Professional Documents
Culture Documents
If conventional T-8 tube light is replaced by T-5 or LED Tube light then the energy will be saved as below ----
For LED Tube light: saved energy = (40-18) = 22watt /tube light
2) POWER FACTOR STUDY: Electric bill based on NON-TOD meter and the average P.F. of whole day is
maintained in between 98.2% to 98.8%.
But for new Tariff rate we are getting 4% rebate which is less than the maximum rebate. Maximum rebate is 5%
for power factor above 99%. So, we are losing 1% rebate each month.
From study it has been observed that at peak load time P.F. goes down to 96.8% to 97.2%. But over all P.F.
remain above 98%. This can be controlled and can avail maximum benefit by introducing A.P.F.C. (Automatic
power factor controller).
By installing APFC panel instrument we can save Rs. 1 lac (approx) per month.
3) COMPRESSED AIR SYSTEM: minimizing by arresting air leakage from different joint, valves, etc we are able
to reduce the operating hours of the compressors and the total energy consumption of compressor.
Previously three number compressor run for supplying compressed air (50 hp IR compressor + 50 hp IR
compressor +40 hp screw compressor= 140 hp).
Now, only two compressor run alternately one number 70HP screw compressor or 50HP IR compressor and
one number 40HP screw compressor i.e. total 110 HP / 90 HP.
Then the energy saved = 320 units / day = 9600 units / month
4) ENERGY SAVER FOR LIGHTING BUSABR: As the Schneider suggested ENERGY SAVER FOR LIGHTING BASBAR for
Bally Jute mill, we are using this type of energy saver from last eight years. We have two numbers Energy saver
5) EARTHING PROTECTION SYSTEM: We are already installed 6 nos. new EARTH PIT at different location for
safety purpose. Now we are planning to install another new 4 nos. earth pit. All installation is carried by in-
house.
6) REPLACEING CONVENTIONAL S.F.U. (SWITCH FUSE UNIT) BY MCB: We are already started replacing old fuse
type main switch by MCB at Drawing section. MCB prevent short circuit fire at drawing machine almost 70%
and thus save the fire maintenance cost of that drawing machine.
7) INSULATION RESISTANCE TEST OF DIFFERENT CABLE IN DIFFERENT LOCATION (TOTAL TEST CARRIED OUT
ONLY WHEN MILL WAS SHUTDOWN i.e. HOLIDAY BY MAGGER 1000 VOLT)
169 (P-E)
176 (P-E)
176 (P-E)
112 (P-N)
112 (P-N)
116 (P-E)
108 (P-E)
110 (P-E)
112 (E-N)
188 (P-P)
198 (P-N)
200 (P-N)
200 (P-N)
200 (P-E)
200 (P-E)
192 (P-E)
200 (N-E)
110 (P-N)
099 (P-N)
108 (P-N)
097 (P-E)
100 (P-E)
100 (P-E)
100 (E-N)
05 MAIN P/H TO EAST SIDE 240 SQ. PILC , COPPER , 150 (P-P)
BUSBAR OF 4 NO. PLATEFORM MM X 3 1.1 KV
½ CORE 138 (P-P)
140 (P-P)
150 (P-N)
150 (P-N)
150 (P-N)
136 (E-N)
140 (E-N)
140 (E-N)
200 (P-N)
200 (P-N)
198 (P-N)
200 (N-E)
200 (N-E)
200 (N-E)
150 (P-N)
170 (P-N)
170 (P-N)
180 (E-N)
180 (E-N)
180 (E-N)
92 (P-N)
90 (P-N)
92 (P-N)
94 (P-E)
88 (P-E)
90 (P-E)
90 (E-N)
09 MAIN P/H TO BOILAR MAIN 50 SQ. XLPE 120 (P-P)
SWITCH MM X 3 ALUMINIUM, 1.1
½ CORE KV 120 (P-P)
120 (P-P)
110 (P-N)
120 (P-N)
120 (P-N)
NOTE: ONE NUMBER OLD CABLE IS FOUND UNDER SIZED. EXSISTING OLD PLC ARMOURED COPPER CABEL IS 70 SQ
MM X 3 CORE AND ITS CURRENT CAPACITY IS 145 AMP AND IT CARRIES 190 -210 AMP CURRENT. SO THERE IS HUGE
HEAT LOSS (BECAUSE THE GENERATED HEAT LOSS INCREASE WITH THE SQURE TIMES OF CURRENT).
