You are on page 1of 2

1. MID EXAM GM 12: PROJECT MGT, SG 1,7,8.9.

10 (Group Works)

Questions for all groups: ( as described


above)

Read Exhibit 1 & Exercise A to answer the 4 (four)


questions, including but not limited to the
following:
a. Table of ES, LS, EF, LF, Slack & Critical Path
b. Step by step/ sequence of crashing an activity
c. Final crashing mode after saturation

Remarks:
1. Activity on Node (AON) shall show all nodes and arrow for the activities
2. Maximum time available is: total 180’ including Group + Individual Work
SUBMISSION:
• Submit the answer in Word, Excel or PPT format
• Include the NIM and names of all members in the file
• Filename: SG1/7/8/9/10_Group Mid Exam OM_GM 12
• One of the group members should upload the file to this link Mid
Exam Operations Management