Safety, Health & Environment Risk Assessment

Project Name SICAST Main Contractor GULF BUILDER Reference

Project no. Subs N/A Date 16-Jul-23

Client Assessor's Name Asif Ali Signature


Re

Init
Location RIYADH (SUDHAR) Task Concrete Risk assessment type
vie
ial
Risk assessment
w
Risk assessment
(before controls) (after controls)

Hazards

Risk factor

Risk factor
Likelihood

Likelihood
Who affected How affected Controls to be implemented

Severity

Severity
(check all that apply)
Risk Risk
level level

Wear respirators or
May affect Respiratory 1. To follow OCP-05: Handling of Cement & Concrete
Air Pollution by cement cover mouth and nose 3 4 12 12 3 1 3 3
System 2. To ensure fulfil of pre task checklist
with wet cloth.

1. To follow OCP-05: Handling of Cement & Concrete


Handling of ingredients Hands injury Use gloves and appropriat 3 5 15 15 2 2 4 4
2. To ensure fulfil of pre task checklist.

Use Safety shoes;


Provide platform above 1. To follow OCP-05: Handling of Cement & Concrete
Protruding reinforcement rods. Feet may get injured 3 4 12 12 2 2 4 4
reinforcement for 2. To ensure fulfil of pre task checklist.
movement of workers.

Ensure earthing of
equipment's and proper
Earthing of electrical mixers, Can cause electrocution / 1. To follow OCP-05: Handling of Cement & Concrete
functioning of electrical 3 4 12 12 2 2 4 4
vibrators, etc. not done. asphyxiation 2. To ensure fulfil of pre task checklist.
circuit before
commencement of work.

Use hard hats;


Remove surplus material 1. To follow OCP-05: Handling of Cement & Concrete
Falling of materials from height. Persons may get injured immediately from work 3 4 12 12 2. To ensure fulfil of pre task checklist. 2 2 4 4
place.

Insist on shift pattern;


Cause tiredness of Ensure lighting 1. To follow OCP-05: Handling of Cement & Concrete
Continuous pouring by same gang workers and may lead to arrangements during 3 4 12 12 2. To ensure fulfil of pre task checklist. 2 2 4 4
accident. night hours.

Allow only mixers with


hoper.
Provide safety cages
1. To follow OCP-05: Handling of Cement & Concrete
Revolving of concrete mixer / Parts of body of clothes around moving motors;
3 4 12 12 2. To ensure fulfil of pre task checklist. 2 2 4 4
vibrators may get entrapped Ensure proper
mechanical locking of
vibrator.
Risk factor method Severity Likelihood Notes
Severity
1 2 3 4 5 Risk level 1 - No potential for injury, illness, or incident 1 - Very Unlikely
Likelihood

2 4 6 8 10 Low 2 - Potential for minor injury, illness, or incident 2 - Unlikely


3 6 9 12 15 Medium 3 - Potential for a recordable injury, illness, or incident 3 - Likely
4 8 12 16 20 High 4 - Potential for major incident, or major injury or illness causing short term disability 4 - Very Likely
5 10 15 20 25 5 - Potential for major incident, or major injury or illness causing a fatality or long term disabil5 - Certain