NOW, THIS UNDER SIZED CABLE WILL BE REPLACED BY A NEW OVER SIZE CABLE (XLPE ARMOURED ALUMINIUM CABLE
240 SQ MM X 3 CORE) IN HOLIDAY TO REDUCE AND MINIMIZE HEAT LOSSES (i.e. LINE TRANSMISSION LOSS) AND
IMPROVE LOAD END VOLTAGE. THUS BY CHANGING OVER SIZE CABLE WE WILL SAVE THE LINE LOSS ENERGY.
A) BOILER-1 (OLD):
SL M/C NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
B) NEW WORKSHOP:
SL M/C NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
01 NEW WORKSHOP 406V 45 A 0.86 27.21
SL M/C NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
SL MACHENE NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
NOTE: QUITE NORMAL EFFICIENCY OF F/CARD MOTOR. IT HAS BEEN OBSERVED FROM STUDY TIME THAT AFTER
‘’AKHRA” THE FINISHER CARD MACHINE’S LOAD CURRENT REDUCED 0.8-1 AMP i.e. 0.4 – 0.5 KW.
SL MACHINE MANE HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
01 B/CARD-6 15HP 400V 16.5A 0.74 8.46 KW 75.60%
NOTE: IT HAS BEEN OBSERVED FROM STUDY TIME THAT WHEN B/CARD M/C STARTS IT DRAW 70-80 AMPS CURRENT
AND STAY ABOUT 20-26 SEC WHICH CAUSE THE FREQUENT BURNT OF THE MOTOR AND THIS ALSO EFFECT ON
MAXIMUM DEMAND. BUT AFTER FULL RUNNING OF THE MACHINE IT CAME DOWN NORMAL CURRENT 14 AMPS TO
17 AMPS.
THE STARTING TORQUE CURRENT CAN BE REDUCED BY INTRODUCING CENTRIFUGAL CLUTCH PULLEY SYSTEM.
SL MACHINE NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
NOTE: IT IS OBSERVED THAT A LITTLE BIT UNIT/HOUR ENERGY WILL BE SAVED BY PROPER LUBRICATION ON PROPER
POINTS OF MACHINE PARTS.
SL MACHINE NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
NOTE: IT IS OBSERVED FROM STUDY TIME THAT NEAR ABOUT 0.6 – 0.8 AMPS CURRENT REDUCED (i.e. APPROX 0.3 –
0.4 UNITS/HOUR ENERGY SAVED) BY PROPER TENSION OF DELIVERY PRESSING ROLLER AND PROPER LUBRICATION ON
PROPER POINTS OF MACHINE PARTS.
SL MACHINE NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
NOTE: IT IS OBSERVED FROM STUDY TIME THAT NEAR ABOUT 0.6 – 0.8 AMPS CURRENT REDUCED (i.e. APPROX 0.3 –
0.4 UNITS/HOUR ENERGY SAVED) BY PROPER TENSION OF DELIVERY PRESSING ROLLER AND PROPER LUBRICATION ON
PROPER POINTS OF MACHINE PARTS.
SL MACHINE NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKS
NO CURRENT
(AMPS)
NOTE: IT IS OBSERVED FROM STUDY TIME THAT NEAR ABOUT 0.6 – 0.8 AMPS CURRENT REDUCED (i.e. APPROX 0.3 –
0.4 UNITS/HOUR ENERGY SAVED) BY PROPER TENSION OF DELIVERY PRESSING ROLLER AND PROPER LUBRICATION ON
PROPER POINTS OF MACHINE PARTS.
SL MACHINE NAME HP/KW VOLT LOAD P.F. LOAD (KW) % LOAD REMARKAS
NO CURRENT
(AMPS)
01 C/S FIN DRG-01 5HP 398V 5.26A 0.78 2.828 75.81%
02 C/S FIN DRG -02 5HP 402V 5.75A 0.81 3.242 86.91%
03 C/S FIN DRG -03 5HP 401V 6.00A 0.82 3.417 91.60%
04 C/S FIN DRG -04 5HP 398V 5.45A 0.76 2.855 76.54%
05 C/S FIN DRG -05 5HP 404V 5.50A 0.80 3.078 82.52%
NOTE: IT IS OBSERVED FROM STUDY TIME THAT NEAR ABOUT 0.6 – 0.8 AMPS CURRENT REDUCED (i.e. APPROX 0.3 –
0.4 UNITS/HOUR ENERGY SAVED) BY PROPER TENSION OF DELIVERY PRESSING ROLLER AND PROPER LUBRICATION ON
PROPER POINTS OF MACHINE PARTS.