC, MRO
Engine gravity the aircraft Cone 550) before remove/installad engine
It's possible for personnel have
difficulty perform lapjoint project due to The possibility find error at Do refreshment for All personnel involved in this ENGINEERING, QA,
23 HIR200423 All Lapjoint Activities 3 C 3C X 2 C 2C
their long absence from carrying out each of the Job tasks project SAFETY
these job
The implementation of work Make sure the SRM, AMM manual , and SB
Preparation of Paper Manuals that will be used as reference
25 HIR200425 are not in accordance with 3 C 3C X that will be used as reference for making paper 2 C 2C ENGINEERING
work of paper work are not updated
the design concept work are updated
RISK PROBABILITY
Continue Operation
Cancel Operation
Risk Probability
RISK SEVERITY
Risk Severity
RISK INDEX
Risk Index
RESPONSIBLE
NO HIRA NO. ACTIVITY HAZARD POTENTIAL RISK MITIGATION
MITIGATION